CN201764474U - Packaged boiler heating system - Google Patents

Packaged boiler heating system Download PDF

Info

Publication number
CN201764474U
CN201764474U CN2010202937336U CN201020293733U CN201764474U CN 201764474 U CN201764474 U CN 201764474U CN 2010202937336 U CN2010202937336 U CN 2010202937336U CN 201020293733 U CN201020293733 U CN 201020293733U CN 201764474 U CN201764474 U CN 201764474U
Authority
CN
China
Prior art keywords
interface
pipeline
water
heating system
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010202937336U
Other languages
Chinese (zh)
Inventor
曹红利
梁科
张晨
刘武琴
张金阳
何小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAANXI FANS GROUP XI'AN BOILER CO Ltd
Original Assignee
SHAANXI FANS GROUP XI'AN BOILER CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAANXI FANS GROUP XI'AN BOILER CO Ltd filed Critical SHAANXI FANS GROUP XI'AN BOILER CO Ltd
Priority to CN2010202937336U priority Critical patent/CN201764474U/en
Application granted granted Critical
Publication of CN201764474U publication Critical patent/CN201764474U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Heat-Pump Type And Storage Water Heaters (AREA)

Abstract

The utility model discloses a packaged boiler heating system, which comprises a box body and water processing equipment, a water tank, a water feeding pump, a boiler combustion unit and a steam distributing cylinder which are arranged inside the box body. The water processing equipment is connected with the water tank, the water feeding pump and the boiler combustion unit by pipelines sequentially. A first steam outlet on the boiler combustion unit is connected with a steam inlet on the steam distributing cylinder by a pipeline. A second steam outlet on the steam distributing cylinder is connected with a heat supply joint arranged outside the box body by the pipeline. The water processing equipment is also connected with a water inlet joint by the pipeline. The water inlet joint is positioned outside the box body. The utility model has the advantages that a mainframe of the boiler heating system and all accessory equipment are integrated in one box body; all joints are arranged outside the box body; the packaged boiler heating system is convenient to use; with the change of the work place, the whole boiler heating system can be moved to the new work place without being disassembled and assembled frequently by professional.

Description

A kind of portable boiler heating system
Technical field
The utility model relates to a kind of boiler heating system technical field, is specifically related to a kind of portable boiler heating system.
Background technology
At present, known boiler heating system is to use assembled in situ debugging back to use the user main frame (boiler, combustor), auxiliary device (water treatment facilities, softening water tank, feed pump, gas-distributing cylinder, switch board, fuel tank, system pipeline valve instrument etc.).When the work-yard changes, need main frame and auxiliary device complete removal thereof with the boiler heating system, class wrapping transports new job site to, is ressembled, is debugged by the professional, uses to the user and causes difficulty.
Summary of the invention
The purpose of this utility model provides a kind of portable boiler heating system, changes the frequently existing deficiency of dismounting to overcome existing boiler heating system because of the job site.
The technical scheme that the utility model adopted is that a kind of portable boiler heating system comprises casing and the water treatment facilities, water tank, feed pump, boiler combustion unit and the gas-distributing cylinder that are arranged on box house; Water treatment facilities are connected with water tank, feed pump and boiler combustion unit successively by pipeline; First venthole on the boiler combustion unit is connected by pipeline with the air intake on the gas-distributing cylinder; Second venthole on the gas-distributing cylinder is connected with the heat supply interface that is arranged on the casing outside by pipeline; Described water treatment facilities also are connected by pipeline with the water inlet interface, and the water inlet interface is positioned at the casing outside.
Wherein, the pipeline between water tank and the feed pump is provided with second valve.
It is characterized in that the boiler combustion unit is provided with electrical control cubicles.
Wherein, the boiler combustion unit is provided with the water level meter, and the water level meter is connected with water-level control apparatus.
Wherein, the water level meter is connected with the 3rd drainage interface by pipeline; Described the 3rd drainage interface is positioned at the casing outside.
Its feature also is, is connected with burner on the boiler combustion unit, and burner is connected with fuel tank by pipeline, and fuel tank is connected with fuel interface by pipeline; Described fuel tank and burner are positioned at box house, and fuel interface is positioned at the casing outside.
Wherein, be disposed with first valve, liquid cleaning device, regulator and stable-pressure device on the pipeline between fuel tank and the burner.
Its feature is that further the boiler combustion unit is connected with the second blowdown interface with second drainage interface by pipeline, and second drainage interface and the second blowdown interface are positioned at the casing outside.
Wherein, gas-distributing cylinder is connected with the 3rd blowdown interface by pipeline, and the 3rd blowdown interface is positioned at the casing outside.
Wherein, water tank is connected with first drainage interface with the first blowdown interface respectively by pipeline; The first blowdown interface and first drainage interface are positioned at the casing outside.
The beneficial effects of the utility model are, main frame and all auxiliary devices of boiler heating system concentrated in the casing, all interfaces are placed outside the casing convenient the use.Like this, along with the change of work-yard, need not whole boiler heating system can be moved and be filled to new job site by the frequent dismounting of professional.Can guarantee that heating system is independent, in the reliably working, conveniently change the job site that overall structure adopts the container-type prefabricated house, is convenient to lifting, transportation.
Description of drawings
Fig. 1 is the structure principle chart of the utility model portable boiler heating system.
Among the figure: 1. fuel tank, 2. water tank, 3. first valve, 4. water treatment facilities, 5. electrical control cubicles, 6. boiler combustion unit, 7. gas-distributing cylinder, 8. feed pump, 9. water inlet interface, the 10. first blowdown interface, 11. fuel interface, 12. power interfaces, 13. first drainage interfaces, 14. second drainage interface, 15. second blowdown interfaces, 16. the 3rd drainage interfaces, 17. the 3rd blowdown interface, 18. heat supply interfaces, 19. water level meters, 20. water level controller, 21. filters, 22. first ventholes, 23 burners, 24. casings, 25. Pressure gauges, 26. second valve, 27. liquid cleaning devices, 28. regulators, 29. stable-pressure device, 30. air intakes, 31. second ventholes.
The specific embodiment
Below in conjunction with the drawings and specific embodiments the utility model is elaborated.
As shown in Figure 1, the utility model provides a kind of portable boiler heating system, comprises casing 24 and the water treatment facilities 4, water tank 2, feed pump 8, boiler combustion unit 6 and the gas-distributing cylinder 7 that are arranged on casing 24 inside; Water treatment facilities 4 are connected with boiler combustion unit 6 with water tank 2, second valve 26, feed pump 8 successively by pipeline; First venthole 22 on the boiler combustion unit 6 is connected with air intake 30 pipelines on the gas-distributing cylinder 7; Second venthole 31 on the gas-distributing cylinder 7 is connected with heat supply interface 18 by pipeline; Water treatment facilities 4 also are connected with filter 21 by pipeline, and the effect of filter 21 is that the contaminant filter in 4 li water of water treatment facilities is fallen, and water treatment facilities 4 also are connected by pipeline with water inlet interface 9.Also be provided with electrical control cubicles 5, water level meter 19, Pressure gauge 25 and burner 23 on the boiler combustion unit 6 respectively.Water level meter 19 is connected with water-level control apparatus 20, and water level meter 19 is connected with the 3rd drainage interface 16 that is arranged on casing 24 outsides by pipeline.Pressure gauge 25 is used to measure the pressure in the boiler combustion unit 6, guarantees that boiler combustion unit 6 is safe in utilization.The burner 23 that is arranged on the boiler combustion unit 6 is connected with fuel tank 1 by pipeline, and fuel tank 1 is connected with fuel interface 11 by pipeline, and fuel tank 1 is positioned at casing 24 inside with burner 23, and fuel interface 11 is positioned at casing 24 outsides.Be disposed with first valve 3, liquid cleaning device 27, regulator 28 and stable-pressure device 29 on the pipeline between fuel tank 1 and the burner 23.
Boiler combustion unit 6 is connected with the second blowdown interface 15 with second drainage interface 14 by pipeline.Gas-distributing cylinder 7 is connected with the 3rd blowdown interface 17 by pipeline, and condensed water and dirt are discharged.Water tank 2 also is connected with first drainage interface 13 with the first blowdown interface 10 respectively by pipeline.
The water inlet interface 9 of this heating system, the first blowdown interface 10, first drainage interface 13, fuel interface 11, second drainage interface 14, the second blowdown interface 15, the 3rd drainage interface 16, the 3rd blowdown interface 17 and heat supply interface 18 all are arranged on casing 24 outsides; Casing 24 outsides also are provided with power interface 12, power for casing 24 interior all consumers by circuit.The miscellaneous part of native system all is to be positioned at casing 24 inside.
Operation principle of the present utility model is: water enters water treatment facilities 4 by water inlet interface 9, and water treatment facilities 4 are with water softening, and filter 21 falls the contaminant filter in the water again, makes the water that is input to 6 li of boiler combustion units meet the use standard.Start feed pump 8, the water after softening flows to water tank 2 by water treatment facilities 4, through second valve 26, feed pump 8, flows in the boiler combustion unit 6 again.Boiler combustion unit 6 is water vapour by burner 23 with the water thermal conversion, water vapour enters into gas-distributing cylinder 7 through first venthole 22 of boiler combustion unit 6 and the air intake 30 of gas-distributing cylinder 7 again, and gas-distributing cylinder 7 is dispensed to each heat supply interface 18 by second venthole 31 with water vapour and uses for the user.Fuel oil enters 1 li of fuel tank by fuel interface 11, and fuel oil makes fuel oil reach instructions for use through first valve 3, liquid cleaning device 27, regulator 28 and stable-pressure device 29 again, and fuel oil after treatment is imported into burner and gives 6 heat supplies of boiler combustion unit for 23 li.
Condensed water in the water tank 2 and dirt are discharged by the first blowdown interface 10, and first drainage interface 13 can be discharged the water in the water tank 2.Condensed water in the boiler combustion unit 6 and dirt are discharged by the second blowdown interface 15, and the water in the boiler combustion unit 6 is discharged by second drainage interface 14.Be arranged on the height that water level meter 19 on the boiler combustion unit 6 is used to measure boiler combustion unit 6 middle water levels, if water level is low, water-level control apparatus 20 is opened feed pump 8 by electrical control cubicles 5, supplies water for boiler combustion unit 6; If the water level height, water-level control apparatus 20 is closed feed pump 8 by electrical control cubicles 5, stops to supply water to boiler combustion unit 6.Also be provided with Pressure gauge 25 on the boiler combustion unit 6, be used to test the pressure in the boiler combustion unit 6, guarantee safe handling.
Each parts of native system all keep reliably being connected with casing 24, and whole heat supply work is all carried out in casing 24, is controlled automatically by the microprocessor in the electrical control cubicles 5, and pre-interface is only stayed in casing 24 outsides, are convenient to user installation and use.Whole boiler heating system is arranged on casing 24 inside, and compact conformation does not have and interferes, and electrical control cubicles 5 is compared the length that reduces pipeline attached on the boiler combustion unit 6 with the conventional boiler room.Can in manufactory, whole boiler heating system be installed in the casing 24 that meets movement requirement, reserve the required pipe joint of user.And whole system is carried out safety test and debugging installing the back, make its in transportation, move and remain complete, heating system independently in the process of dress.The user is in use as needing to change the system works place, only need the pipe joint removal outside the casing 24, whole casing is transported to newly, and connecting pipe joint again can normally use, and reaches still the be kept perfectly purpose of operate as normal of frequent mobile working place.

Claims (10)

1. a portable boiler heating system is characterized in that: comprise casing (24) and be arranged on casing (24) inner water treatment facilities (4), water tank (2), feed pump (8), boiler combustion unit (6) and gas-distributing cylinder (7); Water treatment facilities (4) are connected with water tank (2), feed pump (8) and boiler combustion unit (6) successively by pipeline; First venthole (22) on the boiler combustion unit (6) is connected by pipeline with air intake (30) on the gas-distributing cylinder (7); Second venthole (31) on the gas-distributing cylinder (7) is connected by the pipeline heat supply interface (18) outside with being arranged on casing (24); Described water treatment facilities (4) also are connected by pipeline with water inlet interface (9), and water inlet interface (9) is positioned at casing (24) outside.
2. boiler heating system according to claim 1 is characterized in that: the pipeline between described water tank (2) and the feed pump (8) is provided with second valve (26).
3. boiler heating system according to claim 1 is characterized in that: described boiler combustion unit (6) is provided with electrical control cubicles (5).
4. boiler heating system according to claim 3 is characterized in that: described boiler combustion unit (6) is provided with water level meter (19), and water level meter (19) is connected with water-level control apparatus (20).
5. boiler heating system according to claim 4 is characterized in that: described water level meter (19) is connected with the 3rd drainage interface (16) by pipeline; Described the 3rd drainage interface (16) is positioned at casing (24) outside.
6. boiler heating system according to claim 1, it is characterized in that: be connected with burner (23) on the described boiler combustion unit (6), burner (23) is connected with fuel tank (1) by pipeline, and fuel tank (1) is connected with fuel interface (11) by pipeline; Described fuel tank (1) is positioned at casing (24) inside with burner (23), and fuel interface (11) is positioned at casing (24) outside.
7. boiler heating system according to claim 6 is characterized in that: be disposed with first valve (3), liquid cleaning device (27), regulator (28) and stable-pressure device (29) on the pipeline between described fuel tank (1) and the burner (23).
8. according to the described boiler heating system of any one claim in the claim 1~7, it is characterized in that: described boiler combustion unit (6) is connected with the second blowdown interface (15) with second drainage interface (14) by pipeline, and described second drainage interface (14) and the second blowdown interface (15) are positioned at casing (24) outside.
9. according to the described boiler heating system of any one claim in the claim 1~7, it is characterized in that: described gas-distributing cylinder (7) is connected with the 3rd blowdown interface (17) by pipeline, and described the 3rd blowdown interface (17) is positioned at casing (24) outside.
10. according to the described boiler heating system of any one claim in the claim 1~7, it is characterized in that: described water tank (2) is connected with first drainage interface (13) with the first blowdown interface (10) respectively by pipeline; Described first blowdown interface (10) and first drainage interface (13) are positioned at casing (24) outside.
CN2010202937336U 2010-08-17 2010-08-17 Packaged boiler heating system Expired - Fee Related CN201764474U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010202937336U CN201764474U (en) 2010-08-17 2010-08-17 Packaged boiler heating system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010202937336U CN201764474U (en) 2010-08-17 2010-08-17 Packaged boiler heating system

Publications (1)

Publication Number Publication Date
CN201764474U true CN201764474U (en) 2011-03-16

Family

ID=43717082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010202937336U Expired - Fee Related CN201764474U (en) 2010-08-17 2010-08-17 Packaged boiler heating system

Country Status (1)

Country Link
CN (1) CN201764474U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106765493A (en) * 2016-12-19 2017-05-31 陈浩军 Portable Fast Installation heating plant and quick heating system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106765493A (en) * 2016-12-19 2017-05-31 陈浩军 Portable Fast Installation heating plant and quick heating system

Similar Documents

Publication Publication Date Title
CN204301824U (en) A kind of aircraft oil scale in situ detection device
CN203656576U (en) Pressure regulating and metering platform for fuel gas
CN209414198U (en) A kind of water pump assembly monitoring system
CN104632737B (en) Flying shear movable hydraulic station
CN201764474U (en) Packaged boiler heating system
CN204164669U (en) Intelligent gas adds smelly system
CN202228188U (en) Gas turbine engine lubricant system
CN106481983B (en) Urban gate station Gas Pressure Regulating Equipment
CN110409878A (en) A kind of arragement construction of nuclear power station oil or gas boiler room
CN203771036U (en) Skid-mounted device for gas station
CN203430482U (en) Wellhole-pipeline self-energy heating paraffin removal integrated device
CN2784715Y (en) Multifunctional heating stove for oil well
CN205504461U (en) Small -size on -vehicle formula moves vaporizing station
CN205110246U (en) Modular decontamination case
CN206222356U (en) Commercial kitchen liquid methanol fuel booster
CN2924492Y (en) Air energy-storage volume pipe liquid flow calibrating device
CN206944115U (en) A kind of steam boiler
CN108042029A (en) A kind of Portable shoer-bath
CN205782802U (en) A kind of can the fuel-steam generator of rate controlling
CN104929578B (en) A kind of small-sized electrical heating operation apparatus for work
CN111176205A (en) Intelligent management system and method for power generation of rainwater drop well
CN206361804U (en) A kind of heating system of cell
CN202692009U (en) Coal additive feeding system for boiler in power plant
CN105444150B (en) Multi-water-source water supply system
CN203478423U (en) Automatic gas exhausting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110316

Termination date: 20150817

EXPY Termination of patent right or utility model