CN206412764U - A kind of new change power network access system - Google Patents

A kind of new change power network access system Download PDF

Info

Publication number
CN206412764U
CN206412764U CN201720057020.1U CN201720057020U CN206412764U CN 206412764 U CN206412764 U CN 206412764U CN 201720057020 U CN201720057020 U CN 201720057020U CN 206412764 U CN206412764 U CN 206412764U
Authority
CN
China
Prior art keywords
transformation device
breaker
disconnecting switch
buses
transformation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720057020.1U
Other languages
Chinese (zh)
Inventor
雷冬阁
朱炜
黄钢
姜春娣
张露
陈勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Quzhou University
Original Assignee
Quzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Quzhou University filed Critical Quzhou University
Priority to CN201720057020.1U priority Critical patent/CN206412764U/en
Application granted granted Critical
Publication of CN206412764U publication Critical patent/CN206412764U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of new change power network access system, is provided with 110KV distribution gauzes;The 110KV distribution wires Netcom crosses electric wire and connects the first disconnecting switch group and the second disconnecting switch group respectively;The first disconnecting switch group is connected by breaker with the first transformation device;The output end of first transformation device is connected by breaker with the 110KV buses on the second transformation device;The second disconnecting switch group is connected by breaker with the 3rd transformation device;The output end of 3rd transformation device is connected by breaker with the 110KV buses on the 4th transformation device;It is connected to after 3rd transformation device is in parallel with the 4th transformation device on 110KV buses;5th transformation device, the 6th transformation device are connected by breaker with the 110KV buses.The utility model has carried out good planning to power network, significant to rational investment.

Description

A kind of new change power network access system
Technical field
The utility model belongs to electric power network technical field, more particularly to a kind of new change power network access system.
Background technology
At present, new chemical materialses Develop Industrial Cluster in Quzhou completes Electric Power Forecasting Based on Artificial beyond original expection Correct on working foundation, it is necessary to regional power grid development plan is modified according to new Electric Power Forecasting Based on Artificial result.
At present, the strong major network in 500 kilovolts of Quzhou is built up substantially, and 500 kv substation two is possessed altogether:The change of letter peace (2 × 750000 kilovolt-amperes), Xia Jinbian (1 × 1,000,000 kilovolt-amperes), and by believing peace~Zhi Yan, Xia Jin~bis- imperial two 500 kilovolts of passages Kept in touch with Zhejiang major network, 500 kv grid rack reliabilities are higher.Root is it was predicted that in " 13 " period, Quzhou chemical industry New material industry cluster electricity needs is about 579.6MW, according to remote planning, becomes the 3rd main transformer (75 of enlarging for letter peace within 2018 Ten thousand kilovolt-amperes), but in view of the development of Quzhou chemical industry cluster, it is necessary to became the 3rd main transformer (75 of enlarging in 2017 for letter peace Ten thousand kilovolt-amperes).
Quzhou new chemical materialses industry cluster is concentrated mainly on hugeization block and high-new confession area.Wherein, hugeization block is powered It is relatively independent, independently planned, be not described herein by Ju Hua companies.High-tech Park is in high-new 110 kv substation and planning Huang Jiabian (high-new II) is main to be supplied.
220 kilovolts of boat ports, which become, was gone into operation in nineteen ninety-five, and main transformer capacity is 2*150MVA, and 2013 yearly maximum loads have reached 249.28MW, load factor is 83.1%, with high-new section chemical industry load rapid growth, and main transformer load factor will further increase, Boat port varying duty is up to 266MW within 2015, and load factor is 88.6%, with the operation of the projects such as Hyosung, to main transformer in 2016 Load is estimated will be fully loaded.In addition, the change of boat port is the uniquely upper level power supply of high-new change, if 220kV boats port becomes equipment fault and tripped, High-new transformer station's no-voltage of entire station can be caused.Therefore, it is necessary to which the Overall Reconstruction for arranging boat port to become in 2017, improves reliability. Or connect Chongwen change with high-new change.But in the long term, it is necessary to accelerate 220 kilovolts of Chi Ke and become construction, it is therefore desirable to Arrange Chi Ke to become before the end of the year 2016 to build.
Put into operation postpartum once 220 kilovolts of Chi Ke become, it is considered to draw high-new, first vertical, the China's friend's change belonged to originally in the change power supply of boat port Gui Chike becomes power supply, and power supply pressure is become to alleviate boat port.Port change of being navigated after adjustment is main rather to be become and high for boat east, deer ring, garden hilllock, day New garden increases other users newly and become.
220 kilovolts of Chi Ke electric substations distant view scales are 3 × 240MVA;2 × 240MVA of main transformer, from on-load voltage regulation transformation Device, voltage class is 220/110/35 kilovolt.
Distant view 12 times, main electrical scheme is single female three section wiring, and the current period is using single female three section wiring.110 KV distributions are filled Put arrangement of being exposed to the north, distant view outlet 12 times, from West to East respectively in Hunan-Town Hydro-electric, twenty, high-new, boat east, vertical member, Hua You, yellow family I, Yellow family II, Quzhou, yellow altar, metal I, metal II.
220 kilovolts of boat ports, which become, was gone into operation in nineteen ninety-five, and main transformer capacity is 2*150MVA, and 2013 yearly maximum loads have reached 249.28MW, load factor is 83.1%, with urban district load rapid growth, and main transformer load factor will further increase, it is contemplated that 2015 Year, boat port varying duty was up to 266MW, and load factor is 88.6%, will be fully loaded to main transformer load in 2017.
High-new section chemical industry load rapidly increases, but uniquely upper level power supply is that boat port becomes for High-tech Park, uses list The emanant wiring of power supply, if boat port becomes fault trip, can cause high-new change no-voltage of entire station.
The content of the invention
If the utility model is solution High-tech Park, uniquely upper level power supply boat port becomes fault trip, can cause high-new become entirely Stand decompression, cause the problem of power supply pressure is lacked and a kind of new change power network access system is provided.The utility model is using new After the mode of connection, the access way of high-new change is changed to π formula wiring by single supply is emanant, and dual power supply bilateral is powered, respectively by red Ke becomes and boat port becomes common power supply, and on the one hand can alleviate boat port becomes loading pressure, on the other hand also increases high and new technology industrial development zone Power supply reliability and flexibility.
The utility model is adopted the technical scheme that to solve technical problem present in known technology:
A kind of new change power network access system, is provided with 110KV distribution gauzes;Electric wire is crossed by the 110KV distribution wires Netcom The first disconnecting switch group and the second disconnecting switch group are connected respectively;The first disconnecting switch group passes through breaker and the first power transformation Device is connected;The output end of first transformation device is connected by breaker with the 110KV buses on the second transformation device;Institute The second disconnecting switch group is stated to be connected with the 3rd transformation device by breaker;The output end of 3rd transformation device passes through open circuit Device is connected with the 110KV buses on the 4th transformation device;It is connected to after 3rd transformation device is in parallel with the 4th transformation device On 110KV buses;5th transformation device, the 6th transformation device are connected by breaker with the 110KV buses;Described 5th Transformation device, the 6th transformation device are in parallel.
Further, the 110KV distribution gauze is provided with 110KV main tracks, 110KV by-passes, 110KV side lines and connected respectively The disconnecting switch set in first disconnecting switch group and the second disconnecting switch group;
The first disconnecting switch group and the second disconnecting switch group are provided with three disconnecting switch, and three disconnecting switch are simultaneously It is connected after connection by electric wire with breaker.
Further, first transformation device is provided with the first transformation device input and the first transformation device output end; The first transformation device input and the first transformation device output end are connected by breaker;The first transformation device output End is connected by breaker with 110KV buses.
Further, second transformation device is provided with the 7th transformation device and the 8th transformation device;7th power transformation The input of device and the 8th transformation device connects 110KV buses by breaker.
Further, the 4th transformation device is provided with the 9th transformation device and the tenth transformation device;9th power transformation The input and output end of device connect 110KV buses by breaker;The input of tenth transformation device passes through disconnected Road device connection 110KV buses.
Further, the 5th transformation device, the input of the 6th transformation device connect 110KV mothers by breaker Line;5th transformation device, the output end of the 6th transformation device are connected with each other.
The utility model has the advantages and positive effects of:The utility model has carried out good planning to power network, right Rational investment is significant.The utility model is used after the wiring, and the high technology industry park second phase can be met first The power reguirements Added User;Secondly boat port main transformer load can be solved close to the problem of being fully loaded with;Three can become for Quzhou Offer condition is transformed in aging.
During one line fault, if whole piece circuit can be divided into stem portion and be turned to supply by remaining circuit, make power supply reliability With flexibility increase.
The utility model can be very good to meet the power supply need of pollution-free industry Nesting Zone particularly high technology industry park Ask, 220 kilovolts of boat ports of mitigation become, Quzhous become pressure of powering, and strengthen the power supply capacity of power network, the matter while improvement power network is powered Amount, improves power supply reliability and flexibility.
Brief description of the drawings
Fig. 1 is the new change power network access system schematic diagram that the utility model embodiment is provided.
In figure:1st, 110KV distribution gauze;2nd, disconnecting switch;3rd, the first disconnecting switch group;4th, the second disconnecting switch group;5、 Breaker;6th, the first transformation device;7th, the 3rd transformation device;8th, the second transformation device;8-1, the 7th transformation device;8-2, the 8th Transformation device;9th, the 4th transformation device;9-1, the 9th transformation device;9-2, the tenth transformation device;10th, 110KV buses;11st, Five transformation devices;12nd, the 6th transformation device.
Embodiment
For invention, features and effects of the present utility model can be further appreciated that, following examples are hereby enumerated, and coordinate Accompanying drawing describes in detail as follows.
Structure of the present utility model is explained in detail with reference to figure.
As shown in figure 1, the new change power network access system that the utility model embodiment is provided, a kind of new change power network access System, is provided with 110KV distribution gauze 1;The 110KV distribution wires Netcom crosses electric wire and connects the He of the first disconnecting switch group 3 respectively Second disconnecting switch group 4;The first disconnecting switch group is connected by breaker 5 with the first transformation device 6;First power transformation The output end of device is connected by breaker with the 110KV buses 10 on the second transformation device 8;The second disconnecting switch group is led to Breaker is crossed to be connected with the 3rd transformation device 7;The output end of 3rd transformation device passes through breaker and the 4th transformation device 9 On 110KV buses connection;It is connected to after 3rd transformation device is in parallel with the 4th transformation device on 110KV buses;5th Transformation device 11, the 6th transformation device 12 are connected by breaker 5 with the 110KV buses 10;5th transformation device, 6th transformation device is in parallel.
The 110KV distribution gauze be provided with 110KV main tracks, 110KV by-passes, 110KV side lines and respectively connection first every From the disconnecting switch 2 set in switches set and the second disconnecting switch group;
The first disconnecting switch group and the second disconnecting switch group are provided with three disconnecting switch 2, three disconnecting switch It is connected after parallel connection by electric wire with breaker.
First transformation device 6 is provided with the first transformation device input and the first transformation device output end;Described One transformation device input and the first transformation device output end are connected by breaker;The first transformation device output end passes through Breaker is connected with 110KV buses.
Second transformation device 8 is provided with the 7th transformation device 8-1 and the 8th transformation device 8-2;7th power transformation The input of device and the 8th transformation device connects 110KV buses by breaker.
4th transformation device 9 is provided with the 9th transformation device 9-1 and the tenth transformation device 9-2;9th power transformation The input and output end of device connect 110KV buses by breaker;The input of tenth transformation device passes through disconnected Road device connection 110KV buses.
5th transformation device, the input of the 6th transformation device connect 110KV buses by breaker;Described Five transformation devices, the output end of the 6th transformation device are connected with each other.
110KV distribution gauze for 220kV Hang Bu transformer stations 110KV just, secondary, other bus;First transformation device is 110KV High-new transformer station;3rd transformation device is 110KV Hang Dong transformer stations;7th transformation device is 110KV Yuan Li transformer stations;8th becomes Denso is set to 110KV Hua You transformer stations;9th transformation device is Huang Jia transformer stations;Tenth transformation device is Hunan-Town Hydro-electric transformer station; 5th transformation device is 220kV Quzhous transformer station;6th transformation device is yellow altar power plant.
The new change power network access system selects ULTC, voltage class 220/110/35kV, and 110kV goes out Line is using single female three section wiring, distant view outlet 12 times;35kV outlets are mainly connect using single mother partition wiring, distant view outlet 8 times High-new, first vertical, Hua You.
Structure of the present utility model is further described with reference to operation principle.
The new change power network access system that the utility model embodiment is provided selects ULTC, voltage class 220/110/35kV, 220 kilovolts of outlets mainly meet high-new, first vertical, Hua You, and thus alleviating boat port becomes pressure of powering, after adjustment Port change of navigating is main rather to be become and the newly-increased other users change in High-tech Park for boat east, deer ring, garden hilllock, day;110kV outlets are using single mother three Section wiring, distant view outlet 12 times, (be respectively from West to East in Hunan-Town Hydro-electric, twenty, it is high-new, boat east, member vertical, Hua You, yellow family 1, yellow Family II, Quzhou, yellow altar, metal 1, metal II, consider the reliability and reasonability of Net Frame of Electric Network in addition, and this patent considers 110 Kilovolt Hunan-Town Hydro-electric fades at twenty li of circuit 60#~61# the Π that is open and enters Chi Ke changes, forms 1 time 110 kilovolts of Chi Ke to Hunan-Town Hydro-electric, and another 1 Return decompression and be connected to twenty li of change for 35 kilovolts, circuit is built by common-tower double-return road, and about 2 × 4.1 kilometers of newly-built double back transmission line is led Line section selection 300mm2;110 kilovolts of boat ports to member is stood simultaneously, the friendly multiple-circuit on same tower opening access Chi Ke of China becomes, formation each 1 110 kilovolts of Chi Ke are returned to the vertical line of member, the friendly line of China, circuit is set up by common-tower double-return road.(Chi Ke is vertical to the member) circuit of west side one time is complete It is long 7.3 kilometers (to utilize old 1.5 kilometers of circuit, newly-built 5.8 kilometers of circuit, wherein double loop set up 3.5 kilometers, and four loops are set up 1.8 kilometers, single loop sets up 0.5 kilometer);(Chi Ke to the Hua You) circuit of east side one time completely (wherein utilizes old circuit for 6.6 kilometers 1.0 kilometers, newly-built 5.6 kilometers of circuit, double loop sets up 3.5 kilometers, and four loops set up 1.8 kilometers, and it is public that single loop sets up 0.3 In).Economic voltage loss 300mm2.);35kV outlets are using single mother partition wiring, distant view outlet 8 times, mainly connect at present it is high-new, Member is stood and Hua You.
Chi Ke is to estimated newly-built 6.1 kilometers of the circuit of high-new double back transmission line, and double loop sets up 4.3 kilometers, four loop framves If 1.8 kilometers.Economic voltage loss 300mm2.Simultaneously yellow altar power plant by 110 kilovolts of main electrical schemes by single busbar band bypass connection Single-trunk segmental wiring is changed to, and in 110 kilovolts of mother stock 1 set of backup auto-activating devices of configuration.
The utility model incorporates high-new, first vertical, the China's friend's change belonged to originally in the change power supply of Chi Ke Bian Gong areas Xian Youhang ports into Chi Ke Become power supply;Port of being navigated after adjustment becomes main and rather become for boat east, deer ring, garden hilllock, day and High-tech Park increases other users' changes newly;By 110 Kilovolt boat port to high-new multiple-circuit on same tower southern side, which opens a section Π 1 time and enters Chi Ke, to be become, while becoming former double T modes of connection and being changed to boat east Π enters, and forms 1 time Chi Ke to high-new, and 1 homeward port is to high-new.
Chi Ke is to estimated newly-built 6.1 kilometers of the circuit of high-new double back transmission line, and double loop sets up 4.3 kilometers, four loop framves If 1.8 kilometers.Economic voltage loss 300mm2
After line adjustment, if boat port becomes failure or maintenance, power-off is needed, then high-new section can still become from Chi Ke to be connect Powered.
Described above is only, to preferred embodiment of the present utility model, not to make any formal to the utility model Limitation, it is every according to technical spirit of the present utility model to any simple modification made for any of the above embodiments, equivalent variations with Modification, is belonged in the range of technical solutions of the utility model.

Claims (6)

1. a kind of new change power network access system, it is characterised in that the new change power network access system is provided with 110KV distribution Gauze;The 110KV distribution wires Netcom crosses electric wire and connects the first disconnecting switch group and the second disconnecting switch group respectively;Described first Disconnecting switch group is connected by breaker with the first transformation device;The output end of first transformation device passes through breaker and 110KV buses connection on two transformation devices;The second disconnecting switch group is connected by breaker with the 3rd transformation device;Institute The output end for stating the 3rd transformation device is connected by breaker with the 110KV buses on the 4th transformation device;3rd power transformation It is connected to after device is in parallel with the 4th transformation device on 110KV buses;5th transformation device, the 6th transformation device pass through open circuit Device is connected with the 110KV buses;5th transformation device, the 6th transformation device are in parallel.
2. new change power network access system as claimed in claim 1, it is characterised in that the 110KV distribution gauze is provided with 110KV main tracks, 110KV by-passes, 110KV side lines simultaneously connect what is set in the first disconnecting switch group and the second disconnecting switch group respectively Disconnecting switch;
The first disconnecting switch group and the second disconnecting switch group are provided with three disconnecting switch, after three disconnecting switch are in parallel It is connected by electric wire with breaker.
3. new change power network access system as claimed in claim 1, it is characterised in that first transformation device is provided with the One transformation device input and the first transformation device output end;First transformation device input and the first transformation device output End is connected by breaker;The first transformation device output end is connected by breaker with 110KV buses.
4. new change power network access system as claimed in claim 1, it is characterised in that second transformation device is provided with the Seven transformation devices and the 8th transformation device;The input of 7th transformation device and the 8th transformation device is connected by breaker Connect 110KV buses.
5. new change power network access system as claimed in claim 1, it is characterised in that the 4th transformation device is provided with the Nine transformation devices and the tenth transformation device;The input and output end of 9th transformation device are connected by breaker 110KV buses;The input of tenth transformation device connects 110KV buses by breaker.
6. new change power network access system as claimed in claim 1, it is characterised in that the 5th transformation device, the 6th become The input of electric installation connects 110KV buses by breaker;5th transformation device, the output end of the 6th transformation device It is connected with each other.
CN201720057020.1U 2017-01-17 2017-01-17 A kind of new change power network access system Expired - Fee Related CN206412764U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720057020.1U CN206412764U (en) 2017-01-17 2017-01-17 A kind of new change power network access system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720057020.1U CN206412764U (en) 2017-01-17 2017-01-17 A kind of new change power network access system

Publications (1)

Publication Number Publication Date
CN206412764U true CN206412764U (en) 2017-08-15

Family

ID=59556964

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720057020.1U Expired - Fee Related CN206412764U (en) 2017-01-17 2017-01-17 A kind of new change power network access system

Country Status (1)

Country Link
CN (1) CN206412764U (en)

Similar Documents

Publication Publication Date Title
CN110112731B (en) Power transmission system
CN104333036B (en) Multi-source coordination control system
CN103986152B (en) The method for arranging of flexible direct current converter station connection district and valve Room power distribution equipment
CN204835226U (en) Line arrangement structure of two complete clusters is joined in marriage into in wiring of one and half circuit breakers
CN103227468B (en) Main wiring pairing and stringing optimization method for transformer station
CN207398833U (en) A kind of multilayer closed loop power distribution system suitable for intelligent building
CN102208811B (en) Wiring structure of distribution network containing microgrid
CN108879698A (en) A kind of medium voltage distribution network dual ring topology structure comprising four port flexible switch
CN204992581U (en) Apply to electric main wiring of two electric pressure intermediate pressure sections of wind -powered electricity generation field
CN206412764U (en) A kind of new change power network access system
CN109671344A (en) A kind of topological structure for direct current transmission and distribution constructional dynamic simulation experimental system
CN105978135B (en) A kind of uninterrupted power exchanger of current source type for alternating-current system
CN206498200U (en) A kind of new 110kV ancillary transmissions circuit
Wang et al. Multi-circuit HVDC system emergency DC power support with reactive control
CN210137183U (en) Power transmission system
CN203787789U (en) T and pi mixed net rack wiring structure applied to high voltage distribution
CN207910471U (en) A kind of hybrid AC/DC power transmission systems containing specific load
CN112952796A (en) Power utilization system wiring of offshore flexible direct current converter station and operation method thereof
CN209169957U (en) A kind of urban distribution network wiring construction
CN203932698U (en) A kind of single busbar connection dual-breaker sectional wiring structure
CN106099916A (en) The method that a kind of 110kV transformer station load transfer scheme quickly determines
CN207504574U (en) A kind of electric power system of based superconductive circuit
CN112398125A (en) Low-voltage fault self-healing device and control method thereof
CN106787123B (en) 30 degree of phase angle difference distribution lines, which do not have a power failure, to be turned for breaker group sequence method
CN105978134B (en) A kind of uninterrupted power exchanger for alternating-current system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170815

Termination date: 20190117

CF01 Termination of patent right due to non-payment of annual fee