CN203771036U - Skid-mounted device for gas station - Google Patents

Skid-mounted device for gas station Download PDF

Info

Publication number
CN203771036U
CN203771036U CN201420071536.8U CN201420071536U CN203771036U CN 203771036 U CN203771036 U CN 203771036U CN 201420071536 U CN201420071536 U CN 201420071536U CN 203771036 U CN203771036 U CN 203771036U
Authority
CN
China
Prior art keywords
ball valve
delivery pipe
manual ball
pipe
skid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201420071536.8U
Other languages
Chinese (zh)
Inventor
林子斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Senges energy equipment (Ningbo) Co., Ltd.
Original Assignee
SAMGAS TRANSMISSION & DISTRIBUTION EQUIPMENTS (NINGBO) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SAMGAS TRANSMISSION & DISTRIBUTION EQUIPMENTS (NINGBO) Co Ltd filed Critical SAMGAS TRANSMISSION & DISTRIBUTION EQUIPMENTS (NINGBO) Co Ltd
Priority to CN201420071536.8U priority Critical patent/CN203771036U/en
Application granted granted Critical
Publication of CN203771036U publication Critical patent/CN203771036U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pipeline Systems (AREA)

Abstract

A skid-mounted device for a gas station relates to a natural gas pressure regulating metering skid, and comprises a skid plate base; an air inlet manifold, an air manifold and an air outlet pipe are arranged on the skid plate base; two delivery pipes A are arranged between the air inlet manifold and the air manifold; a delivery pipe B and a delivery pipe C are arranged between the air manifold and the air outlet pipe; an insulated joint and an electric ball valve are arranged on the air inlet pipe; a manual ball valve A, a filter, a pressure regulating device and a manual ball valve B are sequentially arranged on each delivery pipe A; a manual ball valve C, a flow meter A and a manual ball valve D are sequentially arranged on the delivery pipe B; a regulating pipe for connecting the delivery pipe B with the delivery pipes C is arranged on the air manifold; a cut-off valve A is arranged on the regulating pipe; the regulating pipe is also connected with a blow-down pipe; a data transmitter is arranged on the slid plate base, and connected with the pressure regulating device, the flow meter and the electric ball valve. Compared with the prior art, the skid-mounted device adopts pressure regulating and measuring integrated design, has a reasonable structure, is convenient to operate, accurate in pressure regulation and measurement, safe and reliable, and has an operation remote-monitoring capability.

Description

Gas station skid mounted equipment
Technical field
The utility model relates to a kind of pressure regulation metering sled, especially a kind of natural gas pressure regulating metering sled.
Background technique
Because rock gas is a kind of clean energy resource, after burning, produce without waste residue, waste water, comparing coal, oil equal energy source has the advantages such as the safety of use, calorific value are high, clean.Along with the enhancing of environmental consciousness and popularizing of natural gas line, increasing cities and towns all adopt rock gas as the necessary energy in daily life.In the time that user provides combustion gas downstream by gas pipeline, need to, by the flow of combustion gas and drift limit in specified wave range, also to give accurate recording to the instantaneous flow of downstream user and integrated flow information.All there is the defect that pipeline is many, structure is more complicated, technology is lower, Security is low in present gas gathering and transportation pipe network structure, especially the voltage-regulating system of part webmaster separates separately with metering system, make gas distribution station volume large, it is required that it has not met city-building planning and development.Therefore, how designing the device of a set of like this pressure regulation and metering combination, when stating function in realization, also will be convenient to assembling and transport, ensure that product safety is reliable, simplify maintenance work, is those skilled in the art's technical problems to be solved.
Summary of the invention
The utility model, for deficiency of the prior art, provides a kind of gas station skid mounted equipment, and Integral design is measured in the pressure regulation of this equipment, installs simply, and rational in infrastructure, easy to operate, pressure regulation is accurate, measures accurately, safe and reliable, has more the ability of telemonitoring operation.
In order to solve the problems of the technologies described above, the utility model is solved by following technical proposals: gas station skid mounted equipment, comprise skid plate base, on described skid plate base, be provided with air inlet header, remittance tracheae and steam outlet pipe, between described air inlet header and described remittance tracheae, be provided with two first delivery pipes, between described remittance tracheae and described steam outlet pipe, be provided with second delivery pipe and the third delivery pipe, in described suction tude, be provided with insulating joint and electric ball valve, on described first delivery pipe, be disposed with first manual ball valve, filter, pressure governor and second manual ball valve, on described second delivery pipe, be disposed with the third manual ball valve, first flowmeter and fourth manual ball valve, on described remittance tracheae, be provided with the adjutage that connects described second delivery pipe and described the third delivery pipe, described adjutage connects one end of described second delivery pipe in the downstream of described first flowmeter and the upstream of described fourth manual ball valve, on described adjutage, be provided with several first block valves, described adjutage is also connected with blow-down pipe, on described skid plate base, be also provided with data transmitter, described data transmitter connects described pressure governor and described flowmeter.Arrange like this, between air inlet header and remittance tracheae, be provided with two-way first delivery pipe, between remittance tracheae and steam outlet pipe, be provided with second delivery pipe and the third delivery pipe; Can move on a road like this, a road is for subsequent use, can realize under the prerequisite of not stopping the supple of gas or steam whole equipment is maintained and safeguarded.On air inlet header, be provided with insulating joint, protect whole equipment to avoid the electrostatic hazard of upstream line.On first delivery pipe, be also provided with pressure governor, mainly upstream gas carried out to pressure regulation operation, guarantee that gas is transferred to downstream stably.Second delivery pipe is a kind of sounding pipe, also has first flowmeter on second delivery pipe, because second delivery pipe is sounding pipe, her length will match with first flowmeter, so just can accurately measure the flow of gas.If do not need measuring flow gas directly to flow out from steam outlet pipe by the third delivery pipe.On remittance tracheae, be also provided with adjutage, adjutage connects blow-down pipe, the gas in blowdown piping so rapidly, convenient maintenance or Emergency time emptying.Further, on skid plate base, be also provided with data transmitter, can or control electric ball valve and block air inlet header by data transmitter remote monitoring, pressure governor is adjusted gas pressure, data on delivery flow rate meter, reach the object of remote monitoring, greatly reduced workman's quantity and working strength, reduced cost.
In technique scheme, preferred, on the third described delivery pipe, be disposed with pungent manual ball valve, second flowmeter and the ninth of the ten Heavenly Stems manual ball valve.Arrange like this, if necessary, can also on the third delivery pipe, be provided with second flowmeter, when the third delivery pipe becomes after sounding pipe, the length of the third delivery pipe will match with second flowmeter, so just can accurately measure gas flow.In the time that second delivery pipe need to overhaul or damage, need again the flow of mensurated gas composition, at this moment gas can pass through the third delivery pipe, allows the second flowmeter on the third delivery pipe carry out gasmetry.To move a road for subsequent use the third delivery pipe and second delivery pipe one tunnel under normal circumstances.
In technique scheme, preferably, on described first delivery pipe, be also disposed with penta manual ball valve and own manual ball valve, penta described manual ball valve and described own manual ball valve are arranged on described filter downstream and described pressure governor upstream, on described remittance tracheae, be also provided with fourth delivery pipe, described fourth delivery pipe is connected with ram's horns, and described ram's horns connects respectively the first delivery pipe described in two, and tie point is in penta described manual ball valve downstream and own manual ball valve upstream.Arrange like this, in particular cases, the gas entering from upstream can be by pressure governor but is directly entered remittance tracheae by ram's horns.
In technique scheme, preferred, on described skid plate base, be provided with several fixed installation holes.Arrange like this, whole device is all arranged on and is fixed on skid plate base, just can fix whole device as long as fix skid plate base, mobile if device needs, and only need to just can easily carry whole device by mobile skid plate base.
In technique scheme, preferred, the filter bottom described in two is connected with drain pipe, is provided with several second block valves on described drain pipe.Arrange like this, be deposited in the pollutant in filter, can be by regular the cleaning out of drain pipe.
Compared with prior art, the beneficial effects of the utility model are: Integral design is measured in the pressure regulation of this equipment, install simply, and rational in infrastructure, easy to operate, pressure regulation is accurate, measure accurately, safe and reliable, have more the ability of telemonitoring operation.
Brief description of the drawings
Fig. 1 is the utility model schematic diagram.
Embodiment
Below in conjunction with accompanying drawing and embodiment, the utility model is described in further detail.As shown in Figure 1, a kind of gas station skid mounted equipment, comprises skid plate base 1, is provided with several fixed installation holes 11 on skid plate base 1.Skid plate base 1 can be fixed on Anywhere by fixed installation hole 11, if after removing also and only need to getting loose by fixed installation hole 11, integrated moving skid plate base 1, no longer needs to reappear the pipeline of installing on skid plate base 1.On skid plate base 1, be provided with air inlet header 2, remittance tracheae 3 and steam outlet pipe 4, between air inlet header 2 and remittance tracheae 3, be provided with two first delivery pipes 5, converge and be provided with second delivery pipe 6 and the third delivery pipe 7 between tracheae 3 and steam outlet pipe 4, in suction tude 3, be provided with insulating joint 21 and electric ball valve 22, on first delivery pipe 5, be disposed with first manual ball valve 51, filter 52, penta manual ball valve 53, own manual ball valve 54, pressure governor 55 and second manual ball valve 56.On remittance tracheae 3, be also provided with fourth delivery pipe 31, fourth delivery pipe 31 is connected with ram's horns 32, ram's horns 32 connects respectively two first delivery pipes 5, and tie point is in penta manual ball valve 53 downstreams and own manual ball valve 54 upstreams, is also provided with moving ball valve 311 in heptan on fourth delivery pipe 31.On second delivery pipe 6, be disposed with on the third manual ball valve 61, first flowmeter 62 and fourth manual ball valve 63, the third delivery pipes 7, be disposed with pungent manual ball valve 71, second flowmeter 72 and the ninth of the ten Heavenly Stems manual ball valve 73.On remittance tracheae 3, be provided with the adjutage 33 that connects second delivery pipe 6 and the third delivery pipe 7, adjutage 33 connects one end of second delivery pipe 6 in the downstream of first flowmeter 62 and the upstream of fourth manual ball valve 63, one end that adjutage 33 connects the third delivery pipe 7 is in the downstream of second flowmeter 72 and manual ball valve in the ninth of the ten Heavenly Stems 73 upstream, on adjutage 33, be provided with the first block valve 331 of the corresponding second delivery pipe 6 of difference and the third delivery pipe 7, adjutage 33 is also connected with blow-down pipe 34, filter 52 bottoms are connected with drain pipe 9, on drain pipe 9, be provided with the second block valve 91 of filter 52 on two corresponding first delivery pipes 5 of difference.On skid plate base 1, be also provided with data transmitter 12, data transmitter 12 connects pressure governor 55 and described first flowmeter 62, second flowmeter 63 and electric ball valve 22.Whole like this device is provided with two-way first delivery pipe 5 between air inlet header 2 and remittance tracheae 3, between remittance tracheae 3 and steam outlet pipe 4, is provided with second delivery pipe 6 and the third delivery pipe 7; Can move on a road like this, a road is for subsequent use, can realize under the prerequisite of not stopping the supple of gas or steam whole equipment is maintained and safeguarded.On skid plate base 1, be also provided with data transmitter 12, can or control electric ball valve 22 and block air inlet header 2 by data transmitter 12 remote monitoring, pressure governor 55 is adjusted gas pressure, data on transmission first flowmeter 62 or second flowmeter 72, reach the object of remote monitoring, the quantity and the working strength that have greatly reduced workman, reduced cost.

Claims (5)

1. gas station skid mounted equipment, comprise skid plate base (1), on described skid plate base (1), be provided with air inlet header (2), remittance tracheae (3) and steam outlet pipe (4), between described air inlet header (2) and described remittance tracheae (3), be provided with two first delivery pipes (5), between described remittance tracheae (3) and described steam outlet pipe (4), be provided with second delivery pipe (6) and the third delivery pipe (7), it is characterized by, in described suction tude (2), be provided with insulating joint (21) and electric ball valve (22), on described first delivery pipe (5), be disposed with first manual ball valve (51), filter (52), pressure governor (55) and second manual ball valve (56), on described second delivery pipe (6), be disposed with the third manual ball valve (61), first flowmeter (62) and fourth manual ball valve (63), on described remittance tracheae (3), be provided with the adjutage (33) that connects described second delivery pipe (6) and described the third delivery pipe (7), described adjutage (33) connects one end of described second delivery pipe (6) in the downstream of described first flowmeter (62) and the upstream of described fourth manual ball valve (63), on described adjutage (33), be provided with several first block valves (331), described adjutage (33) is also connected with blow-down pipe (34), on described skid plate base (1), be also provided with data transmitter (12), described data transmitter (12) connects described pressure governor (55), described first flowmeter (62) and described electric ball valve (22).
2. gas station according to claim 1 skid mounted equipment, it is characterized by, on described the third delivery pipe (7), be disposed with pungent manual ball valve (71), second flowmeter (72) and manual ball valve in the ninth of the ten Heavenly Stems (73), described data transmitter (12) connects described second flowmeter (72).
3. gas station according to claim 1 skid mounted equipment, it is characterized by, on described first delivery pipe (5), be also disposed with penta manual ball valve (53) and own manual ball valve (54), described penta manual ball valve (53) and described own manual ball valve (54) are arranged on described filter (52) downstream and described pressure governor (55) upstream, on described remittance tracheae (3), be also provided with fourth delivery pipe (31), described fourth delivery pipe (31) is connected with ram's horns (32), described ram's horns (32) connects respectively the first delivery pipe (5) described in two, and tie point is in described penta manual ball valve (53) downstream and described own manual ball valve (54) upstream.
4. gas station according to claim 1 skid mounted equipment, is characterized by, and is provided with several fixed installation holes (11) on described skid plate base (1).
5. gas station according to claim 1 skid mounted equipment, is characterized by, and filter (52) bottom described in two is connected with drain pipe (9), is provided with several second block valves (91) on described drain pipe (9).
CN201420071536.8U 2014-02-19 2014-02-19 Skid-mounted device for gas station Expired - Fee Related CN203771036U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420071536.8U CN203771036U (en) 2014-02-19 2014-02-19 Skid-mounted device for gas station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420071536.8U CN203771036U (en) 2014-02-19 2014-02-19 Skid-mounted device for gas station

Publications (1)

Publication Number Publication Date
CN203771036U true CN203771036U (en) 2014-08-13

Family

ID=51288227

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420071536.8U Expired - Fee Related CN203771036U (en) 2014-02-19 2014-02-19 Skid-mounted device for gas station

Country Status (1)

Country Link
CN (1) CN203771036U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107091408A (en) * 2017-07-03 2017-08-25 常熟市上海飞奥压力容器制造有限公司 Two-way gas pressure regulating station
CN107270126A (en) * 2017-08-08 2017-10-20 盘锦奥德燃气装备制造有限公司 Large-scale pressure regulation metering sled
WO2019022678A1 (en) * 2017-07-26 2019-01-31 Ptt Public Company Limited Gas metering and regulating station for hdpe pipeline network
CN110925601A (en) * 2019-12-31 2020-03-27 天津华迈燃气装备股份有限公司 Pipeline gas storage type air pressure regulating device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107091408A (en) * 2017-07-03 2017-08-25 常熟市上海飞奥压力容器制造有限公司 Two-way gas pressure regulating station
WO2019022678A1 (en) * 2017-07-26 2019-01-31 Ptt Public Company Limited Gas metering and regulating station for hdpe pipeline network
CN107270126A (en) * 2017-08-08 2017-10-20 盘锦奥德燃气装备制造有限公司 Large-scale pressure regulation metering sled
CN110925601A (en) * 2019-12-31 2020-03-27 天津华迈燃气装备股份有限公司 Pipeline gas storage type air pressure regulating device

Similar Documents

Publication Publication Date Title
CN203771036U (en) Skid-mounted device for gas station
CN103306968B (en) transformer oil pump test device and test method thereof
CN102373921A (en) Vehicular oil/gas filed ground test system
CN201096268Y (en) Flux monitoring -type gas pressure regulating apparatus
CN103939746A (en) Well mouth prizer and integrated device including well mouth prizer
CN205261210U (en) LNG loading sledge integrated device
CN202901829U (en) Skid-mounted natural gas gathering and transporting device with gas collection, metering and pipe cleaning functions
CN201991517U (en) Multiphase continuous and separately measuring device for oil well
CN203130063U (en) Skid-mounted intelligent well selection metering system
CN102262105B (en) Dryness and flow measurement system for wet steam pipe network
CN201730604U (en) Spiral passive gas-liquid separator
CN202598128U (en) Skid-mounted type natural gas gasification pressure-regulating and measuring output device
CN203162237U (en) Gas pressure regulation valve
CN208670599U (en) A kind of coal bed gas well site gas-liquid gathering and transporting device
CN203798391U (en) Gas metering skid with real flow comparison function
CN201772261U (en) External output metering prizer
CN205117328U (en) Sled dress formula oil field individual well metering device
CN203444347U (en) Automatic measurement and control system of skidded three-phase separator
CN205261234U (en) Measurement integrated device cools down
CN205297524U (en) Portable oil field well site gas -liquid metering device
CN205155556U (en) Point supplies gasification equipment
CN203241082U (en) Fuel gas metering sledge
CN202141692U (en) Dryness flow measurement system of wet steam pipe network
CN203940234U (en) A kind of sledge dress crude oil metering device with filtration and check function
CN204988381U (en) It is experimental with condensate flow measuring device among flow nozzle access power plant DCS

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: Tonghui road Jiangbei District 315033 Zhejiang city of Ningbo province No. 777

Patentee after: Senges energy equipment (Ningbo) Co., Ltd.

Address before: 315033 No. 738-1, Changyang Road, Jiangbei District, Zhejiang, Ningbo

Patentee before: SAMGAS TRANSMISSION & DISTRIBUTION EQUIPMENTS (NINGBO) CO., LTD.

CP03 Change of name, title or address
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140813

Termination date: 20190219

CF01 Termination of patent right due to non-payment of annual fee