CN206502777U CN201720195932.5U CN201720195932U CN206502777U CN 206502777 U CN206502777 U CN 206502777U CN 201720195932 U CN201720195932 U CN 201720195932U CN 206502777 U CN206502777 U CN 206502777U
Authority
CN
China
Prior art keywords
guide rail
coke
plate
guide
side plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720195932.5U
Other languages
Chinese (zh)
Inventor
陈立京
王俭华
罗治秋
徐朝兵
李世兵
周子然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pangang Group Panzhihua Steel and Vanadium Co Ltd
Original Assignee
Pangang Group Panzhihua Steel and Vanadium Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pangang Group Panzhihua Steel and Vanadium Co Ltd filed Critical Pangang Group Panzhihua Steel and Vanadium Co Ltd
Priority to CN201720195932.5U priority Critical patent/CN206502777U/en
Application granted granted Critical
Publication of CN206502777U publication Critical patent/CN206502777U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Furnace Housings, Linings, Walls, And Ceilings (AREA)

Abstract

The utility model is related to a kind of coke guide coke guidance device upper rail, category coke oven for iron field.The utility model includes guide rail bottom plate, guide rail side plate, guide rail top plate, guide rail plate-side plate welding both sides at the top of guide rail bottom plate form box-structure, guide rail top plate is welded on the outside of guide rail side plate, guide rail top plate, guide rail side plate, guide rail bottom plate outer end form trench structure, the messenger that burnt grid are led for hanging is provided with the outside of guide rail side plate, guide rail top plate is adapted with messenger, and messenger is play the guiding role.The utility model is box shape steel structure, lead burnt grid by messenger hang on upper rail complete lead burnt work, the upper rail is firm, reliable, long lifespan, can improve the stability of coke guide coke guidance device operation, prevent the failure that upper rail in the prior art frequently snaps, is broken.The utility model have be simple to manufacture, the advantage such as cost is low, long lifespan.

Description

Coke guide coke guidance device upper rail
Technical field
The utility model is related to a kind of coke guide coke guidance device upper rail, category coke oven for iron field.
Background technology
Coke guide is one of key equipment of Coke-fired Furnace Machinery Equipments, the normal life of the safe and reliable operation of coke guide to coke oven Production plays an important role.Coke guide is contacted with pusher machine according to plan will push away certain number firehole, and coke guide moves to the firehole, will lead Burnt grid are directed at the firehole, lead limited after burnt grid are moved on to first, it is mobile take a machine and rotate to takes a position to carry out taking door, retrogressing Return;Movement leads burnt grid forward again, and alignment fire door locking carries out leading Jiao, scrapper conveyor is started during this period, Jiao that will be taken out of when leading Jiao Carbon is scraped into coke quenching cart, is led Jiao and is finished, and is led burnt grid and is returned to after centre position, locking and can walk, is ready for leading for next stove Jiao's work.Contacted due to leading incandescent coke of the burnt grid directly with more than 1000 DEG C, and whole coke guidance device is in a relative envelope In the environment closed, easily there is deformation, track fracture in prolonged production run, the U-bar guide rail of coke guidance device upper rail, leads Cause is led burnt grid and can not be operating normally, influence coke oven production.
Utility model content
Technical problem to be solved in the utility model is:There is provided one kind deform in high temperature environments it is small, be not in disconnected Split, the coke guide coke guidance device upper rail of service life length.
It is to solve the technical scheme that is used of above-mentioned technical problem the utility model:Coke guide coke guidance device upper rail, Including guide rail bottom plate, guide rail side plate, guide rail top plate, guide rail plate-side plate welding both sides at the top of guide rail bottom plate form box-structure, lead Rail top plate is welded on the outside of guide rail side plate, and guide rail top plate, guide rail side plate, guide rail bottom plate outer end form trench structure, guide rail side plate Outside is provided with the messenger that burnt grid are led for hanging, and guide rail top plate is adapted with messenger, messenger is play the guiding role.
It is further:Guide rail bottom base plate both sides are welded with H profile steel, the wherein wing plate of H profile steel in it is horizontally disposed with Guide rail bottom plate is mutually welded.
It is further:Guide rail side plate interior sides are welded with triangle stiffener plate, and triangle stiffener plate is along guide rail side plate Length direction is arranged at intervals.
It is further:Guide rail side plate is overall deformed steel flats.
It is further:Continuously welded for groove between guide rail bottom plate and guide rail side plate.
It is further:The afterbody of coke guide coke guidance device upper rail is provided with suspension rod bolt.
The beneficial effects of the utility model are:Guide rail bottom plate, guide rail plate-side plate welding are into the box-structure of an entirety, guide rail Top plate does not stress in the running for leading burnt grid, only plays the guide effect of messenger, and overall structure is stable, firm.Further, since Guide rail bottom plate and guide rail side plate are the continuous solder type of groove, and guide rail bottom base plate has H profile steel, guide rail side plate interior sides to have triangle Be not in guide rail deformation of bottom and weld seam drawing crack situation in stiffener plate, use;The sketch plate that guide rail side plate is integral, increases The weight capacity of guide rail is added, has been not in that side plate snaps or drawing crack situation;Afterbody uses suspension rod hanging structure, cantilever upper rail Longtime running is not in afterbody lower flexure strain.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is coke guide coke guidance device upper rail sectional schematic diagram of the present utility model;
Fig. 3 is close-up schematic view at Fig. 2 A;
Fig. 4 is the coke guide coke guidance device upper rail sectional schematic diagram of prior art;
Parts, position and numbering in figure:1- guide rails bottom plate, 2- guide rails side plate, 3- guide rails top plate, 4-H shaped steel, 5- triangles Shape stiffener plate, 6- messengers, 7- suspension rod bolts.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
As shown in FIG. 1 to 3, the utility model includes guide rail bottom plate 1, guide rail side plate 2, guide rail top plate 3, guide rail side plate 2 It is welded in the top both sides of guide rail bottom plate 1 and forms box-structure, guide rail top plate 3 is welded in the outside of guide rail side plate 2, guide rail top plate 3, leads Trackside plate 2, the outer end of guide rail bottom plate 1 form trench structure, and the outside of guide rail side plate 2 is provided with the messenger 6 that burnt grid are led for hanging, led Rail top plate 3 is adapted with messenger 6, and messenger 6 is play the guiding role.Guide rail bottom plate 1, guide rail side plate 2 are welded into the case of an entirety Type structure, guide rail top plate 3 does not stress in the running for leading burnt grid, only the guide effect of a messenger 6, overall structure stabilization, Firmly.In the present embodiment, guide rail bottom plate 1 is a 25mm steel plate, and guide rail side plate 2 is the thick special-shaped monoblock steel plates of 16mm, will Together with 2 dozens of groove weldings of guide rail bottom plate 1 and guide rail side plate, the box-structure as an entirety, due to guide rail bottom plate and leading Trackside plate is the continuous solder type of groove, and whole guide rail side plate 2 is overall deformed steel flats, may be such that the upper rail of box-structure The globality of beam is highly stable and firm.
The two bottom sides of guide rail bottom plate 1 are welded with H profile steel 4, and a wherein wing plate for H profile steel 4 is in horizontally disposed and guide rail bottom plate 1 Mutually weld.In the traveling weight bearing area welded H section steel 4 of 1 bottom both sides messenger of guide rail bottom plate 6, guide rail bottom when can strengthen 6 traveling of messenger The rigidity of plate 1, and guide rail bottom plate 1 is not in the torsional deformation of above-below direction at high temperature.
The inner side of guide rail side plate 2 is welded with triangle stiffener plate 5, and triangle stiffener plate 5 is along the length direction of guide rail side plate 2 It is arranged at intervals.In the present embodiment, totally 12 groups thick of triangle stiffener plates 5 of 12mm are welded in the inner side total length direction of guide rail side plate 2, Strengthen the load-bearing property of upper rail, be not in weld cracking in high temperature, heavily loaded environment lower guideway bottom plate 1 and guide rail side plate 2.
The afterbody of coke guide coke guidance device upper rail is provided with suspension rod bolt 7, by the steel of upper rail afterbody hanging up On structural beams, and stress can be adjusted by nut, prevent the long-term stress of upper rail afterbody from lower flexure strain occur.
Whole upper rail in the utility model all can make of Q345B materials steel plate, high temperature resistant, wear resistance compared with It is good.

Claims (6)

1. coke guide coke guidance device upper rail, it is characterised in that:Including guide rail bottom plate (1), guide rail side plate (2), guide rail top plate (3), guide rail side plate (2) is welded in both sides at the top of guide rail bottom plate (1) and forms box-structure, and guide rail top plate (3) is welded in rail-sides On the outside of plate (2), guide rail top plate (3), guide rail side plate (2), guide rail bottom plate (1) outer end are formed on the outside of trench structure, guide rail side plate (2) The messenger (6) that burnt grid are led for hanging is provided with, guide rail top plate (3) is adapted with messenger (6), and messenger (6) is play the guiding role.
2. coke guide coke guidance device upper rail as claimed in claim 1, it is characterised in that:Guide rail bottom plate (1) two bottom sides are welded H profile steel (4) is connected to, a wherein wing plate for H profile steel (4) is mutually welded in horizontally disposed with guide rail bottom plate (1).
3. coke guide coke guidance device upper rail as claimed in claim 1, it is characterised in that:It is welded with the inside of guide rail side plate (2) Triangle stiffener plate (5), triangle stiffener plate (5) is arranged at intervals along guide rail side plate (2) length direction.
4. coke guide coke guidance device upper rail as claimed in claim 1, it is characterised in that:Guide rail side plate (2) is overall abnormity Steel plate.
5. coke guide coke guidance device upper rail as claimed in claim 1, it is characterised in that:Guide rail bottom plate (1) and guide rail side plate (2) continuously welded for groove between.
6. the coke guide coke guidance device upper rail as described in any one in Claims 1 to 5, it is characterised in that:Coke guide is led The afterbody of coke installation upper rail is provided with suspension rod bolt (7).
CN201720195932.5U 2017-03-02 2017-03-02 Coke guide coke guidance device upper rail Active CN206502777U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720195932.5U CN206502777U (en) 2017-03-02 2017-03-02 Coke guide coke guidance device upper rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720195932.5U CN206502777U (en) 2017-03-02 2017-03-02 Coke guide coke guidance device upper rail

Publications (1)

Publication Number Publication Date
CN206502777U true CN206502777U (en) 2017-09-19

Family

ID=59842191

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720195932.5U Active CN206502777U (en) 2017-03-02 2017-03-02 Coke guide coke guidance device upper rail

Country Status (1)

Country Link
CN (1) CN206502777U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110467930A (en) * 2019-09-09 2019-11-19 石横特钢集团有限公司 The first track infrastructure of coke guide

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110467930A (en) * 2019-09-09 2019-11-19 石横特钢集团有限公司 The first track infrastructure of coke guide
CN110467930B (en) * 2019-09-09 2024-05-24 石横特钢集团有限公司 First track foundation structure of coke guide

Similar Documents

Publication Publication Date Title
CN206502777U (en) Coke guide coke guidance device upper rail
CN105752839A (en) Heavy monorail crane rail
RU2481986C2 (en) Bogie solebar
CN210625355U (en) Furnace top sealing structure of suspension type heat treatment furnace
CN203269375U (en) Trolley flexible cable protective device
CN105064149A (en) Track skeleton adjusting device
CN208667591U (en) One kind leading track beam structure on burnt grid
CN206345356U (en) Reclaimer walking track structure
CN102679733A (en) Novel high-temperature resistance heated furnace
CN204509373U (en) Sectional type oxygen rifle fixed guide
RU173550U1 (en) LATER FRAME OF RAILWAY TROLLEY
CN205474812U (en) Landing stage is from restoring to throne roller support device
CN106672749A (en) Lift car guide shoe
CN209368528U (en) A kind of high-precision, high-intensitive oil-free guide rail
CN219950889U (en) Tool trolley device for replacing coke grating of coke guide in furnace
CN220376154U (en) Flange link has hanger rail track device who prevents beat stable structure
CN204369513U (en) Tobacco leaf falls apart the dress roasting device of leaf
CN206309694U (en) Bending machine curved cylinder support
JP6822064B2 (en) Reactor tightening structure and furnace tightening method for chamber coke oven
CN216027971U (en) Track of hot-feeding steel pushing device of continuous casting machine
RU2661662C2 (en) High load capacity monorail beam
CN216473061U (en) Novel coke guide grid of coke guide
CN220056072U (en) Double-rail single-span type pump head replacement tool
RU111503U1 (en) LATERAL TROLLEY FRAME
CN214083236U (en) High-molecular composite material one-step forming railcar shell