CN206581303U - A kind of seabed vacuum tunnel of band sightseeing function - Google Patents

A kind of seabed vacuum tunnel of band sightseeing function Download PDF

Info

Publication number
CN206581303U
CN206581303U CN201720025563.5U CN201720025563U CN206581303U CN 206581303 U CN206581303 U CN 206581303U CN 201720025563 U CN201720025563 U CN 201720025563U CN 206581303 U CN206581303 U CN 206581303U
Authority
CN
China
Prior art keywords
tunnel
seabed
concrete structure
seabed tunnel
vacuum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720025563.5U
Other languages
Chinese (zh)
Inventor
贺维国
范国刚
洪开荣
宋仪
张美琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
Original Assignee
CRTG Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRTG Survey and Design Institute Co Ltd filed Critical CRTG Survey and Design Institute Co Ltd
Priority to CN201720025563.5U priority Critical patent/CN206581303U/en
Application granted granted Critical
Publication of CN206581303U publication Critical patent/CN206581303U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

A kind of seabed vacuum tunnel of band sightseeing function, the utility model is related to seabed tunnel technical field;Seabed tunnel body is made up of several tunnel segments, and described tunnel segment is made up of seabed tunnel upper transparent structure, seabed tunnel lower concrete structure, seabed tunnel joint arched concrete structure, foundation pile, supporting plate;The top of seabed tunnel lower concrete structure, which is provided between seabed tunnel upper transparent structure, every two adjacent tunnel segments, passes through the connection of seabed tunnel joint arched concrete structure;Described supporting plate is arranged on the junction of adjacent tunnel segmentation;Described seabed tunnel body is shape of a hoof seabed tunnel body;Described seabed tunnel lower concrete structure is groove-shaped steel reinforcement concrete structure;Described seabed tunnel upper transparent structure is circular arc high-strength transparence glass;Described seabed tunnel body is vacuum seabed tunnel body.Its constructing tunnel difficulty is small, technique is simple, speed of application is fast, cost is low, and practicality is stronger.

Description

A kind of seabed vacuum tunnel of band sightseeing function
Technical field
The utility model is related to seabed tunnel technical field, and in particular to a kind of seabed vacuum tunnel of band sightseeing function.
Background technology
The concept of " building ocean power " enters 18 big reports, and marine economy has turned into pulls China's national economy development Strong engine.Ocean power is built, to possess powerful in terms of exploitation ocean, using ocean, protection ocean, management and control ocean Comprehensive strength, in these areas, Development of Marine traffic can play important and unique positive role.
The development spaces such as sea traffic is related under beach, sea, sea, coastal waters, ocean.Sea traffic development is with cleverly Flexible way ensures national interests, and the rights and interests of blue territory are safeguarded in the way of fusion.The development of Marine Tourism is directed not only to neck Native safety, is directed to economic security, information security, energy security.Tunnel is then to connect ocean islands and the important way in continent One of.
Seabed tunnel is often very long, although present high ferro can substantially reduce people's trip on the way or crossing-river tunnel Time used, but pursuit of the people to speed and efficiency never stop.Under unlimited atmospheric condition, restriction high ferro highest warp The principal element for speed of helping is dense air, the problem of also facing same for seabed major long tunnel:Air drag and train The speed of service square into approximate proportional relation, speed improves 2 times, and air drag will increase to 4 times.When train is with per hour 200 When kilometer traveling, air drag accounts for 70% of drag overall or so;Harmony CRH380A runs out of speed per hour 486.1 in Beijing-Shanghai express railway During kilometer, aerodynamic drag has exceeded the 92% of drag overall;If going to more than 500 kilometers, in drag overall, more than 95% is all pneumatic Resistance.Bullet train speed per hour is more than 400 kilometers, energy consumption and noise severe overweight in dense atmosphere, it is impossible to which input business is transported Battalion.If enclosed tunnel can be built, it is evacuated by being evacuated station, can be achieved with ultrahigh speed, the low noise operation of bullet train, That is seabed " vacuum tunnel superexpress train ".
If benthal tourism can be gone sightseeing and ultrahigh speed vacuum tunnel transportation trade is combined, tunnel can run super Bullet train, can also expand the development traveled under sea, make tunnelling function more perfect.
Utility model content
The purpose of this utility model is that defect and deficiency for prior art, there is provided one kind is simple in construction, is designed and closed The seabed vacuum tunnel of reason, band sightseeing function easy to use, its constructing tunnel difficulty is small, technique is simple, speed of application is fast, into This is low, and practicality is stronger.
To achieve the above object, the technical solution adopted in the utility model is:It includes seabed tunnel body, seabed tunnel Body is arranged on below sea;Seabed tunnel body is made up of several tunnel segments, and described tunnel segment is on seabed tunnel Portion's transparent configuration, seabed tunnel lower concrete structure, seabed tunnel joint arched concrete structure, foundation pile, supporting plate are constituted; The top of seabed tunnel lower concrete structure is provided between seabed tunnel upper transparent structure, every two adjacent tunnel segments Connected by seabed tunnel joint arched concrete structure, lower edge and the seabed tunnel of seabed tunnel joint arched concrete structure The top edge connection of road lower concrete structure;Described supporting plate is arranged on the junction of adjacent tunnel segmentation, and the bottom of supporting plate Portion is provided with several foundation piles;Described seabed tunnel body is shape of a hoof seabed tunnel body;Mix described seabed tunnel bottom Xtah Crude Clay structure is groove-shaped steel reinforcement concrete structure;Described seabed tunnel upper transparent structure is circular arc high-strength transparence glass Glass;Described seabed tunnel body is vacuum seabed tunnel body.
Further, the bottom of described seabed tunnel lower concrete structure is arranged on the bottom in seabed, its top two End dew is located at the top in seabed.
Further, the sectional area of described seabed tunnel body is between 12 ㎡ to 40 ㎡.
Further, several described tunnel segments to form tunnel in marine be docked and connected, and is then discharged out in tunnel empty Gas, forms vacuum.
Further, the top and the left and right sides of described seabed tunnel body are without earthing, and bottom contacts setting with sea bed.
After said structure, the utility model has the beneficial effect that:A kind of band sightseeing function described in the utility model Seabed vacuum tunnel, its constructing tunnel difficulty is small, technique is simple, speed of application is fast, cost is low, and practicality is stronger, and this practicality is new Type has simple in construction, and it is reasonable to set, the advantages of low manufacture cost.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art Or the accompanying drawing used required in description of the prior art is briefly described, it should be apparent that, drawings in the following description are only It is some embodiments of the present utility model, for those of ordinary skill in the art, before creative labor is not paid Put, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is structural representation of the present utility model.
Fig. 2 be in Fig. 1 A-A to sectional view.
Description of reference numerals:
Sea 1, seabed 2, seabed tunnel upper transparent structure 3, seabed tunnel lower concrete structure 4, seabed tunnel connect Head arched concrete structure 5, foundation pile 6, supporting plate 7.
Embodiment
The utility model is further described below in conjunction with the accompanying drawings.
Referring to as depicted in figs. 1 and 2, the technical scheme that present embodiment is used is:It includes seabed tunnel body, Seabed tunnel body is arranged on the lower section of sea 1;Seabed tunnel body is made up of several tunnel segments, and described tunnel segment is by sea Bottom tunnel upper transparent structure 3, seabed tunnel lower concrete structure 4, seabed tunnel joint arched concrete structure 5, basis Stake 6, supporting plate 7 are constituted;The top of seabed tunnel lower concrete structure 4 is provided with seabed tunnel upper transparent structure 3, per adjacent Connected between two tunnel segments by seabed tunnel joint arched concrete structure 5, seabed tunnel joint arched concrete knot The lower edge of structure 5 is connected with the top edge of seabed tunnel lower concrete structure 4;Described supporting plate 7 is arranged on adjacent tunnel point The junction of section, and the bottom of supporting plate 7 is provided with several foundation piles 6;Described seabed tunnel body is shape of a hoof seabed tunnel sheet Body;Described seabed tunnel lower concrete structure 4 is groove-shaped steel reinforcement concrete structure;Described seabed tunnel upper transparent knot Structure 3 is circular arc high-strength transparence glass;Described seabed tunnel body is vacuum seabed tunnel body.
Further, the bottom of described seabed tunnel lower concrete structure 4 is arranged on the bottom in seabed 2, its top Reveal the top for being located at seabed 2 in two ends.
Further, the sectional area of described seabed tunnel body is between 12 ㎡ to 40 ㎡, and prefabricated difficulty is small, prefabricated speed Degree is fast.
Further, several described tunnel segments to form tunnel in marine be docked and connected, and is then discharged out in tunnel empty Gas, forms vacuum.
Further, the top and the left and right sides of described seabed tunnel body are without earthing, and bottom contacts setting with sea bed.
The construction method of present embodiment is as follows:
1st, the seabed tunnel plane with sightseeing function, vertical line type are fitted according to underwater topography and line requirements;
2nd, according to circuit is flat, vertical line type, seabed tunnel is divided into some sections, prefabricated bottom is groove-shaped steel reinforcement by land The seabed tunnel lower concrete structure 4 of concrete, it is the seabed tunnel top that circular arc high strength glass is made to install top Transparent configuration 3, every section of tunnel joint is seabed tunnel joint arched concrete structure 5;
3rd, every section of seabed tunnel joint arched concrete structure 5 nearby sets foundation pile 6 and supporting plate 7, the top surface absolute altitude of supporting plate 7 It is identical with the elevation of bottom of seabed tunnel structure base slab 4;
4th, can prefabricated tunnel structure, and pre- on the outside of tunnel concrete structure simultaneously during construction pile foundation 6 and supporting plate 7 Stay lifting components;
5th, after the completion of every section of tunnel is prefabricated, it is lifted to docking in water, connection forms the seabed tunnel with sightseeing function;
6th, when tunnel is runed, air in tunnel is taken away, vacuum is formed.Passenger can take closed and with sightseeing window Superexpress train appreciates seabed landscape.
After said structure, present embodiment has the beneficial effect that:A kind of band described in present embodiment is seen The seabed vacuum tunnel of light function, its constructing tunnel difficulty is small, technique is simple, speed of application is fast, cost is low, and practicality is stronger, The utility model has simple in construction, and it is reasonable to set, the advantages of low manufacture cost.
It is described above, only to illustrate the technical solution of the utility model and unrestricted, those of ordinary skill in the art couple Other modifications or equivalent substitution that the technical solution of the utility model is made, without departing from technical solutions of the utility model Spirit and scope, all should cover among right of the present utility model.

Claims (4)

1. a kind of seabed vacuum tunnel of band sightseeing function, it is characterised in that:It includes seabed tunnel body, seabed tunnel body It is arranged on below sea;Seabed tunnel body is made up of several tunnel segments, and described tunnel segment is saturating by seabed tunnel top Bright structure, seabed tunnel lower concrete structure, seabed tunnel joint arched concrete structure, foundation pile, supporting plate are constituted;Seabed The top of tunnel bottom concrete structure, which is provided between seabed tunnel upper transparent structure, every two adjacent tunnel segments, to be passed through Seabed tunnel joint arched concrete structure is connected, lower edge and the seabed tunnel bottom of seabed tunnel joint arched concrete structure The top edge connection of portion's concrete structure;Described supporting plate is arranged on the junction of adjacent tunnel segmentation, and the bottom of supporting plate is set There are several foundation piles;Described seabed tunnel body is shape of a hoof seabed tunnel body;Described seabed tunnel lower concrete Structure is groove-shaped steel reinforcement concrete structure;Described seabed tunnel upper transparent structure is circular arc high-strength transparence glass;Institute The seabed tunnel body stated is vacuum seabed tunnel body.
2. a kind of seabed vacuum tunnel of band sightseeing function according to claim 1, it is characterised in that:Described seabed tunnel The bottom of road lower concrete structure is arranged on the bottom in seabed, and its both upper ends thereof reveals the top for being located at seabed.
3. a kind of seabed vacuum tunnel of band sightseeing function according to claim 1, it is characterised in that:Described seabed tunnel The sectional area of road body is between 12 ㎡ to 40 ㎡.
4. a kind of seabed vacuum tunnel of band sightseeing function according to claim 1, it is characterised in that:Described seabed tunnel The top and the left and right sides of road body contact setting with sea bed without earthing, bottom.
CN201720025563.5U 2017-01-11 2017-01-11 A kind of seabed vacuum tunnel of band sightseeing function Active CN206581303U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720025563.5U CN206581303U (en) 2017-01-11 2017-01-11 A kind of seabed vacuum tunnel of band sightseeing function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720025563.5U CN206581303U (en) 2017-01-11 2017-01-11 A kind of seabed vacuum tunnel of band sightseeing function

Publications (1)

Publication Number Publication Date
CN206581303U true CN206581303U (en) 2017-10-24

Family

ID=60110613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720025563.5U Active CN206581303U (en) 2017-01-11 2017-01-11 A kind of seabed vacuum tunnel of band sightseeing function

Country Status (1)

Country Link
CN (1) CN206581303U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759494A (en) * 2017-01-11 2017-05-31 中铁隧道勘测设计院有限公司 A kind of seabed vacuum tunnel with sightseeing function
CN108343088A (en) * 2018-05-16 2018-07-31 上海市城市建设设计研究总院(集团)有限公司 Without earthing along river open trench tunnel structure
CN108594783A (en) * 2018-07-03 2018-09-28 成都博士信智能科技发展有限公司 Aeroamphibious tubular type system and aeroamphibious experiencing system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759494A (en) * 2017-01-11 2017-05-31 中铁隧道勘测设计院有限公司 A kind of seabed vacuum tunnel with sightseeing function
CN108343088A (en) * 2018-05-16 2018-07-31 上海市城市建设设计研究总院(集团)有限公司 Without earthing along river open trench tunnel structure
CN108343088B (en) * 2018-05-16 2023-07-04 上海市城市建设设计研究总院(集团)有限公司 Non-earthing open cut tunnel structure along river
CN108594783A (en) * 2018-07-03 2018-09-28 成都博士信智能科技发展有限公司 Aeroamphibious tubular type system and aeroamphibious experiencing system
CN108594783B (en) * 2018-07-03 2024-08-20 成都博士信智能科技发展有限公司 Air-water pipe system and air-water experience system

Similar Documents

Publication Publication Date Title
CN206581303U (en) A kind of seabed vacuum tunnel of band sightseeing function
CN204919245U (en) Overhead bridge in city - mixed transportation systems of sky rail
CN106759494A (en) A kind of seabed vacuum tunnel with sightseeing function
CN201620318U (en) Railroad bed sunshade shed in permafrost region
CN103382713A (en) Foundation quay wall structure and construction method thereof
CN101311413A (en) Process for using underground passage combined with roads on ground as passage of trolley bus
CN204780646U (en) Electric Railway's windbreak under strong wind environment
CN101307659A (en) Storied building type channel
CN201786364U (en) Cable tunnel waterproof structure layer
CN107697080A (en) A kind of vacuum high-speed transit pipeline
CN206581302U (en) A kind of joint connection manner of vacuum submerged tunnel
CN201738252U (en) Semi-enclosed hurricane resistant corridor
CN206737124U (en) One kind is tethered at space structure system
CN106854876A (en) A kind of joint connection manner of vacuum submerged tunnel
CN205276236U (en) Inverted -siphon formula two -way rectilinear ship lift of passing a bridge
CN205603992U (en) Prefabricated road deck of RPC shell light aggregate concrete base member
CN206581304U (en) A kind of structure type in Seafloor sightseeing tunnel
CN205714225U (en) A kind of railway culvert, tunnel defect wavy metal culvert pipe liner bracing means
CN205501859U (en) Wind -proof construction who increases on existing wind -break wall
CN101581159A (en) Building channel
CN212556715U (en) Stone-structure lamp pile
CN205223778U (en) Porous cement road surface of water resistance heat structural layer is protected in high reflection
CN204023349U (en) Backroad hard surface system
CN206888014U (en) A kind of full intercommunicating system of underwater grade separation of double Y-shapeds
CN106894447A (en) A kind of structure type in Seafloor sightseeing tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180625

Address after: 300000 room 2-3116, 88 Ring Road South, Tianjin Airport Economic Zone

Patentee after: CHINA RAILWAY LIUYUAN GROUP CO., LTD.

Address before: 300000 Hebei Avenue, new Hongqiao, Hongqiao District, Tianjin City, No. 1

Patentee before: Zhongtie Tunnel Survey and Design Inst., Ltd.