CN206378257U - A valve pressure test device - Google Patents
A valve pressure test device Download PDFInfo
- Publication number
- CN206378257U CN206378257U CN201621461673.8U CN201621461673U CN206378257U CN 206378257 U CN206378257 U CN 206378257U CN 201621461673 U CN201621461673 U CN 201621461673U CN 206378257 U CN206378257 U CN 206378257U
- Authority
- CN
- China
- Prior art keywords
- valve
- pressure test
- pressure
- liquid supply
- booster pump
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Measuring Fluid Pressure (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及阀门试压技术领域,特别涉及一种阀门试压装置。The utility model relates to the technical field of valve pressure testing, in particular to a valve pressure testing device.
背景技术Background technique
油田使用的阀门连接方式多为法兰或卡箍连接,阀门在使用过程中会出现损坏,需要更换新的阀门或者对阀门进行修复。其中,修复之后的阀门需要按铭牌压力的1.25倍进行试压并稳压5分钟,以检验修复后的阀门的密封性是否达到要求。Most of the valves used in the oil field are connected by flanges or clamps. The valves will be damaged during use and need to be replaced with new valves or repaired. Among them, the repaired valve needs to be pressure tested at 1.25 times the nameplate pressure and stabilized for 5 minutes to check whether the leak tightness of the repaired valve meets the requirements.
目前,阀门试压通常直接在生产流程上进行阀门试压,首先将阀门安装在生产流程的管线中,然后增加压力以达到试压要求,如果阀门达到试压要求,则降低压力至正常的生产压力,若阀门未达到试压要求,则需要将阀门拆卸,重新修复之后再安装于生产流程的管线中重新进行阀门试压。At present, the valve pressure test is usually carried out directly on the production process. First, the valve is installed in the pipeline of the production process, and then the pressure is increased to meet the pressure test requirements. If the valve meets the pressure test requirements, the pressure is reduced to normal production. If the valve does not meet the pressure test requirements, the valve needs to be disassembled, repaired, and then installed in the pipeline of the production process to perform the valve pressure test again.
在实现本实用新型的过程中,设计人发现现有技术至少存在以下问题:In the process of realizing the utility model, the designer finds that the prior art has at least the following problems:
阀门试压直接在生产流程中进行试压,压力的增加会对生产带来一定的影响,并且试压压力控制困难,难以达到稳压时间的要求,同时,在生产流程上试压需要安装、拆卸阀门,增加了员工劳动强度。The valve pressure test is carried out directly in the production process. The increase in pressure will have a certain impact on production, and it is difficult to control the pressure test pressure, and it is difficult to meet the requirements of the pressure stabilization time. At the same time, the pressure test in the production process requires installation, Dismantling the valve increases the labor intensity of the staff.
实用新型内容Utility model content
为了解决现有技术的上述问题,本实用新型实施例提供了一种阀门试压装置,技术方案如下:In order to solve the above-mentioned problems in the prior art, the embodiment of the utility model provides a valve pressure test device, the technical solution is as follows:
本实用新型实施例提供一种阀门试压装置,所述装置包括:供液罐、与所述供液罐连通的供液管线和回流管线;The embodiment of the utility model provides a valve pressure test device, the device includes: a liquid supply tank, a liquid supply pipeline and a return pipeline connected with the liquid supply tank;
与所述供液管线连接的增压泵、与所述增压泵连接用于与阀门连接的试压组件;a booster pump connected to the liquid supply pipeline, and a pressure test component connected to the booster pump for connection with a valve;
所述试压组件包括用于观察压力值的压力表;The pressure test assembly includes a pressure gauge for observing the pressure value;
所述试压组件通过控制阀与所述增压泵连接;The pressure test assembly is connected to the booster pump through a control valve;
所述试压组件通过回流阀与所述回流管线连接。The pressure test assembly is connected with the return pipeline through a return valve.
具体地,所述试压组件还包括:与所述控制阀连接的试压管、与所述试压管连接的放空阀和阀门接头。Specifically, the pressure test assembly further includes: a pressure test tube connected to the control valve, a vent valve and a valve joint connected to the pressure test tube.
具体地,所述压力表以及所述回流阀均与所述试压管相连接。Specifically, both the pressure gauge and the return valve are connected to the pressure test tube.
具体地,所述试压组件、所述回流阀、所述控制阀的数量均为2个。Specifically, the number of the pressure test assembly, the return valve, and the control valve is two.
具体地,两个所述试压组件与增压泵以及供液罐之间的连接形成了并联的连接方式。Specifically, the connection between the two pressure test assemblies, the booster pump and the liquid supply tank forms a parallel connection.
具体地,所述试压组件中所述阀门接头为一个法兰式阀门接头和一个卡箍式阀门接头。Specifically, the valve joints in the pressure test assembly are a flanged valve joint and a clamped valve joint.
具体地,所述试压管通过试压管接箍以及异径接头与所述法兰式阀门接头连接。Specifically, the pressure test pipe is connected to the flanged valve joint through a pressure test pipe collar and a different diameter joint.
优选地,所述试压管为耐压管。Preferably, the pressure test tube is a pressure resistant tube.
具体地,所述增压泵的进液口通过所述供液管线与供液罐连接,所述增压泵的出液口通过所述控制阀与所述试压组件连接。Specifically, the liquid inlet of the booster pump is connected to the liquid supply tank through the liquid supply line, and the liquid outlet of the booster pump is connected to the pressure test assembly through the control valve.
优选地,所述供液罐为圆锥形罐体。Preferably, the liquid supply tank is a conical tank.
本实用新型实施例提供的技术方案带来的有益效果是:The beneficial effects brought by the technical solution provided by the embodiment of the utility model are:
通过增压泵将供液罐中的液体增压后输出,将试压组件与阀门进行连接,并使该阀门处于关闭状态,由于所述试压组件通过控制阀与所述增压泵连接,当打开控制阀时,通过增压泵输出的高压液体进入试压组件,高压液体停留在试压组件中,其压力保持在预设值,等待阀门试压所需要稳压的时间之后,通过压力表观察试压组件中的压力值是否变化,实现对阀门的试压。并且本实用新型采用单独的阀门试压装置,而不是在生产流程中进行试压,不影响生产的正常进行。The liquid in the liquid supply tank is boosted by the booster pump and then output, and the pressure test component is connected to the valve, and the valve is closed. Since the pressure test component is connected to the booster pump through the control valve, When the control valve is opened, the high-pressure liquid output by the booster pump enters the pressure test assembly, and the high-pressure liquid stays in the pressure test assembly, and its pressure remains at the preset value. Observe whether the pressure value in the pressure test assembly changes, and realize the pressure test of the valve. Moreover, the utility model adopts a separate valve pressure test device instead of carrying out pressure test in the production process, which does not affect the normal progress of production.
附图说明Description of drawings
为了更清楚地说明本实用新型实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本实用新型的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings that need to be used in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some implementations of the present invention. For example, those of ordinary skill in the art can also obtain other drawings based on these drawings on the premise of not paying creative efforts.
图1是本实用新型实施例提供的阀门试压装置结构示意图。Fig. 1 is a schematic structural diagram of a valve pressure testing device provided by an embodiment of the present invention.
其中,附图标示为:Among them, the accompanying drawings are indicated as:
1、供液罐;2、供液管线;3、回流管线;4、增压泵;6、控制阀;7、回流阀;1. Liquid supply tank; 2. Liquid supply pipeline; 3. Return pipeline; 4. Booster pump; 6. Control valve; 7. Return valve;
501、压力表;502、试压管;503、放空阀;504、阀门接头;504a、法兰式阀门接头;504b、卡箍式阀门接头;505、试压管接箍;506、异径接头;501. Pressure gauge; 502. Pressure test tube; 503. Vent valve; 504. Valve connector; 504a. Flange valve connector; 504b. Clamp valve connector; 505. Pressure test tube collar; ;
具体实施方式detailed description
为使本实用新型的目的、技术方案和优点更加清楚,下面将结合附图对本实用新型实施方式作进一步地详细描述。In order to make the purpose, technical solutions and advantages of the present utility model clearer, the implementation of the present utility model will be further described in detail below in conjunction with the accompanying drawings.
本实用新型提供一种阀门试压装置,参见图1,所述装置包括:供液罐1、与所述供液罐1连通的供液管线2和回流管线3;The utility model provides a valve pressure test device, referring to Fig. 1, the device comprises: a liquid supply tank 1, a liquid supply pipeline 2 and a return pipeline 3 connected with the liquid supply tank 1;
与所述供液管线2连接的增压泵4、与所述增压泵4连接用于与阀门连接的试压组件;A booster pump 4 connected to the liquid supply pipeline 2, and a pressure test assembly connected to the booster pump 4 for connecting with a valve;
所述试压组件包括用于观察压力值的压力表501;The pressure test assembly includes a pressure gauge 501 for observing the pressure value;
所述试压组件通过控制阀6与所述增压泵4连接;The pressure test assembly is connected to the booster pump 4 through a control valve 6;
所述试压组件通过回流阀7与所述回流管线3连接。The pressure test assembly is connected to the return line 3 through a return valve 7 .
本实用新型实施例利用增压泵4将供液罐1中的液体增压后输出,将试压组件与需要进行试压的阀门进行连接,例如将图1中示出的504a或者504b与需要进行试压的阀门进行连接,并使该阀门处于关闭状态,由于所述试压组件通过控制阀6与所述增压泵4连接,当打开控制阀6时,通过增压泵4输出的高压液体进入试压组件,由于需要进行试压的阀门处于关闭状态,高压液体不会通过该阀门流出,而停留在试压组件中,同时由于试压组件通过回流阀7与所述回流管线3连接,将回流阀7关闭,高压液体在试压组件中的压力保持在预设值,等待阀门试压所需要稳压的时间之后,通过压力表501观察试压组件中的压力值是否变化,如果压力值变化了,说明阀门密封性没有达到要求,如果压力值没有发生变化,说明阀门密封性达到要求,最后将回流阀7打开,解除试压组件中的压力,使其通过回流管线3回流到供液罐1中,实现对阀门的试压。并且本实用新型采用单独的阀门试压装置先对需要进行试压的阀门进行试压,若该阀门密封性达到了要求,则将试压合格的阀门安装到生产流程中的管线上,若该阀门密封性没有达到要求,则不能将其安装于生产流程中,需要重新对该阀门进行修复。而不是将阀门直接安装在生产流程中来进行试压,不影响生产的正常进行。In the embodiment of the present invention, the booster pump 4 is used to pressurize the liquid in the liquid supply tank 1 and output it, and the pressure test assembly is connected to the valve that needs to be tested, for example, the 504a or 504b shown in Figure 1 is connected to the valve that needs to be tested. The valve for the pressure test is connected and the valve is closed. Since the pressure test assembly is connected with the booster pump 4 through the control valve 6, when the control valve 6 is opened, the high pressure output by the booster pump 4 When the liquid enters the pressure test assembly, since the valve that needs to be tested is in a closed state, the high-pressure liquid will not flow out through the valve, but stays in the pressure test assembly, and because the pressure test assembly is connected to the return line 3 through the return valve 7 , close the return valve 7, keep the pressure of the high-pressure liquid in the pressure test assembly at the preset value, wait for the time required for the pressure stabilization of the valve pressure test, and observe whether the pressure value in the pressure test assembly changes through the pressure gauge 501, if If the pressure value changes, it means that the valve tightness does not meet the requirements. If the pressure value does not change, it means that the valve tightness meets the requirements. Finally, the return valve 7 is opened to release the pressure in the pressure test assembly, so that it can flow back through the return line 3 to In the liquid supply tank 1, the pressure test of the valve is realized. Moreover, the utility model adopts a separate valve pressure test device to test the pressure of the valve that needs to be tested first. If the sealing performance of the valve meets the requirements, the valve that has passed the pressure test is installed on the pipeline in the production process. If the sealing performance of the valve does not meet the requirements, it cannot be installed in the production process, and the valve needs to be repaired again. Instead of installing the valve directly in the production process for pressure testing, it does not affect the normal production.
具体地,继续参见图1,所述试压组件还包括:与所述控制阀6连接的试压管502、与所述试压管502连接的放空阀503和阀门接头504。并且,上述压力表501以及上述回流阀7均与试压管502相连接。由于与供液罐1连通的供液管线2为直径较小的高压钢管,通常约为15mm,而油田领域使用的阀门直径较大,通常法兰式连接的阀门直径约为200mm,卡箍连接式的阀门直径大于50mm,虽然各种型号或者厂家的阀门大小不一致,但其直径与供液管线2的直径相比则大很多,若直接将供液管线2与阀门连接存在安全隐患,因此在试压组件中设置试压管502,该试压管502的直径比供液管线2的直径大,作为一种优选方案,可以设置为65mm,保证了施工人员的安全,增压泵4输出端通过与所述供液管线2规格一致的高压管线与控制阀6连接,该试压管502通过螺纹与高压管线连接。另外,采用放空阀503与试压管502连接,将试压完的阀门取下之前,先通过回流阀7解除试压管502中的压力,为了保证安全,则通过放空阀503将试压管502中的压力完全放空,最后再将试压完的阀门取下。Specifically, referring to FIG. 1 , the pressure test assembly further includes: a pressure test tube 502 connected to the control valve 6 , a vent valve 503 and a valve joint 504 connected to the pressure test tube 502 . Moreover, both the pressure gauge 501 and the return valve 7 are connected to the pressure test tube 502 . Since the liquid supply pipeline 2 connected with the liquid supply tank 1 is a high-pressure steel pipe with a small diameter, usually about 15mm, and the valve used in the oil field has a large diameter, usually the diameter of the valve connected by the flange is about 200mm, and the clamp connection The diameter of the type valve is greater than 50mm. Although the valve sizes of various models or manufacturers are inconsistent, its diameter is much larger than that of the liquid supply pipeline 2. If the liquid supply pipeline 2 is directly connected to the valve, there will be safety hazards. Therefore, in A pressure test tube 502 is set in the pressure test assembly. The diameter of the pressure test tube 502 is larger than the diameter of the liquid supply pipeline 2. As a preferred solution, it can be set to 65 mm to ensure the safety of the construction personnel. The output port of the booster pump 4 It is connected to the control valve 6 through a high-pressure pipeline with the same specifications as the liquid supply pipeline 2, and the pressure test tube 502 is connected to the high-pressure pipeline through threads. In addition, the vent valve 503 is used to connect the pressure test tube 502. Before removing the valve after the pressure test, the pressure in the pressure test tube 502 is released through the return valve 7. In order to ensure safety, the pressure test tube is drained through the vent valve 503. The pressure in 502 is completely vented, and finally the valve after the pressure test is removed.
在上文所述的实施例中,在油田领域常使用的阀门有两种,法兰式连接的阀门和卡箍连接式的阀门,为了满足者两种不同的阀门的试压需求,所述试压组件、所述回流阀7、所述控制阀6的数量均为2个。In the above-mentioned embodiment, there are two types of valves commonly used in the oilfield field, flange-connected valves and clamp-connected valves. In order to meet the pressure test requirements of the two different valves, the The number of the pressure test assembly, the return valve 7 and the control valve 6 is two.
参见图1,两个试压组件与增压泵4以及供液罐1之间的连接形成了并联的连接方式,当试压组件为两个时,这两个试压组件中的试压管502均通过控制阀6与所述增压泵4相连接,并且这两个试压组件中的试压管502也同样地均通过回流阀7与回流管线3连接,增压泵4均可以为两个试压组件增压,两个试压组件解除压力时回流的液体均可以回流到供液罐1中。Referring to Fig. 1, the connection between the two pressure test assemblies and the booster pump 4 and the liquid supply tank 1 forms a parallel connection mode. When there are two pressure test assemblies, the pressure test tubes in the two pressure test assemblies 502 are all connected to the booster pump 4 through the control valve 6, and the pressure test tubes 502 in the two pressure test assemblies are also connected to the return line 3 through the return valve 7, and the booster pump 4 can be The two pressure test assemblies are pressurized, and the liquid returned when the pressure is released from the two pressure test assemblies can flow back into the liquid supply tank 1 .
如上文所述,设置两个试压组件时为了满足两种不同连接方式的阀门,所述试压组件中所述阀门接头504为一个法兰式阀门接头504a和一个卡箍式阀门接头504b。对于卡箍连接式的阀门,试压组件中的试压管502可以直接与卡箍式阀门接头504b连接,使用时直接将卡箍连接式的阀门与该卡箍式阀门接头504b连接即可,而对于法兰式连接的阀门,需要将所述试压管502通过试压管接箍505以及异径接头506与所述法兰式阀门接头504a连接,用于配合法兰式阀门接头504a,然后再将法兰式连接的阀门与所述法兰式阀门接头504a连接,再进行试压操作。其中试压管502、试压管接箍505、异径接头506和法兰式阀门接头504a之间的连接都可以通过螺纹连接,例如,试压管502两端带有外螺纹,试压管接箍505两端带有内螺纹,试压管502的一端可与试压管接箍505的一端相连接,其余部件连接方式雷同。As mentioned above, in order to meet the valves with two different connection modes when two pressure test assemblies are provided, the valve joint 504 in the pressure test assembly is a flange type valve joint 504a and a clamp type valve joint 504b. For clamp-connected valves, the pressure test tube 502 in the pressure test assembly can be directly connected to the clamp-type valve joint 504b. When in use, directly connect the clamp-connected valve to the clamp-type valve joint 504b. For flanged valves, the pressure test pipe 502 needs to be connected to the flanged valve joint 504a through a pressure test pipe collar 505 and a different diameter joint 506 to match the flanged valve joint 504a. Then the flanged valve is connected to the flanged valve joint 504a, and then the pressure test operation is performed. Wherein the connection between the pressure test pipe 502, the pressure test pipe collar 505, the reducing joint 506 and the flanged valve joint 504a can be connected by threads, for example, the two ends of the pressure test pipe 502 have external threads, and the pressure test pipe Both ends of the coupling 505 have internal threads, and one end of the pressure test tube 502 can be connected with one end of the pressure test tube coupling 505, and the other parts are connected in the same way.
本实用新型对阀门进行试压的具体流程为:先打开回流阀7,打开控制阀6,关闭放空阀503,启动增压泵4,然后缓慢关闭回流阀7,观察压力表501的压力值到预设的试压压力时,关闭控制阀6,稳压至规定时间,观察压力表501的压力值是否发生变化,如果压力值变化了,说明阀门密封性没有达到要求,如果压力值没有发生变化,说明阀门密封性达到要求,然后缓慢打开回流阀7,待压力表501显示压力值为0时,停止增压泵4,打开放空阀503,最后将阀门拆卸。The specific flow of the utility model for pressure testing the valve is: first open the return valve 7, open the control valve 6, close the vent valve 503, start the booster pump 4, then slowly close the return valve 7, observe the pressure value of the pressure gauge 501 to At the preset test pressure, close the control valve 6, stabilize the pressure for the specified time, and observe whether the pressure value of the pressure gauge 501 changes. If the pressure value changes, it means that the valve sealing performance does not meet the requirements. If the pressure value does not change , indicating that the valve tightness meets the requirements, then slowly open the return valve 7, and when the pressure gauge 501 shows a pressure value of 0, stop the booster pump 4, open the vent valve 503, and finally disassemble the valve.
通过采用两个试压组件的形式,其不同的阀门接头504可以满足不同的连接方式的阀门,并且,可以通过本实用新型提供的阀门试压装置来同时进行两个阀门的试压,可以将一个卡箍连接式的阀门与卡箍式阀门接头504b相连接,再将一个法兰式连接的阀门与法兰式阀门接头504a连接,若这两个需要试压的阀门所需的试压压力不一致时,则选择先试低压阀门,在对低压阀门进行试压时,需要关闭与所述低压阀门相连接的高压阀门的控制阀6和回流阀7,同样地,在对高压阀门进行试压时,需要关闭与所述高压阀门相连接的高压阀门的控制阀6和回流阀7,选择先试低压阀门是出于安全因素的考虑,通常对高压阀门进行试压所需压力是对低压阀门进行试压所需压力的10倍左右,若先对高压阀门进行试压,整个液体流通回路的压力较高,不易控制,若在整个液体流通回路还保持在较高水平时对低压阀门进行试压,一旦打开与低压阀门相连接的控制阀6,就可能会出现低压阀门不能承受液体流通回路里的压力,而损坏低压阀门。By adopting the form of two pressure test components, the different valve joints 504 can meet the valves of different connection modes, and the pressure test of two valves can be carried out at the same time through the valve pressure test device provided by the utility model, which can be A clamp-connected valve is connected to the clamp-type valve connector 504b, and then a flange-connected valve is connected to the flange-type valve connector 504a. If the pressure test pressure required by the two valves requiring pressure test When inconsistent, then choose to test the low-pressure valve first. When the low-pressure valve is tested, it is necessary to close the control valve 6 and the return valve 7 of the high-pressure valve connected to the low-pressure valve. Similarly, when the high-pressure valve is tested When it is necessary to close the control valve 6 and the return valve 7 of the high-pressure valve connected to the high-pressure valve, it is necessary to test the low-pressure valve first for safety reasons. Usually, the pressure required for the pressure test of the high-pressure valve is the same as that for the low-pressure valve. It is about 10 times the pressure required for the pressure test. If the pressure test is performed on the high-pressure valve first, the pressure of the entire liquid circulation circuit will be high and difficult to control. Once the control valve 6 connected to the low-pressure valve is opened, the low-pressure valve may not be able to bear the pressure in the liquid circulation circuit, and the low-pressure valve may be damaged.
对高压阀门的试压要求可为25Mpa,因此要求所述试压管502为耐高压管,不会在试压的过程中损坏。The pressure test requirement for high-pressure valves can be 25Mpa, so the pressure test tube 502 is required to be a high-pressure tube that will not be damaged during the pressure test.
另外,如图1所示,所述增压泵4的进液口通过所述供液管线2与供液罐1连接,所述增压泵4的出液口通过所述控制阀6与所述试压组件连接。优选地,所述供液罐1为圆锥形罐体。In addition, as shown in FIG. 1 , the liquid inlet of the booster pump 4 is connected to the liquid supply tank 1 through the liquid supply line 2 , and the liquid outlet of the booster pump 4 is connected to the liquid supply tank 1 through the control valve 6 . The above pressure test assembly connection. Preferably, the liquid supply tank 1 is a conical tank.
上述所有可选技术方案,可以采用任意结合形成本公开的可选实施例,在此不再一一赘述。All the above optional technical solutions may be combined in any way to form optional embodiments of the present disclosure, which will not be repeated here.
以上所述仅为本实用新型的较佳实施例,并不用以限制本实用新型,凡在本实用新型的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present utility model, and are not intended to limit the present utility model. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present utility model shall be included in this utility model. within the scope of protection of utility models.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201621461673.8U CN206378257U (en) | 2016-12-29 | 2016-12-29 | A valve pressure test device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201621461673.8U CN206378257U (en) | 2016-12-29 | 2016-12-29 | A valve pressure test device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206378257U true CN206378257U (en) | 2017-08-04 |
Family
ID=59408899
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201621461673.8U Active CN206378257U (en) | 2016-12-29 | 2016-12-29 | A valve pressure test device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206378257U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115814980A (en) * | 2021-09-20 | 2023-03-21 | 湖南迪宏物联科技有限公司 | Liquid diversion system, control method and device |
| CN116839818A (en) * | 2023-07-26 | 2023-10-03 | 吉林梦溪工程管理有限公司 | Pressure test monitoring system based on valve pressure test station |
-
2016
- 2016-12-29 CN CN201621461673.8U patent/CN206378257U/en active Active
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115814980A (en) * | 2021-09-20 | 2023-03-21 | 湖南迪宏物联科技有限公司 | Liquid diversion system, control method and device |
| CN116839818A (en) * | 2023-07-26 | 2023-10-03 | 吉林梦溪工程管理有限公司 | Pressure test monitoring system based on valve pressure test station |
| CN116839818B (en) * | 2023-07-26 | 2024-03-05 | 吉林梦溪工程管理有限公司 | Pressure test monitoring system based on valve pressure test station |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN210141973U (en) | Clamping device for valve pressure test | |
| CN103791238A (en) | Experimental apparatus for measuring medium leakage characteristic of fuel gas pipeline | |
| CN201765743U (en) | Chemical pipeline blocking leakage under pressure test training integrated equipment | |
| CN206019960U (en) | Lift non-return valve work seal detection means | |
| CN110031161A (en) | More specification valve pressure testing devices | |
| CN206378257U (en) | A valve pressure test device | |
| CN201974277U (en) | Air-tight testing device | |
| CN204514558U (en) | A kind of tube bundle heat exchanger quick leak-checking instrument | |
| CN103134646B (en) | The watertightness detection system of pipeline and detection method thereof | |
| CN106964612B (en) | Hydraulic pipeline oil flushing method | |
| CN203979895U (en) | A test device for the sealing effect of pipeline under pressure | |
| CN204556396U (en) | A kind of quick mounting type pressure testing device | |
| CN217926233U (en) | Portable electric pressure test pump | |
| CN218584282U (en) | Pressure and flow integrated test tool | |
| CN204716662U (en) | A kind of pressure control circuit | |
| CN202110046U (en) | Automobile shock absorber liquid storage cylinder leak test system | |
| CN205908903U (en) | Take screw ferrule in pressure release hole | |
| CN207908118U (en) | The airtight testing stand of high pressure | |
| CN204789168U (en) | Tubular product pressure testing device | |
| CN209894429U (en) | Traction converter cooling water pipe flow test tool | |
| CN208254746U (en) | Pressure test tool | |
| CN204269312U (en) | A kind of helium nitrogen gas mixing device for gases at high pressure leak detection | |
| CN210893900U (en) | Pressure device for pipeline rapid pressure test | |
| CN108051288A (en) | A kind of PE pipelines pressue device and method | |
| CN207609993U (en) | Oil-gas pipeline safety detects the medium supply apparatus of simulation system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |