CN206555710U - A kind of safe and simple cylinder filling frame - Google Patents

A kind of safe and simple cylinder filling frame Download PDF

Info

Publication number
CN206555710U
CN206555710U CN201720076066.8U CN201720076066U CN206555710U CN 206555710 U CN206555710 U CN 206555710U CN 201720076066 U CN201720076066 U CN 201720076066U CN 206555710 U CN206555710 U CN 206555710U
Authority
CN
China
Prior art keywords
crane
charge
longeron
pulley
conductor rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720076066.8U
Other languages
Chinese (zh)
Inventor
侯大庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FUJIAN QUANHUI MEISAIER GAS Co Ltd
Original Assignee
FUJIAN QUANHUI MEISAIER GAS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN QUANHUI MEISAIER GAS Co Ltd filed Critical FUJIAN QUANHUI MEISAIER GAS Co Ltd
Priority to CN201720076066.8U priority Critical patent/CN206555710U/en
Application granted granted Critical
Publication of CN206555710U publication Critical patent/CN206555710U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of safe and simple cylinder filling frame, including support, crane, moving guiding mechanism, counterweight, conductor rope, pulley mechanism and loading line, the many inflations that loading line includes the multiple gas cylinders settings of correspondence are in charge of, every inflation, which is in charge of, is provided with control valve, control valve is arranged on outside support, inflate the two ends being in charge of and be set to first end and the second end, inflate the first end being in charge of and be connected to high-pressure air source, second end provided with joint is filled soon, and the position inflated between the first end being in charge of and the second end is connected on crane by connector.Every inflation, which is in charge of, in the utility model is equipped with control valve, and control valve will be arranged on outside support, in gas replenishment process, once detect some gas cylinder gas leakage, corresponding control valve is then closed by control valve, in the case where ensureing safety, other gas cylinders can be inflated smoothly, the utility model eliminates the setting of return duct simultaneously, and overall structure is eased.

Description

A kind of safe and simple cylinder filling frame
Technical field
The utility model is related to a kind of safe and simple cylinder filling frame, category cylinder filling servicing unit field.
Background technology
In gas cylinder (also referred to as " steel cylinder ") gas fill be gas generation enterprise important step, gas cylinder in bulk fills, The mode that many companies all take with lattice in bulk to fill at present, substitutes traditional mode along blast wall single-row arrangement, with Improve efficiency.But it is exactly to fill flexible pipe and the connection of bottle head and asking for separating that lattice in bulk, which fill the very big practical problem of mode one, Topic, if flexible pipe can not be lifted, lattice in bulk enter fill when, flexible pipe can be collided, gas bottle head can be damaged;Filling After end, lattice in bulk are pulled out when filling, and flexible pipe can be collided again;Therefore, fill flexible pipe to be required to easily lift, It can guarantee that efficiency.
At present, in the market has had the design of pneumatic hydraulic lifting frame, but is all a total air induction hose lifting, then from The mode of point 16 flexible pipes on collecting pipe, but all not accounting for solution has the safety for closing the leakage pipeline when filling leakage to ask Topic;And apparatus cost is high, maintenance cost is also high.The design of some fueling stations of East China, is to use the mode for filling hose locker will Flexible pipe is scaled in casing, and pull out flexible pipe from chest by root during connection gas cylinder is connected with gas cylinder, fills after end, that pulls down fills Dress head can be withdrawn into casing by the gravity of flexible pipe.But also each pipeline that fills is set up individually not on master control panel Valve.
Studied before the applicant filling frame, and in the U of Authorization Notice No. CN 204345258, it is entitled " a kind of Filling head can cylinder filling frame of the automatic lifting with device for monitoring temperature " Chinese utility model patent in, describe one kind and fill Fill head can cylinder filling frame of the automatic lifting with device for monitoring temperature, including carried for the inflation platform and Duo Gen for placing gas cylinder The gas tube of joint is filled soon, joint is filled soon gas tube is communicated to by connecting tube, gas tube is arranged on the top of inflation platform simultaneously Connected with high-pressure air source, in addition to the support being arranged on inflation platform, support is provided with guide rail, and guide rail is provided with can be along guide rail Lead-frame is fixedly connected with the guide block of up and down motion, guide block, lead-frame is located at the top of gas cylinder, and the gas tube correspondence is fixed In lead-frame, the top of lead-frame is provided with pulley, in addition to around the conductor rope being located on pulley, one end and the lead-frame of conductor rope are consolidated Fixed connection, the other end of conductor rope is connected with counterweight, and the weight of counterweight is more than the weight of lead-frame.
A total air induction hose is with the lifting of crane one in the patent, then picks out from the collecting pipe on crane 16 Flexible pipe is filled, fill flexible pipe by 16 picks out to gas cylinder head from the valve on collecting pipe, lifts frame lift band together with collecting pipe Dynamic total air induction hose lifting;But actually these valves be in filling process can not go close (especially pressure is more than 100 Kilogram when), even if fill initial stage find have leakage, it is also unsafe to go to close corresponding valve, is detected in filling process It during leakage, will be unable to individually close the gas cylinder, the valve that can only be closed on total valve or collecting pipe, will own in the lattice in bulk After gas cylinder release, then the gas cylinder of leakage is picked out, this will cause very big waste, and reduction fills efficiency.
In consideration of it, the present inventor carries out in-depth study to above mentioned problem, there is this case generation then.
Utility model content
The purpose of this utility model is to provide a kind of simple structure, using safer safe and simple cylinder filling frame.
In order to achieve the above object, the utility model is using such technical scheme:
A kind of safe and simple cylinder filling frame, including support, be liftably arranged on support crane, to drive Moving guiding mechanism that crane is moved up and down on support, counterweight, conductor rope, to guide pulley mechanism that conductor rope moves and Loading line, one end of conductor rope is reconnected with matching somebody with somebody, and the other end of conductor rope is connected with crane, and it is many that the loading line includes correspondence The many inflations that individual gas cylinder is set are in charge of, and every inflation, which is in charge of, is provided with control valve, and control valve is arranged on the branch Outside frame, inflate the two ends being in charge of and be set to first end and the second end, inflate the first end being in charge of and be connected to high-pressure air source, the second end is set Have and fill joint soon, the position inflated between the first end being in charge of and the second end is connected on crane by connector.
As a kind of preferred embodiment of the present utility model, hard tube and flexible pipe including interconnection, institute are in charge of in the inflation State and fill joint soon and be connected on flexible pipe, flexible pipe is connected on the crane by the connector, the control valve is set On hard tube and after the blast wall filled outside region, the connector is plastics line card.
As a kind of preferred embodiment of the present utility model, the inflation is in charge of for 12,16,24 or 32.
As a kind of preferred embodiment of the present utility model, the support includes support underframe and mounting bracket, and mounting bracket includes First longeron, the second longeron and the crossbeam being arranged between the upper end of the upper end of the first longeron and the second longeron, the first longeron, Second longeron and crossbeam surround " door " font.
As a kind of preferred embodiment of the present utility model, the pulley mechanism includes the first movable pulley, the second movable pulley, the One fixed pulley and the second fixed pulley, the first movable pulley and the second movable pulley are fixed on the crane, the first fixed pulley and Second fixed pulley is fixed on the crossbeam, and the conductor rope includes the first conductor rope and the second conductor rope, and one end of the first conductor rope is fixed On the crossbeam, the other end is successively around being located on the first movable pulley and the first fixed pulley and being connected to the counterweight, and second leads One end of rope is fixed on the crossbeam, and the other end is described around being located on the second movable pulley and the second fixed pulley and being connected to successively Counterweight.
As a kind of preferred embodiment of the present utility model, the crane is arranged on first longeron and indulged with described second Between beam, the crane includes the first crane, the second crane and to connect the first crane and the second crane Link, the first crane and the second crane set up separately in the both sides of the mounting bracket.
After the technical solution of the utility model, directly inflation is in charge of by connector and is connected on crane, often Root inflation, which is in charge of, is equipped with control valve, and control valve will be arranged on outside support, in gas replenishment process, once detect Some gas cylinder gas leakage, then close corresponding control valve by control valve, and in the case where ensureing safety, other gas cylinders can Smoothly inflation, while the utility model eliminates the setting of return duct, overall structure is eased.
Brief description of the drawings
Fig. 1 is the structural representation of the first embodiment of the utility model;
Fig. 2 is the enlarged drawing at A in Fig. 1;
Fig. 3 is the structural representation of the first embodiment of the utility model;
Fig. 4 is the main structure diagram of the first embodiment of the utility model;
Fig. 5 is the structural representation of the first roller group in the utility model;
Fig. 6 is the partial structural diagram of the first longeron in the utility model;
Fig. 7 is the main structure diagram of second of embodiment of the utility model;
Fig. 8 (rolls for the dimensional structure diagram of second of embodiment of the utility model in figure before loading line, first Wheel, the first rear roller, the second front wheel and the second rear roller are not shown);
Fig. 9 is the dimensional structure diagram (loading line is not shown in figure) of second of embodiment of the utility model;
Figure 10 is the overlooking the structure diagram (loading line is not shown in figure) of second of embodiment of the utility model.
In figure:
10- supports the first longerons of 11-
111- the first guide plate the first flat boards of 112-
The flat boards of the second flat boards of 113- 114- the 3rd
The spacing arcs of the spacing arc 116- second of 115- first
The first guiding clearances of 117- the first chutes of 118-
119- the first bolt the first contiguous blocks of 1192-
1193- the first roller the second longerons of 12-
121- the second guide plate 13- crossbeams
14- support underframe 20- cranes
21- the first crane the second cranes of 22-
30- lattice 31- gas cylinders in bulk
40- counterweight 41- directive wheels
42- drawstring 43- hanging rings
The hooks of 44- first 45- second is linked up with
51- the first guiding piece the second guiding pieces of 52-
53- the first front wheel the first rear rollers of 54-
55- the second front wheel the second rear rollers of 56-
57- connecting cross beams 571- first is connected crossbeam
572- second is connected crossbeam the first buttress braces of 581-
582- the second buttress brace the first guides of 591-
592- the second guide 60- loading lines
61- flexible pipe 62- hard tubes
63- fills joint 70- conductor ropes soon
71- the first movable pulley the second movable pulleys of 72-
73- the first fixed pulley the second fixed pulleys of 74-
75- the first conductor rope the second conductor ropes of 76-
77- movable pulley 78- fixed pulleys
80- connecting cross beams
Embodiment
In order to which the technical solution of the utility model is explained further, it is described in detail below in conjunction with the accompanying drawings.
Referring to figs. 1 to Figure 10, a kind of safe and simple cylinder filling frame, including support 10, liftably it is arranged on support 10 On crane 20, to drive moving guiding mechanism, counterweight 40, conductor rope 70 that crane 20 moves up and down over the mount 10, To the pulley mechanism and loading line 60 for guiding conductor rope 70 to move, one end of conductor rope 70 is connected with counterweight 40, conductor rope 70 The other end is connected with crane 20.
The many inflations that loading line 60 described in the utility model includes the multiple settings of gas cylinders 31 of correspondence are in charge of, and every is filled Control valve 64 is provided with qi leel pipe, control valve 64 is arranged on outside the support 10, inflates the two ends be in charge of and be set to the One end and the second end, inflate the first end being in charge of and are connected to high-pressure air source, the second end provided with joint 63 is filled soon, and joint 63 is filled soon can On bottle head quickly to snap fit onto gas cylinder 31, the position inflated between the first end being in charge of and the second end is connected to by connector On crane 20.The weight of counterweight 70 is more than the gross weight of crane 20 and corresponding loading line 60 in the utility model, When not carrying out cylinder filling, crane 20 is stretched to higher position, to facilitate the gas that forklift truck is placed on lattice in bulk Bottle 31 is transported to the lower section of crane 20.
As a kind of preferred embodiment of the present utility model, hard tube 62 and flexible pipe including interconnection are in charge of in the inflation 61, the joint 63 that fills soon is connected on flexible pipe 61, and flexible pipe 61 is connected on the crane 20 by the connector, in reality Apply in example, probably flexible pipe 61 is fixed on crane 20 by plastics line card at the length of flexible pipe 1/61st 3, the control Valve 64 processed is arranged on hard tube 62 and after the blast wall filled outside region.So allow for the filling tube of each gas cylinder 31 Road keeps independent, so as in filling process, safely has the respective line of gas leakage gas cylinder filling outdoor closing at any time, not shadow Ring filling for other non-gas leakage steel cylinders.
In the utility model, it can be 12,16,24 or 32 that the inflation, which is in charge of,.In Fig. 1 and Fig. 7, Fully being in charge of has 32, and control valve 64 is 32 accordingly.
As a kind of preferred embodiment of the present utility model, the support 10 includes support underframe 14 and mounting bracket, supports bottom Frame 14 whole fill frame and rested easily within level land to enable.Mounting bracket includes the first longeron 11, the second longeron 12 And it is arranged on the crossbeam 13 between the upper end of the upper end of the first longeron 11 and the second longeron 12, the first longeron 11, the second longeron 12 and crossbeam 13 surround " door " font.
Referring to figs. 1 to Fig. 6, it is the first embodiment of the present utility model, in this embodiment, the support 10 Including support underframe 14 and mounting bracket, mounting bracket includes the first longeron 11, the second longeron 12 and is arranged on the first longeron 11 Crossbeam 13 between upper end and the upper end of the second longeron 12, the first longeron 11, the second longeron 12 and crossbeam 13 surround portal frame Structure, the first longeron 11 is provided with the first chute 118 vertically, and the second longeron 12 is provided with second vertically Chute, in addition to the first guide 591 being connected with the crane 20 and the second guide being connected with the crane 20 592, the first guide 591 is provided with the first roller group that can be rolled in the first chute 118, and the second guide 592 is provided with The second roller group that can be rolled in the second chute.
As a kind of preferred embodiment of the present utility model, first roller group is two, the edge of the first guide 591 Vertical direction is set, and first roller group is arranged on the upper end of first guide 591, another described first rolling Wheel group is arranged on the lower end of first guide 591.
As a kind of preferred embodiment of the present utility model, second roller group is two, the edge of the second guide 592 Vertical direction is set, and second roller group is arranged on the upper end of second guide 592, another described second rolling Wheel group is arranged on the lower end of second guide 592.
As a kind of preferred embodiment of the present utility model, the first linking crossbeam 571 and are fixed with the crane 20 Two linking crossbeams 572, first guide 591 and second guide 592 are held in the mouth by the first linking crossbeam 571 and second Crossbeam 572 is connect to be fixed together.
As a kind of preferred embodiment of the present utility model, first longeron 11 includes the first flat board 112, the second flat board 113rd, the 3rd flat board 114, the first spacing arc 116 of spacing arc 115 and second, the second flat board 113 and the 3rd flat board 114 vertically set up separately at the two ends of the first flat board 112, and one end of the first spacing arc 115 is connected on the second flat board 113, separately One end extends to the second spacing arc 116, and one end of the second spacing arc 116 is connected on the 3rd flat board 114, the other end Extend to the first spacing arc 115, the first flat board 112, the second flat board 113, the 3rd flat board 114, the first spacing arc 115 And second spacing arc 116 surround first chute 118, first roller group includes the first contiguous block 1192, used So that the first contiguous block 1192 to be locked in the first bolt 1191 of the first guide 591 and is arranged on the first contiguous block 1192 Multiple first rollers 1193, in embodiment, the number of the first roller 1193 is four, and four the first rollers 1193 are rotatable Ground is connected on the first contiguous block 1192, and the both sides of the first contiguous block 1192 set two rollers, the first arc-shaped limit plate respectively 115 and second form the first guiding clearance 117 stretched out for the first bolt 1191 between arc-shaped limit plate 116, during installation, by the One roller 1193 correspondence is contained in the first spacing arc 115 and the second spacing arc 116 in, the first bolt 1191 from Stretch out and be connected on the first guide 591 in first guiding clearance 117.
As a kind of preferred embodiment of the present utility model, first longeron 11 is identical with the structure of the second longeron 12, First chute 118 is identical with second sliding groove structure, the structure phase of first roller group and second roller group Together, the first roller group is identical with the fit structure of the second chute with the second roller group with the fit structure of the first chute 118.Using This structure, is rolled, the second roller group is rolled in the second chute, so as to draw by the first roller group in the first chute 118 Lead crane 20 swimmingly to slide up and down, compared to traditional guide pin bushing and guide rod structure, the frictional force that the utility model is slided is smaller, And requirement on machining accuracy is relatively low, whole moving guiding mechanism simple structure, cost is relatively low.
In the first embodiment of the present utility model, crane 20 passes through movable pulley 77, fixed pulley 78 and conductor rope 70 are connected with support 10, specifically, multiple movable pulleys 77 are provided with the first linking crossbeam 572, provided with multiple on crossbeam 13 Fixed pulley 78, one end of conductor rope 70 is fixed on crossbeam 13, and the other end alternately bypasses movable pulley 77 and fixed pulley 78 and is connected to In counterweight 40.
As a kind of preferred embodiment of the present utility model, the crane 20 is arranged on first longeron 11 and described the Between two longerons 12, the crane 20 includes the first crane 21, the second crane 22 and to connect the first crane 21 With the link of the second crane 22, link is the first linking linking crossbeam 572 of crossbeam 571 and second, the first crane 21 Set up separately with the second crane 22 in the front and rear sides of the mounting bracket.Using this structure, in the first crane 21 and second liter Loading line can be laid respectively on drop frame 22, and demand is filled with meet multiple lattice in bulk.
Reference picture 7 is to Figure 10, and it is the structural representation of second of embodiment of the utility model, preferably In, the support 10 includes support underframe 14 and mounting bracket, and mounting bracket includes the first longeron 11, the second longeron 12 and is arranged on Crossbeam 13 between the upper end of first longeron 11 and the upper end of the second longeron 12, the first longeron 11 is provided with the vertically One guide plate 111, the second longeron 12 is provided with the second guide plate 121 vertically, specifically, the first longeron 11 and the second longeron 12 can directly use channel-section steel.The utility model also include the first guiding piece 51 for being connected with the crane 20 and with the liter The second guiding piece 52 that frame 20 is connected is dropped, and the first guiding piece 51 is provided with before the first front wheel 53 and the first rear roller 54, first The rear roller 54 of roller 53 and first is rollably supported on the first guide plate 111, and the first guide plate 11 is folded in the first front wheel 53 Between the first rear roller 54, the second guiding piece 121 is provided with the second front wheel 55 and the second rear roller 56, the second front wheel 55 Rollably supported on the second guide plate 121 with the second rear roller 56, the second guide plate 121 is folded in the second front wheel 55 and second Between rear roller 56.
As a kind of preferred embodiment of the present utility model, first front wheel 53 and first rear roller 54 are two Individual, first guiding piece 51 is vertically set, first front wheel 53 and first rear roller 54 The upper end of first guiding piece 51 is arranged on, another described first front wheel 53 and another described first rear roller 54 are set Put in the lower end of first guiding piece 51.
As a kind of preferred embodiment of the present utility model, second front wheel 55 and second rear roller 56 are two Individual, second guiding piece 52 is vertically set, second front wheel 55 and second rear roller 56 The upper end of second guiding piece 52 is arranged on, another described second front wheel 55 and another described second rear roller 56 are set Put in the lower end of second guiding piece 52.
Using the technical solution of the utility model, the first front wheel 53 and the first rear roller 54 are rolled on the first guide plate 111 Dynamic, the second front wheel 55 and the second rear roller 56 are rolled on the second guide plate 121, so as to guide crane 20 is swimmingly upper to glide Dynamic, compared to traditional guide pin bushing and guide rod structure, the frictional force that the utility model is slided is smaller, and requirement on machining accuracy is relatively Low, whole moving guiding mechanism simple structure, cost is relatively low.
As a kind of preferred embodiment of the present utility model, connecting cross beam 80, described first are fixed with the crane 20 Guiding piece 51 and second guiding piece 52 are fixed on connecting cross beam 80, in embodiment, and connecting cross beam 80 is two.
It is used as a kind of preferred embodiment of the present utility model, in addition to the first buttress brace 581 and the second buttress brace 582, first The upper end of buttress brace 581 is connected with the upper end of first guiding piece 51, the lower end of the first buttress brace 581 and the crane 20 Connection, the first buttress brace 581, first guiding piece 51 and the crane 20 surround triangle, the second buttress brace 582 Upper end is connected with the upper end of second guiding piece 52, and the lower end of the second buttress brace 582 is connected with the crane 20, and second adds Brutal 582, second guiding piece 52 and the crane 20 surround triangle.
Referring to figs. 1 to Figure 10, the utility model is also made that conductor rope in improvement, the utility model to the mounting structure of counterweight 70 one end is connected with crane 20, and the other end is connected by assembly pulley with counterweight 40, and the weight of counterweight 40 is more than crane 20 Weight, directive wheel 41 is provided with the support 10, directive wheel 41 is arranged on the top of counterweight 40, in addition to drawstring 42, drawn One end of rope 42 is connected with counterweight 40, and the other end is upwardly extended and around being located on directive wheel 41 and be downwardly extending free end, Free end is provided with keeper, and the first positioning to cause crane 20 to be positioned at the first height is provided with the support 10 Block is with so that crane 20 is positioned at the second locating piece of the second height, and keeper is matched somebody with somebody with the first locating piece and the second locating piece Close and set.
As a kind of preferred embodiment of the present utility model, the keeper is hanging ring 43, and first locating piece is first Hook 44, second locating piece is the second hook 45.It is used as a kind of preferred embodiment of the present utility model, first hook 44 It is arranged on the described second hook 45 on first longeron 11 or second longeron 12, the directive wheel 41 is arranged on institute State on crossbeam 13.In use, by pull drawstring 42 so that hanging ring 43 hook first hook 44 or second hook 45 on so that Crane 20 is positioned at different height.After the technical solution of the utility model, by counterweight 40 set drawstring 42, Keeper, the first locating piece and the second locating piece, when in use, pull counterweight 40 to drive on crane 20 by keeper Lower motion, when crane 20 moves to precalculated position, keeper is connected on the first locating piece and the second locating piece, is realized The positioning of crane 20, so as to facilitate the joint that fills soon on loading line to be docked with the bottle head of gas cylinder, is formed with to loading line The protection of effect ground.
In Fig. 1 into Fig. 6, crane is realized by a conductor rope 70, multiple movable pulleys 77 and multiple fixed pulleys 78 20 with the connection of counterweight 40.In Fig. 7 into Figure 10, the connection of crane 20 and counterweight 40 is realized using another way, specifically Ground, assembly pulley includes the first movable pulley 71, the second movable pulley 72, the first fixed pulley 73 and the second fixed pulley 74, the first dynamic cunning The movable pulley 72 of wheel 71 and second is fixed on the crane 20, and the first fixed pulley 73 and the second fixed pulley 74 are fixed on the horizontal stroke On beam 13, the conductor rope 70 includes the first conductor rope 75 and the second conductor rope 76, and one end of the first conductor rope 75 is fixed on the crossbeam 13 On, the other end is successively around being located on the first movable pulley 71 and the first fixed pulley 73 and be connected to counterweight 40, and the one of the second conductor rope 76 End is fixed on the crossbeam 13, and the other end is described around being located on the second movable pulley 71 and the second fixed pulley 72 and being connected to successively Counterweight 40.In this configuration, counterweight 40 is arranged between the first fixed pulley 73 and the second fixed pulley 74.Although in Fig. 7 to figure In 10, corresponding first hook and the second hook are not shown over the mount 10, those skilled in the art can be according to liter The position location that frame 20 needs is dropped, the first hook and the second hook are set on support.
Product form of the present utility model is not limited to this case diagram and embodiment, and anyone carries out similar thinking to it Appropriate change is modified, and all should be regarded as not departing from patent category of the present utility model.

Claims (6)

1. a kind of safe and simple cylinder filling frame, including support, be liftably arranged on support crane, to drive liter Drop frame moved up and down on support moving guiding mechanism, counterweight, conductor rope, to guide conductor rope move pulley mechanism and fill Air pipe, one end of conductor rope is reconnected with matching somebody with somebody, and the other end of conductor rope is connected with crane, it is characterised in that:The loading line The many inflations set including the multiple gas cylinders of correspondence are in charge of, and every inflation, which is in charge of, is provided with control valve, and control valve is set Put outside the support, inflate the two ends being in charge of and be set to first end and the second end, inflate the first end being in charge of and be connected to high pressure gas Source, the second end provided with joint is filled soon, and the position inflated between the first end being in charge of and the second end is connected to lifting by connector On frame.
2. a kind of safe and simple cylinder filling frame as claimed in claim 1, it is characterised in that:The inflation is in charge of including mutual The hard tube and flexible pipe of connection, the joint that fills soon are connected on flexible pipe, and flexible pipe is connected to the crane by the connector On, the control valve is arranged on hard tube and after the blast wall filled outside region, and the connector is plastics line card.
3. a kind of safe and simple cylinder filling frame as claimed in claim 2, it is characterised in that:It is described inflation be in charge of for 12, 16,24 or 32.
4. a kind of safe and simple cylinder filling frame as claimed in claim 1, it is characterised in that:The support includes support underframe And mounting bracket, mounting bracket is including the first longeron, the second longeron and is arranged on the upper end of the first longeron and the upper end of the second longeron Between crossbeam, the first longeron, the second longeron and crossbeam surround " door " font.
5. a kind of safe and simple cylinder filling frame as claimed in claim 4, it is characterised in that:The pulley mechanism includes first Movable pulley, the second movable pulley, the first fixed pulley and the second fixed pulley, the first movable pulley and the second movable pulley are fixed on the liter Drop on frame, the first fixed pulley and the second fixed pulley are fixed on the crossbeam, the conductor rope includes the first conductor rope and the second conductor rope, One end of first conductor rope is fixed on the crossbeam, and the other end is successively around being located on the first movable pulley and the first fixed pulley and connect To the counterweight, one end of the second conductor rope is fixed on the crossbeam, and the other end is successively around being located at the second movable pulley and second fixed On pulley and it is connected to the counterweight.
6. a kind of safe and simple cylinder filling frame as claimed in claim 5, it is characterised in that:The crane is arranged on described Between first longeron and second longeron, the crane includes the first crane, the second crane and to connect first The link of crane and the second crane, the first crane and the second crane set up separately in the both sides of the mounting bracket.
CN201720076066.8U 2017-01-19 2017-01-19 A kind of safe and simple cylinder filling frame Expired - Fee Related CN206555710U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720076066.8U CN206555710U (en) 2017-01-19 2017-01-19 A kind of safe and simple cylinder filling frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720076066.8U CN206555710U (en) 2017-01-19 2017-01-19 A kind of safe and simple cylinder filling frame

Publications (1)

Publication Number Publication Date
CN206555710U true CN206555710U (en) 2017-10-13

Family

ID=60359795

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720076066.8U Expired - Fee Related CN206555710U (en) 2017-01-19 2017-01-19 A kind of safe and simple cylinder filling frame

Country Status (1)

Country Link
CN (1) CN206555710U (en)

Similar Documents

Publication Publication Date Title
CN202186848U (en) Universal movable maintenance gantry crane
CN105347206B (en) The intelligent assistance platform of GIS dismounting
CN105128982B (en) Centre of gravity trailer with elevating mechanism
CN206555708U (en) A kind of novel gas bottle fills the crane moving guiding mechanism of frame
CN108560591A (en) The pipeline transportation device used in pipe gallery
CN109572928A (en) A kind of ship pipe lane cabin operating trolley
CN206219071U (en) A kind of switch cubicle installation lifting appliance
CN206555710U (en) A kind of safe and simple cylinder filling frame
CN206555707U (en) A kind of counterweight mounting structure of cylinder filling frame
CN206555709U (en) A kind of crane moving guiding mechanism of cylinder filling frame
CN106829781A (en) Mobile shipment crane and its operating method of one kind
CN207061656U (en) Goods lifting system and wind power generating set
CN206692295U (en) A kind of translation positioning apparatus of jumbo
CN205527435U (en) Installation and device of dismantling jib loading boom
CN115259035B (en) Lifting operation table for overhauling transformer
CN209684577U (en) A kind of dual-purpose transfer tooling of the wind electricity blade web of grider
CN107244616A (en) A kind of tensile testing machine lifts by crane turnover device
CN206799012U (en) A kind of concrete batten transport of small space and installation tool group
CN106315351B (en) A kind of counter weight construction of improved elevator sky rail detection device
CN106198087B (en) A kind of detection device of improved elevator sky rail
CN108726371A (en) A kind of substation's GIS device hanging apparatus
CN209602005U (en) A kind of shield machine penstock installation lifting device
CN205114946U (en) A hydraulic lifting platform for motorcycle exhibition show
CN107572428A (en) A kind of electronic heavy lift machinery device
CN106809665A (en) Automatic tube filling machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171013

Termination date: 20190119