CN206267299U - Radiator structure in Basement Mass Concrete process of setting - Google Patents
Radiator structure in Basement Mass Concrete process of setting Download PDFInfo
- Publication number
- CN206267299U CN206267299U CN201621313959.1U CN201621313959U CN206267299U CN 206267299 U CN206267299 U CN 206267299U CN 201621313959 U CN201621313959 U CN 201621313959U CN 206267299 U CN206267299 U CN 206267299U
- Authority
- CN
- China
- Prior art keywords
- basement
- water
- plc
- circulatory pool
- hot channel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Sewage (AREA)
Abstract
The utility model discloses the radiator structure in a kind of Basement Mass Concrete process of setting, including concrete layer, it is characterized in that:A plurality of hot channel is laid with concrete layer, stream has liquid heat eliminating medium in hot channel, hot channel is circulated by circulating pump with the liquid heat eliminating medium in the external world.The radiator structure can outwardly distribute the heat in concrete layer process of setting.
Description
Technology leads city
The utility model is related to the radiator structure in a kind of Basement Mass Concrete process of setting.
Background technology
The wall of basement is because of the extruding by surrounding soil, it is necessary to larger thickness can play support and waterproof is imitated
Really, thus the larger basement of depth concrete layer volume it is often very big, and concrete layer can be produced during solidification
The substantial amounts of heat of life, the larger concrete layer of volume is often difficult to come out heat therein, causes this kind of large volume to be mixed
Solidifying soil layer often occurs crack.
Utility model content
Technical problem to be solved in the utility model is to provide in a kind of Basement Mass Concrete process of setting
Radiator structure, the radiator structure can outwardly distribute the heat in concrete layer process of setting.
The technical scheme that the utility model is used is:Radiator structure in Basement Mass Concrete process of setting,
Including concrete layer, it is characterized in that:A plurality of hot channel is laid with concrete layer, stream has liquid to radiate and is situated between in hot channel
Matter, hot channel is circulated by circulating pump with the liquid heat eliminating medium in the external world.
The utility model has the following effects that:The method of above-mentioned radiator structure and casting concrete layer can be by concrete layer
In heat circulated by the liquid medium in hot channel and outwards distribute, the freezing period of concrete layer can be shortened, it is to avoid coagulation
Soil layer in the process of setting because heat is too high, excessively concentrate there is crack.
Below in conjunction with the accompanying drawings and specific embodiment the utility model is described in further detail.
Brief description of the drawings
The structural representation of the radiator structure in the Basement Mass Concrete process of setting that Fig. 1 is provided for the utility model
Figure.
PLC in radiator structure in the Basement Mass Concrete process of setting that Fig. 2 is provided for the utility model with
The annexation schematic diagram of temperature sensing device and each controller.
Specific embodiment
Shown in reference picture 1, the radiator structure in the Basement Mass Concrete process of setting that the utility model is provided, bag
Concrete layer 1 is included, in order to avoid the cracking of concrete layer 1 can add building fiber in concrete layer, is laid in concrete layer 1
There is a plurality of hot channel 2, stream has liquid heat eliminating medium in hot channel 2, and hot channel 2 is by circulating pump 3 and extraneous liquid
Heat eliminating medium is circulated, and extraneous liquid heat eliminating medium typically uses water, because water consumption is larger, if near water such as rivers
Source ground, is typically directly circulated with river etc..
Described in reference picture 1, in order to adapt to more geographical conditions, when construction area is in the more rich place of underground water
When, underground water as liquid heat eliminating medium, the basement underground of buildings in general can be carried sump 4, sump 4 is connected
There is upward evacuation duct 5, evacuation duct 5 is configured with the first exhaust device 6, and evacuation duct 5 is connected with sedimentation basin 7, sump 4
In underground water acted on by the first exhaust device 6 and being discharged in sedimentation basin 7 through evacuation duct 5, the top of sedimentation basin 7 carries drinking-water pipe
8, draw water end of the drinking-water pipe 8 in sedimentation basin is configured with screen pack, and drinking-water pipe 8 is configured with the second exhaust device 9, drinking-water pipe 8 with
Circulatory pool 10 is connected, and the two ends of the hot channel 2 are connected with circulatory pool 10, and the liquid heat eliminating medium is in circulatory pool 10
Water.This structure for making full use of underground water, is not only able in time by the water discharge in the sump of underground, and can be by this
Part water for radiating after the treatment such as precipitation filtering by circulating.
Shown in reference picture 1, Fig. 2, in order to temperature in time in concrete layer and the temperature of recirculated water are adjusted, with
Preferably regulate and control the setting temperature of concrete layer, the first temperature sensing device, the first temperature sense are embedded with the concrete layer 1
Answer device to be connected with PLC signals, PLC is connected with the controller of circulating pump 3, the second temperature is provided with the water body of the circulatory pool 10
Degree induction installation, when the PLC receives the temperature value that the first temperature sensing device senses and exceeds setting value, the PLC controls
Circulating pump processed 3 accelerates circulation rate, makes to drop to setting value at the temperature in concrete layer 1, so as to be more beneficial for solidification;It is described heavy
Shallow lake pond 7 is connected with reflux line 11 with circulatory pool, and reflux line 11 is configured with the 3rd exhaust device 12 and controls the valve of its keying
Door 13, valve 13 is in normally off, and the PLC is connected with the controller of the 3rd exhaust device 12 and valve 13, and the PLC is received
When exceeding setting value to the temperature value that second temperature induction installation is sensed, now the coolant-temperature gage of circulatory pool 10 has been unfavorable for dissipating
Thermal cycle, PLC control valves 13 are opened, while control the 3rd exhaust device 12 that the water in circulatory pool 10 is pumped into sedimentation basin 7,
The water in sedimentation basin 7 is also carried out circulation with the water in circulatory pool 10, the water energy in circulatory pool 10 is accessed cooling, be beneficial to
Radiating circulation.
Shown in reference picture 1, Fig. 2, the utility model is additionally provided using above-mentioned Basement Mass Concrete process of setting
In the radiator structure method that pours Basement Mass Concrete, comprise the following steps:
A, template is set up, set up hot channel 2, by the liquid heat eliminating medium company in hot channel 2 and circulating pump 3 and the external world
Connect;
After B, casting concrete layer 1, open the circulation pump 3 makes liquid of the liquid heat eliminating medium in hot channel 2 and the external world be situated between
Circulated between matter storage, reduce the temperature in concrete layer 1, until concrete layer 1 completes solidification;
C, the concrete layer 1 are poured after finishing, and cement mortar is injected to hot channel 2.Can also portion to hot channel 2
Injection cement mortar, strength enhancing is conducive to after certain cement injection mortar.
In above-mentioned steps B, the basement underground carries sump 4, and sump 4 is connected with upward evacuation duct 5,
Evacuation duct 5 is configured with the first exhaust device 6, and evacuation duct 5 is connected with sedimentation basin 7, and the underground water in sump 4 is taken out by first
Arranging device 6 is acted on and is discharged in sedimentation basin 7 through evacuation duct 5, and the top of sedimentation basin 7 carries drinking-water pipe 8, and drinking-water pipe 8 is in sedimentation basin 7
In end of drawing water be configured with screen pack, drinking-water pipe 8 is configured with the second exhaust device 9, and drinking-water pipe 8 is connected with circulatory pool 10, described
The two ends of hot channel 2 are connected with circulatory pool 10, and the liquid heat eliminating medium is the water in circulatory pool 10, the circulatory pool 10
Water is extracted from the sedimentation basin 7 using the second exhaust device 9, circulating pump 3 is carried out to hot channel 2 with the water in circulatory pool 10
Circulation.
Claims (4)
1. a kind of radiator structure in Basement Mass Concrete process of setting, including concrete layer, it is characterized in that:Concrete
A plurality of hot channel is laid with layer, stream has liquid heat eliminating medium in hot channel, and hot channel is by circulating pump and the external world
Liquid heat eliminating medium is circulated.
2. Basement Mass Concrete pouring structure according to claim 1, it is characterized in that:Basement ground lower band
There is sump, sump is connected with upward evacuation duct, and evacuation duct is configured with the first exhaust device, evacuation duct and precipitation
Pond is connected, and the underground water in sump is discharged in sedimentation basin by exhaust device effect through the first evacuation duct, the top of sedimentation basin
With drinking-water pipe, draw water end of the drinking-water pipe in sedimentation basin is configured with screen pack, and drinking-water pipe is configured with the second exhaust device, draws water
Pipe is connected with circulatory pool, and the two ends of the hot channel are connected with circulatory pool, and the liquid heat eliminating medium is in circulatory pool
Water.
3. Basement Mass Concrete pouring structure according to claim 2, it is characterized in that:Buried in the concrete layer
The first temperature sensing device is provided with, the first temperature sensing device is connected with PLC signals, and PLC is connected with the controller of circulating pump, institute
Second temperature induction installation is provided with the water body for stating circulatory pool, the PLC receives what the first temperature sensing device was sensed
When temperature value exceeds setting value, the PLC controls circulating pump accelerates circulation rate;The sedimentation basin is connected with backflow with circulatory pool
Pipeline, reflux line be configured with the 3rd exhaust device and control its open and close valve, valve be in normally off, the PLC with
The controller connection of the 3rd exhaust device and valve, the PLC receives the temperature value that second temperature induction installation senses and exceeds
During setting value, the PLC control valves are opened, while controlling the 3rd exhaust device that the water in circulatory pool is pumped into sedimentation basin.
4. the radiator structure in the Basement Mass Concrete process of setting according to claim 1 or 2 or 3, its feature
It is:Being added in the concrete layer has concrete fiber.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621313959.1U CN206267299U (en) | 2016-12-02 | 2016-12-02 | Radiator structure in Basement Mass Concrete process of setting |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621313959.1U CN206267299U (en) | 2016-12-02 | 2016-12-02 | Radiator structure in Basement Mass Concrete process of setting |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206267299U true CN206267299U (en) | 2017-06-20 |
Family
ID=59042551
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621313959.1U Active CN206267299U (en) | 2016-12-02 | 2016-12-02 | Radiator structure in Basement Mass Concrete process of setting |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206267299U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106480981A (en) * | 2016-12-02 | 2017-03-08 | 温州中海建设有限公司 | Radiator structure in Basement Mass Concrete process of setting and the method pouring Basement Mass Concrete |
-
2016
- 2016-12-02 CN CN201621313959.1U patent/CN206267299U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106480981A (en) * | 2016-12-02 | 2017-03-08 | 温州中海建设有限公司 | Radiator structure in Basement Mass Concrete process of setting and the method pouring Basement Mass Concrete |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104018673B (en) | Ultra-large volume concrete one-time continuous pours into a mould multi cycle real-time temperature control construction technology | |
CN203616679U (en) | Cooling water circulating control device for mass concrete | |
CN103940151B (en) | A kind of method that combined-type ground source heat pump and water resource heat pump recharge | |
CN105256998B (en) | A kind of automatic maintenance method of on-site concrete vertical structure cycling use of water | |
CN206801032U (en) | A kind of mass concrete cracking-proof system | |
CN106480981A (en) | Radiator structure in Basement Mass Concrete process of setting and the method pouring Basement Mass Concrete | |
CN209228030U (en) | It is a kind of for pouring the temperature control template component of massive concrete walls body | |
CN102756423A (en) | Maintenance device and maintenance method for prestressed centrifugal concrete hollow square pile water maintenance pile | |
CN206267299U (en) | Radiator structure in Basement Mass Concrete process of setting | |
CN204691287U (en) | A kind of Temperature Controlling of Mass Concrete system | |
CN210238549U (en) | Full-automatic water circulation temperature control device for pile foundation construction in frozen soil area | |
CN109235441A (en) | A kind of temperature automatically controlled technique of the circulation fluid of mass concrete construction | |
CN206053349U (en) | For the cooling system of xoncrete structure | |
CN206396771U (en) | Building basement ground construction conserves discharge structure | |
CN208072434U (en) | Subway foundation pit dewatering well vacuum system | |
CN207727854U (en) | Board house of the construction site with cooling water circulation device | |
CN111350362A (en) | Large-volume concrete circulating water cooling construction method | |
CN107010993B (en) | Cooling system for mass concrete | |
CN216586626U (en) | Basement post-cast strip drainage system | |
CN106142315A (en) | Assembling die conduction oil maintenance technology | |
CN106703057A (en) | Basement ground construction maintenance drainage structure of large building and method for constructing basement concrete layer | |
CN208375547U (en) | A kind of apparatus for concrete member curing device | |
CN206071834U (en) | A kind of Lime Factory air compressor machine circulating water cooling device | |
CN115538442A (en) | Construction method of concrete bottom plate | |
CN206581978U (en) | A kind of tunnel water handling integrated system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: 325000 Room 101, 832 Gaotong Road, Panqiao Street, Ouhai District, Wenzhou City, Zhejiang Province Patentee after: ZHEJIANG ZHENGLI HIGH TECHNOLOGY CONSTRUCTION CO., LTD. Address before: 325000 Great Wall Group, Jingshan Street, Ouhai District, Wenzhou City, Zhejiang Province, Room 301-310 Patentee before: Wenzhou Zhonghai Construction Co., Ltd. |