CN206670117U - Skyscraper is cold and hot double for journey piping installation, building air-conditioner device - Google Patents

Skyscraper is cold and hot double for journey piping installation, building air-conditioner device Download PDF

Info

Publication number
CN206670117U
CN206670117U CN201621482882.0U CN201621482882U CN206670117U CN 206670117 U CN206670117 U CN 206670117U CN 201621482882 U CN201621482882 U CN 201621482882U CN 206670117 U CN206670117 U CN 206670117U
Authority
CN
China
Prior art keywords
delivery pipe
stop valve
pipe
power plant
thermal power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621482882.0U
Other languages
Chinese (zh)
Inventor
何宗衡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Constan Energy Ltd By Share Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201621482882.0U priority Critical patent/CN206670117U/en
Application granted granted Critical
Publication of CN206670117U publication Critical patent/CN206670117U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Other Air-Conditioning Systems (AREA)

Abstract

It the utility model is related to air-conditioning device technical field, it is that a kind of skyscraper is cold and hot double for journey piping installation, building air-conditioner device, it includes thermal power plant unit, refrigeration unit, the first delivery pipe, the second delivery pipe, the 3rd delivery pipe, interlayer feed pipe, interlayer return pipe, thermal power plant unit is fixedly mounted on top, and refrigeration unit is fixedly mounted on bottom.The utility model reasonable and compact in structure, it is easy to use, it adds a refrigeration unit on the basis of heating installation, refrigeration unit shares a set of delivery pipe with thermal power plant unit, pass through the control of stop valve, when heating in the winter time, start thermal power plant unit and simultaneously open corresponding stop valve, you can by delivery pipe be user's heat supply;When refrigeration is needed in summer, start refrigeration unit and simultaneously open corresponding stop valve, you can by delivery pipe be user's cooling, with the same Cheng Pingheng of cold and hot waterpower, it is safe, laborsaving, easy, efficient the characteristics of.

Description

Skyscraper is cold and hot double for journey piping installation, building air-conditioner device
Technical field
Air-conditioning device technical field is the utility model is related to, is that a kind of skyscraper is cold and hot double for journey piping installation, building Space air-conditioning device.
Background technology
Authorization Notice No. is that CN204128033U patent document discloses a kind of segmentation water circulation heating device and building Heating plant, heat-source Cycles, the defeated circulation of pipe and user's circulation are divided into three independent closed circulations, while ring ring phase again by it Button, the pressure difference very little of each point in defeated circulation is managed, only needs the pump of a power very little to drive, it is not necessary to be divided again by skyscraper Come for high segment, middle section and lower curtate to high rise building heating, substantially reduce the transmission & distribution water that subregion is installed in piping shaft Guard system quantity and section cyclic supply-water pump quantity, electric energy is saved, reduced pipe-line equipment cost.But this heating installation is only Use in the winter time, most long usage time is low all in idle state, utilization rate in spring, summer, Qiu Sanji at five months or so; And the equipment such as air-conditioning, fan are also purchased in addition and are freezed in the period of summer sweltering heat, user so that existing in user family Heating installation, there is refrigeration plant again, heating installation spring and autumn three quarters are all in idle state, and refrigeration plant is in the winter time in idle State so that the utilization rate of heating installation and refrigeration plant is not high, huge waste be present.A kind of therefore it provides air-conditioning dress Put, the function of heating and refrigeration can be had concurrently, be those skilled in the art's technical problem urgently to be resolved hurrily.
The content of the invention
It is cold and hot double for journey piping installation, building air-conditioner device, overcoming that the utility model provides a kind of skyscraper The deficiency of above-mentioned prior art, it can be effectively solved existing for existing heating installation and refrigeration plant, high rise building heating or drop Temperature is by high segment, middle section and lower curtate division, and the heat supply brought and cooling pipeline system partitioning subsystem are set, existing pipe Road system utilization rate is not high, the problem of huge waste be present.
The first technical scheme of the present utility model is realized by following measures:A kind of cold and hot double confessions of skyscraper Supplied water with journey piping installation, including thermal power plant unit, refrigeration unit, the first delivery pipe, the second delivery pipe, the 3rd delivery pipe, interlayer Pipe, interlayer return pipe, thermal power plant unit are fixedly mounted on top, and refrigeration unit is fixedly mounted on bottom;The high temperature of thermal power plant unit goes out The mouth of a river connects with the upper end of the first delivery pipe, and the top of the first delivery pipe is serially connected with the first stop valve;The low temperature of thermal power plant unit returns The mouth of a river connects with the upper end of the second delivery pipe, and the top of the second delivery pipe is serially connected with the second stop valve;The upper end of 3rd delivery pipe Connected with the second delivery pipe below the second stop valve, the top of the 3rd delivery pipe is serially connected with the 3rd stop valve;Refrigeration unit Low temperature delivery port connects with the lower end of the first delivery pipe, and the bottom of the first delivery pipe is serially connected with the 4th stop valve;Refrigeration unit High-temperature tempering mouth connects with the lower end of the second delivery pipe, and the bottom of the second delivery pipe is serially connected with the 5th stop valve;3rd delivery pipe Lower end connected with the second delivery pipe above the 5th stop valve, the bottom of the 3rd delivery pipe is serially connected with the 6th stop valve;First At least two interlayer feed pipes are parallel with the first delivery pipe between stop valve and the 4th stop valve;3rd stop valve and the 6th At least two interlayer return pipes are accordingly parallel with the 3rd delivery pipe between stop valve;Each interlayer feed pipe with it is corresponding At least two recuperated cycle sections are parallel between interlayer return pipe.
Here is the further optimization and/or improvements to above-mentioned utility model technical scheme:
Above-mentioned skyscraper is cold and hot double for also being followed with journey piping installation including the user corresponding with each recuperated cycle section Ring segment.
Second of technical scheme of the present utility model is realized by following measures:A kind of cold and hot double confessions of skyscraper Supplied water with journey piping installation, including thermal power plant unit, refrigeration unit, the first delivery pipe, the second delivery pipe, the 3rd delivery pipe, interlayer Pipe, interlayer return pipe, refrigeration unit are fixedly mounted on top, and thermal power plant unit is fixedly mounted on bottom;The high temperature of refrigeration unit goes out The mouth of a river connects with the upper end of the first delivery pipe, and the top of the first delivery pipe is serially connected with the first stop valve;The low temperature of refrigeration unit returns The mouth of a river connects with the upper end of the second delivery pipe, and the top of the second delivery pipe is serially connected with the second stop valve;The upper end of 3rd delivery pipe Connected with the second delivery pipe below the second stop valve, the top of the 3rd delivery pipe is serially connected with the 3rd stop valve;Thermal power plant unit Low temperature delivery port connects with the lower end of the first delivery pipe, and the bottom of the first delivery pipe is serially connected with the 4th stop valve;Thermal power plant unit High-temperature tempering mouth connects with the lower end of the second delivery pipe, and the bottom of the second delivery pipe is serially connected with the 5th stop valve;3rd delivery pipe Lower end connected with the second delivery pipe above the 5th stop valve, the bottom of the 3rd delivery pipe is serially connected with the 6th stop valve;First At least two interlayer feed pipes are parallel with the first delivery pipe between stop valve and the 4th stop valve;Second stop valve and the 5th At least two interlayer return pipes are accordingly parallel with the second delivery pipe between stop valve;Each interlayer feed pipe with it is corresponding At least two recuperated cycle sections are parallel between interlayer return pipe.
Here is the further optimization and/or improvements to above-mentioned utility model technical scheme:
Above-mentioned skyscraper is cold and hot double for also being followed with journey piping installation including the user corresponding with each recuperated cycle section Ring segment.
The third technical scheme of the present utility model is realized by following measures:One kind uses above-mentioned skyscraper Cold and hot double building air-conditioner devices for journey piping installation, including building body and piping shaft, building body are internally provided with through type The piping shaft in lower direction, thermal power plant unit are fixedly mounted on the top of building body, and refrigeration unit is fixedly mounted on the bottom of building body, and first Delivery pipe, the second delivery pipe, the 3rd delivery pipe are respectively and fixedly installed to the inside of piping shaft.
4th kind of technical scheme of the present utility model is realized by following measures:One kind uses above-mentioned skyscraper Cold and hot double building air-conditioner devices for journey piping installation, including building body and piping shaft, building body are internally provided with through type The piping shaft in lower direction, refrigeration unit are fixedly mounted on the top of building body, and thermal power plant unit is fixedly mounted on the bottom of building body, and first Delivery pipe, the second delivery pipe, the 3rd delivery pipe are respectively and fixedly installed to the inside of piping shaft.
The utility model reasonable and compact in structure, easy to use, it adds a refrigeration on the basis of heating installation Unit, refrigeration unit share a set of pipeline system with thermal power plant unit, by the control of stop valve, when heating in the winter time, opened Dynamic thermal power plant unit simultaneously opens corresponding stop valve, you can is supplied by the first delivery pipe, the second delivery pipe, the 3rd delivery pipe for user Heat;When refrigeration is needed in summer, start refrigeration unit and simultaneously open corresponding stop valve, you can by the first delivery pipe, second defeated It is user's cooling to send pipe, the 3rd delivery pipe;The utility model has just been provided simultaneously with the function of heat supply and cooling, improves heat supply dress The utilization rate of pipeline is put, meanwhile, user need not purchase the refrigeration plants such as air-conditioning, fan in summer, it is possible to enjoy and be similar to The cooling service of central heating, reduce the spending of buying refrigeration plant, it is not necessary to refrigeration plant, section are installed and placed in house The about interior space, it is identical with traditional central heating pattern using this refrigeration modes, there are quiet, cleaning, energy-conserving and environment-protective Advantage;The utility model is set by rational pipeline, stop valve, can make each recuperated cycle section to thermal power plant unit/system The stroke of cold group is identical, so that pressure loss of the heating agent/refrigerant when reaching each recuperated cycle section is identical, and then It ensure that temperature when heating agent/refrigerant reaches each recuperated cycle section, flow are identical, avoid the occurrence of situation uneven in temperature, Avoid to increase the temperature of some recuperated cycle section, flow increases the power of whole thermal power plant unit/refrigeration unit, save energy Source, energy waste is reduced, there is the characteristics of same Cheng Pingheng of cold and hot waterpower, safe, laborsaving, easy, efficient.
Brief description of the drawings
Accompanying drawing 1 is the main structure diagram of the utility model embodiment one.
Accompanying drawing 2 is the main structure diagram of the utility model embodiment two.
Accompanying drawing 3 is the main view broken section structural representation of the utility model embodiment three.
Accompanying drawing 4 is the main view broken section structural representation of the utility model embodiment four.
Coding in accompanying drawing is respectively:1 is thermal power plant unit, and 2 be refrigeration unit, and 3 be the first delivery pipe, and 4 be the second conveying Pipe, 5 be the 3rd delivery pipe, and 6 be interlayer feed pipe, and 7 be interlayer return pipe, and 8 be the first stop valve, and 9 be the second stop valve, and 10 are 3rd stop valve, 11 be the 4th stop valve, and 12 be the 5th stop valve, and 13 be the 6th stop valve, and 14 be recuperated cycle section, and 15 be use Family circulation section, 16 be building body, and 17 be piping shaft.
Embodiment
The utility model is not limited by following embodiments, can according to the technical solution of the utility model and actual conditions come Determine specific embodiment.
In the utility model, for the ease of description, the description of the relative position relation of each part is according to specification The Butut mode of accompanying drawing 1 is described, such as:The position relationship of forward and backward, upper and lower, left and right etc. is according to Figure of description Butut direction determine.
The utility model is further described with reference to embodiment and accompanying drawing:
Embodiment one:As shown in Figure 1, the skyscraper is cold and hot double for including thermal power plant unit 1, refrigeration with journey piping installation Unit 2, the first delivery pipe 3, the second delivery pipe 4, the 3rd delivery pipe 5, interlayer feed pipe 6, interlayer return pipe 7, thermal power plant unit 1 are solid Dingan County is mounted in top, and refrigeration unit 2 is fixedly mounted on bottom;The high-temperature water outlet mouth of thermal power plant unit 1 and the upper end of the first delivery pipe Connection, the top of the first delivery pipe is serially connected with the first stop valve 8;The low-temperature return water mouth of thermal power plant unit 1 is upper with the second delivery pipe End connection, the top of the second delivery pipe is serially connected with the second stop valve 9;The upper end of 3rd delivery pipe 5 and the lower section of the second stop valve 9 Second delivery pipe connects, and the top of the 3rd delivery pipe is serially connected with the 3rd stop valve 10;The low temperature delivery port of refrigeration unit 2 and first The lower end connection of delivery pipe, the bottom of the first delivery pipe is serially connected with the 4th stop valve 11;The high-temperature tempering mouth of refrigeration unit 2 and The lower end connection of two delivery pipes, the bottom of the second delivery pipe is serially connected with the 5th stop valve 12;The lower end and the 5th of 3rd delivery pipe 5 The second delivery pipe connection of the top of stop valve 12, the bottom of the 3rd delivery pipe is serially connected with the 6th stop valve 13;First stop valve 8 with At least two interlayer feed pipes 6 are parallel with the first delivery pipe between 4th stop valve 11;3rd stop valve 10 and the 6th section Only at least two interlayer return pipes 7 are accordingly parallel with the 3rd delivery pipe 5 between valve 13;Each interlayer feed pipe 6 with it is right At least two recuperated cycle sections 14 are parallel between the interlayer return pipe 7 answered.The utility model is on the basis of related heating installation On add a refrigeration unit 2, refrigeration unit 2 shares a set of delivery pipe with thermal power plant unit 1, by the control of stop valve, During heat supply in winter, start thermal power plant unit 1 and simultaneously open corresponding stop valve, you can pass through the first delivery pipe 3, the second delivery pipe 4, the Three delivery pipes 5 are user's heat supply;When refrigeration is needed in summer, start refrigeration unit 2 and open corresponding stop valve, you can pass through First delivery pipe 3, the second delivery pipe 4, the 3rd delivery pipe 5 are user's cooling.So, the utility model has just been provided simultaneously with heat supply With the function of cooling, the utilization rate of heating plant pipeline is improved, meanwhile, user need not purchase the system such as air-conditioning, fan in summer Cool equipment, it is possible to enjoy the cooling service similar to central heating, reduce the spending of buying refrigeration plant, it is not necessary in room Refrigeration plant is installed and placed within doors, saves the interior space, it is identical with traditional central heating pattern using this refrigeration modes, The advantages of with quiet, cleaning, energy-conserving and environment-protective.During heat supply in winter, the first stop valve 8, the second stop valve 9, the 6th stop valve 13 Open, the 3rd stop valve 10, the 4th stop valve 11, the 5th stop valve 12 are closed, and start thermal power plant unit 1, by supplying High-temperature water after heat engine group 1 heats passes through the first delivery pipe 3, interlayer feed pipe 6, recuperated cycle section 14, interlayer return pipe successively 7th, the 3rd delivery pipe 5 returns to the second delivery pipe 4, and low-temperature return water is transported in thermal power plant unit 1 by the second delivery pipe 4, so as to complete Heating cycle;During summer cooling, the 3rd stop valve 10, the 4th stop valve 11, the 5th stop valve 12 are opened, the first stop valve 8, Second stop valve 9, the 6th stop valve 13 are closed, and start refrigeration unit 2, the low temperature after the refrigeration of refrigeration unit 2 Water returns to the by the first delivery pipe 3, interlayer feed pipe 6, recuperated cycle section 14, interlayer return pipe 7, the 3rd delivery pipe 5 successively High-temperature tempering is transported in refrigeration unit 2 by two delivery pipes 4, the second delivery pipe 4, so as to complete cooling circulation, refrigeration unit 2 For public technology, such as air-conditioning, fan." same to journey " described in the utility model refers to that heating agent is delivered to from thermal power plant unit Each recuperated cycle section, and it is identical from the recuperated cycle section to return to the stroke that thermal power plant unit passed by;Or refer to refrigerant from system Cold group is delivered to each recuperated cycle section, and it is identical from the recuperated cycle section to return to the stroke that refrigeration unit passed by.By Identical in stroke of the heating agent between thermal power plant unit and each recuperated cycle section, refrigerant follows in refrigeration unit and each heat exchange Stroke between ring segment is identical, so pressure loss is identical, temperature, flow phase when heating agent reaches each recuperated cycle section Together, the temperature, flow when refrigerant reaches each recuperated cycle section are identical, occur so as to avoid between each recuperated cycle section Phenomenon uneven in temperature, the cold and hot same Cheng Pingheng of waterpower, the energy is greatlyd save, reduce energy waste, more energy-conserving and environment-protective.
Can be according to being actually needed, cold and hot to above-mentioned skyscraper pair for further optimizing or/and changing with journey piping installation Enter:
As shown in Figure 1, above-mentioned skyscraper is cold and hot double for also including and each recuperated cycle section 14 with journey piping installation Corresponding user's circulation section 15.User's circulation section 15 can carry out heat exchange with recuperated cycle section 14, so as to be obtained in summer Cooling service is obtained, obtains heat supply service in the winter time.
Embodiment two:As shown in Figure 2, the skyscraper is cold and hot double for including thermal power plant unit 1, refrigeration with journey piping installation Unit 2, the first delivery pipe 3, the second delivery pipe 4, the 3rd delivery pipe 5, interlayer feed pipe 6, interlayer return pipe 7, refrigeration unit 2 are solid Dingan County is mounted in top, and thermal power plant unit 1 is fixedly mounted on bottom;The high-temperature water outlet mouth of refrigeration unit 2 and the upper end of the first delivery pipe Connection, the top of the first delivery pipe is serially connected with the first stop valve 8;The low-temperature return water mouth of refrigeration unit 2 is upper with the second delivery pipe End connection, the top of the second delivery pipe is serially connected with the second stop valve 9;The upper end of 3rd delivery pipe 5 and the lower section of the second stop valve 9 Second delivery pipe connects, and the top of the 3rd delivery pipe is serially connected with the 3rd stop valve 10;The low temperature delivery port of thermal power plant unit 1 and first The lower end connection of delivery pipe, the bottom of the first delivery pipe is serially connected with the 4th stop valve 11;The high-temperature tempering mouth of thermal power plant unit 1 and The lower end connection of two delivery pipes, the bottom of the second delivery pipe is serially connected with the 5th stop valve 12;The lower end and the 5th of 3rd delivery pipe 5 The second delivery pipe connection of the top of stop valve 12, the bottom of the 3rd delivery pipe is serially connected with the 6th stop valve 13;First stop valve 8 with At least two interlayer feed pipes 6 are parallel with the first delivery pipe between 4th stop valve 11;Second stop valve 9 and the 5th cut-off At least two interlayer return pipes 7 are accordingly parallel with the second delivery pipe between valve 12;Each interlayer feed pipe 6 with it is corresponding At least two recuperated cycle sections 14 are parallel between interlayer return pipe 7.The present embodiment and embodiment one are essentially identical, its difference Be in:Refrigeration unit 2 is fixedly mounted on top, and thermal power plant unit 1 is fixedly mounted on bottom.
Can be according to being actually needed, cold and hot to above-mentioned skyscraper pair for further optimizing or/and changing with journey piping installation Enter:
As shown in Figure 2, above-mentioned skyscraper is cold and hot double for also including and each recuperated cycle section 14 with journey piping installation Corresponding user's circulation section 15.User's circulation section 15 can carry out heat exchange with recuperated cycle section 14, so as to be obtained in summer Cooling service is obtained, obtains heat supply service in the winter time.
Embodiment three:As shown in Figure 3, this is cold and hot double for journey piping installation using the skyscraper described in embodiment one Building air-conditioner device, including building body 16 and piping shaft 17, the piping shaft for being internally provided with through type above-below direction of building body 16 17, thermal power plant unit 1 is fixedly mounted on the top of building body 16, and refrigeration unit 2 is fixedly mounted on the bottom of building body 16, the first conveying Pipe, the second delivery pipe, the 3rd delivery pipe are respectively and fixedly installed to the inside of piping shaft 17.So, the utility model supplies in correlation A refrigeration unit 2 is added on the basis of thermal, coordinates the use of stop valve, while realizes heat supply and cooling function, Heat supply and refrigeration share a set of delivery pipe, it is not necessary to set up delivery pipe in addition, reduce construction cost, while save the sky of piping shaft 17 Between so that piping shaft 17 need not be made big, reduce space waste.
Example IV:As shown in Figure 4, this is cold and hot double for journey piping installation using the skyscraper described in embodiment two Building air-conditioner device, including building body 16 and piping shaft 17, the piping shaft for being internally provided with through type above-below direction of building body 16 17, refrigeration unit 2 is fixedly mounted on the top of building body 16, and thermal power plant unit 1 is fixedly mounted on the bottom of building body 16, the first conveying Pipe, the second delivery pipe, the 3rd delivery pipe are respectively and fixedly installed to the inside of piping shaft 17.The present embodiment and three basic phase of embodiment Together, its difference is:Refrigeration unit 2 is fixedly mounted on the top of building body 16, and thermal power plant unit 1 is fixedly mounted on building body 16 Bottom.
Application method during three heat supply in winter of embodiment one and embodiment, is carried out in accordance with the following steps:
The first step, open the first stop valve 8, the second stop valve 9 and the 6th stop valve 13;
Second step, close the 3rd stop valve 10, the 4th stop valve 11 and the 5th stop valve 12;
3rd step, start thermal power plant unit 1.
Application method during three cooling in summer of embodiment one and embodiment, is carried out in accordance with the following steps:
The first step, open the 3rd stop valve 10, the 4th stop valve 11 and the 5th stop valve 12;
Second step, close the first stop valve 8, the second stop valve 9 and the 6th stop valve 13;
3rd step, start refrigeration unit 2.
Application method when embodiment two and example IV cooling in summer, is carried out in accordance with the following steps:
The first step, open the first stop valve 8, the second stop valve 9 and the 6th stop valve 13;
Second step, close the 3rd stop valve 10, the 4th stop valve 11 and the 5th stop valve 12;
3rd step, start refrigeration unit 2.
Application method when embodiment two and example IV heat supply in winter, is carried out in accordance with the following steps:
The first step, open the 3rd stop valve 10, the 4th stop valve 11 and the 5th stop valve 12;
Second step, close the first stop valve 8, the second stop valve 9 and the 6th stop valve 13;
3rd step, start thermal power plant unit 1.
The utility model by rational pipeline, stop valve set, can make each recuperated cycle section to thermal power plant unit/ The stroke of refrigeration unit is identical, so that pressure loss of the heating agent/refrigerant when reaching each recuperated cycle section is identical, enters And ensure that temperature when heating agent/refrigerant reaches each recuperated cycle section, flow are identical, avoid the occurrence of feelings uneven in temperature Condition, avoid to increase the temperature of some recuperated cycle section, flow increases the power of whole thermal power plant unit/refrigeration unit, section The about energy, reduce energy waste.
Above technical characteristic constitutes embodiment of the present utility model, and it has stronger adaptability and implementation result, can According to the non-essential technical characteristic of increase and decrease is actually needed, to meet the needs of different situations.

Claims (6)

1. a kind of skyscraper is cold and hot double for journey piping installation, it is characterised in that including thermal power plant unit, refrigeration unit, first defeated Pipe, the second delivery pipe, the 3rd delivery pipe, interlayer feed pipe, interlayer return pipe are sent, thermal power plant unit is fixedly mounted on top, refrigeration Unit is fixedly mounted on bottom;The high-temperature water outlet mouth of thermal power plant unit connects with the upper end of the first delivery pipe, the first delivery pipe it is upper Portion is serially connected with the first stop valve;The low-temperature return water mouth of thermal power plant unit connects with the upper end of the second delivery pipe, the second delivery pipe it is upper Portion is serially connected with the second stop valve;The upper end of 3rd delivery pipe connects with the second delivery pipe below the second stop valve, the 3rd conveying The top of pipe is serially connected with the 3rd stop valve;The low temperature delivery port of refrigeration unit connects with the lower end of the first delivery pipe, the first conveying The bottom of pipe is serially connected with the 4th stop valve;The high-temperature tempering mouth of refrigeration unit connects with the lower end of the second delivery pipe, the second conveying The bottom of pipe is serially connected with the 5th stop valve;The lower end of 3rd delivery pipe connects with the second delivery pipe above the 5th stop valve, the The bottom of three delivery pipes is serially connected with the 6th stop valve;It is parallel with the first delivery pipe between first stop valve and the 4th stop valve At least two interlayer feed pipes;At least two are accordingly parallel with the 3rd delivery pipe between 3rd stop valve and the 6th stop valve Individual interlayer return pipe;At least two recuperated cycle sections are each parallel between interlayer feed pipe and corresponding interlayer return pipe.
2. skyscraper according to claim 1 is cold and hot double for journey piping installation, it is characterised in that skyscraper is cold and hot It is double to supply also to include the user circulation section corresponding with each recuperated cycle section with journey piping installation.
3. the cold and hot double building air-conditioner devices for journey piping installation of skyscraper described in a kind of usage right requirement 1 or 2, its It is characterised by including building body and piping shaft, the piping shaft for being internally provided with through type above-below direction of building body, thermal power plant unit is fixed Installed in the top of building body, refrigeration unit is fixedly mounted on the bottom of building body, the first delivery pipe, the second delivery pipe, the 3rd conveying Pipe is respectively and fixedly installed to the inside of piping shaft.
4. a kind of skyscraper is cold and hot double for journey piping installation, it is characterised in that including thermal power plant unit, refrigeration unit, first defeated Pipe, the second delivery pipe, the 3rd delivery pipe, interlayer feed pipe, interlayer return pipe are sent, refrigeration unit is fixedly mounted on top, heat supply Unit is fixedly mounted on bottom;The high-temperature water outlet mouth of refrigeration unit connects with the upper end of the first delivery pipe, the first delivery pipe it is upper Portion is serially connected with the first stop valve;The low-temperature return water mouth of refrigeration unit connects with the upper end of the second delivery pipe, the second delivery pipe it is upper Portion is serially connected with the second stop valve;The upper end of 3rd delivery pipe connects with the second delivery pipe below the second stop valve, the 3rd conveying The top of pipe is serially connected with the 3rd stop valve;The low temperature delivery port of thermal power plant unit connects with the lower end of the first delivery pipe, the first conveying The bottom of pipe is serially connected with the 4th stop valve;The high-temperature tempering mouth of thermal power plant unit connects with the lower end of the second delivery pipe, the second conveying The bottom of pipe is serially connected with the 5th stop valve;The lower end of 3rd delivery pipe connects with the second delivery pipe above the 5th stop valve, the The bottom of three delivery pipes is serially connected with the 6th stop valve;It is parallel with the first delivery pipe between first stop valve and the 4th stop valve At least two interlayer feed pipes;At least two are accordingly parallel with the second delivery pipe between second stop valve and the 5th stop valve Individual interlayer return pipe;At least two recuperated cycle sections are each parallel between interlayer feed pipe and corresponding interlayer return pipe.
5. skyscraper according to claim 4 is cold and hot double for journey piping installation, it is characterised in that skyscraper is cold and hot It is double to supply also to include the user circulation section corresponding with each recuperated cycle section with journey piping installation.
6. the cold and hot double building air-conditioner devices for journey piping installation of skyscraper described in a kind of usage right requirement 4 or 5, its It is characterised by including building body and piping shaft, the piping shaft for being internally provided with through type above-below direction of building body, refrigeration unit is fixed Installed in the top of building body, thermal power plant unit is fixedly mounted on the bottom of building body, the first delivery pipe, the second delivery pipe, the 3rd conveying Pipe is respectively and fixedly installed to the inside of piping shaft.
CN201621482882.0U 2016-12-30 2016-12-30 Skyscraper is cold and hot double for journey piping installation, building air-conditioner device Active CN206670117U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621482882.0U CN206670117U (en) 2016-12-30 2016-12-30 Skyscraper is cold and hot double for journey piping installation, building air-conditioner device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621482882.0U CN206670117U (en) 2016-12-30 2016-12-30 Skyscraper is cold and hot double for journey piping installation, building air-conditioner device

Publications (1)

Publication Number Publication Date
CN206670117U true CN206670117U (en) 2017-11-24

Family

ID=60356936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621482882.0U Active CN206670117U (en) 2016-12-30 2016-12-30 Skyscraper is cold and hot double for journey piping installation, building air-conditioner device

Country Status (1)

Country Link
CN (1) CN206670117U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106595124A (en) * 2016-12-30 2017-04-26 何宗衡 Cooling and heating equal pipeline device for high-rise building, air conditioner for building and use method of air conditioner for building
CN114261499A (en) * 2021-12-20 2022-04-01 中船邮轮科技发展有限公司 Hot drinking water distribution system for mail steamer

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106595124A (en) * 2016-12-30 2017-04-26 何宗衡 Cooling and heating equal pipeline device for high-rise building, air conditioner for building and use method of air conditioner for building
CN114261499A (en) * 2021-12-20 2022-04-01 中船邮轮科技发展有限公司 Hot drinking water distribution system for mail steamer
CN114261499B (en) * 2021-12-20 2024-05-14 中船邮轮科技发展有限公司 Post wheel hot drink water distribution system

Similar Documents

Publication Publication Date Title
CN103542614B (en) heating and refrigerating system
CN107763726B (en) heat pump system
CN206670117U (en) Skyscraper is cold and hot double for journey piping installation, building air-conditioner device
CN203949271U (en) A kind of domestic heating and Living Water one water system
CN206651620U (en) A kind of energy-saving variable-temperature mattress
CN202511359U (en) Combined station sewage waste heat direct heating system
CN204678563U (en) Large-scale water-loop heat pump system
CN105571151B (en) A kind of solar magnetic suspension central air-conditioning heating system
CN204962942U (en) Carbon dioxide heat pump heating device
CN204100645U (en) A kind of geothermal heat pump air-conditioner and hot-water heating system
CN103758591A (en) Heat supplying system for generating power by recycling steam as function force
CN204026891U (en) Recuperation of heat ladder-elevating temperature and water inflow control system
CN207881280U (en) Heat pump monoblock type Cooling and Heat Source computer room
CN103471192B (en) Multiple Air Conditioning System with Heat and operation method thereof
CN202769858U (en) Multi-user ground source heat pump air conditioning system
CN104676928A (en) Coil pipe auxiliary heating double-container type water tank of solar and heat pump water heater
CN106595124A (en) Cooling and heating equal pipeline device for high-rise building, air conditioner for building and use method of air conditioner for building
CN107387259A (en) A kind of heating available for cold, heat and electricity triple supply, the refrigeration system available for cold, heat and electricity triple supply and cold, heat and power triple supply system
CN103174474A (en) System used for improving combined cycle generator set vacuumizing efficiency and saving air conditioner power utilization
CN102914000A (en) Fresh air humidification air-conditioning unit
CN204313478U (en) A kind of once-through cycle formula air-source water heater
CN203893298U (en) Novel domestic heater
CN209376399U (en) The recycling of farm's thermal energy and heating system
CN203385201U (en) Split heat pump water heater
CN203274352U (en) Air conditioner heat pump hot water and solar energy heating integrated system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20181220

Address after: 830000 Xinjiang Uygur Autonomous Region Urumqi High-tech Industrial Development Zone (New Urban District) North District 21

Patentee after: Xinjiang Constan energy Limited by Share Ltd

Address before: 830000 Xinjiang Uygur Autonomous Region Urumqi High-tech Zone North District 21 Xinjiang Kangsjia Cold and Heating Equipment Company

Patentee before: He Zongheng

TR01 Transfer of patent right