CN206439507U - High altitude operation hanging frame - Google Patents

High altitude operation hanging frame Download PDF

Info

Publication number
CN206439507U
CN206439507U CN201621485439.9U CN201621485439U CN206439507U CN 206439507 U CN206439507 U CN 206439507U CN 201621485439 U CN201621485439 U CN 201621485439U CN 206439507 U CN206439507 U CN 206439507U
Authority
CN
China
Prior art keywords
snap ring
plate
slide rail
fixedly connected
fixed plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621485439.9U
Other languages
Chinese (zh)
Inventor
高洪龙
董建明
张绪东
刘国禄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ronghua Construction Group Co Ltd
Original Assignee
Ronghua Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ronghua Construction Group Co Ltd filed Critical Ronghua Construction Group Co Ltd
Priority to CN201621485439.9U priority Critical patent/CN206439507U/en
Application granted granted Critical
Publication of CN206439507U publication Critical patent/CN206439507U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses high altitude operation hanging frame, including wall, top on the right side of the wall is fixedly connected with the first fixed plate, the right side of the wall and it is fixedly connected with the second fixed plate positioned at the bottom of the first fixed plate, the top and bottom on the right side of the second slide rail, first fixed plate are provided with the right side of the second fixed plate inner chamber and are provided with the first slide rail.The utility model is by setting using cooperatively for the second fixed plate, swash plate, the first fixed plate, the second slide rail, the second chute, the first slide rail, slide plate, the first chute and supporting plate, steel construction in first snap ring and the second snap ring can effectively be moved, the using effect of so pylon is more preferable, pylon is solved during use, because pylon is immovable, so as to cause the problem of pylon can not effectively be moved to steel construction, so as to be moved to the steel construction in the first snap ring and the second snap ring.

Description

High altitude operation hanging frame
Technical field
The utility model is related to pylon technical field, specially high altitude operation hanging frame.
Background technology
A kind of " electric hoist pipeline pylon " (patent No. is disclosed in Chinese patent:201420378191.0) patent makes Used time, fixing anchor bar need to be set in lane side, first half bicircular arcs part is hung on the anchor pole of lane side by hanging hole, laid After upper supply water dust-proof pipeline and air line, then to connecting second half bicircular arcs part, fishbolt is tightened, although the patent Many pipelines can be hung and be fixed on lane side simultaneously, but the patent utilization pylon can not effectively be moved to steel construction The problem of.
Utility model content
The purpose of this utility model is to provide high altitude operation hanging frame possess the advantage moved to steel construction, solve The problem of pylon of having determined can not effectively be moved to steel construction.
To achieve the above object, the utility model provides following technical scheme:High altitude operation hanging frame, including wall, institute State the top on the right side of wall and be fixedly connected with the first fixed plate, the right side of the wall and fixed positioned at the bottom of the first fixed plate It is connected with the right side of the second fixed plate, the second fixed plate inner chamber and is provided with the second slide rail, on the right side of first fixed plate Top and bottom be provided with the top that is provided with the right side of the first slide rail, first slide rail on the left of slide plate, the slide plate and Bottom offers the first chute matched with the first slide rail, and the inner chamber of the slide plate is provided through rotating shaft, the rotating shaft Right side be provided with supporting plate, the right side that one end of the supporting plate is run through at the top of slide plate, the supporting plate is provided through drawing Pulling block is provided with the top of bar, the pull bar, the bottom of the pull bar is provided with draw ring, and the bottom of the draw ring inner chamber is provided with Connecting rod, the bottom of the connecting rod is fixedly connected with fixed block, and the fixing bolt that passes on left of the fixed block is fixedly connected There is the first snap ring, the right side of the fixed block is fixedly connected with the second snap ring, first snap ring and second by fixing bolt The bottom of snap ring is fixedly connected by connecting bolt, and the bottom of the supporting plate is fixedly connected with swash plate, one end of the swash plate Through the second fixed plate, one end of the swash plate offers the second chute matched with the second slide rail.
It is preferred that, the left side of first fixed plate and the fixture that passes on left of the second fixed plate fix company with wall Connect, the top of the swash plate is fixedly connected with the junction of supporting plate by fixture.
It is preferred that, the inner chamber of the draw ring, the first snap ring and the second snap ring is provided with wear-resistant pad.
It is preferred that, the surface of the pull bar, which is offered, is provided with fix bar, the fixation on the right side of through hole, the supporting plate One end of bar, which is run through on the right side of supporting plate and through hole, the fix bar, is provided with handle.
It is preferred that, the top and bottom on the outside of first snap ring and the second snap ring are provided with fastening bolt, described The surface of one snap ring, the second snap ring and wear-resistant pad offers the bolt hole matched with fastening bolt.
It is preferred that, the surface of first slide rail and the second slide rail is provided with antifriction particle, the pull bar and handle Surface be arranged with Anti-slip cover.
Compared with prior art, the beneficial effects of the utility model are as follows:
1st, the utility model is by setting the second fixed plate, swash plate, the first fixed plate, the second slide rail, the second chute, first Slide rail, slide plate, the first chute and supporting plate are used cooperatively, and the steel construction in the first snap ring and the second snap ring can be carried out effective Mobile, the using effect of such pylon more preferably, solves pylon during use, because pylon is immovable, from And the problem of pylon can not effectively be moved to steel construction is caused, so as to the steel construction in the first snap ring and the second snap ring Move, be adapted to promote the use of.
2nd, the utility model can be protected by wear-resistant pad to draw ring, and the use time of such draw ring is longer, it is to avoid Draw ring is during prolonged use, and draw ring inner chamber is directly contacted with pull bar and fix bar, so that draw ring serious wear is caused, So as to cause the problem of draw ring is damaged, by swash plate, support, the using effect of such supporting plate can be played a part of to supporting plate More preferably, it is to avoid the first snap ring is heavier with steel construction in the second snap ring, so as to cause the problem of supporting plate is broken, passes through Fastening bolt, the steel construction in the first snap ring and the second snap ring can be fixed, and the using effect of such pylon more preferably, is kept away The first snap ring is exempted from more loose with steel construction in the second snap ring, so as to cause steel construction out of the first snap ring and the second snap ring The problem of coming off occurs, by connecting bolt, and the first snap ring and the second snap ring effectively can be connected, such first snap ring and The using effect of second snap ring is more preferable, it is to avoid the first snap ring can not be connected with the second snap ring, so as to cause pylon to have The storage steel construction of effect.
Brief description of the drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is the utility model A-A enlarged drawings;
Fig. 3 is the utility model B-B enlarged drawings;
Fig. 4 is the utility model C-C enlarged drawings.
In figure:1 wall, 2 second fixed plates, 3 swash plates, 4 first snap rings, 5 connecting bolts, 6 fastening bolts, 7 wear-resistant pads, 8 Second snap ring, 9 connecting rods, 10 draw rings, 11 pull bars, 12 handles, 13 fix bars, 14 through holes, 15 pulling blocks, 16 first fixed plates, 17 Second slide rail, 18 second chutes, 19 fixed blocks, 20 fixing bolts, 21 first slide rails, 22 slide plates, 23 rotating shafts, 24 first chutes, 25 supporting plates.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belongs to the scope of the utility model protection.
Fig. 1-4, high altitude operation hanging frame, including wall 1 are referred to, the top on the right side of wall 1 is fixedly connected with first and consolidated Fixed board 16, the right side of wall 1 and is fixedly connected with the second fixed plate 2, the second fixed plate 2 positioned at the bottom of the first fixed plate 16 The second slide rail 17 is provided with the right side of chamber, the top and bottom on the right side of the first fixed plate 16 are provided with the first slide rail 21, first The right side of slide rail 21 is provided with slide plate 22, and the top and bottom in the left side of slide plate 22 offer the matched with the first slide rail 21 One chute 24, the inner chamber of slide plate 22 is provided through rotating shaft 23, and the right side of rotating shaft 23 is provided with supporting plate 25, the one of supporting plate 25 Slide plate 22 is run through at end, and the right side at the top of supporting plate 25 is provided through pull bar 11, and the top of pull bar 11 is provided with pulling block 15, pull bar 11 surface offers through hole 14, and the right side of supporting plate 25 is provided with fix bar 13, and supporting plate 25 is run through in one end of fix bar 13 With through hole 14, the right side of fix bar 13 is provided with handle 12, and the surface of the first slide rail 21 and the second slide rail 17 is provided with antifriction The surface of wiping particle, pull bar 11 and handle 12 is arranged with Anti-slip cover, and the bottom of pull bar 11 is provided with draw ring 10, the inner chamber of draw ring 10 Bottom be provided with connecting rod 9, the bottom of connecting rod 9 is fixedly connected with fixed block 19, and fixed block 19 passes on left fixed spiral shell Bolt 20 is fixedly connected with the first snap ring 4, and the right side of fixed block 19 is fixedly connected with the second snap ring 8, draw ring by fixing bolt 20 10th, the inner chamber of the first snap ring 4 and the second snap ring 8 is provided with wear-resistant pad 7, by wear-resistant pad 7, and draw ring 10 can be protected, The use time of so draw ring 10 is longer, it is to avoid draw ring 10 is during prolonged use, the inner chamber of draw ring 10 and pull bar 11 Directly contacted with fix bar 13, so that the serious wear of draw ring 10 is caused, so as to cause the problem of draw ring 10 is damaged, the first snap ring 4 Fastening bolt 6 is provided with the top and bottom in the outside of the second snap ring 8, can be to the first snap ring 4 and the by fastening bolt 6 Steel construction in two snap rings 8 is fixed, and the using effect of such pylon is more preferable, it is to avoid the first snap ring 4 and the second snap ring 8 Interior steel construction is more loose, thus cause steel construction from the first snap ring 4 with being come off in the second snap ring 8 the problem of occur, first The surface of snap ring 4, the second snap ring 8 and wear-resistant pad 7 offers the bolt hole matched with fastening bolt 6, the first snap ring 4 and The bottom of two snap rings 8 is fixedly connected by connecting bolt 5, by connecting bolt 5, and the first snap ring 4 and the second snap ring 8 can be carried out Effective connection, the using effect of such snap ring 8 of first snap ring 4 and second is more preferable, it is to avoid the first snap ring 4 and the second snap ring 8 are not It can connect, so as to cause pylon effectively to deposit steel construction, the bottom of supporting plate 25 is fixedly connected with swash plate 3, first The fixture that passes on left of the left side of fixed plate 16 and the second fixed plate 2 is fixedly connected with wall 1, the top of swash plate 3 and support The junction of plate 25 is fixedly connected by fixture, by swash plate 3, can play a part of support to supporting plate 25, is so supported The using effect of plate 25 is more preferable, it is to avoid the first snap ring 4 and steel construction in the second snap ring 8 are heavier, so as to cause supporting plate 25 The second fixed plate 2 is run through in the problem of being broken, one end of swash plate 3, and one end of swash plate 3 is offered to match with the second slide rail 17 The second chute 18, by setting the second fixed plate 2, swash plate 3, the first fixed plate 16, the second slide rail 17, the second chute 18, the One slide rail 21, slide plate 22, the first chute 24 and supporting plate 25 are used cooperatively, can be to the steel in the first snap ring 4 and the second snap ring 8 Structure is effectively moved, and the using effect of such pylon more preferably, solves pylon during use, because of pylon It is immovable, so that the problem of pylon can not effectively be moved to steel construction is caused, so as to the first snap ring 4 and the second card Steel construction in ring 8 is moved, and is adapted to promote the use of.
In use, first chute 24 in the left side of slide plate 22 is moved on the surface of the first slide rail 21, second chute in the left side of swash plate 3 18 in the movement of the surface of the first slide rail 21, so as to be moved to pylon.
In summary:The high altitude operation hanging frame, by setting the second fixed plate 2, swash plate 3, the first fixed plate 16, second Slide rail 17, the second chute 18, the first slide rail 21, slide plate 22, the first chute 24 and supporting plate 25 are used cooperatively, and solve hanging The problem of frame can not effectively be moved to steel construction.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art, It is appreciated that these embodiments can be carried out in the case where not departing from principle of the present utility model and spirit a variety of changes, repaiies Change, replace and modification, scope of the present utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. high altitude operation hanging frame, including wall (1), it is characterised in that:Top on the right side of the wall (1) is fixedly connected with One fixed plate (16), the right side of the wall (1) and is fixedly connected with the second fixed plate positioned at the bottom of the first fixed plate (16) (2) top on the right side of the second slide rail (17), first fixed plate (16), is provided with the right side of the second fixed plate (2) inner chamber Portion and bottom are provided with the right side of the first slide rail (21), first slide rail (21) and are provided with slide plate (22), the slide plate (22) top and bottom on the left of offer the first chute (24) matched with the first slide rail (21), the slide plate (22) Inner chamber is provided through on the right side of rotating shaft (23), the rotating shaft (23) being provided with supporting plate (25), the one of the supporting plate (25) The right side that end is run through at the top of slide plate (22), the supporting plate (25) is provided through pull bar (11), the top of the pull bar (11) Pulling block (15) is provided with, the bottom of the pull bar (11) is provided with draw ring (10), and the bottom of draw ring (10) inner chamber is provided with Connecting rod (9), the bottom of the connecting rod (9) is fixedly connected with fixed block (19), and passing on left for the fixed block (19) is solid Determine bolt (20) and be fixedly connected with the first snap ring (4), the right side of the fixed block (19) is fixedly connected by fixing bolt (20) There is the second snap ring (8), first snap ring (4) is fixedly connected with the bottom of the second snap ring (8) by connecting bolt (5), described The bottom of supporting plate (25) is fixedly connected with swash plate (3), and the second fixed plate (2), the swash plate are run through in one end of the swash plate (3) (3) one end offers the second chute (18) matched with the second slide rail (17).
2. high altitude operation hanging frame according to claim 1, it is characterised in that:The left side of first fixed plate (16) and The fixture that passes on left of second fixed plate (2) is fixedly connected with wall (1), top and the supporting plate (25) of the swash plate (3) Junction be fixedly connected by fixture.
3. high altitude operation hanging frame according to claim 1, it is characterised in that:The draw ring (10), the first snap ring (4) and The inner chamber of second snap ring (8) is provided with wear-resistant pad (7).
4. high altitude operation hanging frame according to claim 1, it is characterised in that:The surface of the pull bar (11) offers logical Fix bar (13) is provided with the right side of hole (14), the supporting plate (25), supporting plate is run through in one end of the fix bar (13) (25) and through hole (14), it is provided with handle (12) on the right side of the fix bar (13).
5. high altitude operation hanging frame according to claim 1, it is characterised in that:First snap ring (4) and the second snap ring (8) top and bottom on the outside of are provided with fastening bolt (6), first snap ring (4), the second snap ring (8) and wear-resistant pad (7) Surface offer the bolt hole matched with fastening bolt (6).
6. high altitude operation hanging frame according to claim 1, it is characterised in that:First slide rail (21) and the second slide rail (17) surface is provided with antifriction particle, and the surface of the pull bar (11) and handle (12) is arranged with Anti-slip cover.
CN201621485439.9U 2016-12-31 2016-12-31 High altitude operation hanging frame Expired - Fee Related CN206439507U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621485439.9U CN206439507U (en) 2016-12-31 2016-12-31 High altitude operation hanging frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621485439.9U CN206439507U (en) 2016-12-31 2016-12-31 High altitude operation hanging frame

Publications (1)

Publication Number Publication Date
CN206439507U true CN206439507U (en) 2017-08-25

Family

ID=59643123

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621485439.9U Expired - Fee Related CN206439507U (en) 2016-12-31 2016-12-31 High altitude operation hanging frame

Country Status (1)

Country Link
CN (1) CN206439507U (en)

Similar Documents

Publication Publication Date Title
CN206797765U (en) A kind of complicated landform unmanned plane charging landing platform
CN209506796U (en) A kind of coal mine leather belt conveyer carrying roller more changing device
CN205998870U (en) A kind of Portable jack bracket fixing device
CN107339579A (en) A kind of mining machinery support platform
CN203998697U (en) Movable type gantry mast-up
CN104891372A (en) Cable inspection well cover opening device
CN106641452A (en) Suspension frame for overhead operation
CN206439507U (en) High altitude operation hanging frame
CN207638250U (en) Cable tunnel lays special stand coaster
CN203818129U (en) Front axle maintenance tray for loader
CN205908031U (en) A rail mounted lifting device for high -rise building curtain wall construction
CN205421890U (en) Die carrier bearing beam
CN206985645U (en) A kind of easy-to-dismount truck hydraulic bar
CN210577392U (en) Overhead device for cable maintenance
CN206457725U (en) It is a kind of to be used for the overall device transferred and remove dragging suspension basket
CN208103072U (en) A kind of belt feeder split shackle of energy fast assembling-disassembling
CN206665992U (en) A kind of plant equipment mast-up
CN106495061A (en) Stable lifting device for steel structure machining
CN207063317U (en) Steel construction cable-stayed support for building
CN207375669U (en) The electronic lifting bracket of cable tunnel inner column formula cable
CN205777537U (en) A kind of upper and lower pressurizing unit of interior wall
CN206623036U (en) A kind of novel coupler provision for disengagement
CN206636801U (en) A kind of Sledge type immersible pump being moved easily
CN204910679U (en) Convenient football goal of settling in non - court
CN205834110U (en) Transmission belt supporting frame is used in a kind of steel-casting processing

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170825

Termination date: 20171231

CF01 Termination of patent right due to non-payment of annual fee