CN206512615U - Bridge maintenance system steel structural embedded parts - Google Patents

Bridge maintenance system steel structural embedded parts Download PDF

Info

Publication number
CN206512615U
CN206512615U CN201720086359.4U CN201720086359U CN206512615U CN 206512615 U CN206512615 U CN 206512615U CN 201720086359 U CN201720086359 U CN 201720086359U CN 206512615 U CN206512615 U CN 206512615U
Authority
CN
China
Prior art keywords
cylinder
buried cylinder
buried
cover
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720086359.4U
Other languages
Chinese (zh)
Inventor
倪志军
彭勇
夏金平
张朝
杨涛
杨洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Hengjia Engineering Consulting Co Ltd
Original Assignee
Chongqing Hengjia Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Hengjia Engineering Consulting Co Ltd filed Critical Chongqing Hengjia Engineering Consulting Co Ltd
Priority to CN201720086359.4U priority Critical patent/CN206512615U/en
Application granted granted Critical
Publication of CN206512615U publication Critical patent/CN206512615U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of bridge maintenance system steel structural embedded parts, including pre-buried cylinder, pre-buried cylinder one end closing, another end opening, the cylinder bottom outer wall of pre-buried cylinder strengthens claw assembly provided with attachment and prevents pulling device, cover is hinged with the nozzle of pre-buried cylinder, being using the beneficial effects of the utility model can be by the direct pre-buried body of a bridge of pre-buried cylinder when constructing a bridge, the support beam for overhauling track can be plugged in during maintenance bridge in pre-buried cylinder, then track is overhauled in laying in support beam, directly support beam is extracted out of pre-buried cylinder when need not use, such a fixed form dismounting is simple, greatly save apparatus for examination and repair sets up the time.Daily cover when need not use can play a part of the pre-buried cylinder of closing, prevent rainwater etc. from stretching into pre-buried cylinder, cause stack shell corruption embroidery, claw assembly and the anti-device that pulls are strengthened in attachment can play a part of fixed pre-buried cylinder, prevent other people from arbitrarily extracting pre-buried cylinder.

Description

Bridge maintenance system steel structural embedded parts
Technical field
The utility model is related to bridge machinery, maintenance, maintenance facility, and a kind of bridge maintenance system steel construction of specific design is pre- Embedded part.
Background technology
Reinforced Concrete Bridge has simple in construction, low cost, long lifespan, easy installation, maintenance and maintenance workload small The advantages of, it is widely applied in trunk railway, highway.But over time with the factor such as the change of external environment condition, The serious plant diseases such as beam body crackle, reinforcing steel bars exposed, diaphragm plate fracture, people's line carrier and bolt corrosion directly endanger bridge security, because This needs is periodically detected and repaired to bridge.Measuring error equipment must be first built before bridge is detected and repaired, Conventional Measuring error equipment is mainly tool car, and then building method is installed tool car first to build repairing frame on bridge On repairing frame, it is not necessary to again remove the repairing frame built when using, but it is to ensure that its is firm when building repairing frame It is attached to build process on bridge comparatively laborious, can be also taken a substantial amount of time during dismounting.
Utility model content
To solve above technical problem, the utility model provides a kind of bridge maintenance system steel structural embedded parts.
Technical scheme is as follows:A kind of bridge maintenance system steel structural embedded parts, its key is:Including pre-buried cylinder, this is pre- One end closing is buried, another end opening, the cylinder bottom outer wall of the pre-buried cylinder pulls device provided with attachment reinforcement claw assembly with anti-, institute State covered with cover on the nozzle of pre-buried cylinder, the cover is hinged with the pre-buried cylinder, the outer wall of the cover is fixed provided with upset Suspension ring.Upset can be triggered solid by suspension hook by the direct pre-buried body of a bridge of pre-buried cylinder when constructing a bridge using the technical program Determining suspension ring makes cover open pre-buried cylinder after rotating 180 °, the support beam for overhauling track is plugged in pre-buried cylinder, then in support Laying maintenance track on beam, it is not necessary to directly extract support beam out of pre-buried cylinder when using, such a fixed form dismounting Simply, greatly save apparatus for examination and repair sets up the time.Daily cover when need not use can play a part of the pre-buried cylinder of closing, Prevent rainwater etc. from stretching into pre-buried cylinder, cause stack shell corruption to embroider, claw assembly and the anti-device that pulls are strengthened in attachment can play fixed pre-buried The effect of cylinder, prevents other people from arbitrarily extracting pre-buried cylinder.
Further, claw assembly is strengthened in above-mentioned attachment includes multiple grapples, the cylinder of the neck of hook of the grapple and the pre-buried cylinder Feather edge is fixedly connected, and the gib head of the grapple is inwardly.Hook the reinforcing bar in the body of a bridge inwardly relatively using this multiple grapple of design, Pre-buried cylinder is prevented to be pulled out or shifted when pouring bridge by concrete apparatus installation site.
Each deep floor that triangle is respectively equipped between the grapple and the pre-buried cylinder, the one of the deep floor Individual side is fixedly connected with the stack shell outer wall of the pre-buried cylinder, another side of the deep floor and the corresponding grapple The neck of hook be fixedly connected.More firm using fixation between this scheme grapple and pre-buried cylinder, grapple is not in transport or installation process Easily deform upon.
The above-mentioned anti-device that pulls pulls bar including anti-, and this prevents that pull the upper end of bar fixes with the cylinder bottom outer wall of the pre-buried cylinder Connection, the anti-bottom for pulling bar is provided with least two and prevents pulling plate, and the anti-cylinder bottom for pulling plate and the pre-buried cylinder is put down OK.Installation rear defence pulls plate and is entrenched in the concrete of the body of a bridge, if there is external force to pull pre-buried cylinder, the anti-cylinder for pulling plate and pre-buried cylinder Between bottom and the adjacent anti-concrete pulled between plate produces a powerful anti-force pulling, pre-buried cylinder is prevented to be pulled out.
Above-mentioned pre-buried cylinder is obliquely installed, and obliquely, the tube port position of the pre-buried cylinder extends out to be formed the nozzle of the pre-buried cylinder Guide openings, the nozzle edge outward flanging of the pre-buried cylinder forms the cover installing plate of annular, and the cover installing plate is located at perpendicular In straight plane, the cover is rotatably installed on the cover installing plate.After being installed using this scheme, the nozzle of pre-buried cylinder With the body of a bridge side it is concordant, it is not only attractive in appearance but do not interfere with laying maintenance track.Cover installing plate is fitted with body of a bridge side, one side side Just install and open cover, another aspect maintainer can find the position of pre-buried cylinder on bridge by cover installing plate.
It is axially arranged with least one floor slot to make way along it on the nozzle inwall of above-mentioned pre-buried cylinder, the floor slot to make way Notch is upward.The deep floor set using this design support beam bending place can be fastened in corresponding cantilever floor slot to make way, It is relatively fixed between support beam and pre-buried cylinder, is not susceptible to relatively rotate, it is more firm during laying maintenance track.
Above-mentioned cover installing plate is provided with cover mounting rod, and the cover passes through institute provided with via, the cover is installed State installation via set to hang on the cover mounting rod, the cover mounting rod is connected with locking end after passing the installation via Head, the cover can rotate around the cover mounting rod, and the fixed suspension ring of upset are located at the underface of the installation via.Adopt The convenient installation support beam of pre-buried cylinder can be opened by designing rotation cover with this, extract cover meeting natural rotation closing after support beam pre- Bury a nozzle.Catching on after the fixed suspension ring of upset rotate 180 ° recycles other devices such as rope class to fix cover, prevents cylinder The pre-buried cylinder of rotary closing under self gravitation effect is covered, support beam is installed in influence.
Above-mentioned pre-buried cylinder is square tube, and the grapple totally eight, eight grapples are uniform along the circumference of the pre-buried cylinder Distribution.Fixation using this pre-buried cylinder of design is more solid and reliable.
Beneficial effect:Being using the beneficial effects of the utility model can be by the direct pre-buried body of a bridge of pre-buried cylinder when constructing a bridge It is interior, the support beam for overhauling track can be plugged in during maintenance bridge in pre-buried cylinder, then the laying maintenance track in support beam, no Directly support beam is extracted out of pre-buried cylinder when needing to use, such a fixed form dismounting is simple, greatlys save maintenance Device sets up the time.Daily cover when need not use can play a part of the pre-buried cylinder of closing, prevent rainwater etc. from stretching into pre-buried In cylinder, cause stack shell corruption embroidery, claw assembly and the anti-device that pulls are strengthened in attachment can play a part of fixed pre-buried cylinder, prevent other people with Meaning extracts pre-buried cylinder.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is Fig. 1 A-A ' profiles;
Fig. 3 is the utility model installment state schematic diagram.
Embodiment
With reference to embodiment and accompanying drawing, the utility model is described in further detail.
As depicted in figs. 1 and 2, a kind of bridge maintenance system steel structural embedded parts, including pre-buried cylinder 1, the pre-buried one end of cylinder 1 Closing, another end opening, the cylinder bottom outer wall of the pre-buried cylinder 1 pulls device 4 provided with attachment reinforcement claw assembly 2 with anti-, described pre- Bury covered with cover 7 on the nozzle of cylinder 1, the cover 7 is hinged with the pre-buried cylinder 1, is hinged with and turns on the outer wall of the cover 7 Turn fixed suspension ring 5.
Claw assembly 2 is strengthened in the attachment includes multiple grapples 201, the cylinder of the neck of hook of the grapple 201 and the pre-buried cylinder 1 Feather edge is fixedly connected, and inwardly, the pre-buried cylinder 1 is square tube, the grapple 201 totally eight, eight to the gib head of the grapple 201 Circumference of the individual grapple 201 along the pre-buried cylinder 1 is uniformly distributed, each between the grapple 201 and the pre-buried cylinder 1 respectively Deep floor 3 provided with triangle a, side of the deep floor 3 is fixedly connected with the stack shell outer wall of the pre-buried cylinder 1, Another side of the deep floor 3 is fixedly connected with the neck of hook of the corresponding grapple 201.
The anti-device 4 that pulls pulls bar 401 including anti-, the cylinder bottom of the anti-upper end and the pre-buried cylinder 1 for pulling bar 401 Outer wall is fixedly connected, the anti-bottom for pulling bar 401 provided with three it is anti-pull plate 402, it is described it is anti-pull plate 402 with it is described pre- The cylinder bottom for burying cylinder 1 is parallel.
The pre-buried cylinder 1 is obliquely installed, and obliquely, the tube port position of the pre-buried cylinder 1 extends out shape to the nozzle of the pre-buried cylinder 1 Into guide openings, the nozzle edge outward flanging of the pre-buried cylinder 1 forms the cover installing plate 6 of annular, the cover installing plate 6 In in perpendicular, the cover 7 is rotatably installed on the cover installing plate 6, and the cover installing plate 6 is provided with cylinder Lid mounting rod 8, the cover 7 hangs over the cover by the installation via set and installed provided with via, the cover 7 is installed On bar 8, the cover mounting rod 8 is connected with locking termination 9 after passing the installation via, and the cover 7 can be around the cover Mounting rod 8 rotates, and the fixed suspension ring 5 of upset are located on the underface of the installation via, the nozzle inwall of the pre-buried cylinder 1 It is axially arranged with three floor slots to make way 10 along it, the notch of the floor slot to make way 10 is upward.
As shown in figure 3, the bridge maintenance system steel structural embedded parts for directly providing the utility model when constructing a bridge are pre- It is embedded in the body of a bridge, wherein the stack shell of pre-buried cylinder 1 is obliquely installed, nozzle is upward and concordant with the side of bridge, is strengthened by adhering to Claw assembly 2 and the anti-device 4 that pulls can make whole device firmly promptly in the body of a bridge, it is necessary to will build maintenance rail when overhauling bridge One end of the support beam 11 in road is inserted in pre-buried cylinder 1, and the upper end of support beam 11 stretches out pre-buried cylinder 1 and is used as supporting part, support beam 11 Pre-buried cylinder 1 is stretched into as fixing end in lower end, and the deep floor 12 that support beam bending place is set is fastened on corresponding floor slot to make way In 10.Because pre-buried cylinder 1 is obliquely installed, the inwall that can be upwarped after the lower end load-bearing of support beam 11 with pre-buried cylinder 1 is pushed against so that will Support beam 11 is fixed, and one end load-bearing that support beam 11 stretches out pre-buried cylinder 1 is bigger, and support beam 11 and the fixation of pre-buried cylinder 1 are more steady Gu.Support beam 11 is directly extracted out of pre-buried cylinder 1 when need not use, this device greatly facilitates taking for maintenance track Build and dismount.
Finally it should be noted that foregoing description is only preferred embodiment of the present utility model, the common skill of this area Art personnel on the premise of without prejudice to the utility model objective and claim, can make under enlightenment of the present utility model Represented as multiple types, such conversion is each fallen within protection domain of the present utility model.

Claims (8)

1. a kind of bridge maintenance system steel structural embedded parts, it is characterised in that:Including pre-buried cylinder (1), the pre-buried end seal of cylinder (1) one Close, another end opening, the cylinder bottom outer wall of the pre-buried cylinder (1) strengthens claw assembly (2) provided with attachment and prevents pulling device (4), institute State covered with cover (7) on the nozzle of pre-buried cylinder (1), the cover (7) is hinged with the pre-buried cylinder (1), outside the cover (7) Wall is provided with the fixed suspension ring (5) of upset.
2. bridge maintenance system steel structural embedded parts according to claim 1, it is characterised in that:Pawl group is strengthened in the attachment Part (2) includes multiple grapples (201), and the neck of hook of the grapple (201) is fixedly connected with the cylinder feather edge of the pre-buried cylinder (1), The gib head of the grapple (201) is inwardly.
3. bridge maintenance system steel structural embedded parts according to claim 2, it is characterised in that:Each grapple (201) deep floor (3) of triangle, a side of the deep floor (3) are respectively equipped between the pre-buried cylinder (1) It is fixedly connected with the stack shell outer wall of the pre-buried cylinder (1), another side and the corresponding grapple of the deep floor (3) (201) the neck of hook is fixedly connected.
4. the bridge maintenance system steel structural embedded parts according to claim 1,2 or 3, it is characterised in that:It is described to prevent pulling Device (4) pulls bar (401) including anti-, and the anti-upper end for pulling bar (401) and the cylinder bottom outer wall of the pre-buried cylinder (1) fix company Connect, the anti-bottom for pulling bar (401) provided with least two it is anti-pull plate (402), it is described it is anti-pull plate (402) with it is described pre- The cylinder bottom for burying cylinder (1) is parallel.
5. the bridge maintenance system steel structural embedded parts according to claim 1,2 or 3, it is characterised in that:The pre-buried cylinder (1) it is obliquely installed, obliquely, the tube port position of the pre-buried cylinder (1) extends out to form guide openings the nozzle of the pre-buried cylinder (1), The nozzle edge outward flanging of the pre-buried cylinder (1) forms the cover installing plate (6) of annular, and the cover installing plate (6) is located at perpendicular In straight plane, the cover (7) is rotatably installed on the cover installing plate (6).
6. the bridge maintenance system steel structural embedded parts described in claim 5, it is characterised in that:The nozzle of the pre-buried cylinder (1) It is axially arranged with least one floor slot to make way (10) along it on inwall, the notch of the floor slot to make way (10) is upward.
7. the bridge maintenance system steel structural embedded parts described in claim 5, it is characterised in that:On the cover installing plate (6) Provided with cover mounting rod (8), the cover (7) is hung over provided with via, the cover (7) is installed by the installation via set On the cover mounting rod (8), the cover mounting rod (8) is connected with locking termination (9) after passing the installation via, described Cover (7) can rotate around the cover mounting rod (8), and the fixed suspension ring (5) of upset are located at the underface of the installation via.
8. the bridge maintenance system steel structural embedded parts described in claim 2, it is characterised in that:The pre-buried cylinder (1) is square Cylinder, the grapple (201) totally eight, circumference of eight grapples (201) along the pre-buried cylinder (1) is uniformly distributed.
CN201720086359.4U 2017-01-23 2017-01-23 Bridge maintenance system steel structural embedded parts Active CN206512615U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720086359.4U CN206512615U (en) 2017-01-23 2017-01-23 Bridge maintenance system steel structural embedded parts

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720086359.4U CN206512615U (en) 2017-01-23 2017-01-23 Bridge maintenance system steel structural embedded parts

Publications (1)

Publication Number Publication Date
CN206512615U true CN206512615U (en) 2017-09-22

Family

ID=59866857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720086359.4U Active CN206512615U (en) 2017-01-23 2017-01-23 Bridge maintenance system steel structural embedded parts

Country Status (1)

Country Link
CN (1) CN206512615U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677081A (en) * 2017-01-23 2017-05-17 重庆恒佳工程技术咨询有限公司 Bridge overhaul system steel structure pre-embedding device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677081A (en) * 2017-01-23 2017-05-17 重庆恒佳工程技术咨询有限公司 Bridge overhaul system steel structure pre-embedding device

Similar Documents

Publication Publication Date Title
CN101634146B (en) Manually digging hole full-steel cylinder-wall protecting construction device for building pile foundation and construction method thereof
CN107083925B (en) Automatic well repair vehicle
CN203760934U (en) Pulley device for cable laying
CN212176541U (en) Light-duty high-efficient construction that can have enough to meet need makes building equipment
CN203270577U (en) Underground pile foundation pulling device with door plate clamp
CN104343086B (en) Cable-stayed bridge upper king-post strut steel anchor beam anchoring section little space construction method
CN206512615U (en) Bridge maintenance system steel structural embedded parts
CN101597958A (en) Can be whole upright, the template system of form removal
CN109881585A (en) A kind of assembly flow shop platform for high pier construction
CN106638300B (en) Great-leap-forward bridge maintenance system
CN206512614U (en) Bridge maintenance system supporting device with steel structure
CN113463583B (en) Method for rapidly disassembling large oil cylinder of gate in water inlet accident of high-water-head power station on site
CN206581141U (en) Bridge maintenance system
CN109989333A (en) Fashioned iron trestle work structure and its installation method for concrete horizontal support
CN202399211U (en) Dismounting device for cartridge valves
CN210086026U (en) A shaped steel landing stage structure for concrete level supports
CN106677081B (en) Bridge maintenance system steel construction pre-embedded device
CN206329143U (en) A kind of embedded maintenance pile bar
CN217379004U (en) Sewer well cover plate
CN106835978B (en) Bridge maintenance rail steel structural support member
CN204982944U (en) Net fixing device is prevented weighing down in precast reinforced concrete integration
CN206143631U (en) A leading wheel device for installation of cable -stay bridge cable
CN207063003U (en) A kind of easy-to-mount well lid of modular segment energy safety manhole
CN206089557U (en) Burnt jar of maintenance support of dry coke quenching
CN202125297U (en) Wellhead fence device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant