CN206494387U - Dustbin weighing device - Google Patents

Dustbin weighing device Download PDF

Info

Publication number
CN206494387U
CN206494387U CN201621040101.2U CN201621040101U CN206494387U CN 206494387 U CN206494387 U CN 206494387U CN 201621040101 U CN201621040101 U CN 201621040101U CN 206494387 U CN206494387 U CN 206494387U
Authority
CN
China
Prior art keywords
dustbin
vertical beam
weighing device
weight
pedestal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621040101.2U
Other languages
Chinese (zh)
Inventor
贾兴卫
张雅晶
李洪丞
郑建坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING HUALIN SPECIAL VEHICLE Co Ltd
Beijing Sanchen Huanwei Mechine Coltd
Beijing Environment Sanitation Engineering Group Co., Ltd.
Original Assignee
BEIJING HUALIN SPECIAL VEHICLE Co Ltd
Beijing Sanchen Huanwei Mechine Coltd
Beijing Environment Sanitation Engineering Group Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING HUALIN SPECIAL VEHICLE Co Ltd, Beijing Sanchen Huanwei Mechine Coltd, Beijing Environment Sanitation Engineering Group Co., Ltd. filed Critical BEIJING HUALIN SPECIAL VEHICLE Co Ltd
Priority to CN201621040101.2U priority Critical patent/CN206494387U/en
Application granted granted Critical
Publication of CN206494387U publication Critical patent/CN206494387U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuse Collection And Transfer (AREA)

Abstract

The utility model provides a kind of dustbin weighing device, including:Pedestal, pedestal includes base and the operating portion being arranged on base;Weight acquisition unit, Weight acquisition unit is arranged on pedestal;Alarm unit, alarm unit is electrically connected with Weight acquisition unit, and alarm unit is according to the preset value signal an alert of the weight of dustbin.The technical solution of the utility model efficiently solves of the prior art the problem of can not be alarmed according to the weight of rubbish in dustbin.

Description

Dustbin weighing device
Technical field
The utility model is related to the technical field that dustbin is weighed, in particular to a kind of dustbin weighing device.
Background technology
In the prior art, want to obtain the weight of rubbish in garbage recovery device, it is necessary to operating personnel to go to dustbin attached Closely, dustbin cover is opened, the weight of rubbish in conjecture dustbin is by virtue of experience carried out according to the quantity of the rubbish in dustbin. The dustbin of said structure has no idea to carry out early warning according to the weight of rubbish in dustbin.
Utility model content
Main purpose of the present utility model is to provide a kind of dustbin weighing device, with solve it is of the prior art can not The problem of being alarmed according to the weight of rubbish in dustbin.
To achieve these goals, the utility model provides a kind of dustbin weighing device, including:Pedestal, pedestal bag Include base and the operating portion being arranged on base;Weight acquisition unit, Weight acquisition unit is arranged on pedestal;Alarm unit, Alarm unit is electrically connected with Weight acquisition unit, and alarm unit is according to the preset value signal an alert of the weight of dustbin.
Further, base includes crossbeam, the first vertical beam and the second vertical beam, and the first vertical beam and the second vertical beam are arranged at intervals, Crossbeam is arranged between the first vertical beam and the second vertical beam and the first vertical beam and the second vertical beam links together.
Further, Weight acquisition unit includes multiple weighing sensors, and multiple weighing sensors are arranged on the first vertical beam On the second vertical beam.
Further, pedestal includes multiple lower margins, and each lower margin is T-type structure, and is connected with the bottom of base.
Further, pedestal also includes loading part, and first side and the base of loading part are pivotably connected, loading part Second side and the first side of loading part are oppositely arranged, and the second side of loading part is used to overlap with ground.
Further, dustbin weighing device also includes control unit, and control unit is electrically connected with Weight acquisition unit, controls Unit processed is according to the Weight control alarm unit of collection.
Further, alarm unit includes audible alarm equipment and/or light warning device.
Further, operating portion includes armstand and transverse arm, and the first end of armstand is arranged on base, and the first end of transverse arm can It is movably arranged at the second end of armstand.
Further, dustbin weighing device also includes dustbin cover, and transverse arm is connected to drive rubbish with dustbin cover Bung is moved.
Further, dustbin cover, which has, is provided with the anti-taking-up structure of rubbish on the inside of opening, dustbin cover.
Using the technical solution of the utility model, dustbin is placed on pedestal, and Weight acquisition unit is provided with pedestal, Weight acquisition unit is gathered the weight of rubbish in dustbin and dustbin in real time.Alarm unit and Weight acquisition unit It is connected, when reaching the preset value for the weight that alarm unit is set, alarm unit sends alarm signal.Skill of the present utility model Art scheme efficiently solves of the prior art the problem of can not be alarmed according to the weight of rubbish in dustbin.
Brief description of the drawings
The Figure of description for constituting the part of the application is used for providing further understanding to of the present utility model, this practicality New schematic description and description is used to explain the utility model, does not constitute to improper restriction of the present utility model. In the accompanying drawings:
Fig. 1 shows the schematic front view of the embodiment according to dustbin weighing device of the present utility model;
Fig. 2 shows the schematic top plan view of Fig. 1 dustbin weighing device;
Fig. 3 shows another angle schematic diagram of Fig. 1 dustbin weighing device;And
Fig. 4 shows the base schematic diagram of Fig. 1 dustbin weighing device.
Wherein, above-mentioned accompanying drawing is marked including the following drawings:
10th, pedestal;11st, base;111st, crossbeam;112nd, the first vertical beam;113rd, the second vertical beam;12nd, operating portion;121st, stand Arm;122nd, transverse arm;13rd, loading part;14th, lower margin;20th, Weight acquisition unit;30th, control unit;40th, dustbin cover;41st, open Mouthful.
Embodiment
It should be noted that in the case where not conflicting, the feature in embodiment and embodiment in the application can phase Mutually combination.Describe the utility model in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
It is noted that described further below is all exemplary, it is intended to provide further instruction to the application.Unless another Indicate, all technologies used herein and scientific terminology are with usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
For the ease of description, space relative terms can be used herein, such as " ... on ", " ... top ", " ... upper surface ", " above " etc., for describing such as a device shown in the figure or feature and other devices or spy The spatial relation levied.It should be appreciated that space relative terms are intended to comprising the orientation except device described in figure Outside different azimuth in use or operation.If for example, the device in accompanying drawing is squeezed, be described as " in other devices It will be positioned as " under other devices or construction after the device of part or construction top " or " on other devices or construction " Side " or " under other devices or construction ".Thus, exemplary term " ... top " can include " ... top " and " in ... lower section " two kinds of orientation.The device can also other different modes positioning (being rotated by 90 ° or in other orientation), and And respective explanations are made to the relative description in space used herein above.
Now, it is more fully described with reference to the accompanying drawings according to illustrative embodiments of the present utility model.However, these show Example property embodiment can be implemented by many different forms, and should not be construed to be limited solely to reality set forth herein Apply mode.It should be appreciated that these embodiments are provided so that disclosure of the present utility model is thoroughly and complete, and The design of these illustrative embodiments is fully conveyed to those of ordinary skill in the art, in the accompanying drawings, for the sake of clarity, Expand layer and the thickness in region, and make to be presented with like reference characters identical device, thus by omit to they Description.
As shown in Figure 1 to Figure 3, the dustbin weighing device of the present embodiment includes:Pedestal 10, Weight acquisition unit 20 and report Alert unit.Pedestal 10 includes the operating portion 12 of base 11 and setting on the pedestal 11.Weight acquisition unit 20 is arranged on pedestal 10 On.Alarm unit is electrically connected with Weight acquisition unit 20, and alarm unit sends alarm signal according to the preset value of the weight of dustbin Number.
Using the technical scheme of the present embodiment, dustbin is placed on pedestal 10, and Weight acquisition list is provided with pedestal 10 Member 20, Weight acquisition unit 20 is gathered the weight of rubbish in dustbin and dustbin in real time.Alarm unit and weight Collecting unit 20 is connected, and when reaching the preset value for the weight that alarm unit is set, alarm unit sends alarm signal.This reality Apply example technical scheme efficiently solve it is of the prior art can not be according to asking that the weight of rubbish in dustbin is alarmed Topic.
As shown in Figure 1 and Figure 4, in the technical scheme of the present embodiment, base 11 includes crossbeam 111, the and of the first vertical beam 112 Second vertical beam 113, the first vertical beam 112 and the second vertical beam 113 are arranged at intervals, and it is perpendicular that crossbeam 111 is arranged on the first vertical beam 112 and second Linked together between beam 113 and by the first vertical beam 112 and the second vertical beam 113.First vertical beam 112 is parallel with the second vertical beam 113 Set, crossbeam 111 is connected between the first vertical beam 112 and the second vertical beam 113.On the one hand said structure ensure that base 11 compares It is firm, on the other hand alleviate the weight of base 11.Specifically, the first vertical beam 112 is identical with the length of the second vertical beam 113, horizontal Beam 111 is three, and three crossbeams 111 are separately positioned on the two ends and centre of the first vertical beam 112 and the second vertical beam 113.
As shown in Figure 1, Figure 2 and Figure 4, in the technical scheme of the present embodiment, Weight acquisition unit 20 includes multiple weigh Sensor, multiple weighing sensors are arranged on the first vertical beam 112 and the second vertical beam 113.Specifically, weighing sensor is four Individual, four sensors are separately positioned on the first vertical beam 112 and the second vertical beam 113, and the position between four weight sensors Four angles that relation is just dustbin are put, said structure ensure that accuracy when being weighed to dustbin.
As shown in figure 1, in the technical scheme of the present embodiment, pedestal 10 includes multiple lower margins 14, each lower margin 14 is T junction Structure, and be connected with the bottom of base 11.Specifically, the stub end of T-type structure is towards ground, the small head end of T-type structure and bottom Seat 11 is connected.Said structure ensure that stability of the dustbin weighing device when not moving.Specifically as shown in figure 1, bottom The downside of seat 11 is additionally provided with push wheel, so more convenient in mobile dustbin weighing device, when dustbin weighing device is moved After moving in place, can pack up push wheel makes T-type structure be supported dustbin weighing device.
As depicted in figs. 1 and 2, in the technical scheme of the present embodiment, pedestal 10 also includes loading part 13, loading part 13 First side is pivotably connected with base 11, and the second side and the first side of loading part 13 of loading part 13 are oppositely arranged, The second side of loading part 13 is used to overlap with ground.Said structure facilitates dustbin up/down steps, specifically, and dustbin can Base 11 is pushed to the second side from loading part 13, when unloading dustbin, dustbin can be pushed from base 11.
As depicted in figs. 1 and 2, in the technical scheme of the present embodiment, dustbin weighing device also includes control unit 30, Control unit 30 is electrically connected with Weight acquisition unit 20, and control unit 30 is according to the Weight control alarm unit of collection.First, root Weight during alarm is set according to the weight of dustbin when rubbish is filled with dustbin.In the concrete scheme of the present embodiment, control Unit 30 can also control the weight (removing the peel) of the housing of the removal dustbin of Weight acquisition unit 20, the dustbin of the present embodiment For collecting kitchen garbage, so, weight when dustbin is filled with according to kitchen garbage sends the alarm signal filled with.When So, as one skilled in the art will appreciate that the rubbish alarm in dustbin can also be configured as needed, for example, working as rubbish Alarm is just sent in advance when will be filled in rubbish bucket, so that operating personnel have the prepared time.In order to ensure that dustbin is sent The alarm filled with is more accurate, and the instruments such as infrared acquisition and weighing instruments can also be set to measure, to ensure alarm signal The accuracy sent.
In the technical scheme of the present embodiment, alarm unit includes audible alarm equipment and light warning device.Sound report The alarm of alert and light is carried out simultaneously, so can more warn operator.Tut is alarmed and light alarm can be as needed It is arranged on around dustbin weighing device, can also be arranged as required in central control room, naturally it is also possible to sets as needed Put on garbage truck.
As depicted in figs. 1 and 2, in the technical scheme of this implementation, operating portion 12 includes armstand 121 and transverse arm 122, armstand 121 first end is set on the pedestal 11, and the first end of transverse arm 122 is movably disposed at the second end of armstand 121.Above-mentioned knot Structure can carry out some other operations to dustbin, for example, transverse arm 122 carries out covering design, Huo Zhezhi to the top of dustbin Connect and move dustbin.
As depicted in figs. 1 and 2, in the technical scheme of the present embodiment, dustbin weighing device also includes dustbin cover 40, Transverse arm 122 is connected to drive dustbin cover 40 to move with dustbin cover 40.When needing to open dustbin cover 40, transverse arm 122 Movement thus opens dustbin cover 40.Specifically, slideway is provided between transverse arm 122 and armstand 121, transverse arm 122 is in liquid In the presence of laminated structure, moved up and down along the slideway of armstand 121.Certainly, as one skilled in the art will appreciate that transverse arm 122 move up and down can also be driven by chain.
As depicted in figs. 1 and 2, in the technical scheme of the present embodiment, dustbin cover 40 has opening 41, dustbin cover 40 Inner side be provided with the anti-taking-up structure of rubbish.Said structure can prevent the rubbish in dustbin from being taken out by secondary, cause again Pollution.Particularly, the dustbin of the present embodiment, which is used to hold, contains a large amount of greases in kitchen garbage, kitchen garbage, some are illegal After molecule refines these waste oil, dining table is brought up to again, this causes serious injury to human body.
As depicted in figs. 1 and 2, in the technical scheme of the present embodiment, when dustbin is put into main body, main body top and bottom are set There are 4 cantilever type weighing sensors, data are transferred to adjustable display, with peeling, accumulative, clearing, also with overweight pre- Alert function.The weight record weighed every time can be recorded using equipment, warning function is to reach the upper of setting in the weight weighed During limit value, the circuit stroke loop that it connects alarm bell (or early-warning lamp) is made by control system, plays a part of early warning.When So, as one skilled in the art will appreciate that the species of sensor, can sense radial type weighing sensor, S types pressure The sensors such as device substitute cantilever type weighing sensor.
It should be noted that term used herein above is merely to describe embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative It is also intended to include plural form, additionally, it should be understood that, when in this manual using term "comprising" and/or " bag Include " when, it indicates existing characteristics, step, operation, device, component and/or combinations thereof.
It should be noted that term " first " in specification and claims of the present utility model and above-mentioned accompanying drawing, " second " etc. is for distinguishing similar object, without for describing specific order or precedence.It should be appreciated that so The data used can be exchanged in the appropriate case, so as to embodiment example of the present utility model described herein if with except Order beyond those for illustrating or describing herein is implemented.In addition, term " comprising " and " having " and theirs is any Deformation, it is intended that covering is non-exclusive to be included, for example, containing the process of series of steps or unit, method, system, production Product or equipment are not necessarily limited to those steps clearly listed or unit, but may include not list clearly or for this A little processes, method, product or the intrinsic other steps of equipment or unit.
Preferred embodiment of the present utility model is the foregoing is only, the utility model is not limited to, for this For the technical staff in field, the utility model can have various modifications and variations.It is all it is of the present utility model spirit and principle Within, any modification, equivalent substitution and improvements made etc. should be included within protection domain of the present utility model.

Claims (9)

1. a kind of dustbin weighing device, it is characterised in that including:
Pedestal (10), the pedestal (10) includes base (11) and the operating portion (12) being arranged on the base (11);
Weight acquisition unit (20), the Weight acquisition unit (20) is arranged on the pedestal (10);
Alarm unit, the alarm unit is electrically connected with the Weight acquisition unit (20), and the alarm unit is according to dustbin Weight preset value signal an alert;
The pedestal (10) also includes loading part (13), and the first side of the loading part (13) and the base (11) are pivotable Ground is connected, and the second side and the first side of the loading part (13) of the loading part (13) are oppositely arranged, the loading part (13) second side is used to overlap with ground.
2. dustbin weighing device according to claim 1, it is characterised in that the base (11) include crossbeam (111), First vertical beam (112) and the second vertical beam (113), first vertical beam (112) and second vertical beam (113) are arranged at intervals, institute Crossbeam (111) is stated to be arranged between first vertical beam (112) and second vertical beam (113) and by first vertical beam (112) linked together with second vertical beam (113).
3. dustbin weighing device according to claim 2, it is characterised in that the Weight acquisition unit (20) includes many Individual weighing sensor, the multiple weighing sensor is arranged on first vertical beam (112) and second vertical beam (113).
4. dustbin weighing device according to claim 1, it is characterised in that the pedestal (10) includes multiple lower margins (14), each lower margin (14) is T-type structure, and is connected with the bottom of the base (11).
5. dustbin weighing device according to claim 1, it is characterised in that the dustbin weighing device also includes control Unit (30) processed, described control unit (30) is electrically connected with the Weight acquisition unit (20), described control unit (30) basis Alarm unit described in the Weight control of collection.
6. dustbin weighing device according to claim 1, it is characterised in that the alarm unit is set including audible alarm Standby and/or light warning device.
7. dustbin weighing device according to claim 1, it is characterised in that the operating portion (12) includes armstand (121) and transverse arm (122), the first end of the armstand (121) is arranged on the base (11), and the of the transverse arm (122) One end is movably disposed at the second end of the armstand (121).
8. dustbin weighing device according to claim 7, it is characterised in that the dustbin weighing device also includes rubbish Rubbish bung (40), the transverse arm (122) is connected to drive the dustbin cover (40) mobile with the dustbin cover (40).
9. dustbin weighing device according to claim 8, it is characterised in that the dustbin cover (40) has opening (41), it is provided with the anti-taking-up structure of rubbish on the inside of the dustbin cover (40).
CN201621040101.2U 2016-09-05 2016-09-05 Dustbin weighing device Active CN206494387U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621040101.2U CN206494387U (en) 2016-09-05 2016-09-05 Dustbin weighing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621040101.2U CN206494387U (en) 2016-09-05 2016-09-05 Dustbin weighing device

Publications (1)

Publication Number Publication Date
CN206494387U true CN206494387U (en) 2017-09-15

Family

ID=59799686

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621040101.2U Active CN206494387U (en) 2016-09-05 2016-09-05 Dustbin weighing device

Country Status (1)

Country Link
CN (1) CN206494387U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108820632A (en) * 2018-03-14 2018-11-16 嘉兴科瑞迪医疗器械有限公司 A kind of Medical Devices waste bin automatic detection device
CN113003058A (en) * 2021-03-19 2021-06-22 四川九哈科技股份有限公司 Gather intelligent bucket of rubbish from cooking

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108820632A (en) * 2018-03-14 2018-11-16 嘉兴科瑞迪医疗器械有限公司 A kind of Medical Devices waste bin automatic detection device
CN113003058A (en) * 2021-03-19 2021-06-22 四川九哈科技股份有限公司 Gather intelligent bucket of rubbish from cooking

Similar Documents

Publication Publication Date Title
CN206494387U (en) Dustbin weighing device
DE102005026984B4 (en) Safety device with function for checking load
CN204021343U (en) Automatic Weighing disengagement gear
CN105416795B (en) One kind picks up medicine machine and its picks up prescription method automatically
AU3425489A (en) Fluid monitoring apparatus and methods
CN206013927U (en) A kind of spiced and stewed food quantitative weighing device
CN110002161A (en) A kind of practice on intelligent hospital classification of drug managing device
KR20180123451A (en) Smart mobile device
US20170327311A1 (en) System and method for weighing contents of roll-off containers
CN206562100U (en) Environmental sanitation dustbin
CN104528399A (en) Rapid collecting and automatic packaging device for tedded fodder
CN106510771A (en) Blood test and urine test sample storage device for clinical labs
CN207096228U (en) Food safe monitoring instrument
CN106053253A (en) Soil grasper measuring device for measuring real displacement of soil sheared by large size soil engineering direct shear apparatus
CN107458632B (en) A kind of material-gathering device of PVC granular material in medical use
CN209160107U (en) Product bagging equipment based on peanut shell granular preparation
CN211919756U (en) Double-barrel wireless intelligent weighing device and weighing equipment of household garbage truck
CN206187800U (en) Electron rotary cabinet
CN208798014U (en) A kind of experimental bench handset bracket
CN205826113U (en) A kind of deformable electronic scale
CN210206933U (en) Teaching experiment table for ceramic material
CN107570429B (en) Logistics weighing and sorting system
CN207114527U (en) A kind of agricultural product quality and safety detection means
CN206494190U (en) It is a kind of to aid in material collecting device from weighing ton bag
CN212167310U (en) Slurry stirring tank

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant