CN206539371U - False lane construction systems - Google Patents

False lane construction systems Download PDF

Info

Publication number
CN206539371U
CN206539371U CN201720222315.XU CN201720222315U CN206539371U CN 206539371 U CN206539371 U CN 206539371U CN 201720222315 U CN201720222315 U CN 201720222315U CN 206539371 U CN206539371 U CN 206539371U
Authority
CN
China
Prior art keywords
tunnel
region
false lane
construction systems
false
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720222315.XU
Other languages
Chinese (zh)
Inventor
尹国光
王照亚
张忠辉
郭建民
李腾
李纪玉
何国强
杨勇
邱英魁
安龙
韩春雨
王攀志
刘涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Gold Mining (laizhou) Co Ltd Jiaojia Gold Mine
Original Assignee
Shandong Gold Mining (laizhou) Co Ltd Jiaojia Gold Mine
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Gold Mining (laizhou) Co Ltd Jiaojia Gold Mine filed Critical Shandong Gold Mining (laizhou) Co Ltd Jiaojia Gold Mine
Priority to CN201720222315.XU priority Critical patent/CN206539371U/en
Application granted granted Critical
Publication of CN206539371U publication Critical patent/CN206539371U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The utility model discloses a kind of false lane construction systems, including it is arranged at the locking device at laneway opening end, locking device and tunnel inwall(1)And ground surrounds space in the tunnel of closing;False lane construction systems also include the structure-steel framing laid along tunnel(2), structure-steel framing(2)Space in tunnel is divided into false lane region and outer peripheral areas;False lane region refers to structure-steel framing(2)With ground area defined, outer peripheral areas is structure-steel framing(2)With tunnel inwall(1)Between region;Be placed with false lane region it is one or more it is soft can filling container;False lane construction systems also include with can filling container be connected with to can in filling container filling water or gas apparatus for filling container, and output end is passed through in outer peripheral areas to fill the cement filling device of binding material in region to the periphery.The utility model has the advantages that low simple to operate, cost, short time limit, efficiency high and security are good.

Description

False lane construction systems
Technical field
The utility model is related to the system and device that false lane is constructed in a kind of mining engineering.
Background technology
During mining usually can because run into crushed zone and caused by wall caving, roof fall situations such as.Solution of the prior art Certainly measure mainly has:A large amount of supporting measures, secondary excavation obturation and engineering is put into change its course.But above-mentioned solution not only cost High, long in time limit, efficiency is low, and can also bring in operation process certain potential safety hazard.
The content of the invention
The utility model proposes a kind of false lane construction systems, the purpose is to:Avoid wall caving, roof fall situation occur apply During work, cost is reduced, shortens the duration, efficiency of construction is improved, potential safety hazard is reduced.
Technical solutions of the utility model are as follows:
False lane construction systems, including be arranged at the locking device at laneway opening end, the locking device and tunnel inwall and Ground surrounds space in the tunnel of closing;
The false lane construction systems also include the structure-steel framing laid along tunnel, and space in tunnel is divided into by the structure-steel framing False lane region and outer peripheral areas;The false lane region refers to structure-steel framing and ground area defined, and the outer peripheral areas is knot Region between framework and tunnel inwall;
Be placed with the false lane region it is one or more it is soft can filling container;
The false lane construction systems also include with can filling container be connected with to can filling water or gas in filling container Apparatus for filling container, and output end are passed through in outer peripheral areas and fill dress with the cement that binding material is filled in region to the periphery Put.
It is used as further improvement of the utility model:It is described can filling container be capsule.
It is used as further improvement of the utility model:Pressure-detecting device is installed on the apparatus for filling container.
Relative to prior art, the utility model has the positive effect that:The utility model is used based on inflation or water Capsule prefabricating technique, on the one hand realize supporting during consolidation operations, it is not necessary to put into substantial amounts of supporting measure again, reduce Form erecting operation program, on the other hand can be formed directly in false tunnel, secondary excavation obturation workload is few, without work after deflation or water Cheng Gaidao, has the advantages that low simple to operate, cost, short time limit, efficiency high and security are good.
Brief description of the drawings
Fig. 1 is the structural representation of specific embodiment.
Fig. 2 is Fig. 1 schematic top plan view.
Embodiment
Describe the technical solution of the utility model in detail below in conjunction with the accompanying drawings:
Such as Fig. 1 and 2, a kind of false lane construction systems, including be arranged at the closing wallboard 4 at laneway opening end, the enclosing wall Plate 4 surrounds space in the tunnel of closing with tunnel inwall 1 and ground;
The false lane construction systems also include the structure-steel framing 2 laid along tunnel, and the structure-steel framing 2 divides space in tunnel Into false lane region and outer peripheral areas;The false lane region refers to structure-steel framing 2 and ground area defined, and the outer peripheral areas is Region between structure-steel framing 2 and tunnel inwall 1;
Be placed with the false lane region it is one or more it is soft can filling container;Preferably, it is described can filling container For capsule 3.
The false lane construction systems also include being connected with capsule 3 filling the vessel filling dress of water or gas into capsule 3 Put, and output end is passed through in outer peripheral areas to fill the cement filling device of binding material in region to the periphery.
Pressure gauge is installed on the apparatus for filling container, for detecting the stuffing pressure in capsule 3.
The step of constructing false lane using above-mentioned false lane construction systems is as follows:
(A)Bar construction frame 2 is laid along along tunnel;
(B)Capsule 3 is laid in the space that structure-steel framing 2 and ground are surrounded;
(C)Inflated using apparatus for filling container to capsule 3 or water-filling, capsule 3 is bulged and fill full structure-steel framing 2 and ground institute The space surrounded;During filling, the pressure in capsule 3 is maintained at 0.05Mpa;
(D)Closing wallboard 4 is installed;
(E)The output end of cement filling device is passed through in outer peripheral areas, binding material is filled in region to the periphery;Institute The cement-sand ratio for stating binding material is 1:4;
(F)After the completion of cementing, closing wallboard 4 is removed;
(G)The gas or water in capsule 3 are released after curing period, capsule 3 is removed.
Debris in false lane is finally cleared up, constructing for false lane is completed.

Claims (3)

1. false lane construction systems, it is characterised in that:Locking device including being arranged at laneway opening end, the locking device and lane Road inwall(1)And ground surrounds space in the tunnel of closing;
The false lane construction systems also include the structure-steel framing laid along tunnel(2), the structure-steel framing(2)Space in tunnel is divided Into false lane region and outer peripheral areas;The false lane region refers to structure-steel framing(2)With ground area defined, the outer peripheral areas For structure-steel framing(2)With tunnel inwall(1)Between region;
Be placed with the false lane region it is one or more it is soft can filling container;
The false lane construction systems also include with can filling container be connected with to can in filling container filling water or gas container Filling device, and output end are passed through in outer peripheral areas to fill the cement filling device of binding material in region to the periphery.
2. vacation lane as claimed in claim 1 construction systems, it is characterised in that:It is described can filling container be capsule(3).
3. vacation lane as claimed in claim 1 or 2 construction systems, it is characterised in that:Pressure is installed on the apparatus for filling container Force checking device.
CN201720222315.XU 2017-03-09 2017-03-09 False lane construction systems Active CN206539371U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720222315.XU CN206539371U (en) 2017-03-09 2017-03-09 False lane construction systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720222315.XU CN206539371U (en) 2017-03-09 2017-03-09 False lane construction systems

Publications (1)

Publication Number Publication Date
CN206539371U true CN206539371U (en) 2017-10-03

Family

ID=59941031

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720222315.XU Active CN206539371U (en) 2017-03-09 2017-03-09 False lane construction systems

Country Status (1)

Country Link
CN (1) CN206539371U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106884674A (en) * 2017-03-09 2017-06-23 山东黄金矿业(莱州)有限公司焦家金矿 False lane construction systems and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106884674A (en) * 2017-03-09 2017-06-23 山东黄金矿业(莱州)有限公司焦家金矿 False lane construction systems and construction method
CN106884674B (en) * 2017-03-09 2019-10-11 山东黄金矿业(莱州)有限公司焦家金矿 False lane construction systems and construction method

Similar Documents

Publication Publication Date Title
CN105937407B (en) A kind of construction method of gob-side entry retaining concrete filling wall annular air-pocket
CN104453930B (en) Tunnel initial lining construction device and method
CN205618200U (en) Inflatable tunnel shield seals high -pressure rubber gasbag
CN107035401A (en) A kind of abandoned mine fire damp administers new technology
CN103195390A (en) Mining-coal bed nearly horizontal gas extraction borehole sealing method
CN105019924B (en) Strong roof support pier column and method for protecting section coal pillar
CN106089252B (en) Grouting reinforcement method for inhomogeneous loose bodies
CN105736046A (en) Coal mine underground sealed wall body and construction method thereof
CN102182468A (en) Method and device for solidifying water-filling cracking surrounding rocks of tunnel by adopting high-pressure air water-dispelling grouting
CN107489432A (en) Tunnel support grouting equipment and its grouting method
CN207620844U (en) A kind of mine high-water material filling unit
CN105952492B (en) A kind of high gas layer working face drilling Gas pre-drainage method
CN206539371U (en) False lane construction systems
CN104500109A (en) Underground support pillar and construction method thereof
CN106194250B (en) A kind of gob-side entry retaining concrete filling wall annular air-pocket template
CN105021796B (en) For simulating the test method of packed type fault belt rock mass
CN207620842U (en) A kind of mine high-water material filling bag fixed frame
CN208456572U (en) Packaged type hydraulic fracturing and injection hole sealing integrated apparatus
CN106884674B (en) False lane construction systems and construction method
CN108756971A (en) A kind of hollow grouting cable anchor and its staged isolation grouting method
CN112682092A (en) Close-range coal seam floor crossing pressure relief drilling and hole sealing system and method
CN205822206U (en) A kind of vertical side slope bracing means
CN208587173U (en) A kind of both ends anchoring prestress component grouted anchor bar for underground mine tunnel
CN104790900A (en) Method for blocking gas extraction boreholes with coal and rock debris as borehole sealing material
CN105781606A (en) Method for sealing large-dip-angle downward coal-seam-penetrating gas extraction-drainage drill hole