CN206635750U - Manually digging hole pile enlarged foot dado structure - Google Patents
Manually digging hole pile enlarged foot dado structure Download PDFInfo
- Publication number
- CN206635750U CN206635750U CN201720086253.4U CN201720086253U CN206635750U CN 206635750 U CN206635750 U CN 206635750U CN 201720086253 U CN201720086253 U CN 201720086253U CN 206635750 U CN206635750 U CN 206635750U
- Authority
- CN
- China
- Prior art keywords
- hole wall
- enlarged footing
- enlarged
- steel floral
- floral tube
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
A kind of manually digging hole pile enlarged foot dado structure is disclosed in the utility model, at hole wall applied to the enlarged footing of artificial digging pile, including some steel floral tubes in the hole wall of the oblique insertion enlarged footing from top to bottom on vertical direction, the expanded metal lath that is fixedly welded on the part for the hole wall that the steel floral tube stretches out enlarged footing and be bonded fixed reinforced mesh with expanded metal lath, the expanded metal lath fits in the hole wall of enlarged footing, it adds the form of reinforcing bar reinforcement by injecting grout through steel perforated pipe, substitute existing man-made digging pile mould-pipe mode, to save the time of template construct and the duration of shortening, it is easy to operate, and reach basically identical retaining wall effect.
Description
Technical field
Hypogee construction field is the utility model is related to, more particularly to a kind of manually digging hole pile enlarged foot dado structure.
Background technology
Artificial digging pile refers to using artificial shoveling, cast-in-place reinforced concrete pile.The general diameter of artificial digging pile
It is larger, it is minimum also in 800 more than ㎜, the larger main structure body of base pressure can be carried.Artificial digging pile is because with construction
Technique is simple, convenient and quick construction, is not required to heavy mechanical equipment, more while can be widely used the advantages that construct.
The general work progress of artificial digging pile is:Some preparations such as place leveling, unwrapping wire, fixed pile are first carried out,
Then downward borehole is started until the depth required for engineering.It should be noted that cleaning stake holes perisporium and check stake holes during borehole
Diameter and perpendicularity, and support dado template is configured with excavation, between template and the hole wall of stake holes in region
Reinforced mesh and casting concrete are set, to form the dado structure of armored concrete.
However, for the enlarged footing of artificial digging pile, because its size is larger, shape is also general irregular, it is necessary to foundation
The expansion head shapes field fabrication template and assembly that practice of construction is encountered are welded and fixed, and the template that this process uses is without certain
Specification and size, it is necessary to make, construction period is longer.
Utility model content
The purpose of this utility model is to provide a kind of manually digging hole pile enlarged foot dado structure, and it passes through injecting grout through steel perforated pipe
Add the form of reinforcing bar reinforcement, substitute existing man-made digging pile mould-pipe mode, shorten work to save the time of template construct
It is phase, easy to operate, and reach basically identical retaining wall effect.
Above-mentioned purpose of the present utility model technical scheme is that:A kind of manually digging hole pile enlarged foot
Dado structure, at the hole wall applied to the enlarged footing of artificial digging pile, including on vertical direction described in oblique insertion from top to bottom
Some steel floral tubes in the hole wall of enlarged footing, the steel plate on the part for the hole wall for being fixedly welded on the steel floral tube stretching enlarged footing
Net and the reinforced mesh that fixation is bonded with expanded metal lath, the expanded metal lath fit in the hole wall of enlarged footing.
By using above-mentioned technical proposal, steel floral tube is squeezed on the hole wall at enlarged footing, then injected into steel floral tube
Cement mortar, treat that cement mortar is combined with surrounding soil and solidifies to form floral tube soil nailing, the soil body of its hole wall to enlarged footing plays can
The supporting role leaned on;With reference to the soil-baffling structure to be formed that is welded and fixed of expanded metal lath and steel floral tube, existing whitewashing retaining wall knot is substituted
Structure, construction is simple, earth-retaining are reliable;And the fixation of reinforced mesh and expanded metal lath, the booster action of degree of playing expanded metal lath.
Alternatively, a kind of manually digging hole pile enlarged foot dado structure, at the hole wall applied to the enlarged footing of artificial digging pile,
Including on vertical direction from bottom to top the steel floral tube in the hole wall of the oblique insertion enlarged footing, be fixedly welded on the steel floral tube
The expanded metal lath that stretches out on the part of the hole wall of enlarged footing and the reinforced mesh for be bonded fixation with expanded metal lath, the expanded metal lath are bonded
In the hole wall of enlarged footing.
By using above-mentioned technical proposal, compared with a upper scheme, by the insertion enlarged footing of steel floral tube from bottom to top
Hole wall, then in slip casting, it is necessary to coordinate the form of high-pressure slip-casting, the possibility of the hole wall of enlarged footing collapses direction as from top to bottom,
And steel floral tube is made into form of lifting from bottom to top, its thought is similar to pre-grouting, can effectively prevent the hole wall soil body
Stay.
Preferably, the spacing between the adjacent steel floral tube vertically is 0.5 meter.
By using above-mentioned technical proposal, 0.5 meter or so of steel floral tube interval can be while retaining wall intensity be ensured, no
Too many steel floral tube is consumed, with the economy of lifting construction.
Preferably, be provided with some cranses for fitting in hole wall in the hole wall of enlarged footing at different height, the cranse with
A circle spray of molten steel tube end at the height is welded and fixed.
By using above-mentioned technical proposal, cranse is adjacent to hole wall, equivalent to the hole wall from enlarged footing to the soil body around it
Expanded metal lath and reinforced mesh are pushed, also, cranse connects the steel floral tube at all sustained heights, can lift the branch of retaining wall
Protect effect.
Preferably, one end that the hole wall of enlarged footing is firstly inserted on the steel floral tube is provided with tip.
By using above-mentioned technical proposal, sophisticated setting, be advantageous to the process that hammers of steel floral tube, especially in excavated by manual work
At the enlarged footing of hole stake, construction space is limited, and one end of steel floral tube is made into tip, can reduce the power of hammering steel floral tube, from
And save large-scale hammering equipment.
Preferably, the stop grouting plug of sealing orifice is provided with the mouth of pipe of the steel floral tube.
By using above-mentioned technical proposal, after high-pressure slip-casting, the solidification of cement mortar needs a period of time, this period domestic demand
Prevent cement mortar from flowing out, the mouth of pipe of steel floral tube is blocked by stop grouting plug, prevent the cement mortar of press-in from flowing out the spray of molten steel before solidification
Pipe.
In summary, the utility model has the advantages that:Steel floral tube is squeezed on the hole wall at enlarged footing, then
Cement mortar is injected into steel floral tube, treats that cement mortar is combined with surrounding soil and solidifies to form floral tube soil nailing, its hole to enlarged footing
The soil body of wall plays reliable supporting role;With reference to the soil-baffling structure to be formed that is welded and fixed of expanded metal lath and steel floral tube, substitute existing
Some whitewashing dado structures, construction is simple, earth-retaining are reliable;And the fixation of reinforced mesh and expanded metal lath, degree of playing expanded metal lath add
Pretend use.
Brief description of the drawings
Fig. 1 is the structural representation of embodiment 1;
Fig. 2 is the Fig. 1 done for display reinforced mesh and steel plate web frame A portions enlarged drawing;
Fig. 3 be for clearly show that the position relationship of cranse set location and itself and steel floral tube does remove expanded metal lath and
The topology view of reinforced mesh;
Fig. 4 is the structural representation of embodiment 2;
Fig. 5 is the Fig. 4 done for display stop grouting plug set location B portions enlarged drawing.
In figure, 1, pile body hole;2nd, enlarged footing;3rd, steel floral tube;30th, it is sophisticated;31st, stop grouting plug;4th, cranse;5th, expanded metal lath;6、
Reinforced mesh.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
Embodiment 1
A kind of manually digging hole pile enlarged foot dado structure, the enlarged footing 2 applied to the lower end of pile body hole 1 of artificial digging pile
On, the retaining wall in pile body hole 1 is carried out in the form of steel form.
Oblique on the hole wall of enlarged footing 2 to be arranged with some steel floral tubes 3, spacing is 0.5 between neighbouring steel floral tube 3
Meter, the distance of the hole wall on sustained height between adjacent steel floral tube 3 along enlarged footing 2 is also 0.5 meter, and steel floral tube 3 squeezes into expansion
The depth of first 2 hole wall is at 0.7 to 1 meter.
For the ease of the process of squeezing into of steel floral tube 3, the end set of steel floral tube 3 has tip 30, should when squeezing into steel floral tube 3
It is initially positioned at when by tip 30 on the hole wall of enlarged footing 2, is then rammed into hole wall obliquely to desired depth.
Injection neat slurry in the steel floral tube 3 squeezed into, cement mortar is after steel floral tube 3 is entered along plum blossom hole and point thereon
The gap at end 30 flows into hole wall, to be reinforced to it.
One end of hole wall on steel floral tube 3 close to enlarged footing 2 is welded with one layer of expanded metal lath 5, and expanded metal lath 5 should cover
The hole wall of enlarged footing 2, to realize the effect of earth-retaining;The outside colligation of expanded metal lath 5 is welded with reinforced mesh 6, reinforcing bar
Mesh sheet 6 is welded the mesh sheet structure for forming 150*150 by some a diameter of 6.5 millimeters of reinforcing bar transverse and longitudinal.
The Longitudinal extending direction of the interior edge artificial digging pile of enlarged footing 2 is provided with some cranses 4, and cranse 4 is a diameter of by two sections
22 millimeters of reinforcing bar muscle of putting more energy into welds to be formed, and cranse 4 is welded and fixed to the end of the steel floral tube 3 of respective heights, and cranse 4 is with posting
The hole wall of the enlarged footing of reinforced mesh 6 contradicts, to play the effect for strengthening retaining wall intensity.
Embodiment 2
A kind of manually digging hole pile enlarged foot dado structure, the difference of itself and embodiment 1 are:Steel floral tube 3 is inserted obliquely
Enter, make the body of steel floral tube 3 obliquely.Now, during injection cement mortar into steel floral tube 3, it is necessary to using high-pressure slip-casting mode,
I.e.:Using grouting pump by water under high pressure mud inject steel floral tube 3, accordingly, at the mouth of pipe of steel floral tube 3 set plugging structure, with
High-pressure slip-casting is reliably blocked after terminating to the mouth of pipe of steel floral tube 3, prevents cement mortar from flowing out.
Plugging structure 3 includes:Sealing stoppers the stop grouting plug 31 in the mouth of pipe of steel floral tube 3, covers the steel floral tube 3 of stop grouting plug 31
One layer of waterproof membrane of mouth of pipe outer cladding, the edge of film is tightened to the outer wall of steel floral tube 3 by band or steel wire, to prevent water
The pressure of mud releases stop grouting plug 31.
Embodiment 3
A kind of manually digging hole pile enlarged foot dado structure construction method:
A diameter of 48 millimeters, the steel floral tube 3 that plum blossom hole aperture is 3.5 millimeters oblique are squeezed into expansion by step 1 using pipe rammer
On the hole wall of major part 2, the spacing of adjacent steel floral tube 3 is 0.5 meter;
Step 2 injects cement mortar into steel floral tube 3, now, when steel floral tube 3 the mouth of pipe obliquely when, using high-pressure slip-casting
Method, and add stop grouting plug 31 in the mouth of pipe,;When steel floral tube 3 the mouth of pipe obliquely when, in general common pressure grouting i.e. can be achieved;
Expanded metal lath 5 and steel floral tube 3 are welded and fixed by step 3 to the expanded metal lath 5 that is sticked on the hole wall of enlarged footing 2;
Step 4 weaves 150*150 reinforced mesh 6 with a diameter of 6.5 millimeters of reinforcing bar, and by it with colligation or weldering
The form connect is fixed with expanded metal lath 5;
Step 5 goes the reinforcing bar reinforcement of two 22 millimeters of diameters to bend to the hole wall for fitting in enlarged footing 2 and forms cranse 4,
Longitudinally disposed multiple cranses 4, the height of each cranse 4 corresponds to the height setting of each steel floral tube 3, to be carried out to both
It is welded and fixed.
This specific embodiment is only that it is not to limitation of the present utility model, ability to explanation of the present utility model
Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but
As long as all protected in right of the present utility model by Patent Law.
Claims (6)
1. a kind of manually digging hole pile enlarged foot dado structure, the enlarged footing applied to artificial digging pile(2)Hole wall at, its feature
It is:The enlarged footing is inserted including oblique from top to bottom on vertical direction(2)Hole wall in some steel floral tubes(3), welding it is solid
Due to the steel floral tube(3)Stretch out enlarged footing(2)Hole wall part on expanded metal lath(5)And and expanded metal lath(5)Fitting is solid
Fixed reinforced mesh(6), the expanded metal lath(5)Fit in enlarged footing(2)Hole wall.
2. a kind of manually digging hole pile enlarged foot dado structure, the enlarged footing applied to artificial digging pile(2)Hole wall at, its feature
It is:The enlarged footing is inserted including oblique from bottom to top on vertical direction(2)Hole wall in steel floral tube(3), be fixedly welded on
The steel floral tube(3)Stretch out enlarged footing(2)Hole wall part on expanded metal lath(5)And and expanded metal lath(5)Fitting fixation
Reinforced mesh(6), the expanded metal lath(5)Fit in enlarged footing(2)Hole wall.
3. manually digging hole pile enlarged foot dado structure according to claim 1 or 2, it is characterized in that:The adjacent steel floral tube
(3)Between spacing vertically be 0.5 meter.
4. manually digging hole pile enlarged foot dado structure according to claim 1 or 2, it is characterized in that:Enlarged footing(2)Hole wall
Some cranses for fitting in hole wall are provided with interior different height(4), the cranse(4)With the circle spray of molten steel at the height
Pipe(3)End is welded and fixed.
5. manually digging hole pile enlarged foot dado structure according to claim 1 or 2, it is characterized in that:The steel floral tube(3)On
It is firstly inserted into enlarged footing(2)One end of hole wall be provided with tip(30).
6. manually digging hole pile enlarged foot dado structure according to claim 2, it is characterized in that:The steel floral tube(3)Pipe
The stop grouting plug of sealing orifice is provided with mouthful(31).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720086253.4U CN206635750U (en) | 2017-01-22 | 2017-01-22 | Manually digging hole pile enlarged foot dado structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720086253.4U CN206635750U (en) | 2017-01-22 | 2017-01-22 | Manually digging hole pile enlarged foot dado structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206635750U true CN206635750U (en) | 2017-11-14 |
Family
ID=60260917
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720086253.4U Active CN206635750U (en) | 2017-01-22 | 2017-01-22 | Manually digging hole pile enlarged foot dado structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206635750U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107675704A (en) * | 2017-11-16 | 2018-02-09 | 贵州建工集团有限公司 | A kind of artificial digging pile assembled retaining wall and its construction technology |
CN108343053A (en) * | 2017-01-22 | 2018-07-31 | 北京爱地地质勘察基础工程公司 | Manually digging hole pile enlarged foot dado structure |
-
2017
- 2017-01-22 CN CN201720086253.4U patent/CN206635750U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108343053A (en) * | 2017-01-22 | 2018-07-31 | 北京爱地地质勘察基础工程公司 | Manually digging hole pile enlarged foot dado structure |
CN107675704A (en) * | 2017-11-16 | 2018-02-09 | 贵州建工集团有限公司 | A kind of artificial digging pile assembled retaining wall and its construction technology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101736760B (en) | Construction method of prestressed anti-floating anchor rod | |
CN106193032B (en) | A kind of anti-float anchor rod construction method | |
CN206467667U (en) | Suspended net shotcrete building enclosure between a kind of stake of use expansion type fixation reinforced mesh | |
CN106498950A (en) | Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body | |
CN108343053A (en) | Manually digging hole pile enlarged foot dado structure | |
CN102605773B (en) | Construction method of slip-casting expanded-base cast-in-situ bored pile and extruding-extending device thereof | |
CN103898916A (en) | Mini-pile combined support structure and construction method thereof | |
CN109914422A (en) | A kind of steel pipe and soil nailing combined type foundation pit supporting construction and construction method | |
CN103452120A (en) | Pile top crown beam structure of high-strength prestress pipe pile for supporting foundation pit and construction method thereof | |
CN206635750U (en) | Manually digging hole pile enlarged foot dado structure | |
CN109881668A (en) | Foundation construction method for soft soil layer, filling soil and sand soil layer | |
CN206408630U (en) | Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body | |
CN102235007B (en) | Method for supporting deep foundation with upper nail-lower pile combination | |
CN106149733B (en) | Tunnel immediately adjacent to bridge section deep foundation pit supporting structure and construction method | |
CN205894734U (en) | Outer unilateral mode structure on shear force wall of basement | |
CN105649106B (en) | The retaining wall structure and its construction method of steel pipe bone rib | |
CN204959787U (en) | Novel tower crane combination formula basis | |
CN109723055A (en) | A kind of diaphram wall bottom ruggedized construction and its construction method | |
CN114483081A (en) | Construction method of deflection-preventing structure of curved middle wall of multi-arch tunnel under terrain bias pressure | |
CN203768914U (en) | Foundation pit bracing diagonal support pile structure | |
CN113529765A (en) | Rapid precipitation construction method of anti-floating anchor rod | |
CN209652909U (en) | A kind of diaphram wall bottom ruggedized construction | |
CN109763507B (en) | Double-wall corrugated pipe foundation and construction process thereof | |
CN208870053U (en) | Deep well dado steel construction supports | |
CN202787275U (en) | Tubular soil nailing wall of novel pneumatic impact anchor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |