CN206477612U - It is outstanding to fill boom support erecting device - Google Patents
It is outstanding to fill boom support erecting device Download PDFInfo
- Publication number
- CN206477612U CN206477612U CN201720077405.4U CN201720077405U CN206477612U CN 206477612 U CN206477612 U CN 206477612U CN 201720077405 U CN201720077405 U CN 201720077405U CN 206477612 U CN206477612 U CN 206477612U
- Authority
- CN
- China
- Prior art keywords
- steel
- vertical rod
- erecting device
- fixed block
- boom support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses the outstanding filling boom support erecting device of one kind, including the support system for defaulting in the I-steel on Xuan Guanliang He being fixed on I-steel, support system include vertical rod and with the integrally formed horizon bar of vertical rod, the fixed block that vertical rod upper end is engaged provided with outwardly convex and with I-steel side, the side of I-steel is provided with the reinforcing plate along I-steel width, the screw nut assembly being secured together is provided with fixed block and the reinforcing plate, the upper surface of horizon bar is provided with steel plate, the one end of horizon bar away from vertical rod is provided with the stopper for raising up and being offseted with steel plate side, it is engaged by fixed block with I-steel, fixed block short transverse can be limited, reduce the situation that fixed block departs from, positioning can be played a part of to fixed block simultaneously, it is more prone to the fixation of screw nut assembly;Stopper can be to limiting, so as to add the structural strength of travelator frame in steel plate horizontal direction.
Description
Technical field
The utility model is related to outstanding filling beam technical field of construction, more specifically, it relates to which a kind of outstanding boom support that fills is installed
Device.
Background technology
Since in recent years, the outstanding beam construction method that fills of China is quickly grown, because the outstanding beam construction method that fills is due in work high above the ground, depositing
In the hidden danger of excessive risk, the problems such as easily causing security incident, the outstanding frontier defense shield of facing for filling beam is very important.The outstanding people's row for filling beam
Road support is generally gathered materials on the spot, with the interim fixed bracket of reinforcement welding.
At present, Publication No. CN204570493U Chinese patent discloses a kind of railroad bridge travelator frame and installs dress
Put, it includes base fixed system, Rack support systems and lift control system;Base fixed system bottom is fixed using bolt
On the pre-buried T shapes steel on the outside of gear tiny fragments of stone, coal, etc. wall, top is hollow tubular;Rack support systems are main by vertical rod and horizon bar one
Body is constituted, and vertical bar lower portions are inserted in base fixed system upper interior portion;Lift control system is filled by roller, steel wire rope and remote control
Composition is put, the upper end of wherein roller is fixed on the outside of horizon bar;Wirerope-winding is on roller;Remote control is by operating personnel
It is hand-held, and electrically connected with the rotating control assembly on roller, the installation used time of each travelator frame is short, substantially reduces
Duration, so as to be that pavement and cable trough construction are ready.
But, the outstanding structural strength for filling boom support erecting device is not strong, in work high above the ground, easily causes security incident.
Utility model content
The purpose of this utility model be to provide it is a kind of outstanding fill boom support erecting device, with easy for installation, structural strength is strong
Advantage.
Above-mentioned technical purpose of the present utility model technical scheme is that:One kind is outstanding to fill boom support peace
Assembling device, including the I-steel defaulted on Xuan Guanliang and the support system being fixed on I-steel, the support system include
Vertical rod and with the integrally formed horizon bar of vertical rod, the vertical rod upper end provided with outwardly convex and with I-steel side phase
The fixed block of cooperation, the side of the I-steel is provided with the reinforcing plate along I-steel width, the fixed block and it is described plus
The screw nut assembly being secured together is provided with strong plate, the upper surface of the horizon bar is provided with steel plate, the level
The one end of bar away from vertical rod is provided with the stopper for raising up and being offseted with steel plate side.
By using above-mentioned technical proposal, travelator frame is installed on Xuan Guanliang, is easy to workmen station on pavement
On be operated, it is so safer;It is engaged, fixed block short transverse can be limited with I-steel by fixed block
System, reduces the situation that fixed block departs from, when fixed block being fixed on into reinforcing plate by screw nut assembly, fixed block and I-steel
Cooperation fixed block can be positioned, be more prone to the fixation of screw nut assembly;Stopper can be to steel plate width
Limited on direction, the situation that steel plate is moved in the horizontal direction is reduced, so as to add the structural strength of travelator frame.
It is preferred that, the recessed groove that the lower surface of the steel plate is provided with along steel plate width direction and is engaged with horizon bar.
By using above-mentioned technical proposal, groove is engaged with horizon bar, can to being limited on steel plate length direction,
The situation that steel plate is moved in the horizontal direction is further reduced, so as to add the stability of travelator frame.
It is preferred that, the upper surface of the horizon bar is rounded to be set.
By using above-mentioned technical proposal, the upper surface of horizon bar is rounded to be set, and is easy to steel plate to be arranged on horizon bar,
Accelerate the installation effectiveness of workmen.
It is preferred that, the steel plate is provided with the cylinder raised up, the cylinder close to the side of stopper and is plugged with shield
Column.
By using above-mentioned technical proposal, the installation of guardrail increases the security of workmen;The lower end of guardrail is inserted
It is very convenient in cylinder, accelerate the installation effectiveness of workmen.
It is preferred that, the guardrail includes some vertical rods be arrangeding in parallel and some horizontally disposed cross bars, the cross bar
On be socketed with several the connector being connected slid with cross bar.
By using above-mentioned technical proposal, connector can link together cross bar and vertical rod, so in dismounting guardrail
When, just can be with as long as connector is disassembled from vertical rod, and cross bar and vertical rod will not be caused to damage, it can repeat to make
With reduction production cost;Connector slides on cross bar, adjusts position of the connector on cross bar according to the distance of vertical rod, just
Fixed in connector in vertical rod.
It is preferred that, the connector include with cross bar be socketed annulus and with the orthogonal clip body of annulus, institute
Stating clip body includes two clip, the connection end located at clip end and the fasteners being hinged, one of connection
One end with fastener is held to be hinged, the other end of another connection end and fastener is snapped connection.
By using above-mentioned technical proposal, clip body is socketed in vertical rod, clip body is supported by fastener
It is pressed on the periphery of vertical rod, cross bar can be thus fixed;The feelings that vertical rod shifts on cylinder are reduced simultaneously
Condition, makes total more consolidate.
It is preferred that, the fastener includes threaded rod and threaded female, and the end of the connection end opens up fluted, described
The width of groove is more than the diameter of threaded rod and less than the minimum periphery width of threaded female.
By using above-mentioned technical proposal, after clip body is enclosed in vertical rod, it is connected to by rotating threaded rod
In groove, then by turning threaded female it is moved on threaded rod, make two connection ends of clip body close to centre, from
And the medial surface of clip body is pressed on the periphery of vertical rod, it is easy to be fixed in vertical rod cross bar;When dismantling guardrail,
It is moved on threaded rod by turning threaded female, two connection ends of clip body is moved to remote direction, realize
Cross bar is disassembled from vertical rod.
It is preferred that, the connection end is located at the card-tight part that groove is provided with outward bending.
By using above-mentioned technical proposal, Access Division can limit the free degree of the threaded female along slot opening direction, reduce
Threaded rod, threaded female and connection end mutually come off.
It is preferred that, the periphery of the vertical rod, which is provided with barrier ring, the vertical rod, is socketed with thread bush, and thread bush is located at
The top of barrier ring, the upper end of the cylinder is provided with the external screw thread being engaged with thread bush.
By using above-mentioned technical proposal, when in vertical rod insertion tube body, barrier ring can offset with the upper surface of cylinder,
Thread bush is fixed on cylinder by turning thread bush, thread bush is pressed on the upper surface of barrier ring, so that vertical rod is solid
It is scheduled in cylinder.
In summary, the utility model has the advantages that:Travelator frame is installed on Xuan Guanliang, is easy to construction
Personnel station is operated on pavement, so safer;It is engaged by fixed block with I-steel, can be high to fixed block
Degree direction is limited, and reduces the situation that fixed block departs from, when fixed block being fixed on into reinforcing plate by screw nut assembly, Gu
Determining the cooperation of block and I-steel can position to fixed block, be more prone to the fixation of screw nut assembly;Stopper energy
Enough to being limited in steel plate horizontal direction, the situation that steel plate is moved in the horizontal direction is reduced, so as to add pavement branch
The structural strength of frame.
Brief description of the drawings
Fig. 1 is the structural representation of the present embodiment;
Fig. 2 is the connection diagram of I-steel, support system and steel plate in the present embodiment;
Fig. 3 is the enlarged drawing of part A in Fig. 2;
Fig. 4 is the schematic diagram of connector in the present embodiment.
In figure:1st, I-steel;2nd, vertical rod;3rd, horizon bar;4th, fixed block;5th, reinforcing plate;6th, screw nut assembly;7th, steel
Plate;8th, stopper;9th, recessed groove;10th, cylinder;11st, guardrail;111st, vertical rod;112nd, cross bar;12nd, connector;121st, annulus;
122nd, clip;123rd, connection end;124th, fastener;1241st, threaded rod;1242nd, threaded female;1243rd, groove;13rd, card-tight part;
14th, barrier ring;15th, thread bush;16th, external screw thread.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
This specific embodiment is only to explain of the present utility model, and it is not to limitation of the present utility model, ability
Field technique personnel can make the modification without creative contribution to the present embodiment as needed after this specification is read, but
As long as all being protected in right of the present utility model by Patent Law.
One kind is outstanding to fill boom support erecting device, as depicted in figs. 1 and 2, including the I-steel 1 defaulted on Xuan Guanliang, work
The both sides of word steel 1 are evenly distributed integrally formed with some reinforcing plates 5;The side of I-steel 1 is provided with support system, branch
Support system includes vertical rod 2 and horizon bar 3, and vertical rod 2 is integrally formed with horizon bar 3, wherein, the upper end of vertical rod 2 is outside
Projection has fixed block 4, and the size of fixed block 4 is as the size of reinforcing plate 5, and fixed block 4 in reinforcing plate 5 with being provided with two
The through hole of alignment, screw nut assembly 6 can link together fixed block 4 with reinforcing plate 5 through through hole.
The upper surface of horizon bar 3 is placed with steel plate 7, and the lower surface of steel plate 7 is provided with the recessed groove 9 being engaged with horizon bar 3,
So in the insertion of horizon bar 3 steel plate 7, it can reduce steel plate 7 to being limited on the length direction of steel plate 7 and move up in the horizontal direction
Dynamic situation;The upper surface of horizon bar 3 is rounded to be set, and is easy to steel plate 7 to be arranged on horizon bar 3;Horizon bar 3 is away from vertical rod
2 one end is welded with the stopper 8 raised up, when steel plate 7 is placed on horizon bar 3, and stopper 8 can be with steel plate 7
Side offsets, so as to being limited on the width of steel plate 7.
As shown in Figures 2 and 3, the upper surface of steel plate 7 is welded with several cylinders 10, cylinder 10 and is plugged with guardrail 11,
Guardrail 11 includes vertical rod 111 and cross bar 112, is fixed together between vertical rod 111 and cross bar 112 by connector 12;Vertical rod 111
Lower end integrally formed with barrier ring 14, the height that barrier ring 14 is located in vertical rod 111 is identical with the height of cylinder 10, vertical rod
Thread bush 15 is socketed with 111, barrier ring 14 is located at the lower section of thread bush 15, and thread bush 15 can be stopped from vertical rod 111
Lower end slides, and is provided with the external screw thread 16 being engaged with thread bush 15 on the periphery of cylinder 10, makes spiral shell by turning thread bush 15
Line set 15 is fixed on cylinder 10, thread bush 15 is pressed on the upper surface of barrier ring 14, so that vertical rod 111 is fixed on cylinder
In 10.
As shown in Figure 2 and Figure 4, connector 12 includes annulus 121 and the body of clip 122, annulus 121 and the body of clip 122
It is mutually perpendicular to, wherein, annulus 121 is socketed on cross bar 112, annulus 121 is slid on cross bar 112, according to vertical rod 111
The distance between regulation connector 12 position on cross bar 112, the body of clip 122 being easy on connector 12 is connected to vertical rod
, just can be with as long as connector 12 is disassembled from vertical rod 111 when so dismantling guard rail 11 on 111, and will not be to cross bar
112 and vertical rod 111 cause damage, can reuse, reduce production cost.
The body of clip 122 includes the clip 122 of two semicirculars in shape, and one end of two clips 122 is hinged on by rotating shaft
Together, other end outward bending has connection end 123, when being drawn close in the middle of two phases of clip 122, the side of two connection ends 123
It can fit together;One of clip 122 is integrally formed with annulus 121, and the connection end 123 of the clip 122 is provided with depression
Threaded rod 1241 is hinged with by rotating shaft on groove 9, recessed groove 9, threaded rod 1241 is in cylinder, the end thread of threaded rod 1241
It is connected with threaded female 1242;Groove 1243 is provided with the end of another connection end 123, the width of groove 1243 is more than threaded rod
1241 diameter and less than threaded female 1242 excircle width, it is necessary to when cross bar 112 is fixed on into vertical rod 111, rotate screw thread
Bar 1241 makes it be connected in groove 1243, then it is moved on threaded rod 1241 by turning threaded female 1242, makes clip
Two connection ends 123 of 122 bodies to centre is close just can be with.
Groove 1243 is U-shaped, and connection end 123 is located at groove 1243 is bent with two to away from another connection end 123
Card-tight part 13, card-tight part 13 can limit the free degree of the threaded female 1242 along the opening direction of groove 1243, can effectively prevent spiral shell
Mutually come off between rasp bar 1241, threaded female 1242 and connection end 123;The inner surface of the body of clip 122 is bonded with by glue
Rubber ring, adds the frictional force between the body of clip 122 and vertical rod 111, reduces what cross bar 112 slid in vertical rod 111
Situation.
Claims (9)
1. one kind is outstanding to fill boom support erecting device, including defaults in the I-steel on Xuan Guanliang (1) and be fixed on I-steel (1)
Support system, the support system include vertical rod (2) and with vertical rod (2) integrally formed horizon bar (3), its feature
It is:Vertical rod (2) upper end is provided with outwardly convex and the fixed block (4) being engaged sideways with I-steel (1), the I-steel
(1) side is provided with the reinforcing plate (5) along I-steel (1) width, the fixed block (4) and the reinforcing plate (5) and set
The screw nut assembly (6) being secured together is equipped with, the upper surface of the horizon bar (3) is provided with steel plate (7), the level
The one end of bar (3) away from vertical rod (2) is provided with the stopper (8) for raising up and being offseted sideways with steel plate (7).
2. outstanding filling boom support erecting device according to claim 1, it is characterized in that:The lower surface of the steel plate (7) is set
The recessed groove (9) for having along steel plate (7) width and being engaged with horizon bar (3).
3. outstanding filling boom support erecting device according to claim 2, it is characterized in that:The upper surface of the horizon bar (3) is in
Fillet is set.
4. outstanding filling boom support erecting device according to claim 1, it is characterized in that:The steel plate (7) is close to stopper (8)
Side be provided with the cylinder (10) that raises up, the cylinder (10) and be plugged with guardrail (11).
5. outstanding filling boom support erecting device according to claim 4, it is characterized in that:The guardrail (11) includes some parallel
Several and cross bar are socketed with the vertical rod (111) of setting and some horizontally disposed cross bars (112), the cross bar (112)
(112) connector (12) of sliding connection.
6. outstanding filling boom support erecting device according to claim 5, it is characterized in that:The connector (12) includes and cross bar
(112) socket annulus (121) and with annulus (121) orthogonal clip (122) body, clip (122) body
Including two clips being hinged (122), the connection end (123) located at clip (122) end and fastener (124), its
In a connection end (123) and one end of fastener (124) be hinged, another connection end (123) and fastener (124)
The other end snap connection.
7. outstanding filling boom support erecting device according to claim 6, it is characterized in that:The fastener (124) includes spiral shell
Rasp bar (1241) and threaded female (1242), the end of the connection end (123) are opened up fluted (1243), the groove (1243)
Width be more than threaded rod (1241) diameter and less than threaded female (1242) minimum periphery width.
8. outstanding filling boom support erecting device according to claim 7, it is characterized in that:The connection end (123) is located at groove
(1243) place is provided with the card-tight part (13) of outward bending.
9. outstanding filling boom support erecting device according to claim 5, it is characterized in that:The periphery of the vertical rod (111) is set
Have and thread bush (15) is socketed with barrier ring (14), the vertical rod (111), and thread bush (15) is located at the upper of barrier ring (14)
Side, the upper end of the cylinder (10) is provided with the external screw thread (16) being engaged with thread bush (15).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720077405.4U CN206477612U (en) | 2017-01-21 | 2017-01-21 | It is outstanding to fill boom support erecting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720077405.4U CN206477612U (en) | 2017-01-21 | 2017-01-21 | It is outstanding to fill boom support erecting device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206477612U true CN206477612U (en) | 2017-09-08 |
Family
ID=59754853
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720077405.4U Active CN206477612U (en) | 2017-01-21 | 2017-01-21 | It is outstanding to fill boom support erecting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206477612U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108907097A (en) * | 2018-08-01 | 2018-11-30 | 衡水裕菖铸锻有限公司 | The casting and molding method of travelator frame a kind of and travelator frame |
-
2017
- 2017-01-21 CN CN201720077405.4U patent/CN206477612U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108907097A (en) * | 2018-08-01 | 2018-11-30 | 衡水裕菖铸锻有限公司 | The casting and molding method of travelator frame a kind of and travelator frame |
CN108907097B (en) * | 2018-08-01 | 2021-11-19 | 衡水中裕铁信装备工程有限公司 | Casting molding method of sidewalk support and sidewalk support |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5047680B2 (en) | Construction method of continuous viaduct | |
CN102587645A (en) | Climbing supporting mechanism having expansion and automatic meshing functions, and construction method thereof | |
KR102125710B1 (en) | Monorail system using prefabricated rail girder | |
CN206477612U (en) | It is outstanding to fill boom support erecting device | |
CN115559588A (en) | Construction method for erecting silo top cornice template by using slip form supporting rod | |
CN103774841A (en) | Track type sliding formwork device | |
CN105401527B (en) | Construction method for anchoring catwalk and catwalk anchoring device | |
CN109881587A (en) | King-tower upper beam bracket integral installation method under a kind of strong wind atmosphere | |
CN101599619A (en) | The erecting device of upright post of spanning frame and installation method thereof | |
CN202347754U (en) | Supporting screw type ladder compartment | |
CN106499420B (en) | A kind of mechanically high constant-resistance individual prop installation method and erection method | |
CN211498507U (en) | Whole reassembling type protection rack | |
CN202627483U (en) | Pressure weight type railless slip form | |
CN102322134A (en) | Method for determining difference in bearing capacities of fastener-type full space support frame and full space scaffold | |
CN204040437U (en) | Cantilever tripod and single-row cantilever protection frame system | |
CN110566241A (en) | Quickly-assembled supporting shed frame | |
CN203924352U (en) | Section steel concrete steel column base | |
CN207277365U (en) | A kind of dismountable retaining wall | |
CN212478488U (en) | Construction work platform is built by laying bricks or stones to chimney inside lining | |
KR20170025768A (en) | Vertical stop device for monorail system | |
CN203531349U (en) | Novel high-bearing easily-dismantled overhanging type scaffold | |
CN214696984U (en) | Cast-in-place box girder concrete curing means | |
CN204959611U (en) | A lifting device for highway construction bridge railing base template | |
CN114046062A (en) | Novel independent braced system of post-cast strip | |
EP0874084B1 (en) | Scaffolding for the renovation of concrete bridges |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |