CN206522919U - Wall-hanging gas-fired speed heat air air-heater - Google Patents
Wall-hanging gas-fired speed heat air air-heater Download PDFInfo
- Publication number
- CN206522919U CN206522919U CN201720108120.2U CN201720108120U CN206522919U CN 206522919 U CN206522919 U CN 206522919U CN 201720108120 U CN201720108120 U CN 201720108120U CN 206522919 U CN206522919 U CN 206522919U
- Authority
- CN
- China
- Prior art keywords
- air
- gas
- heat
- preheating chamber
- air cleaning
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Direct Air Heating By Heater Or Combustion Gas (AREA)
Abstract
The utility model provides a kind of wall-hanging gas-fired speed heat air air-heater, including cuboid casing, it is distributed in the air cleaning preheating chamber in casing, Heat Room, burning gas distributing chamber, gas burner and proportioning valve are provided with burning gas distributing chamber, gas distributing chamber bottom burn provided with air distribution hole, direct combustion heat exchanger tube provided with interconnected distribution of spiraling in Heat Room and air cleaning preheating chamber, air cleaning preheating chamber upper end is provided with outdoor gas-distribution pipe and indoor air admission hole, hole is communicated between air cleaning preheating chamber and Heat Room, intercommunicating pore is provided with an air blower, air cleaning filter is provided with air cleaning preheating chamber.The utility model directly heats direct combustion heat exchanger tube using gas burner, then heated using the air in direct combustion heat exchanger tube heat exchanging room, hot-air is sent out by hot-blast outlet and is used as heating reservoir gas, instant-heating, there is air-cleaning function simultaneously, equipment volume is small, easy to install, good heating effect.
Description
Technical field
The utility model is related to heating power switching equipment technical field, more particularly to a kind of wall-hanging gas-fired speed heat air hot blast
Machine.
Background technology
It is seriously polluted that coal heating equipment is caused to atmospheric environment, and heat energy loss is larger, is that promotion makes energetically for this country
Heating fuel is used as with the natural gas of clean environment firendly.Gas heating equipment of the prior art is generally gas water heating heating stove or straight
Combustion speed heat Gas Generator Set, gas water heating heating stove is compact and flexible, power be arranged such that is worked as, but using water as medium.It is this
The water in several years is heated to tens degree by heating stove first, then is warmed oneself by radiator or floor heating heat loss through radiation, there is heating speed
Degree is slow, many heat wastes, long operational time, high energy consumption the problems such as, to prevent fin and the icing of pipeline low temperature of centre, heating season
Mid-term can not stop.If ventilation can reduce indoor temperature rapidly during heating.Direct-fired speed heat Gas Generator Set one is opened i.e.
Heat, with low temperature frozen pipe with opening, is not afraid of, manufacturing cost and operating cost are low, and energy utilization rate is high, heating and good heating effect,
It is adapted to the enterprise and unit of non-working time and festivals or holidays without heating, energy-saving and environmental protection effect is obvious.But it is this direct-fired
Speed heat Gas Generator Set is generally Large-scale machine set, complicated, and installation difficulty is big, and domestic consumer is difficult to receive, and is unfavorable for promoting
Popularization.
The content of the invention
The technical problem that the utility model is solved is to provide a kind of wall-hanging gas-fired speed heat air air-heater, the device
Have the advantages that convenient for installation and maintenance, programming rate is fast, energy utilization rate is high, disposal of pollutants is few, equipment investment is few.
In order to solve the above technical problems, the utility model is adopted the following technical scheme that:A kind of wall-hanging gas-fired speed heat air
Air-heater, it is characterised in that:Including cuboid casing, it is distributed in the air cleaning preheating chamber on casing top, is distributed in casing
Gas burner and proportioning valve, combustion are provided with the Heat Room at middle part, the burning gas distributing chamber for being distributed in bottom of shell, burning gas distributing chamber
Burn gas distributing chamber bottom and be provided with the direct combustion heat exchange provided with interconnected distribution of spiraling in air distribution hole, Heat Room and air cleaning preheating chamber
Pipe, air cleaning preheating chamber upper end is provided with outdoor gas-distribution pipe and indoor air admission hole, and direct combustion heat exchanger tube upper end is in outdoor gas-distribution pipe
The heart is extended to be connected outside air cleaning preheating chamber with flue tube, and flue tube is provided with air-introduced machine, direct combustion heat exchanger tube bottom and combustion
Air burner is connected, and hole is communicated between air cleaning preheating chamber and Heat Room, and intercommunicating pore is provided with an air blower, air blast seat in the plane
In the air in air cleaning preheating chamber is blowed into Heat Room in air cleaning preheating chamber, Heat Room is provided with the hot blast for leading to interior
Air cleaning filter is provided with outlet, air cleaning preheating chamber.
As the further improvement of the technical program, the direct combustion heat exchanger tube is thin-wall stainless steel.
As the further improvement of the technical program, the heat exchange chamber outer wall is provided with heat-insulation layer, the outdoor gas-distribution pipe and
Change-over switch is provided between indoor air admission hole.
As the further improvement of the technical program, a master controller, master controller are provided with outside the burning gas distributing chamber
It is connected with air blower, gas burner.
Wall-hanging gas-fired speed heat air air-heater described in the utility model, directly utilizes gas burner heating direct combustion heat exchange
Pipe, is then heated using the air in direct combustion heat exchanger tube heat exchanging room, is sent out hot-air by hot-blast outlet and is used as heating
Heat source gas, instant-heating is not afraid of low temperature frozen pipe, and energy heat utilization efficiency is high.Air cleaning preheating chamber has air cleaning simultaneously
Function, air cleaning preheating chamber, Heat Room, burning gas distributing chamber are reasonably distributed, and compact conformation, equipment volume is small, the side of installing and using
Just, good heating effect.
Brief description of the drawings
Fig. 1 is the structural representation of wall-hanging gas-fired speed heat air air-heater described in the utility model.
Corresponding component names are in figure:1 casing, 2 air cleaning preheating chambers, 3 Heat Rooms, 4 burning gas distributing chamber, 5 combustion gas
Burner, 6 proportioning valves, 7 air distribution holes, 8 direct combustion heat exchanger tubes, gas-distribution pipe outside Room 9, air admission hole, 11 flue tubes, 12 connections in Room 10
Hole, 13 air blowers, 14 hot-blast outlets, 15 air cleaning filters, 16 heat-insulation layers, 17 master controllers, 18 air-introduced machines.
Embodiment
Refer to shown in Fig. 1, the utility model provides a kind of wall-hanging gas-fired speed heat air air-heater, including cuboid
Casing 1, the air cleaning preheating chamber 2 for being distributed in casing top, the Heat Room 3 being distributed in the middle part of casing, it is distributed in bottom of shell
Burning gas distributing chamber 4, be provided with gas burner 5 and proportioning valve 6 in burning gas distributing chamber, burning gas distributing chamber bottom provided with air distribution hole 7,
Direct combustion heat exchanger tube 8 provided with interconnected distribution of spiraling in Heat Room and air cleaning preheating chamber, air cleaning preheating chamber upper end
Provided with outdoor gas-distribution pipe 9 and indoor air admission hole 10, it is pre- that direct combustion heat exchanger tube upper end extends to air cleaning by outdoor distribution tube hub
Connected outside hot cell with flue tube 11, flue tube is provided with air-introduced machine 18, direct combustion heat exchanger tube bottom is connected with gas burner, it is empty
Hole 12 is communicated between gas purifying, preheating room and Heat Room, intercommunicating pore is provided with an air blower 13, and air blower is located at air cleaning
The air in air cleaning preheating chamber is blowed into Heat Room in preheating chamber, Heat Room is provided with the hot-blast outlet 14 for leading to interior, empty
Air cleaning filter 15 is provided with gas purifying, preheating room.The heat exchange chamber outer wall is provided with heat-insulation layer 16, the outdoor gas-distribution pipe
Change-over switch is provided between indoor air admission hole.A master controller 17, master controller and drum are provided with outside the burning gas distributing chamber
Blower fan, air-introduced machine, gas burner connection.The direct combustion heat exchanger tube 8 is thin-wall stainless steel.
Wall-hanging gas-fired speed heat air air-heater based on said structure design, when in use, complete machine suspension are installed
In on indoor wall, flue tube 11 and outdoor gas-distribution pipe 9 are disposed in the outdoor through wall, the outlet of flue tube 11 and outdoor distribution
The entrance of pipe 9 reserves enough distances to ensure that the air got in is fresh.Flue tube 11 sets air-introduced machine 18 to be used to force
Smoke evacuation and solid waste gas.Hot-blast outlet 14 is arranged on the interior for needing to warm oneself, and gas burner is connected with fuel gas transportation pipeline, fires
The gas being burning is delivered to direct combustion heat exchanger tube 8 by air burner, and gas in combustion rapidly heats direct combustion heat exchanger tube 8,
Direct combustion heat exchanger tube 8 heats rapidly the gas in Heat Room 3, the blowing in air blower 13 of the hot gas in gas in Heat Room 3
Under power effect, hot-blast outlet 14 delivers to the interior for needing to warm oneself, and reaches the purpose of heating.Flue tube 11 is in outdoor gas-distribution pipe 9
The heart, into outer gas-distribution pipe 9 gas can be carried out using the direct combustion heat exchanger tube 8 in flue tube 11 and air cleaning preheating chamber 2 it is pre-
Heat, air cleaning filter 15 is re-fed into heating of house after being purified to the gas in air inlet purifying, preheating room 2, to protect
Demonstrate,prove room air pure and fresh.
It is described above, only it is most preferred embodiment of the present utility model, not makees any formal to the utility model
Limitation, any those skilled in the art, in the case where not departing from technical solutions of the utility model ambit, using above-mentioned
The method content of announcement makes many possible variations and modification to technical solutions of the utility model, belongs to claims guarantor
The scope of shield.
Claims (4)
1. a kind of wall-hanging gas-fired speed heat air air-heater, it is characterised in that:Including cuboid casing, it is distributed in casing top
Air cleaning preheating chamber, be distributed in the middle part of casing Heat Room, be distributed in the burning gas distributing chamber of bottom of shell, gas distributing chamber of burning
Interior to be provided with gas burner and proportioning valve, burning gas distributing chamber bottom, which is provided with air distribution hole, Heat Room and air cleaning preheating chamber, to be set
There is the direct combustion heat exchanger tube of interconnected distribution of spiraling, air cleaning preheating chamber upper end is provided with outdoor gas-distribution pipe and indoor air admission hole,
Direct combustion heat exchanger tube upper end is extended to by outdoor distribution tube hub and connected outside air cleaning preheating chamber with flue tube, is set on flue tube
There is air-introduced machine, direct combustion heat exchanger tube bottom is connected with gas burner, and hole is communicated between air cleaning preheating chamber and Heat Room,
Intercommunicating pore is provided with an air blower, and air blower is located in air cleaning preheating chamber blows to heat exchange by the air in air cleaning preheating chamber
Room, Heat Room, which is provided with the hot-blast outlet for leading to interior, air cleaning preheating chamber, is provided with air cleaning filter.
2. wall-hanging gas-fired speed heat air air-heater according to claim 1, it is characterised in that:The direct combustion heat exchanger tube is
Thin-wall stainless steel.
3. wall-hanging gas-fired speed heat air air-heater according to claim 2, it is characterised in that:The heat exchange chamber outer wall is set
There is heat-insulation layer, change-over switch is provided between the outdoor gas-distribution pipe and indoor air admission hole.
4. wall-hanging gas-fired speed heat air air-heater according to claim 2, it is characterised in that:Outside the burning distribution room
Portion is provided with a master controller, and master controller is connected with air blower, gas burner.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720108120.2U CN206522919U (en) | 2017-02-05 | 2017-02-05 | Wall-hanging gas-fired speed heat air air-heater |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720108120.2U CN206522919U (en) | 2017-02-05 | 2017-02-05 | Wall-hanging gas-fired speed heat air air-heater |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206522919U true CN206522919U (en) | 2017-09-26 |
Family
ID=59890242
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720108120.2U Expired - Fee Related CN206522919U (en) | 2017-02-05 | 2017-02-05 | Wall-hanging gas-fired speed heat air air-heater |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206522919U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108548322A (en) * | 2018-04-09 | 2018-09-18 | 李涛 | A kind of direct combustion gas type thermal energy conversion warm-air drier and its application method |
-
2017
- 2017-02-05 CN CN201720108120.2U patent/CN206522919U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108548322A (en) * | 2018-04-09 | 2018-09-18 | 李涛 | A kind of direct combustion gas type thermal energy conversion warm-air drier and its application method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206522919U (en) | Wall-hanging gas-fired speed heat air air-heater | |
CN211146674U (en) | Waste heat exchange device and heat exchange system using same | |
CN205373043U (en) | Grain drying tower heating system's surplus heat energy -saving processing system | |
CN201377902Y (en) | Gas warmer | |
CN110542148A (en) | Domestic natural gas heating system | |
CN202546917U (en) | Heater using smoke waste heat | |
CN211204201U (en) | Integrated solar air hot air system | |
CN206522884U (en) | Quick-cooling, heating group of switches | |
CN202328498U (en) | Multi-gas intelligent heating stove | |
CN206073769U (en) | A kind of waste heat recovery device | |
CN206310711U (en) | A kind of energy-saving type wall-hung boiler and heating system | |
CN1558159A (en) | All-day air renewal solar energy system for heat and hot water supply of building | |
CN201331096Y (en) | Honeycomb briquette environment-friendly and energy-saving hot air heating device | |
CN2826231Y (en) | Heating apparatus employing electrically-heated circulating water | |
CN108489079A (en) | A kind of energy saving gas burning water heater | |
CN201680420U (en) | Biomass energy water heated air-conditioner system for cooking, bathing and heating | |
CN2371492Y (en) | Small fuel oil heating air conditioner | |
CN206300340U (en) | A kind of hen house hot-blast stove | |
CN200993406Y (en) | Efficient energy-saving environmental protection heating stove | |
CN201110595Y (en) | Gas combustion heat recycling heating air conditioner | |
CN201527095U (en) | High-efficient environment-friendly energy-saving hot air heating boiler | |
CN2775547Y (en) | Wair air air conditioner | |
CN205669843U (en) | A kind of effective warming uses gas and hot water spit of fland | |
CN202221152U (en) | Gas air heater | |
CN2521547Y (en) | Outdoor domestic gas-fired warmer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170926 Termination date: 20210205 |
|
CF01 | Termination of patent right due to non-payment of annual fee |