CN206539370U - Tunnel escape device - Google Patents

Tunnel escape device Download PDF

Info

Publication number
CN206539370U
CN206539370U CN201720174811.2U CN201720174811U CN206539370U CN 206539370 U CN206539370 U CN 206539370U CN 201720174811 U CN201720174811 U CN 201720174811U CN 206539370 U CN206539370 U CN 206539370U
Authority
CN
China
Prior art keywords
escape
tunnel
room
face
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720174811.2U
Other languages
Chinese (zh)
Inventor
龚凯华
李学文
龙永强
时定伟
陈和盛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201720174811.2U priority Critical patent/CN206539370U/en
Application granted granted Critical
Publication of CN206539370U publication Critical patent/CN206539370U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model is related to a kind of tunnel escape device, including:Escape room at tunnel tunnel face, portion within doors of escaping is formed with escape space, and escape room and offers the inlet and outlet connected with escape space;And it is installed in the escape tube for exporting and being connected with escape space.The utility model tunnel escape device sets safe escape room at face, escape room is communicated with escape tube, when face unstability is caved in, escape room provides a closing, interim safety for the operating personnel of construction below face and protects place, and to starting rescue, time enough is striven in work.

Description

Tunnel escape device
Technical field
The utility model is related to the realm of building construction, espespecially a kind of tunnel escape device.
Background technology
In the construction of newly built tunnels, because geological state is complicated and changeable, there is the possibility of landslide, construction in work progress The accident of casualties occurs in personnel if it can not flee from time.
According to current highway engineering construction safety technical specification, Support System in Soft Rock Tunnels is excavated face to two linings and must be provided with Passway for escaping, as face constantly moves forward, passway for escaping from cannot be greater than 20 meters with a distance from face, the rigidity of passway for escaping, Intensity, impact capacity should meet safety requirements, and passway for escaping is difficult to be less than 0.8m.
Given a lesson to according to previous experiences, escape tubular type passway for escaping is only applicable to the face rear in the tunnel and caved in thing Therefore when workmen be trapped in hole ideally, escape tube be trapped personnel conveying air, food and relief goods or Voluntarily withdrawn from passage.
But actual weak tunnel is in digging process, the probability that face unstability is caved in is much larger than face rear unstability The probability caved in, and the space that the personnel operated in this case in face almost do not survive, if workmen can not Flee from time, the accident of casualties occurs.
Utility model content
The purpose of this utility model is that the defect for overcoming prior art, there is provided a kind of tunnel escape device, is solved existing The problem of space that the personnel operated when face unstability is caved in technology in face almost do not survive.
Realizing the technical scheme of above-mentioned purpose is:
The utility model provides a kind of tunnel escape device, including:
Escape room at tunnel tunnel face, portion is formed with escape space, and the escape room within doors for the escape Offer the inlet and outlet connected with the escape space;And
It is installed in the escape tube for exporting and being connected with the escape space.
The beneficial effect of the utility model tunnel escape device:
The utility model tunnel escape device sets safe escape room at face, and escape room is communicated with escape tube, When face unstability is caved in, escape room provides a closing, interim safety for the operating personnel of construction below face and protected Place, to starting rescue, time enough is striven in work.
The utility model tunnel escape device further improvement is that, the escape room is spelled by multiple corrugated steel units Connect and form.
The utility model tunnel escape device further improvement is that, the escape room be cylindrical structure, the cartridge type The top of structure is arc tip.
The utility model tunnel escape device further improvement is that, the outlet is relative located at the cylindrical structure One end away from the face.
The utility model tunnel escape device further improvement is that, the end of two neighboring corrugated steel unit is mutual Overlap joint, and be fixedly connected by the first bolt.
The utility model tunnel escape device further improvement is that, the edge of the import is fixed with angle steel flange.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model tunnel escape device.
Fig. 2 is the utility model tunnel escape device side view.
Fig. 3 is the front view of the utility model tunnel escape device.
The enlarged diagram that Fig. 4 is A in Fig. 3.
The enlarged diagram that Fig. 5 is B in Fig. 3.
Embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1, it is shown that the structural representation of the utility model tunnel escape device.As shown in figure 1, the utility model Tunnel escape device includes:Escape room 10 and escape tube 20, wherein, escape room 10 is at tunnel tunnel face, the tunnel face Face is the working face constantly pushed ahead during tunnelling.Escape room 10 has been internally formed escape space.Escape room 10 Offer import 100 and outlet 101, import 100 is connected with escape space, escape tube 20 be installed in outlet 101 and with escape Space is connected.The utility model tunnel escape device sets safe escape room at face, and escape room is communicated with escape tube, When face unstability is caved in, escape room provides a closing, interim safety for the operating personnel of construction below face and protected Place, to starting rescue, time enough is striven in work.
Refering to Fig. 2, it is shown that the utility model tunnel escape device side view.Refering to Fig. 3, it is shown that the utility model tunnel The front view of road escape device.With reference to shown in Fig. 1 to Fig. 3, escape room 10 is cylindrical structure, and the top of cylindrical structure is arc point End.When tunnel surrounding caves in, the area for receiving frontal impact greatly reduces, and the body that caves in runs into the backward escape in arc tip The both sides in room and diffuse to form native arch, so in the case of equal material and size, using the cylindrical structure with arc tip Than the pressure of more large impact can be born using rectangular parallelepiped structure.
Refering to Fig. 4, it is shown that A enlarged diagram in Fig. 3.With reference to shown in Fig. 3 and Fig. 4, escape room 10 is by multiple ripples Steel plate unit 1020 is spliced.Using corrugated steel material compared to plane steel plate is used, impact of the corrugated portion to falling rocks has There are bigger buffering and smaller deflection, it is not easy to destroyed by falling rocks.So in other words, under equal impact resistance, Using corrugated steel material than the weight saving 50% using plane steel plate, the installation weight being so made is small, is more conducive to exist Frequently moved in digging process.
Specifically, to obtain the suitable specification of corrugated steel, following experiment has been carried out:
Due to the impact resistance of mainly consider to escape when Tunnel Landslide room and escape tube, and pounded position and need satisfaction The evacuation demand of personnel.The utility model tunnel escape device is subjected to field test.Impact test piece is block boulder, and weight is 1000KG.The utility model tunnel escape device is placed on sand bedding course, impact test piece mainly takes from escape room distance from top Certainly in the excavation height of tunnel cross-section, such as, when the height of tunnel excavation is 8.45m, during a height of 2m in room of escaping, this is tested Height be set to 7m, the height of stone test specimen is lifted by crane.In test, through measurement either middle part or end Maximum distortion is respectively less than 150mm, fully meets escape and requires.Therefore the model of corrugated steel can be set to waveform 75mm × 25mm, thickness of slab is 4mm.It is possible to more more severe than test situation in view of actual field situation, to obtain corrugated portion to falling Stone impacts bigger buffering and smaller deflection, and bigger ripple 150mm × 50mm × 4mm will be selected during actual production.
With reference to shown in Fig. 3 and Fig. 4, the end of two neighboring corrugated steel unit 1020 is mutually overlapped, and passes through the first spiral shell Bolt 30 is fixedly connected.Specifically, the crest and crest of two corrugated steel units 1020 is overlapped, trough and trough are mutual It is overlapping, the first bolt 30 is worn to two overlapped troughs, and be screwed together on the first bolt 30 to fix using nut.
Specifically, escape room 10 import 100 located at cylindrical structure side middle part, escape room 10 import 100 with Escape space is connected.In the present embodiment, the edge of import 100 is fixed with angle steel flange.So when face unstability is caved in, The operating personnel of construction can be entered at the import 100 in escape room 10 in escape room 10 below face, and escape room 10 can One closing, interim safety are provided with the operating personnel for construction below face and protect place, work is striven to starting rescue Take time enough.
The outlet 101 in escape room 10 is located at one end for being relatively distant from face of cylindrical structure.Export to be communicated with 101 and escape Raw pipe 20, the so operating personnel into escape room 10 can just go out at outlet 101 by escape tube 20.
Refering to Fig. 5, it is shown that B enlarged diagram in Fig. 3.With reference to shown in Fig. 3 to Fig. 5, the end in room 10 of escaping, ripple The trough laminating of line steel plate unit 1020 is placed on the top of the end in escape room 10, the second bolt 40 is worn overlapped The top of the end in trough and escape room 10, and be screwed together on the second bolt 40 to fix using nut.
The utility model tunnel escape device has the beneficial effect that:
The utility model tunnel escape device sets safe escape room at face, and escape room is communicated with escape tube, When face unstability is caved in, escape room provides a closing, interim safety for the operating personnel of construction below face and protected Place, to starting rescue, time enough is striven in work.The cross section in escape room is horseshoe type face, and the top in horseshoe type face is arc Shape tip, when tunnel surrounding caves in, the area that arc tip receives frontal impact greatly reduces, and the body that caves in runs into The both sides in the backward escape room in arc tip diffuse to form native arch, and the shape of a hoof can be held than rectangle in the case of equal material and size By the pressure of more large impact.The side in escape room is formed using multiple corrugated steel unit spliceds, in equal impact resistance Under, it is more many than the weight saving using general steel plate using corrugated steel, escape room is continually moved more conducively in digging process It is dynamic.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to described above.Thus, some of embodiment details should not be constituted to this practicality New restriction, the utility model regard the scope defined using appended claims as protection domain of the present utility model.

Claims (6)

1. a kind of tunnel escape device, it is characterised in that including:
Escape room at tunnel tunnel face, portion is formed with escape space, and the escape room and opened up within doors for the escape There is the inlet and outlet connected with the escape space;And
It is installed in the escape tube for exporting and being connected with the escape space.
2. tunnel escape device as claimed in claim 1, it is characterised in that spelled by multiple corrugated steel units in the escape room Connect and form.
3. tunnel escape device as claimed in claim 1, it is characterised in that the escape room is cylindrical structure, the cartridge type The top of structure is arc tip.
4. tunnel escape device as claimed in claim 3, it is characterised in that the outlet is relative located at the cylindrical structure One end away from the face.
5. tunnel escape device as claimed in claim 2, it is characterised in that the end of two neighboring corrugated steel unit is mutual Overlap joint, and be fixedly connected by the first bolt.
6. tunnel escape device as claimed in claim 1, it is characterised in that the edge of the import is fixed with angle steel flange.
CN201720174811.2U 2017-02-27 2017-02-27 Tunnel escape device Expired - Fee Related CN206539370U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720174811.2U CN206539370U (en) 2017-02-27 2017-02-27 Tunnel escape device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720174811.2U CN206539370U (en) 2017-02-27 2017-02-27 Tunnel escape device

Publications (1)

Publication Number Publication Date
CN206539370U true CN206539370U (en) 2017-10-03

Family

ID=59946500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720174811.2U Expired - Fee Related CN206539370U (en) 2017-02-27 2017-02-27 Tunnel escape device

Country Status (1)

Country Link
CN (1) CN206539370U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173296A (en) * 2019-06-17 2019-08-27 中交一公局第一工程有限公司 A kind of safe escape room and its preparation and application
CN117307239A (en) * 2023-11-29 2023-12-29 泰兴市华诚机电制造有限公司 Air supply device of tunnel construction rescue capsule and use method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173296A (en) * 2019-06-17 2019-08-27 中交一公局第一工程有限公司 A kind of safe escape room and its preparation and application
CN110173296B (en) * 2019-06-17 2024-05-07 中交一公局第一工程有限公司 Safe danger-avoiding escape house and preparation and use methods thereof
CN117307239A (en) * 2023-11-29 2023-12-29 泰兴市华诚机电制造有限公司 Air supply device of tunnel construction rescue capsule and use method
CN117307239B (en) * 2023-11-29 2024-01-30 泰兴市华诚机电制造有限公司 Air supply device of tunnel construction rescue capsule and use method

Similar Documents

Publication Publication Date Title
Wang et al. Overlying strata movement rules and safety mining technology for the shallow depth seam proximity beneath a room mining goaf
CN205654349U (en) Device based on interconnection removes shield zone cataract or glaucoma impenetrability foreign matter
CN103939144B (en) A kind of consecutive intervals cushion wall for closed large scale mined area
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN201155331Y (en) Head-on safe protection shield for tunnel development
CN108005655A (en) A kind of projecting coal bed double lane arrangements of high methane are without pillar mining method
CN109611103B (en) Method for reinforcing shield section suspended boulder group
CN111997639B (en) Method for getting rid of trouble and reinforcing and improving geology of TBM construction tunnel bad geology section card machine
CN206539370U (en) Tunnel escape device
CN108150187A (en) A kind of huge loose talus shield encircles the method into hole
CN104141500B (en) One hardens sand and gravel stratum cavern con struction method
CN203700978U (en) Box culvert pilot tubal curtain device
CN202611714U (en) Tunnel assembly type construction trolley without welding
CN104747197B (en) A kind of balancing earth-pressure shielding machine soil storehouse mud cake detection device
CN102080551A (en) Three-amplitude construction method for inverted arch of primary support of weak broken wall rock tunnel
CN211144498U (en) Novel shield cutter head
CN217327382U (en) Integrated excavation working face head-on rib-splitting prevention temporary support system
CN207332903U (en) A kind of new pressure type goaf gangue stopping device that allows
CN212656835U (en) Broken type stope supporting construction of ore rock
CN113356907A (en) Gob-side entry retaining construction process for coal seam disaster prevention and control
CN111119891A (en) Long wall mining 120 method
CN208056130U (en) Power transmission tower foundation protective device in mud-rock flow raceway groove
CN206928968U (en) A kind of rigid backbone scraper loader guard rail
CN207080251U (en) A kind of tunnel pipe for escaping of adjustable elevation angle
CN207278269U (en) A kind of combination moving type construction operation platform for mining sectbn

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171003