CN206656713U CN201720295725.7U CN201720295725U CN206656713U CN 206656713 U CN206656713 U CN 206656713U CN 201720295725 U CN201720295725 U CN 201720295725U CN 206656713 U CN206656713 U CN 206656713U
Authority
CN
China
Prior art keywords
magnet ring
vertical settlement
testing tube
sleeve pipe
locating ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720295725.7U
Other languages
Chinese (zh)
Inventor
姜永涛
姜克寒
周中
高东东
杨光
张齐芳
岳志坤
杨金庞
朱辉
张家贺
耿石军
周成丰
汪志峰
李光山
李丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Sinohydro Bureau 8 Co Ltd
PowerChina Railway Construction Co Ltd
Original Assignee
Central South University
Sinohydro Bureau 8 Co Ltd
PowerChina Railway Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University, Sinohydro Bureau 8 Co Ltd, PowerChina Railway Construction Co Ltd filed Critical Central South University
Priority to CN201720295725.7U priority Critical patent/CN206656713U/en
Application granted granted Critical
Publication of CN206656713U publication Critical patent/CN206656713U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of deep rock mass or the Vertical Settlement magnet ring structure of soil body sedimentation and deformation test device,Vertical Settlement magnet ring (5) is covered in the outer surface of outer connection sleeve pipe (4),And can be in certain scope in described outer connection sleeve pipe (4) freely up and down slip,The both ends of described Vertical Settlement magnet ring (5) are equipped with rubber spring set (5 1),The port of each described rubber spring set (5 1) is provided with locating ring (5 2),Each described locating ring (5 2) is provided with multiple locating ring fastening screws (5 3),Described rubber spring set (5 1) is enclosed in described outer connection sleeve pipe (4),Described locating ring (5 2) location sealing is on described testing tube (3),Described locating ring (5 2) is fixed on described testing tube (3) by described locating ring fastening screw (5 3).The utility model can be greatly enhanced measuring accuracy.The high-precision safety monitoring project of various requirement can be better met, such as applies to the deformation monitoring of tunnel, high slope, deep basal pit and dam body.

Description

The Vertical Settlement magnet ring structure of deep rock mass or soil body sedimentation and deformation test device
Technical field
A kind of sedimentation magnet ring structure is the utility model is related to, a kind of deep rock mass or the soil body sedimentation and deformation is specifically related to and surveys The Vertical Settlement magnet ring structure that trial assembly is put.
Background technology
With the development of China's economic society, the development foundation Facilities Construction of country energetically, engineering project is increasingly pursued The security of construction, the working security monitoring and life-cycle monitoring of project are taken seriously especially.As tunnel, high slope, deep basal pit and The deformation monitoring of the projects such as dam body is to construction and safe to use plays very big forewarning function.For the Deep Rock soil on project periphery Body deformation monitoring pursues high-frequency, high precision.The magnet ring of existing measurement Deep Rock soil body Vertical Settlement is positioned using separate type Ring constraint is slided thereon, but is easy to make its downslide when drilling and backfilling, and can not be embedded in projected depth.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of Deep Rock soil body that can meet project periphery and carried out With high-frequency, high precision deformation monitoring, with good integrity, good seal and it is a range of slidably The deep rock mass of property or the Vertical Settlement magnet ring structure of soil body sedimentation and deformation test device.
In order to solve the above-mentioned technical problem, deep rock mass or the soil body sedimentation and deformation test device provided by the utility model Vertical Settlement magnet ring structure, including testing tube and Vertical Settlement magnet ring, described Vertical Settlement magnet ring are enclosed on described testing tube Outer surface, and can be in certain scope on described testing tube freely up and down slip, or the testing tube described in more Between connected by outer connection sleeve pipe, described Vertical Settlement magnet ring is enclosed on the outer surface of described outer connection sleeve pipe, and can be Slip in certain scope in described outer connection sleeve pipe freely up and down, the both ends of described Vertical Settlement magnet ring are equipped with Rubber spring set, the port of each described rubber spring set are provided with locating ring, and it is multiple fixed that each described locating ring is provided with Position ring fastening screw, described rubber spring set are enclosed on described testing tube or in described outer connection sleeve pipe, and described determines For position ring location sealing on described testing tube, described locating ring is fixed on described survey by described locating ring fastening screw On test tube.
Described rubber spring set is tubbiness, and upper and lower two parts are seamless with described Vertical Settlement magnet ring top and bottom respectively Knot, described rubber spring set stress can slide up and down >=± 30mm in the range of stretch, ensure described Vertical Settlement magnet ring With suitable range.
Described locating ring is enclosed on the both ends of described rubber spring set, and its internal diameter can be adjusted, and pass through described positioning Ring fastening screw fastens, and ensures that described Vertical Settlement magnet ring is overall and forms closed cavity with described testing tube, prevents miscellaneous Thing enters and influences described Vertical Settlement magnet ring and freely synchronously deformed with periphery rock mass or the soil body.
Described testing tube is the pvc pipe with interior grooves, and inside is clinometer probe provided with " ten " word cross recesses Roller guide groove.
Described outer connection sleeve pipe internal diameter is equal to the external diameter of described testing tube, and convex inside described outer connection sleeve pipe Rise and be engaged with described testing tube exterior groove.
The both ends of described outer connection sleeve pipe are close to relatively with described test pipe end, and tighten described outer adapter sleeve The screw at two of pipe is with fixation.
Using the deep rock mass of above-mentioned technical proposal or the Vertical Settlement magnet ring structure of soil body sedimentation and deformation test device, rubber Two parts cover stress to glue spring housing with described Vertical Settlement magnet ring top and bottom seamless coupling, described rubber spring respectively up and down It can within the specific limits stretch, ensure that Vertical Settlement magnet ring has suitable range.Locating ring is enclosed on the two of rubber spring set End, its internal diameter can be adjusted, and be fastened by locating ring fastening screw, and it is closed to ensure that Vertical Settlement magnet ring is integrally formed with testing tube Cavity, prevent debris from entering and influence Vertical Settlement magnet ring and freely synchronously deformed with periphery rock mass or the soil body..This practicality is new Type can be greatly enhanced measuring accuracy.The high-precision safety monitoring project of various requirement can be better met, such as apply to tunnel, The deformation monitoring of high slope, deep basal pit and dam body.
In summary, the utility model meets that the Deep Rock soil body on project periphery have high-frequency, high precision Deformation monitoring, the magnet ring for overcoming existing measurement Deep Rock soil body Vertical Settlement easily glide when drilling and backfilling, not Projected depth problem can be accurately embedded in, there is good integrity, good seal and a range of slidably property.
Brief description of the drawings
Fig. 1 is that testing tube of the present utility model lays overall schematic.
Fig. 2 is Vertical Settlement magnet ring of the present utility model and testing tube junction schematic diagram.
Fig. 3 is Vertical Settlement magnet ring overall schematic of the present utility model.
In figure:1st, measurement drilling;2nd, bottom;3rd, testing tube;4th, outer connection sleeve pipe;5th, Vertical Settlement magnet ring;5-1, rubber Spring housing;5-2, locating ring;5-3, locating ring fastening screw;6th, slip casting flexible pipe;7th, prefabricated backfill material pneumatic mortar machine;8th, tube top is tested Lid;9th, bung is protected.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
Referring to Fig. 2 and Fig. 3, a kind of Vertical Settlement magnet ring structure of deep rock mass or the soil body sedimentation and deformation test device, bag Testing tube 3, outer connection sleeve pipe 4 and Vertical Settlement magnet ring 5 are included, is connected between more testing tubes 3 by outer connection sleeve pipe 4, vertically 5 sets of magnet ring is settled in the outer surface of outer connection sleeve pipe 4, and can in certain scope outside in connection sleeve pipe 4 freely up and down Slide, the both ends of Vertical Settlement magnet ring 5 are equipped with rubber spring set 5-1, and each rubber spring set 5-1 port is provided with locating ring 5-2, each locating ring 5-2 are provided with multiple locating ring fastening screw 5-3, and rubber spring set 5-1 is covered in outer connection sleeve pipe 4, On testing tube 3, locating ring 5-2 is fixed on testing tube 3 locating ring 5-2 location sealings by locating ring fastening screw 5-3.
Preferably, rubber spring set 5-1 is tubbiness, and upper and lower two parts are seamless with the top and bottom of Vertical Settlement magnet ring 5 respectively Knot, rubber spring set 5-1 stress can slide up and down >=± 30mm in the range of stretch, ensure that described Vertical Settlement magnet ring 5 has There is suitable range.
Specifically, locating ring 5-2 is enclosed on rubber spring set 5-1 both ends, and its internal diameter can be adjusted, and be fastened by locating ring Screw 5-3 is fastened, and is ensured that Vertical Settlement magnet ring 5 is overall and is formed closed cavity with testing tube 3, prevents debris from entering and influence perpendicular Freely synchronously deformed with periphery rock mass or the soil body to sedimentation magnet ring 5.
Preferably, testing tube 3 is the pvc pipe with interior grooves, and inside is provided with " ten " word cross recesses and visited for inclinometer Head roller guide groove.
Specifically, the outer internal diameter of connection sleeve pipe 4 is equal to pvc pipe external diameter, and outside outer connection sleeve pipe internal protrusion and pvc pipe Groove is engaged.
Specifically, the both ends of outer connection sleeve pipe 4 are close to relatively with the described termination of testing tube 3, and tighten outer connection sleeve pipe 4 Two screw with fixation.
Referring to Fig. 1, Fig. 2 and Fig. 3, the utility model is applied to the deep layer of deep rock mass or soil body sedimentation and deformation test device Rock mass or soil body sedimentation and deformation method of testing, including instrument connection drills through, deep rock mass or the soil body vertical displacement test device installation, Instrument connection backfills and protection and apparatus measures.As shown in figure 1, first, certain depth is drilled through on design measuring point using drilling machine A diameter of 108mm joint tests drilling 1;Then deep rock mass or soil body sedimentation and deformation test device, installation steps bag are installed The installation of the bottom 2 of first testing tube 3 is included, is fixed the pipe end of slip casting flexible pipe 6 one and testing tube 3 and together, used with adhesive tape The outer connection of connection sleeve pipe 4 plus testing tube 3, install Vertical Settlement magnet ring 5 in the outer connection sleeve pipe 4 of each junction.It is vertical heavy Drop magnet ring 5 encloses rubber spring set 5-1, screwed in place ring fastening screw 5-3 by the locating ring 5-2 at two and fixed, progressively Repeat the above steps, during constantly toward clear water is filled in testing tube 3, transfer to installation top cover 8 behind position;Followed by pre- System backfill material pneumatic mortar machine 7 up injects prefabricated backfill to 1 bottom of measurement drilling by slip casting flexible pipe 6 and expected, during slip casting slowly Hoisting grouting flexible pipe 6.Stop backfill when backfill is away from mouth of pipe 1m or so, after filling settlement to be returned is closely knit, returned with concrete Ferrule is filled out, the backfill of measurement drilling 1 is measuring the hell installation protection cover 9 of drilling 1 after finishing.Finally, it is to be tested After device is stable, deep rock mass or soil body vertical displacement are measured with sedimentometer.
Another way, testing tube 3 are integral, and Vertical Settlement magnet ring 5 is enclosed on the outer surface of testing tube 3, and can be one Slip in fixed scope on testing tube 3 freely up and down, the two of Vertical Settlement magnet ring 5 is equipped with rubber spring set 5-1, each Rubber spring set 5-1 port is provided with multiple locating ring fastening screw 5-3, rubber provided with locating ring 5-2, each locating ring 5-2 Glue spring housing 5-1 is enclosed on testing tube 3, and on testing tube 3, locating ring fastening screw 5-3 will be positioned locating ring 5-2 location sealings Ring 5-2 is fixed on testing tube 3.
The utility model sedimentation magnetic ring device can be greatly enhanced measuring accuracy.It is high-precision various requirement to be better met The safety monitoring project of degree, such as apply to the deformation monitoring of tunnel, high slope, deep basal pit and dam body.

Claims (7)

1. the Vertical Settlement magnet ring structure of a kind of deep rock mass or soil body sedimentation and deformation test device, including testing tube (3) and perpendicular To sedimentation magnet ring (5), it is characterized in that:Described Vertical Settlement magnet ring (5) is enclosed on the outer surface of described testing tube (3), and energy Pass through between slip in certain scope on described testing tube (3) freely up and down, or testing tube (3) described in more The connection of outer connection sleeve pipe (4), described Vertical Settlement magnet ring (5) are enclosed on the outer surface of described outer connection sleeve pipe (4), and can be Slip in certain scope in described outer connection sleeve pipe (4) freely up and down, the both ends of described Vertical Settlement magnet ring (5) Rubber spring set (5-1) is equipped with, the port of each described rubber spring set (5-1) is provided with locating ring (5-2), each described Locating ring (5-2) be provided with multiple locating ring fastening screws (5-3), described rubber spring set (5-1) is enclosed on described survey On test tube (3) or in described outer connection sleeve pipe (4), described locating ring (5-2) location sealing is in described testing tube (3) On, described locating ring (5-2) is fixed on described testing tube (3) by described locating ring fastening screw (5-3).
2. the Vertical Settlement magnet ring structure of deep rock mass according to claim 1 or soil body sedimentation and deformation test device, its It is characterised by:Described rubber spring set (5-1) is tubbiness, upper and lower two parts respectively with described Vertical Settlement magnet ring (5) Seamless coupling below.
3. the Vertical Settlement magnet ring structure of deep rock mass according to claim 1 or soil body sedimentation and deformation test device, its It is characterised by:Described rubber spring set (5-1) stress can slide up and down >=± 30mm in the range of stretch.
4. the Vertical Settlement magnet ring structure of deep rock mass according to claim 1 or 2 or soil body sedimentation and deformation test device, It is characterized in that:Described locating ring (5-2) is enclosed on the both ends of described rubber spring set (5-1), and its internal diameter can be adjusted, and be led to Described locating ring fastening screw (5-3) fastening is crossed, ensures the overall and described testing tube of described Vertical Settlement magnet ring (5) (3) closed cavity is formed.
5. the Vertical Settlement magnet ring structure of deep rock mass according to claim 1 or 2 or soil body sedimentation and deformation test device, It is characterized in that:Described testing tube (3) is the pvc pipe with interior grooves, and inside is deviational survey provided with " ten " word cross recesses Instrument probe roller guide groove.
6. the Vertical Settlement magnet ring structure of deep rock mass according to claim 1 or 2 or soil body sedimentation and deformation test device, It is characterized in that:Described outer connection sleeve pipe (4) internal diameter is equal to the external diameter of described testing tube (3), and described outer connection Sleeve pipe (4) internal protrusion is engaged with described testing tube (3) exterior groove.
7. the Vertical Settlement magnet ring structure of deep rock mass according to claim 1 or 2 or soil body sedimentation and deformation test device, It is characterized in that:The both ends of described outer connection sleeve pipe (4) are close to relatively with described testing tube (3) termination, and tighten described Outer connection sleeve pipe (4) two screw with fixation.
CN201720295725.7U 2017-03-24 2017-03-24 The Vertical Settlement magnet ring structure of deep rock mass or soil body sedimentation and deformation test device Expired - Fee Related CN206656713U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720295725.7U CN206656713U (en) 2017-03-24 2017-03-24 The Vertical Settlement magnet ring structure of deep rock mass or soil body sedimentation and deformation test device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720295725.7U CN206656713U (en) 2017-03-24 2017-03-24 The Vertical Settlement magnet ring structure of deep rock mass or soil body sedimentation and deformation test device

Publications (1)

Publication Number Publication Date
CN206656713U true CN206656713U (en) 2017-11-21

Family

ID=60315715

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720295725.7U Expired - Fee Related CN206656713U (en) 2017-03-24 2017-03-24 The Vertical Settlement magnet ring structure of deep rock mass or soil body sedimentation and deformation test device

Country Status (1)

Country Link
CN (1) CN206656713U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109540014A (en) * 2018-11-06 2019-03-29 北京市政建设集团有限责任公司 One kind being used for tunnel tunnel face extrusion deformation monitoring method
CN112595287A (en) * 2020-11-25 2021-04-02 淮南冠东信息科技有限公司 Stratum settlement monitoring equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109540014A (en) * 2018-11-06 2019-03-29 北京市政建设集团有限责任公司 One kind being used for tunnel tunnel face extrusion deformation monitoring method
CN112595287A (en) * 2020-11-25 2021-04-02 淮南冠东信息科技有限公司 Stratum settlement monitoring equipment

Similar Documents

Publication Publication Date Title
CN206656709U (en) A kind of deep rock mass or soil deformation test backfilling apparatus
CN100535585C (en) Sleeve bore multidot tensiometer
CN106918322B (en) Horizontal and vertical deformation combined test method for deep rock mass or soil body
CN105403930A (en) Surrounding rock mining damage range segmented testing system
CN103996348A (en) Laboratory model test device for testing influence on operating tunnel from vertically-overlapped tunnel construction
CN204421889U (en) Ground layering perpendicular displacement monitoring device
CN105806712B (en) Hole internal water pressure test device and test macro
CN104697496B (en) Split type static hydraulic pressure difference settlement monitoring system and installation method thereof
CN203587075U (en) Building foundation pit slope horizontal displacement monitoring device
CN108332706B (en) Underground double-sleeve probe for borehole strain measurement
CN206656713U (en) The Vertical Settlement magnet ring structure of deep rock mass or soil body sedimentation and deformation test device
CN113125066B (en) Device and method for testing upper floating force of single-ring duct piece
CN106595548A (en) Displacement measuring method for the inner part of enclosing rock for tunnel inner face
CN205176296U (en) Destruction scope sectionalization test system is adopted to country rock
CN106643649B (en) Device and method for measuring deep settlement and pore water pressure of soil body
CN202562470U (en) Buried type foundation settlement observing device
CN107435325B (en) Recoverable pore water pressure and layered settlement observation device and use method thereof
CN106767662B (en) A kind of coal mine roadway country rock deep multipoint displacement meter
CN201000324Y (en) Casing tube type drilling multi-point extensometer
CN208432321U (en) A kind of silent method underground water level measurement device
CN102817605A (en) Method for accurately measuring elevation of drilling point in subterranean drilling
CN214503289U (en) Water pressure test device
CN206459650U (en) A kind of mangneto sedimentometer
CN210426413U (en) Multipoint displacement measuring system based on magnetic displacement sensor
CN210714663U (en) Device for testing gas flow while drilling

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant