CN206554698U - A kind of belt switch determines the assembled connecting bridge service door of door gear - Google Patents

A kind of belt switch determines the assembled connecting bridge service door of door gear Download PDF

Info

Publication number
CN206554698U
CN206554698U CN201720095555.8U CN201720095555U CN206554698U CN 206554698 U CN206554698 U CN 206554698U CN 201720095555 U CN201720095555 U CN 201720095555U CN 206554698 U CN206554698 U CN 206554698U
Authority
CN
China
Prior art keywords
door
connecting bridge
door frame
hole
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201720095555.8U
Other languages
Chinese (zh)
Inventor
胡克明
牛福维
符平宣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mideals Intelligent Equipment Co Ltd
Original Assignee
Mideals Intelligent Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mideals Intelligent Equipment Co Ltd filed Critical Mideals Intelligent Equipment Co Ltd
Priority to CN201720095555.8U priority Critical patent/CN206554698U/en
Application granted granted Critical
Publication of CN206554698U publication Critical patent/CN206554698U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Corner Units Of Frames Or Wings (AREA)

Abstract

The utility model discloses the assembled connecting bridge service door that a kind of belt switch determines door gear, including:Both sides doorframe, with first breach for the flanging insertion at hole on connecting bridge, flanging is inserted by the connection of the first fastener after the first breach, and the side wall of connecting bridge is connected with side door frame by the second fastener;Upper door frame, with second breach for the flanging insertion at hole on connecting bridge, flanging is inserted by the connection of the 3rd fastener after the second breach, and the side wall of connecting bridge is connected with upper door frame by the 4th fastener;Door body, one end is rotatably coupled by hinge with wherein side doorframe.It is connected in the utility model by side door frame and upper door frame with the flanging on connecting bridge at hole by the first fastener, the second fastener, the 3rd fastener, the 4th fastener, firm and reliable connection, the various defects occurred when being connected in conventional art using welding manner are avoided, facilitate later maintenance.

Description

A kind of belt switch determines the assembled connecting bridge service door of door gear
Technical field
The utility model is related to the assembled connecting bridge service door that a kind of belt switch determines door gear.
Background technology
Generally there is a service elevator that can be synchronized with the movement with connecting bridge between connecting bridge and machine level ground, be at this moment accomplished by that clothes are installed Business door is used for staff, can also be exported as emergency evacuation.
There is the side wall of connecting bridge a hole with flanging to be used to install service door, and connecting bridge is steel construction piece, is stepped on now The doorframe of the service door of machine bridge is all to use welding manner, or even hinge is also coupled frequently with welding.But service is installed The side wall of door is sheet metal, is also easy to produce welding deformation, for control quality, needs many people, spends more man-hour carry out group weldering, even if So, still it is difficult to ensure the smooth of service door opening and closing in technique, often occurs opening difficult phenomenon, have to hinge sometimes Pin diameter repair smaller, deformed sometimes because of the release of welding stress, cause the connecting bridge general assembly stage also to have repair conditions, Even because welding the cable bad that will be laid.In addition can be very heavy using the service door of structure steel fabrication, switch gate inertia force Greatly, easily cause hinge and door lock hits and damaged.On airport, connecting bridge service door is using frequently, and damage is common occurrence, dimension Repair, change and need to repair very inconvenient with electric welding, it is necessary to apply for welding and cutting permit, very big puzzlement is caused to airport and after-sale service.
In addition, sometimes for using, it is necessary to service door is in open mode, prior art is all using buckling the need for upper Etc be fixed, but airport environment is spacious, and wind is larger, and the phenomenon rocked or closed suddenly easily occurs in service door.For this Utility model provides the assembled connecting bridge service door that a kind of belt switch of brand new determines door gear.
Utility model content
In order to solve the above problems, the utility model provides the assembled connecting bridge service that a kind of belt switch determines door gear Door.
The utility model solves the technical scheme that its technical problem used:
A kind of belt switch determines the assembled connecting bridge service door of door gear, including:
Both sides doorframe, with first breach for the flanging insertion at hole on connecting bridge, flanging inserts the first breach Connected afterwards by the first fastener, the side wall of connecting bridge is connected with side door frame by the second fastener;
Upper door frame, with second breach for the flanging insertion at hole on connecting bridge, flanging is inserted after the second breach Connected by the 3rd fastener, the side wall of connecting bridge is connected with upper door frame by the 4th fastener;
Door body, one end is rotatably coupled by hinge with wherein side doorframe.
All in a tubular form, the side door inframe being connected with door body is provided with one first reinforcing plate for the side door frame and upper door frame, hinge Chain is connected by screw with side door frame, and the side wall of screw through side door frame is connected with the first reinforcing plate.
The second reinforcing plate is provided with the inside of the side docked on the side door frame with for the flanging at hole on connecting bridge, First fastener is connected through side door is wide with the second reinforcing plate.
The utility model also include certain door gear, it is described determine door gear include magnet base, base and support, the support On base, floor installation is on connecting bridge, and the magnet base is installed in rotation on support.
One through hole is set in the middle part of the door body, and through hole side is provided with a location-plate, and location-plate is extended in through hole, through hole Opposite side be provided with pressing plate, pressing plate is extended in through hole, between pressing plate and location-plate have gap, be provided with the gap location One windowpane.
The door body bottom is also associated with a water and scrapes seat, and water scrapes a bottom and is provided with a T-shaped hole, is provided with the T-shaped hole One water scraping blade, water scraping blade upper end has a head coordinated with T-shaped hole.
The door body lower sidewall is provided with skirting board.
Reinforced seat is provided with the upper door frame, door closer, door closer and upper door frame are provided between upper door frame and door body Junction is connected through upper door frame side wall and with reinforced seat by screw.
Fluid sealant is all provided between the side door frame and connecting bridge side wall, between upper door frame and connecting bridge side wall.
The side door frame extends to the rib on connecting bridge in hole with one;There are multiple cavitys, cavity inside door body It is interior to be filled with heat insulation foam.
The beneficial effects of the utility model are:In the utility model by side door frame and upper door frame with hole on connecting bridge Flanging pass through the first fastener, the second fastener, the 3rd fastener, the 4th fastener connect, firm and reliable connection, it is to avoid pass The various defects occurred when being connected in system technology using welding manner, facilitate later maintenance;In addition, structure of the present utility model can So that the passage production and the manufacture of service door of connecting bridge can be carried out simultaneously or sequentially, service door is assembled i.e. before connecting bridge dispatches from the factory Can, improve the production efficiency of whole connecting bridge.
Brief description of the drawings
The utility model is further illustrated with reference to the accompanying drawings and examples:
Fig. 1 is schematic diagram of the present utility model;
Fig. 2 is the schematic diagram of side door frame and upper door frame in the utility model;
Fig. 3 is the diagrammatic cross-section of upper door frame in the utility model;
Fig. 4 is the diagrammatic cross-section for the side door frame for being provided with hinge;
Fig. 5 is the diagrammatic cross-section that windowpane annex is provided with door body;
Fig. 6 is the diagrammatic cross-section of door body bottom and stainless steel sill;
Fig. 7 is sectional view of the upper door frame at installation door closer;
Fig. 8 is the schematic diagram for determining door gear.
Embodiment
1~Fig. 8 of reference picture, the utility model is the assembled connecting bridge service door that a kind of belt switch determines door gear, including:
Both sides doorframe 1, with first breach inserted for the flanging 3 at hole 2 on connecting bridge, the insertion of flanging 3 first Connected after breach by the first fastener 4, the side wall 7 of connecting bridge is connected with side door frame 1 by the second fastener 5;
Upper door frame 6, with second breach inserted for the flanging 3 at hole 2 on connecting bridge, the insertion of flanging 3 second lacks Connected after mouthful by the 3rd fastener, the side wall 7 of connecting bridge is connected with upper door frame 6 by the 4th fastener 8;
Door body 9, one end is rotatably coupled by hinge 10 with wherein side doorframe 1, and the inside of door body 9 has multiple cavitys 11, cavity 11 is interior to be filled with heat insulation foam, and the weight of door body 9 that the door body 9 of the structure is relatively conventional is greatly lowered, and reduces door body 9 The impact dynamics of offside doorframe 1, it is to avoid the situation that side door frame 1 is deformed occurs.Pass through side door frame 1 and upper door frame in the utility model 6 are connected with the flanging 3 at hole on connecting bridge 2 by the first fastener 4, the second fastener 5, the 3rd fastener, the 4th fastener 8 Connect, the first fastener 4 and the second fastener 5 are respectively used to the side of fastening flanging 3, the side wall 7 of connecting bridge, flanging 3 and connecting bridge Wall 7 is vertical, it is seen that the first fastener 4 and the second fastener 5 can fix the both direction of side door frame 1, firm and reliable connection, 3rd fastener and the 4th fastener 8 can play similar technology effect to upper door frame 6;First fastener 4, the second fastener 5, 3rd fastener, the 4th fastener 8 use screw or bolt, and the utility model can be avoided in conventional art using welding manner company The various defects occurred when connecing, facilitate later maintenance;In addition, structure of the present utility model may be such that connecting bridge passage production and The manufacture of service door can be carried out simultaneously or sequentially, and service door is assembled before connecting bridge dispatches from the factory, and improve the life of whole connecting bridge Produce efficiency.
As illustrated, the side door frame 1 and upper door frame 6 are all in a tubular form, one is provided with the side door frame 1 being connected with door body 9 First reinforcing plate 12, hinge 10 is connected by screw with side door frame 1, side wall and first reinforcing plate 12 of the screw through side door frame 1 Connection, provides hinge 10 by the first reinforcing plate 12 and installs required intensity, it is ensured that side door frame 1 is used for a long time indeformable;It is described Side door frame 1 has one to extend to rib 13 on connecting bridge in hole 2, for stopping that door body 9 passes completely through hole 2;The side The second reinforcing plate 14, the first fastening are provided with the inside of the side docked on doorframe 1 with for the flanging 3 at hole 2 on connecting bridge Part 4 is connected through side door is wide with the second reinforcing plate 14, and the setting of the second reinforcing plate 14 can be more firm with flanging by side door frame 1 Reliably, bigger internal stress is born without deforming.
As illustrated, the utility model also include certain door gear, it is described determine door gear include magnet base 15, the and of base 16 Support 17, the support 17 is arranged on base 16, and base 16 is arranged on connecting bridge, and the magnet base 15 is rotatably mounted On support 17;There is a switch 18 to control magnet base 15 whether to work, it is necessary to which door body is fixed on into setting position on magnet base 15 When, controlling switch 18 opens magnet base 15, and magnet base 15 produces powerful suction and fixes door body 9, and magnet base 15 is rotatable Ground, which is set, can cause magnet base 15 to reach the effect that face is contacted with door body 9 all the time so that connection is more solid and reliable.
As illustrated, the middle part of door body 9 sets a through hole, through hole side is provided with a location-plate 19, and location-plate 19 prolongs Reach in through hole, the opposite side of through hole is provided with pressing plate 20, and pressing plate 20 is extended in through hole, have between pressing plate 20 and location-plate 19 There is gap, the gap location is provided with a windowpane 21, rubber lining bar is provided between windowpane 21 and location-plate 19, pressing plate 20 22, the lower end of rubber lining bar 22 and the joint face of windowpane 21 sets fluid sealant;Location-plate 19 and pressing plate 20 all pass through screw and door Body 9 is connected, and windowpane 21 can be assembled in door body 9 in advance, improves general assembly efficiency, the windowpane 21 of the structure can be square in addition Just later maintenance is changed;The position docked in door body 9 with upper door frame 6 and side door frame 1 is provided with fire-proof expansion seal strip 23, is meeting Played a protective role during to fire.
As illustrated, the bottom of door body 9, which is also associated with a water, scrapes seat 24, water scrapes the bottom of seat 24 and is provided with a T-shaped hole, should One water scraping blade 25 is installed, the upper end of water scraping blade 25 has a head coordinated with T-shaped hole, and connecting bridge ground is to answering the door in T-shaped hole Stainless steel sill 26 is provided with body 9;Water scraping blade 25 is arranged on the bottom of door body 9 by screw, sets water scraping blade 25 can be timely The water of residual is blown off;The water of the structure scrapes seat 24 and water scraping blade 25 is easy to assembly quick, is easy to later maintenance to change.
As illustrated, because unexpected impact is often born in the bottom of door body 9, so in the both sides of the lower sidewall of door body 9 Skirting board 27 is provided with, to improve the service life of door body 9.
As illustrated, being provided with reinforced seat 28 in the upper door frame 6, door closer is provided between upper door frame 6 and door body 9 29, door closer 29 is connected through the side wall of upper door frame 6 and with reinforced seat 28 with the junction of upper door frame 6 by screw;Door closer 29 Setting can be easy to close automatically after door body 9 is opened, and the setting of reinforced seat 28 can reduce door closer 29 and install to upper door frame 6 The influence of structural strength, reduces the deformation of upper door frame 6.
As illustrated, being all provided between the side door frame 1 and connecting bridge side wall, between upper door frame 6 and connecting bridge side wall Fluid sealant 30, sets fluid sealant to be used to prevent water from entering in upper door frame 6 and side door frame 1, ensures its normal service life.
Above-described embodiment is preferred scheme of the present utility model, and the utility model can also have other embodiments.Ability The technical staff in domain can also make equivalent variations or replacement on the premise of without prejudice to the utility model spirit, these equivalent changes Type or replacement are all contained in the scope set by the application claim.

Claims (10)

1. a kind of belt switch determines the assembled connecting bridge service door of door gear, it is characterised in that including:
Both sides doorframe, with first breach for the flanging insertion at hole on connecting bridge, flanging, which is inserted after the first breach, to be led to The connection of the first fastener is crossed, the side wall of connecting bridge is connected with side door frame by the second fastener;
Upper door frame, with second breach for the flanging insertion at hole on connecting bridge, flanging passes through after inserting the second breach 3rd fastener is connected, and the side wall of connecting bridge is connected with upper door frame by the 4th fastener;
Door body, one end is rotatably coupled by hinge with wherein side doorframe.
2. a kind of belt switch as claimed in claim 1 determines the assembled connecting bridge service door of door gear, it is characterised in that described All in a tubular form, the side door inframe being connected with door body is provided with one first reinforcing plate for side door frame and upper door frame, hinge by screw with Side door frame is connected, and the side wall of screw through side door frame is connected with the first reinforcing plate.
3. a kind of belt switch as claimed in claim 2 determines the assembled connecting bridge service door of door gear, it is characterised in that described The second reinforcing plate is provided with the inside of the side docked on side door frame with for the flanging at hole on connecting bridge, the first fastener is worn Cross that side door is wide to be connected with the second reinforcing plate.
4. a kind of belt switch as claimed in claim 1 determines the assembled connecting bridge service door of door gear, it is characterised in that it is also Described to determine door gear including magnet base, base and support including certain door gear, the support is arranged on base, base peace On connecting bridge, the magnet base is installed in rotation on support.
5. a kind of belt switch as claimed in claim 1 determines the assembled connecting bridge service door of door gear, it is characterised in that described One through hole is set, and through hole side is provided with a location-plate, and location-plate is extended in through hole, the opposite side of through hole is set in the middle part of door body There is pressing plate, pressing plate is extended in through hole, there is gap between pressing plate and location-plate, the gap location is provided with a windowpane.
6. a kind of belt switch as claimed in claim 1 determines the assembled connecting bridge service door of door gear, it is characterised in that described Door body bottom is also associated with a water and scrapes seat, and water scrapes a bottom and is provided with a T-shaped hole, and a water scraping blade is provided with the T-shaped hole, and water is scraped Piece upper end has a head coordinated with T-shaped hole.
7. a kind of belt switch as claimed in claim 1 determines the assembled connecting bridge service door of door gear, it is characterised in that described Door body lower sidewall is provided with skirting board.
8. a kind of belt switch as claimed in claim 1 determines the assembled connecting bridge service door of door gear, it is characterised in that described Reinforced seat is provided with upper door frame, door closer is provided between upper door frame and door body, door closer passes through spiral shell with upper door frame junction Nail is connected through upper door frame side wall and with reinforced seat.
9. a kind of belt switch as claimed in claim 1 determines the assembled connecting bridge service door of door gear, it is characterised in that described Fluid sealant is all provided between side door frame and connecting bridge side wall, between upper door frame and connecting bridge side wall.
10. a kind of belt switch as claimed in claim 1 determines the assembled connecting bridge service door of door gear, it is characterised in that described Side door frame extends to the rib on connecting bridge in hole with one;Have inside door body in multiple cavitys, cavity filled with heat-insulated Cotton.
CN201720095555.8U 2017-01-22 2017-01-22 A kind of belt switch determines the assembled connecting bridge service door of door gear Withdrawn - After Issue CN206554698U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720095555.8U CN206554698U (en) 2017-01-22 2017-01-22 A kind of belt switch determines the assembled connecting bridge service door of door gear

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720095555.8U CN206554698U (en) 2017-01-22 2017-01-22 A kind of belt switch determines the assembled connecting bridge service door of door gear

Publications (1)

Publication Number Publication Date
CN206554698U true CN206554698U (en) 2017-10-13

Family

ID=60010518

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720095555.8U Withdrawn - After Issue CN206554698U (en) 2017-01-22 2017-01-22 A kind of belt switch determines the assembled connecting bridge service door of door gear

Country Status (1)

Country Link
CN (1) CN206554698U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593205A (en) * 2017-01-22 2017-04-26 美迪斯智能装备有限公司 Assembly type boarding bridge service door with on-off door fixing device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593205A (en) * 2017-01-22 2017-04-26 美迪斯智能装备有限公司 Assembly type boarding bridge service door with on-off door fixing device
CN106593205B (en) * 2017-01-22 2018-10-16 美迪斯智能装备有限公司 Belt switch determines the assembled connecting bridge service door of door gear

Similar Documents

Publication Publication Date Title
CN104652670B (en) It is a kind of can indoor location glass curtain wall system
CN206554698U (en) A kind of belt switch determines the assembled connecting bridge service door of door gear
CN111852255A (en) Door-wall integrated equipment well door frame and installation method
JP2006342542A (en) Sill modification structure of double sliding sash
CN106593205B (en) Belt switch determines the assembled connecting bridge service door of door gear
CN103255980B (en) Door window functional-type auxiliary frame, auxiliary frame structure and installing method of functional-type doors and windows
CN111350542A (en) Fireproof protective airtight door for movable doorsill of high-speed railway tunnel evacuation channel
CN215565446U (en) Double-layer heat-insulation stone door
CN212225322U (en) Fireproof protective airtight door for movable doorsill of high-speed railway tunnel evacuation channel
KR101553571B1 (en) Swing type floodgate for underground parking lot ramp and construction method thereof
CN212054311U (en) Hidden door structure capable of being completely opened
CN213742924U (en) Structure self-waterproof door and window connecting node suitable for double-sided laminated sandwich heat-insulation wallboard
CN104058313B (en) A kind of hoistway moisture-proof construction of elevator
CN210713312U (en) Openable explosion venting window wall
CN205778198U (en) A kind of plastic-steel window being easy to load and unload glass
CN208073309U (en) A kind of buried cable piping lane fire resistant doorsets
CN206668068U (en) A kind of sliding plastic-steel window of locking rail mechanism
CN217952511U (en) Wall body convenient to outer machine of installation air conditioner
JP4874708B2 (en) Sliding door device
CN219569720U (en) Flip type camping house
JP3809505B2 (en) door
CN204098747U (en) Cleaning door
JP2010184755A (en) Landing hall unit of elevator
CN212613900U (en) Metal combination anchoring part for repairing falling-off of external thermal insulation board of external wall
CN206592016U (en) A kind of pneumatic outstanding window system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20171013

Effective date of abandoning: 20181016