CN206627252U - A kind of oil-gas pipeline water filling, pressure testing, drainage system - Google Patents

A kind of oil-gas pipeline water filling, pressure testing, drainage system Download PDF

Info

Publication number
CN206627252U
CN206627252U CN201720357896.8U CN201720357896U CN206627252U CN 206627252 U CN206627252 U CN 206627252U CN 201720357896 U CN201720357896 U CN 201720357896U CN 206627252 U CN206627252 U CN 206627252U
Authority
CN
China
Prior art keywords
valve
pressure testing
oil
pressure
gas pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720357896.8U
Other languages
Chinese (zh)
Inventor
王志芳
许金生
张志梁
李明泽
高义斌
孙学敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Engineering Group Co Ltd
Sinopec Nanjing Engineering Co Ltd
Original Assignee
Sinopec Engineering Group Co Ltd
Sinopec Nanjing Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Engineering Group Co Ltd, Sinopec Nanjing Engineering Co Ltd filed Critical Sinopec Engineering Group Co Ltd
Priority to CN201720357896.8U priority Critical patent/CN206627252U/en
Application granted granted Critical
Publication of CN206627252U publication Critical patent/CN206627252U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Examining Or Testing Airtightness (AREA)

Abstract

A kind of oil-gas pipeline water filling, pressure testing, drainage system are the utility model is related to, belongs to oil-gas pipeline Hydraulic test technique field.Its object is to solve the problems, such as that water filling, pressure testing, drainage procedure disconnect.The utility model includes catch pit and oil-gas pipeline, waterflood-transmission line is provided between catch pit and oil-gas pipeline, pressure testing pipeline and flowing line, described oil-gas pipeline one end is service end, the other end is receipts ball end, the service end is connected with air compressor machine, the waterflood-transmission line and pressure testing pipeline are arranged in parallel between catch pit and service end, the flowing line is arranged between catch pit and receipts ball end, Water filling valve and pressure testing valve are respectively equipped with waterflood-transmission line and pressure testing pipeline, flowing line is provided with water discharging valve, the waterflood-transmission line is provided with water injecting pump, the pressure testing pipeline is provided with booster, wiper is provided with the oil-gas pipeline.The utility model beneficial effect is to improve efficiency of construction, reduces operating expenses, reduce construction risk.

Description

A kind of oil-gas pipeline water filling, pressure testing, drainage system
Technical field
A kind of oil-gas pipeline water filling, pressure testing, drainage system are the utility model is related to, belongs to oil-gas pipeline Hydraulic test technique Field.
Background technology
Oil-gas pipeline pressure test mainly has the water pressure test and gas pressure test, and because gas pressure test potential safety hazard is big, risk is high, It is less using gas pressure test in industry at present, substantially using the water pressure test, for gas pressure test the water pressure test more pacify It is complete reliable, this is also just based on, often neglects the safety operation of the water pressure test, after the completion of water filling, waterflood-transmission line is removed, then connects again Booster system is connect, connected mode using welding, not only causes work progress repeatedly to interrupt, delay the duration more, while connects interim Easily there is leakage point in pipeline, and operations involving high pressure security is poor, and draining generally requires to install pigging again after cutting off transmitting-receiving ball end seal head Device, draining again after welding.That is, in the existing oil-gas pipeline water pressure test, water filling, pressure testing, draining are divided into three individually Process, inter process linking easily disconnect, and the technical problem that construction is intermittent, construction risk is high be present.Therefore compel to be essential A kind of water filling, pressure testing and drainage system are wanted, only by operating valve just energy continuous control water filling, boosting and draining, improves construction Efficiency, reduce construction risk.
The content of the invention
The purpose of this utility model is to provide a kind of oil-gas pipeline water filling, pressure testing, drainage system, to solve prior art The problem of oil-gas pipeline water pressure test water filling, pressure testing, drainage procedure disconnect, water filling, pressure testing, draining integration are realized, simplifies pipe Road hydrostatic test step.
The utility model adopts the technical scheme that:A kind of oil-gas pipeline water filling, pressure testing, drainage system, including catch pit And oil-gas pipeline, waterflood-transmission line, pressure testing pipeline and flowing line, the oil-gas pipeline one are provided between catch pit and oil-gas pipeline It is to receive ball end to hold as service end, the other end, and the service end is connected with air compressor machine, and the waterflood-transmission line and pressure testing pipeline parallel connection are set Put between catch pit and service end, between the flowing line is arranged on catch pit and receives ball end, waterflood-transmission line and pressure testing pipe Water filling valve and pressure testing valve are respectively equipped with line, flowing line is provided with water discharging valve, and the waterflood-transmission line is provided with water filling Pump, the pressure testing pipeline are provided with booster, wiper are provided with the oil-gas pipeline.The waterflood-transmission line and pressure testing pipeline are simultaneously The end being linked togather is provided with the main pipe line being connected on service end, and main pipe line is provided with total valve.Total valve include valve C and High-pressure ball valve B, high-pressure ball valve B are close to service end, and valve C is away from service end.The Water filling valve is included before being arranged on water injecting pump The valve A at the end and check-valves A for being arranged on water injecting pump rear end, the pressure testing valve include the valve B for being arranged on booster front end With the check-valves B for being arranged on booster rear end.Water discharging valve on the flowing line includes high-pressure ball valve C, and high-pressure ball valve C is leaned on It is near to receive ball end.The quantity at least two of the wiper.High-pressure ball valve A is provided between the service end and air compressor machine.It is described Thermometer and pressure gauge are equipped with service end and receipts ball end.
The beneficial effects of the utility model are:The system by three oil-gas pipeline water filling, pressure testing, draining autonomous systems melt for One, by the way that water filling and boosting two systems is in parallel, by opening valve A, check-valves A, valve C, high-pressure ball valve B, high pressure Ball valve C, close valve B, check-valves B, high-pressure ball valve A, start water injecting pump, can the water filling into pipe, water promotes wiper in pipe Walk before introversive, be vented using high pressure valve C.After the completion of water filling, valve A, check-valves A, high-pressure ball valve C are closed, opens valve B, check-valves B, using booster, into pipe, water filling is boosted, boost phase strict implement job specfication and design drawing requirement, directly Reach Strengh testing pressure to pressure, close valve B, check-valves B, valve C, high-pressure ball valve B.High-pressure ball valve C is slowly opened, will Pressure is let out to atmospheric pressure state, then by the air compressor machine that high-pressure ball valve A is connected using compressed air as pressure testing in powered pipeline Flowed with water to ball end is received, catch pit is emitted into by drainage pipeline by hydraulic water is tried by high-pressure ball valve C.
It is divided into three independent processes, work compared to water filling, pressure testing, draining in existing oil-gas pipeline Hydraulic test technique feature Linking easily disconnects between sequence, and construction is intermittent, and construction risk is high, and the utility model can solve the problem that water filling, pressure testing, draining The problem of process disconnects, can be by controlling water injecting pump, booster, air compressor machine and connecting valve complete after the system installation Into water filling and boost operations, efficiency of construction is improved, reduces operating expenses, reduces construction risk.The utility model is in oil-gas pipeline Interior to be provided with one or more wiper, wiper can be by Valve controlling, after pressure testing terminates, without slicing off both sides end socket Wiper is reinstalled, service end can be returned to by Valve controlling wiper.
Brief description of the drawings
Fig. 1 is a kind of oil-gas pipeline water filling of the present utility model, pressure testing, drainage system schematic flow sheet;
In figure, 1. catch pits, 2. service ends, 3. receive ball ends, 4. waterflood-transmission lines, 5. pressurized pipelines, 6. valve A, and 7. Water injecting pump, 8. check-valves A, 9. valve B, 10. boosters, 11. check-valves B, 12. valve C, 13. high-pressure ball valve A, 14. High-pressure ball valve B, 15. high-pressure ball valve C, 16. thermometers, 17. pressure gauges, 18. wipers.
Embodiment
The utility model is described in detail with specific embodiment below in conjunction with the accompanying drawings.
As shown in figure 1, a kind of oil-gas pipeline water filling, pressure testing, drainage system are the utility model is related to, including the He of catch pit 1 Oil-gas pipeline, waterflood-transmission line 4, pressure testing pipeline 5 and flowing line are provided between catch pit 1 and oil-gas pipeline(Do not show in accompanying drawing Show), described oil-gas pipeline one end is service end 2, the other end is to receive ball end 3, and the service end 2 is connected with air compressor machine(In accompanying drawing Do not show), the waterflood-transmission line 4 and pressure testing pipeline 5 be arranged in parallel catch pit 1 and service end 2 between, the flowing line is set Put between catch pit 1 and receipts ball end 3, Water filling valve and pressure testing valve are respectively equipped with waterflood-transmission line 4 and pressure testing pipeline 5, arrange Water pipeline is provided with water discharging valve, and the waterflood-transmission line 4 is provided with water injecting pump 7, and the pressure testing pipeline 5 is provided with booster 10, Wiper 18 is provided with the oil-gas pipeline.The end that the waterflood-transmission line 4 and pressure testing pipeline 5 are connected in parallel is provided with and is connected to The main pipe line served a ball on end 2, main pipe line are provided with total valve.Total valve includes valve C12 and high-pressure ball valve B14, high-pressure ball valve B14 is close to service end 2, and valve C12 is away from service end 2.The Water filling valve include be arranged on the front end of water injecting pump 7 valve A6 and The check-valves A8 of the rear end of water injecting pump 7 is arranged on, the pressure testing valve includes being arranged on valve B9 and the setting of the front end of booster 10 Check-valves B11 in the rear end of booster 10.Water discharging valve on the flowing line includes high-pressure ball valve C15, high-pressure ball valve C15 Close to receipts ball end 3.The quantity at least two of the wiper 18.High-pressure ball valve is provided between the service end 2 and air compressor machine A13.Thermometer 16 and pressure gauge 17 are equipped with the service end 2 and receipts ball end 3.
It is as follows that the utility model operation is divided into preparation of construction, water filling, four pressure testing, draining steps:
Preparation of construction:Special construction plan is write, water quality test is qualified, and the measurement instrument such as pressure gauge assay approval is simultaneously having In the effect phase, personnel, equipment meet that the connection such as construction demand, pipeline, valve pump is completed, and place Security alert is intact.
Water filling:Valve A, check-valves A, valve C, high-pressure ball valve B, high-pressure ball valve C are opened, closes valve B, check-valves B, height Pressure ball valve A, start water injecting pump, start the water filling into pipe, water promotes wiper to be vented using valve, until clear in walking in pipe Water filling is completed after pipe device reaches receipts ball end.
Pressure testing:After the completion of water filling, valve A, check-valves A, high-pressure ball valve C are closed, valve B, check-valves B is opened, utilizes liter Press pump water filling into pipe is boosted, boost phase strict implement job specfication and design drawing requirement, until pressure reaches intensity examination Pressure is tested, closes valve B, check-valves B, valve C, high-pressure ball valve B, beginning timing after pressure stabilisation, voltage stabilizing 4 hours, voltage stabilizing Period, pressure and temperature of every 15 minutes records, using pipeline without deformation, No leakage is qualified;After strength test is qualified, slowly Open high-pressure ball valve C, pressure release to leak test pressure starts timing after pressure stability, voltage stabilizing 24 hours, during voltage stabilizing, often Pressure and temperature of 30 minutes records, using pressure drop no more than 1% test pressure and no more than 0.1MPa to be qualified.
Draining:After the completion of leak test, high-pressure ball valve C is slowly opened, pressure is let out to atmospheric pressure state, then passes through height Pressure ball valve A connection air compressor machines, using compressed air as hydraulic water is tried in powered pipeline to the flowing of ball end is received, pass through high-pressure ball valve Catch pit is flowed into after C discharge lines, row after water quality meets discharge condition is chemically examined after to be precipitated and arrives neighbouring irrigation canals and ditches.
Water filling of the present utility model, pressure testing, draining integral structure, which overcome water filling, pressure testing, drainage procedure disconnect asks Topic, water filling, pressure testing, draining integration are realized, simplifies pipeline hydraulic pressure experimental procedure.
General principle, principal character and advantage of the present utility model has been shown and described above.The ordinary skill of this area Personnel are not it should be appreciated that above-described embodiment limits the scope of protection of the utility model, all use equivalent substitutions etc. in any form The technical scheme that mode is obtained, falls within the scope of protection of the utility model.
The utility model is not directed to partly same as the prior art or can realized using prior art.

Claims (8)

1. a kind of oil-gas pipeline water filling, pressure testing, drainage system, including catch pit(1)And oil-gas pipeline, catch pit(1)And oil gas Waterflood-transmission line is provided between pipeline(4), pressure testing pipeline(5)And flowing line, described oil-gas pipeline one end are service end(2), it is another One end is receipts ball end(3), it is characterised in that:The service end(2)It is connected with air compressor machine, the waterflood-transmission line(4)With pressure testing pipe Line(5)It is arranged in parallel in catch pit(1)With end of serving a ball(2)Between, the flowing line is arranged on catch pit(1)With receiving ball end (3)Between, waterflood-transmission line(4)With pressure testing pipeline(5)On be respectively equipped with Water filling valve and pressure testing valve, flowing line is provided with row Penstock, the waterflood-transmission line(4)It is provided with water injecting pump(7), the pressure testing pipeline(5)It is provided with booster(10), the oil Wiper is provided with feed channel(18).
2. oil-gas pipeline water filling according to claim 1, pressure testing, drainage system, it is characterised in that:The waterflood-transmission line (4)With pressure testing pipeline(5)The end being connected in parallel, which is provided with, is connected to service end(2)On main pipe line, main pipe line is provided with total Valve.
3. oil-gas pipeline water filling according to claim 2, pressure testing, drainage system, it is characterised in that:Total valve includes valve C(12)With high-pressure ball valve B(14), high-pressure ball valve B(14)Close to service end(2), valve C(12)Away from service end(2).
4. oil-gas pipeline water filling according to claim 1, pressure testing, drainage system, it is characterised in that:The Water filling valve bag Include and be arranged on water injecting pump(7)The valve A of front end(6)Be arranged on water injecting pump(7)The check-valves A of rear end(8), the pressure testing valve Including being arranged on booster(10)The valve B of front end(9)Be arranged on booster(10)The check-valves B of rear end(11).
5. oil-gas pipeline water filling according to claim 1, pressure testing, drainage system, it is characterised in that:On the flowing line Water discharging valve include high-pressure ball valve C(15), high-pressure ball valve C(15)Close to receipts ball end(3).
6. oil-gas pipeline water filling according to claim 1, pressure testing, drainage system, it is characterised in that:The wiper(18) Quantity at least two.
7. oil-gas pipeline water filling according to claim 1, pressure testing, drainage system, it is characterised in that:The service end(2) High-pressure ball valve A is provided between air compressor machine(13).
8. oil-gas pipeline water filling according to claim 1, pressure testing, drainage system, it is characterised in that:The service end(2) With receipts ball end(3)On be equipped with thermometer(16)And pressure gauge(17).
CN201720357896.8U 2017-04-07 2017-04-07 A kind of oil-gas pipeline water filling, pressure testing, drainage system Active CN206627252U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720357896.8U CN206627252U (en) 2017-04-07 2017-04-07 A kind of oil-gas pipeline water filling, pressure testing, drainage system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720357896.8U CN206627252U (en) 2017-04-07 2017-04-07 A kind of oil-gas pipeline water filling, pressure testing, drainage system

Publications (1)

Publication Number Publication Date
CN206627252U true CN206627252U (en) 2017-11-10

Family

ID=60207316

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720357896.8U Active CN206627252U (en) 2017-04-07 2017-04-07 A kind of oil-gas pipeline water filling, pressure testing, drainage system

Country Status (1)

Country Link
CN (1) CN206627252U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108593448A (en) * 2018-04-24 2018-09-28 中国化学工程第三建设有限公司 Test run method for synchronously constructing is rinsed in industrial system pressure testing
CN109556967A (en) * 2018-12-30 2019-04-02 广东省工业设备安装有限公司 A kind of environment-friendly type monolithic conduit pressure device and hammering method
CN109655349A (en) * 2018-12-18 2019-04-19 海洋石油工程(青岛)有限公司 The high pressure pressure testing device of pipeline for remotely controlling
CN110082049A (en) * 2019-05-30 2019-08-02 苏州热工研究院有限公司 A kind of nuclear power station container water pressure test water inlet bulge test device
CN110208100A (en) * 2019-06-12 2019-09-06 海洋石油工程股份有限公司 A kind of key equipment applied to deep-sea oil gas pipeline pressure test operation
CN111579161A (en) * 2020-06-02 2020-08-25 珠海格力智能装备有限公司 Leak detection device

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108593448A (en) * 2018-04-24 2018-09-28 中国化学工程第三建设有限公司 Test run method for synchronously constructing is rinsed in industrial system pressure testing
CN109655349A (en) * 2018-12-18 2019-04-19 海洋石油工程(青岛)有限公司 The high pressure pressure testing device of pipeline for remotely controlling
CN109556967A (en) * 2018-12-30 2019-04-02 广东省工业设备安装有限公司 A kind of environment-friendly type monolithic conduit pressure device and hammering method
CN110082049A (en) * 2019-05-30 2019-08-02 苏州热工研究院有限公司 A kind of nuclear power station container water pressure test water inlet bulge test device
CN110208100A (en) * 2019-06-12 2019-09-06 海洋石油工程股份有限公司 A kind of key equipment applied to deep-sea oil gas pipeline pressure test operation
CN111579161A (en) * 2020-06-02 2020-08-25 珠海格力智能装备有限公司 Leak detection device

Similar Documents

Publication Publication Date Title
CN206627252U (en) A kind of oil-gas pipeline water filling, pressure testing, drainage system
CN101598623B (en) Leak detection tool applied to high pressure gas leak detection method
CN203798681U (en) Hydraulic pipe strength test system
CN102489650B (en) Automatic liquid supplementing and draining system with liquid filling tank
CN101672748A (en) 400MPa super-high pressure fatigue test device and test method
CN107942000A (en) A kind of mining multifunctional modularization carbon dioxide foaming crushing test method
CN106289662A (en) A kind of steel pipe sealing inflating pressure detection device
CN204988892U (en) Pressure collision test equipment
CN102345592B (en) Automatic pressing pump test device
CN104165739B (en) Method for testing pressure by adoption of vertical and automatic heat collector flow channel pressure test machine
CN104215548B (en) The static corrosion inhibition rate test combination unit of a kind of corrosion inhibiter and method of testing
CN105021466B (en) A kind of compression shock testing equipment
CN211317708U (en) Temperature alternating pressure fatigue test device for plate heat exchanger
CN202330174U (en) Blasting tester for fire fighting hose
CN201632936U (en) Micro-porous nozzle internal runner processing device utilizing abrasive suspension jet
CN108561176B (en) Automatic blocking and permeability-increasing device and method for gas extraction drilling
CN104614253A (en) Heat exchange unit pressure test equipment and pressure test method
CN206930530U (en) A kind of hydraulic pressure tester for pipe fitting height pressure control system
CN104261150A (en) Discharging system for ammonium nitrate tank truck
CN102840953A (en) Method for confirming damage of cooling water pipe of blast furnace cooling wall
CN109975128A (en) A kind of tubing Strength test method
CN104948188B (en) Overload protection device for stone cracking equipment
CN208060300U (en) A kind of pneumatic pressure testing device of vehicle mounted electric
CN209372323U (en) A kind of valve casing casting leakage test device
CN210071484U (en) Manifold tool based on partial pressure and pressure regulation

Legal Events

Date Code Title Description
GR01 Patent grant