CN206617763U - Automate LNG filling decompression units - Google Patents

Automate LNG filling decompression units Download PDF

Info

Publication number
CN206617763U
CN206617763U CN201720087138.9U CN201720087138U CN206617763U CN 206617763 U CN206617763 U CN 206617763U CN 201720087138 U CN201720087138 U CN 201720087138U CN 206617763 U CN206617763 U CN 206617763U
Authority
CN
China
Prior art keywords
emptying
filling
pressure
branch pipe
voltage regulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720087138.9U
Other languages
Chinese (zh)
Inventor
林子斌
周宝发
朱治光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Senges energy equipment (Ningbo) Co., Ltd.
Original Assignee
SAMGAS TRANSMISSION & DISTRIBUTION EQUIPMENTS (NINGBO) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SAMGAS TRANSMISSION & DISTRIBUTION EQUIPMENTS (NINGBO) Co Ltd filed Critical SAMGAS TRANSMISSION & DISTRIBUTION EQUIPMENTS (NINGBO) Co Ltd
Priority to CN201720087138.9U priority Critical patent/CN206617763U/en
Application granted granted Critical
Publication of CN206617763U publication Critical patent/CN206617763U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Measuring Fluid Pressure (AREA)

Abstract

Automate LNG filling decompression units, it is related to a kind of LNG plant, including integrated skid structure, two sets of filling pressure reducing circuits and blowdown piping are provided with described integrated skid structure, described filling pressure reducing circuit includes the high-pressure inlet header being sequentially connected, electric heating water bath heater, high pressure filter, one-level pressure regulator, second voltage regulation device, turbine flowmeter, bellows and three-level pressure regulator valve, filling pressure reducing circuit described in two is connected with escape pipe jointly, connecting tube is provided between described second voltage regulation device and described turbine flowmeter, described blowdown piping, which includes emptying, to be responsible for, first emptying branch pipe is also associated with described emptying supervisor, second is vented branch pipe and emptying straight tube.Compared with prior art, this equipment filling pressure regulation measurement Integral design, installs simple, rational in infrastructure, easy to operate, and filling is accurate, pressure regulation is accurate, measurement is accurate, and integrated level is high, and floor space is small, safe and reliable.

Description

Automate LNG filling decompression units
Technical field
The utility model is related to a kind of LNG plant, especially a kind of LNG filling sled.
Background technology
Because natural gas is a kind of clean energy resource, produced after burning without waste residue, waste water, comparing coal, oil equal energy source has Use the advantages such as safety, calorific value height, cleaning.With the enhancing and the popularization of natural gas line of environmental consciousness, increasing city Town is all used as the necessary energy in daily life using natural gas.When by gas pipeline, downstream user provides combustion gas, Need the flow of combustion gas and drift limit in specified fluctuation range, both combustion gas was depressurized, while will also be to downstream The instantaneous delivery and integrated flow information of user gives accurate recording, and both combustion gas was measured.Present gas gathering and transportation pipe There is the pressure regulation system of the defect that pipeline is more, structure is more complicated, technology is relatively low, security is low, especially part webmaster in web frame System and metering system are separately separated so that gas distribution station volume is big, and it has not been met needed for town construction planning development.Therefore, How device that so a set of pressure regulation and metering combine is designed, while stating function in realization, to be also easy to assembling and transport, Ensure that product safety is reliable, simplify maintenance work, be those skilled in the art's technical problem to be solved.
The content of the invention
The utility model is for deficiency of the prior art there is provided one kind automation LNG filling decompression units, and this equipment adds Pressure regulation measurement Integral design is noted, installs simple, rational in infrastructure, easy to operate, filling is accurate, pressure regulation is accurate, measurement is accurate, integrated Degree is high, and floor space is small, safe and reliable.
In order to solve the above-mentioned technical problem, the utility model is addressed by following technical proposals:Automate LNG filling Two sets of filling pressure reducing circuits and blowdown piping are provided with decompression unit, including integrated skid structure, described integrated skid structure, Described filling pressure reducing circuit includes the high-pressure inlet header being sequentially connected, electric heating water bath heater, high pressure filter, one Level pressure regulator, second voltage regulation device, turbine flowmeter, bellows and three-level pressure regulator valve, the filling pressure reducing circuit described in two are common Escape pipe is connected with, connecting tube, described emptying are provided between described second voltage regulation device and described turbine flowmeter Pipeline, which includes emptying, to be responsible for, and first emptying branch pipe, second emptying branch pipe and emptying straight tube are also associated with described emptying supervisor, described First emptying branch pipe be arranged on two it is described filling pressure reducing circuits between the one-level pressure regulator and the second voltage regulation device, institute Be respectively arranged with the first emptying branch pipe stated with two corresponding switch valves of the filling pressure reducing circuit, set in described connecting tube Be equipped with diffusion valve, described connecting tube and the described second emptying branch pipe of described diffusion valve connection, described second voltage regulation device and It is provided with first switch valve between described connecting tube, second switch is provided between described connecting tube and described turbine flowmeter Valve.
In above-mentioned technical proposal, it is preferred that between described electric heating water bath heater and described high pressure filter It is provided with high-pressure pneumatic ball valve.
In above-mentioned technical proposal, it is preferred that be provided with bullet between described one-level pressure regulator and described second voltage regulation device The third emptying branch pipe is provided between the spring loaded safety valve on spring formula safety valve, two filling pressure reducing circuits, it is described The described emptying supervisor of the third emptying branch pipe connection.
In above-mentioned technical proposal, it is preferred that reserved straight tube is additionally provided with described filling pressure reducing circuit, described is reserved Straight tube is arranged between described second voltage regulation device and described turbine flowmeter.
In above-mentioned technical proposal, it is preferred that on described high-pressure inlet header, described connecting tube and described escape pipe It is both provided with pressure sensor, pressure sensing is also equipped between described one-level pressure regulator and described second voltage regulation device Device.
In above-mentioned technical proposal, it is preferred that temperature sensor is provided with described electric heating water bath heater and double Metallic thermometer.
In above-mentioned technical proposal, it is preferred that described high pressure filter bottom is provided with soil pipe.
In above-mentioned technical proposal, it is preferred that be additionally provided with armored cassette in described integrated skid structure.
The present apparatus is a kind of filling pressure regulation measurement one LNG sleds, and whole skid-mounted device integrated level is high, under limited space The loop of layout whole device as rational as possible.The present apparatus has two performance loops, and each performance loop can be independent Carry out filling pressure regulation measurement work, can also carry out simultaneously so that the efficiency of the present apparatus is significantly improved, at the same two loops it Between be additionally provided with connecting tube, once some performance loop goes wrong, can change at once will not allow whole device to stop work, increase Serious forgiveness.
Compared with prior art, this equipment filling pressure regulation measurement Integral design, installs simple, rational in infrastructure, easy to operate, Filling is accurate, pressure regulation is accurate, measurement is accurate, and integrated level is high, and floor space is small, safe and reliable.
Brief description of the drawings
Fig. 1 is the utility model schematic perspective view.
Fig. 2 is the utility model flowmeter system schematic diagram.
Embodiment
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings.
As depicted in figs. 1 and 2, a kind of automation LNG filling decompression units, including integrated skid structure 1, described integrated sled Assembling structure 1 includes several main horizontal frame bars 11 and the vertical frame bar 12 of several masters, and described main horizontal frame bar 11 and described master indulge frame Bar 12 constitutes and several horizontal frame bars 13 of connection and the vertical frame bar 14 of several connections is provided with framework, described framework, described Connect horizontal frame bar 13 and described connection is indulged and is provided with several vertical bars 16 on frame bar 14.
Frame is indulged in described main horizontal frame bar 11, the vertical frame bar 12 of described master, the described horizontal frame bar 13 of connection and described connection All it is evenly arranged with several fixing holes 100 on bar 14, described main horizontal frame bar 11, described master indulge frame bar 12, described company Connect horizontal frame bar 13 and described connection indulge the both sides of frame bar 14 be both provided with being provided with stator, described stator with it is described solid Determine the spacing hole that hole 100 is engaged, described fixing hole 100 and the spacing hole are bolted.Described main horizontal frame bar 11st, the vertical frame bar 12 of described master, the described horizontal frame bar 13 of connection and the vertical frame bar 14 of described connection both pass through spacing hole and fixation Hole 100 interfixes, because fixing hole 100 can indulge frame bar 12, described connection in described main horizontal frame bar 11, described master Horizontal frame bar 13 and described connection, which are indulged, sets many on frame bar 14, then can carry out the assembling of any various structure sizes.Institute The bottom of vertical bar 15 stated is provided with fixed socket, described fixed socket to be provided with connects horizontal frame bar 13 and described with described The recess hole being engaged with the fixing hole 100 is provided with the fixed groove that the vertical frame bar 114 of connection is engaged, fixed groove, Described recess hole and described fixing hole 100 are bolted.Similarly vertical bar 15 can also connect the horizontal He of frame bar 13 Arbitrarily installed on the vertical frame bar 14 of connection.It is additionally provided with described vertical bar 15 on vertical cross bar 16, described vertical cross bar 16 Be evenly arranged with several cross bar holes, the described top of vertical bar 15 be provided with vertical piece, described vertical piece be provided with The vertical holes that the cross bar hole is engaged, described cross bar hole and described vertical holes are bolted.Similarly vertical cross bar 16 can also arbitrarily install in vertical bar 15.
Described main horizontal frame bar 11, described master indulge frame bar 12, described horizontal frame bar 13, described connection and indulge the and of frame bar 14 It is both provided with fixing on described vertical cross bar 16 on laminate 101, described fixation laminate 101 and is provided with equipment opening 102.So Various components can indulge frame bar 12, described horizontal frame bar 13, described connection in described main horizontal frame bar 11, described master Arbitrarily installed on vertical frame bar 14 and described vertical cross bar 16.Described main horizontal frame bar 11 and described master indulge also to be set on frame bar 12 Dismountable fixator 17 is equipped with, fixator 17 primarily serves the effect that whole integrated skid structure 1 is fixed on the ground.
This skid structure constitutes basic framework by leading vertical frame bar 12, main horizontal frame bar 11, and the size of basic framework can basis Actual conditions are arbitrarily set.Then the vertical frame bar 14 of connection is set on the basis of basic framework, horizontal frame bar 13 and vertical bar is connected 15, the vertical frame bar 14 of connection, the horizontal frame bar 13 of connection, vertical bar 15 and vertical cross bar 16 are arbitrarily set also according to actual use situation, And vertical frame bar 14, the horizontal frame bar 13 of connection, vertical bar 15 and vertical cross bar 16 is connected in actual use to be torn open at any time Remove.After LNG sled service lifes expire, this skid structural demolition into various masters can be indulged frame bar 12, main horizontal frame bar 11, connection Re-started after vertical frame bar 14, the horizontal frame bar 13 of connection, vertical bar 15 and vertical cross bar 16 using the new different size of assembled formation Skid structure.
Two sets of filling pressure reducing circuits and blowdown piping, described integrated skid are provided with described integrated skid structure 1 Armored cassette 19 is additionally provided with structure 1.Described filling pressure reducing circuit includes high-pressure inlet header 21, the electrical heating being sequentially connected Water-bath type heater 22, high pressure filter 23, one-level pressure regulator 24, second voltage regulation device 25, turbine flowmeter 26, the and of bellows 27 Three-level pressure regulator valve 28, the filling pressure reducing circuit described in two is connected with escape pipe 29 jointly.Described electric heating water bath heating High-pressure pneumatic ball valve 41 is provided between device 22 and described high pressure filter 23.Set on described electric heating water bath heater It is equipped with temperature sensor and bimetallic thermometer.The described bottom of high pressure filter 23 is provided with soil pipe 231.
Connecting tube 41, described emptying are provided between described second voltage regulation device 24 and described turbine flowmeter 25 Pipeline includes being also associated with first emptying branch pipe 32, second emptying branch pipe 33 and emptying on emptying supervisor 31, described emptying supervisor 31 Straight tube 34, described first emptying branch pipe 32 is arranged on the one-level pressure regulator 23 and described two on two filling pressure reducing circuits Between level pressure regulator 24, switch corresponding with two filling pressure reducing circuits is respectively arranged with described first emptying branch pipe 32 Valve.Diffusion valve 43 and pressure sensor 44, described connecting tube 42 and described diffusion valve are provided with described connecting tube 42 The described second emptying branch pipe 33 of 43 connections, first switch valve is provided between described second voltage regulation device 25 and described connecting tube 42 45, it is provided with second switch valve 45 between described connecting tube 42 and described turbine flowmeter 26.Described one-level pressure regulator 24 The spring on spring loaded safety valve 47, two filling pressure reducing circuits is provided between described second voltage regulation device 25 The third emptying branch pipe 35 is provided between formula safety valve 47, the third described emptying branch pipe 35 connects described emptying supervisor 31.It is described Filling pressure reducing circuit on be additionally provided with reserved straight tube 48, described reserved straight tube 48 is arranged on the described He of second voltage regulation device 25 26 between described turbine flowmeter.Pressure sensing is both provided with described high-pressure inlet header 21, described escape pipe 29 Device 44, pressure sensor 44 is also equipped between described one-level pressure regulator 24 and described second voltage regulation device 25.
It is provided between described turbine flowmeter 26 and described bellows 27 in loop pipe 51, described loop pipe 51 It is provided with switch valve 52, described bellows 27 and is provided with first controlling switch valve 53, described second voltage regulation device 25 and turbine Second switch valve 46 is provided between flowmeter 26.Remote data transmission device 261, institute are provided with described turbine flowmeter 26 The two ends of turbine flowmeter 26 stated are additionally provided with fast connection interface.
In use, connect source of the gas and high-pressure inlet header 21 by discharge column 18, high-pressure inlet header 21, then gas lead to Cross high-pressure inlet header 21 and enter electric heating water bath heater 22 and be changed into gaseous state from liquid, subsequently by high-pressure filteration Device 23 goes out crude removal, and the dirt being removed can be discharged by soil pipe 231.Subsequently carry out one-level pressure regulator 24 and two grades of tune Depressor 25, once pressure goes wrong, the valve that can be vented with manual unlocking first on branch pipe 32 is exhausted, or according to spring Formula safety valve 47 is vented automatically.Pressure regulation enters turbine flowmeter 26 and carries out flow measurement after finishing, measurement is passed through again after terminating Exported after crossing the pressure regulation of three-level pressure regulator valve 28 from escape pipe 29.The setting of connecting tube 42 primarily serves the work of regulation filling pressure reducing circuit Make state, can just allow each regulation filling pressure reducing circuit to work independently or tandem working by connecting tube 42, once some Performance loop goes wrong, and can change at once will not allow whole device to stop work, and add serious forgiveness, it is ensured that the peace of gas transmission Entirely.Turbine flowmeter 26 also has single double loop simultaneously, and turbine flowmeter 26 is used alone for two-way when normally using.Need Can be by loop pipe 51 by two equipment of turbine flowmeter 26 series connection progress series connection measurements, while being passed by teledata when wanting Whether defeated device 261 can compare two measurement pipeline medium hour flow readings of turbine flowmeter 26 online consistent.If occurring Reading has deviation, and any one turbine flowmeter 26 can be discharged by fast connection interface, goes to demarcation center to be demarcated, so as to sentence Disconnected is the problem of which platform turbine flowmeter 26 has error in dipping.Substantially increase the facility of equipment in actual use Property, also improve the feature of overall metering system.

Claims (8)

1. LNG filling decompression units are automated, including integrated skid structure(1), described integrated skid structure(1)On be provided with two Set filling pressure reducing circuit and blowdown piping, it is characterized in that, the high-pressure inlet that described filling pressure reducing circuit includes being sequentially connected converges Pipe(21), electric heating water bath heater(22), high pressure filter(23), one-level pressure regulator(24), second voltage regulation device(25), whirlpool Flowmeters(26), bellows(27)With three-level pressure regulator valve(28), the filling pressure reducing circuit described in two is connected with outlet jointly Pipe(29), in described second voltage regulation device(25)With described turbine flowmeter(26)Between be provided with connecting tube(42), it is described Blowdown piping include emptying be responsible for(31), described emptying supervisor(31)On be also associated with first emptying branch pipe(32), second emptying Branch pipe(33)With emptying straight tube(34), described first emptying branch pipe(32)It is arranged on described one on two filling pressure reducing circuits Level pressure regulator(24)With the second voltage regulation device(25)Between, described first emptying branch pipe(32)On be respectively arranged with and two institutes State the corresponding switch valve of filling pressure reducing circuit, described connecting tube(42)On be provided with diffusion valve(43), described connecting tube (42)With described diffusion valve(43)The described second emptying branch pipe of connection(33), described second voltage regulation device(25)With described company Adapter(42)Between be provided with first switch valve(45), described connecting tube(42)With described turbine flowmeter(26)Between set There is second switch valve(46).
2. automation LNG according to claim 1 fills decompression unit, it is characterized in that, described electric heating water bath heating Device(22)With described high pressure filter(23)Between be provided with high-pressure pneumatic ball valve(41).
3. automation LNG according to claim 1 fills decompression unit, it is characterized in that, described one-level pressure regulator(24)With Described second voltage regulation device(25)Between be provided with spring loaded safety valve(47), two bullets filled on pressure reducing circuits Spring formula safety valve(47)Between be provided with the third emptying branch pipe(35), described third emptying branch pipe(35)The described emptying supervisor of connection (31).
4. automation LNG according to claim 1 fills decompression unit, it is characterized in that, on described filling pressure reducing circuit also It is provided with reserved straight tube(48), described reserved straight tube(48)It is arranged on described second voltage regulation device(25)With described turbine flow Gauge(26)Between.
5. automation LNG according to claim 1 fills decompression unit, it is characterized in that, described high-pressure inlet header(21)、 Described connecting tube(42)With described escape pipe(29)On be both provided with pressure sensor(44), described one-level pressure regulator (24)With described second voltage regulation device(25)Between be also equipped with pressure sensor(44).
6. automation LNG according to claim 1 fills decompression unit, it is characterized in that, described electric heating water bath heating Device(22)On be provided with temperature sensor and bimetallic thermometer.
7. automation LNG according to claim 1 fills decompression unit, it is characterized in that, described high pressure filter(23)Bottom Portion is provided with soil pipe(231).
8. automation LNG according to claim 1 fills decompression unit, it is characterized in that, described integrated skid structure(1)On It is additionally provided with armored cassette(19).
CN201720087138.9U 2017-01-23 2017-01-23 Automate LNG filling decompression units Expired - Fee Related CN206617763U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720087138.9U CN206617763U (en) 2017-01-23 2017-01-23 Automate LNG filling decompression units

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720087138.9U CN206617763U (en) 2017-01-23 2017-01-23 Automate LNG filling decompression units

Publications (1)

Publication Number Publication Date
CN206617763U true CN206617763U (en) 2017-11-07

Family

ID=60230425

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720087138.9U Expired - Fee Related CN206617763U (en) 2017-01-23 2017-01-23 Automate LNG filling decompression units

Country Status (1)

Country Link
CN (1) CN206617763U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111692530A (en) * 2020-05-19 2020-09-22 徐州华宝能源科技有限公司 Natural gas pressure regulating skid-mounted device with multistage safety protection function
WO2023155275A1 (en) * 2022-02-21 2023-08-24 烟台杰瑞石油装备技术有限公司 Pressure regulating system and pressure regulating system control method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111692530A (en) * 2020-05-19 2020-09-22 徐州华宝能源科技有限公司 Natural gas pressure regulating skid-mounted device with multistage safety protection function
CN111692530B (en) * 2020-05-19 2021-09-03 徐州华宝能源科技有限公司 Natural gas pressure regulating skid-mounted device with multistage safety protection function
WO2023155275A1 (en) * 2022-02-21 2023-08-24 烟台杰瑞石油装备技术有限公司 Pressure regulating system and pressure regulating system control method

Similar Documents

Publication Publication Date Title
US9651199B1 (en) Hydrogen supply method and system
CN206617763U (en) Automate LNG filling decompression units
CN201705330U (en) Mobile oil well multi-phase flow meter
JP5946976B2 (en) Fluid use facility management method or fluid use facility management system
CN107587868B (en) Oil well metering integrated device
CN203285424U (en) Thickened oil single-tank automatic counting device
CN105737135A (en) Small boiler water replenishing system
WO2017027943A1 (en) Intergated compact station for subsea separation and injection
CN206617765U (en) LNG skid flowmeter comparison devices
CN206617760U (en) LNG skid operation readiness mounting structures
WO2017135982A1 (en) Modular systems and methods for developing gas fields
CN203771036U (en) Skid-mounted device for gas station
CN206668247U (en) A kind of automatic Metering Device for Petroleum Well
Mubarok et al. Steam-field design overview of the Ulubelu geothermal project, Indonesia
CN105807000B (en) A kind of on-line chemical monitoring instrument standard calibration device and method
CN208595428U (en) A kind of integrated seriation splicing skid-mounted unit
CN106198299A (en) A kind of for pipeline and the comprehensive skid-mounted device of equipment corrosion Data Trend Monitor
CN205261234U (en) Measurement integrated device cools down
CN220269156U (en) Multifunctional gas pipeline parameter measuring device
CN210622785U (en) Gas-liquid separation device for oil field metering and three-phase metering system thereof
CN201764474U (en) Packaged boiler heating system
CA3014272C (en) Modular well pad systems and methods
CN209385113U (en) More wells go alone constant pressure metering device
CA3014562C (en) Modular well pad systems and methods
RU33778U1 (en) SETTING WELL PRODUCT DEBIT MEASUREMENT

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 315000 Tonghui Road, Jiangbei District, Ningbo, Zhejiang Province, No. 777

Patentee after: Senges energy equipment (Ningbo) Co., Ltd.

Address before: 315000 Tonghui Road, Jiangbei District, Ningbo, Zhejiang Province, No. 777

Patentee before: SAMGAS TRANSMISSION & DISTRIBUTION EQUIPMENTS (NINGBO) CO., LTD.

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171107

Termination date: 20210123

CF01 Termination of patent right due to non-payment of annual fee