CN206562786U - A kind of metal Roof construction safety protection device - Google Patents

A kind of metal Roof construction safety protection device Download PDF

Info

Publication number
CN206562786U
CN206562786U CN201720054382.5U CN201720054382U CN206562786U CN 206562786 U CN206562786 U CN 206562786U CN 201720054382 U CN201720054382 U CN 201720054382U CN 206562786 U CN206562786 U CN 206562786U
Authority
CN
China
Prior art keywords
latch fitting
metal roof
lock
vertical rod
safe vertical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720054382.5U
Other languages
Chinese (zh)
Inventor
徐坤
姚苇
何洪
段其磊
贺印
黄思成
张海龙
涂永博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Industry Corp Ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201720054382.5U priority Critical patent/CN206562786U/en
Application granted granted Critical
Publication of CN206562786U publication Critical patent/CN206562786U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model is applied to the realm of building construction, there is provided a kind of metal Roof construction safety protection device, including safe vertical rod and safety rope, also include fixed locker, the fixing lock folder includes the first latch fitting and the second latch fitting, first latch fitting is fastened on the lock seaming bearing of metal Roof and is removably connected jointly with the second latch fitting, and the safe vertical rod is detachably connected to the top of the first latch fitting, is drawn between adjacent two safe vertical rods and is provided with the safety rope.The first latch fitting and the second latch fitting of fixed locker are fastened on lock seaming bearing, and removably connect by the protector jointly using the lock seaming bearing laid on the metal Roof of completion.Safe vertical rod is detachably connected to the top of first latch fitting, is drawn between adjacent two safe vertical rods and sets safety rope, so as to form horizontal protective.Because the fixed locker and the safe vertical rod are respectively provided with detachability, therefore peace can be easy to tear open, each part can be recycled, and reduce construction cost.

Description

A kind of metal Roof construction safety protection device
Technical field
The utility model belongs to the realm of building construction, more particularly to a kind of metal Roof construction safety protection device.
Background technology
When metal Roof carries out construction operation, it is necessary to set protector in roofing, slided to prevent workmen from roof Fall.
At present, by the way of the facing and welded using safe vertical rod and keel more than the horizontal protective of side of metal Roof laying stage.Root According to the trend of metal Roof keel, disposable security protection vertical rod is made, the connection of node carries out lower unit metal typically using welding Again welded and installed after this security protection vertical rod is cut again during roofing operation.Security protection vertical rod needs constantly welding, cutting, adds The proportion of goods damageds of material, reduce access times.
Meanwhile, when carrying out next step operation, because metal Roof has laid completion, it is impossible to recycle under metal Roof The keel of side build horizontal protective.Generally require outwards to encorbelment a segment type steel in cornice region as conversion, significantly increase The risk of operation, and, it has not been convenient to peace is torn open, is wasted time and energy.
Utility model content
Technical problem to be solved in the utility model is a kind of metal Roof construction safety protection device of offer, it is intended to solved Certainly because after the completion of the laying of metal Roof in the prior art and inconvenience security protection is set the problem of.
In order to solve the above technical problems, the utility model is achieved in that a kind of metal Roof construction safety protection dress Put, including safe vertical rod and safety rope, in addition to fixed locker, the fixing lock, which is pressed from both sides, includes the first latch fitting and the second latch fitting, institute State the first latch fitting to be fastened on the lock seaming bearing of metal Roof and be removably connected jointly with second latch fitting, the safety Vertical rod is detachably connected to the top of first latch fitting, is drawn between adjacent two safe vertical rods and is provided with the safety rope.
Further, first latch fitting includes steel plate, lock and steel pipe, and the steel-pipe welding is on the steel plate top Portion, the lock, which is welded on the steel plate bottom, the periphery of the steel pipe, offers bolt hole, the safe vertical rod insertion institute State steel pipe, and with the steel pipe bolt connection.
Further, the lock is provided with spacing preiection, and the top of second latch fitting is separably fastened on described In the groove that spacing preiection is formed with the steel plate.
Further, the lock and the second latch fitting bolt connection.
Compared with prior art, beneficial effect is the utility model:A kind of metal Roof construction peace of the present utility model Full protection device, using the lock seaming bearing laid on the metal Roof of completion, by the first latch fitting and second of fixed locker Latch fitting is fastened on the lock seaming bearing jointly, and first latch fitting is removably connected with second latch fitting, and will peace Full vertical rod is detachably connected to the top of first latch fitting, is drawn between adjacent two safe vertical rods and sets safety rope, so that Form horizontal protective.Because the fixed locker and the safe vertical rod are respectively provided with detachability, therefore it can be easy to described anti- The peace of protection unit is torn open, and will not destroy the metal Roof formed, and each part can be recycled, so as to reduce measure throwing Enter, reduce construction cost.Further, since outer again shaped steel need not be hanged, security is also improved.
Brief description of the drawings
Fig. 1 is a kind of structural representation for metal Roof construction safety protection device that the utility model embodiment is provided.
Fig. 2 is the structural representation of the first latch fitting in Fig. 1.
Fig. 3 is the structural representation of the second latch fitting in Fig. 1.
Embodiment
In order that the purpose of this utility model, technical scheme and advantage are more clearly understood, below in conjunction with accompanying drawing and implementation Example, the utility model is further elaborated.It should be appreciated that specific embodiment described herein is only to explain The utility model, is not used to limit the utility model.
As shown in Figure 1 to Figure 3, a kind of metal Roof construction safety protection dress provided for the utility model embodiment 100 are put, it includes safe vertical rod 1, safety rope 2 and fixed locker 3.
The fixing lock folder includes the first latch fitting 31 and the second latch fitting 32, first latch fitting 31 and second latch fitting 32 It is fastened on the lock seaming bearing 50 of metal Roof and removably connects jointly.It is achieved thereby that the stationary lock part 3 is removable Unloading property, will not damage the roofing for having laid completion due to operations such as welding cuttings.
The safe vertical rod 1 is detachably connected to the top of first latch fitting 31, between adjacent two safe vertical rods 1 Draw and be provided with the safety rope 2.Ensure the security of construction by the safety rope 2, prevent workmen from sliding.
Specifically, reference picture 2 and Fig. 3, first latch fitting 31 include lock 311, steel plate 312 and steel pipe 313, described Steel pipe 313 is welded on the top of the steel plate 312, and the lock 311 is welded on the bottom of the steel plate 312, and formation one is whole Body.Offer bolt hole (not marking) on the periphery of the steel pipe 313, the steel pipe 313 is inserted in the safe vertical rod 1, and with The bolt connection of steel pipe 313.When needing arrangement safety rope 2, the safe vertical rod 1 is inserted in the steel pipe 313, then is drawn If safety rope 2;When completion of constructing needs to remove, after directly bolt is backed out, by the safe vertical rod from the steel pipe Extracted in 313, it is convenient to assemble and disassemble, and material will not be damaged in itself, it can be recycled.
The lock 311 is provided with spacing preiection 3111, and the top of second latch fitting 32 is separably fastened on described In the groove that spacing preiection 3111 is formed with the steel plate 312, in order to fixed first latch fitting 31 and the described second lock The relative position of part 32.The lock 311 and the bolt connection of the second latch fitting 32, to realize the lock 311 and described the The detachability of two latch fittings 32, so that the protector 100 is convenient to assemble and disassemble, uses manpower and material resources sparingly.
In summary, a kind of metal Roof construction safety protection device 100 that the utility model embodiment is provided, it includes Safe vertical rod 1, safety rope 2 and fixed locker 3., will be solid using the lock seaming bearing 50 laid on the metal Roof of completion Lock folder 3 the first latch fitting 31 and the second latch fitting 32 be fastened on jointly it is described lock seaming bearing 50 on, and first latch fitting 31 with Second latch fitting 32 is removably connected.The safe vertical rod 1 is detachably connected to the top of first latch fitting 31, Drawn between adjacent two safe vertical rods 1 and set safety rope 2, so as to form horizontal protective.Due to the fixed locker 3 and described Safe vertical rod 1 is respectively provided with detachability, therefore the peace of the protector 100 can be easy to tear open, and will not destroy what is formed Metal Roof, each part can be recycled, so as to reduce measure input, reduce construction cost.Further, since need not Outer again to hang shaped steel, security is also improved.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model Any modifications, equivalent substitutions and improvements made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (4)

1. a kind of metal Roof construction safety protection device, including safe vertical rod and safety rope, it is characterised in that also including fixation Locker, the fixing lock folder includes the first latch fitting and the second latch fitting, and first latch fitting is fastened on jointly with second latch fitting Connect on the lock seaming bearing of metal Roof and removably, the safe vertical rod is detachably connected to the top of first latch fitting Portion, draws between adjacent two safe vertical rods and is provided with the safety rope.
2. metal Roof construction safety protection device as claimed in claim 1, it is characterised in that first latch fitting includes steel Plate, lock and steel pipe, the steel-pipe welding is at the top of the steel plate, and the lock is welded on the steel plate bottom, the steel Offer bolt hole on the periphery of pipe, the steel pipe is inserted in the safe vertical rod, and with the steel pipe bolt connection.
3. metal Roof construction safety protection device as claimed in claim 2, it is characterised in that the lock is provided with spacing Projection, the top of second latch fitting is separably fastened in the groove that the spacing preiection is formed with the steel plate.
4. metal Roof construction safety protection device as claimed in claim 3, it is characterised in that the lock and described second Latch fitting bolt connection.
CN201720054382.5U 2017-01-17 2017-01-17 A kind of metal Roof construction safety protection device Active CN206562786U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720054382.5U CN206562786U (en) 2017-01-17 2017-01-17 A kind of metal Roof construction safety protection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720054382.5U CN206562786U (en) 2017-01-17 2017-01-17 A kind of metal Roof construction safety protection device

Publications (1)

Publication Number Publication Date
CN206562786U true CN206562786U (en) 2017-10-17

Family

ID=60029915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720054382.5U Active CN206562786U (en) 2017-01-17 2017-01-17 A kind of metal Roof construction safety protection device

Country Status (1)

Country Link
CN (1) CN206562786U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104495A (en) * 2018-01-18 2018-06-01 精工工业建筑系统有限公司 A kind of safety device for roofing construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104495A (en) * 2018-01-18 2018-06-01 精工工业建筑系统有限公司 A kind of safety device for roofing construction
CN108104495B (en) * 2018-01-18 2023-12-15 精工工业建筑系统有限公司 Safety protection device for roof construction

Similar Documents

Publication Publication Date Title
CN206562786U (en) A kind of metal Roof construction safety protection device
CN204571384U (en) A kind of sizing chemoprevention pounds switchbox protection canopy
CN204299145U (en) For the operating platform that external climbing tower crane support frame is installed
CN103758045B (en) Box girder wet joint formwork construction method under space limitation condition
CN107100647B (en) A kind of assembling and construction method of the trolley formwork of tunnel arch wall lining section gradual change
CN107939292A (en) Karst region subway tunnel limestone section grouting for water blocking drilling deviation correcting device and method
CN204703740U (en) The underground chamber To Construction of Silo cat ladder of quickly dismantled reusable edible
CN204691212U (en) A kind of nylon pin handsheet pedal of scaffold
CN204958175U (en) Collapsible monorail of suspension type
CN207296451U (en) Reusable guard rail device
CN203066752U (en) Protective door of discharging platform of construction elevator
CN205421978U (en) Elevartor shaft protection module
CN207538492U (en) A kind of combination tool formula faces side hole protector
CN206309027U (en) A kind of closing creeping formwork faces side safety device with wall space
CN207392719U (en) Scaffold dust suppression/safety net
CN204754265U (en) Be used for reinforced concrete floor to reserve entrance to a cave safety device
CN206487230U (en) A kind of foldable guardrail protector
CN205711585U (en) Anti-for massif slope type buried pipeline buries frame
CN206428979U (en) Face frontier defense protection unit
CN205476571U (en) Novel protector of elevator well head
CN204715725U (en) Overhanging type discharging platform node fixed structure
CN204917628U (en) Hanging flower basket
CN202808145U (en) Primary and secondary protective doors for elevator shaft
CN204418637U (en) For the telescopic scaffold floor of integrated form scaffold
CN211572832U (en) Consolidate iron tower device with high bearing capacity

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Engineering Group Co.,Ltd.

Address before: 518000 Guangdong city of Shenzhen province Futian District Che Kung Temple Binhe Tairan industry tipping 17 storey building No. 17A

Patentee before: China Construction Steel Structure Corp.,Ltd.

CP03 Change of name, title or address