CN206267033U - A kind of Hanging Basket prepressing device - Google Patents

A kind of Hanging Basket prepressing device Download PDF

Info

Publication number
CN206267033U
CN206267033U CN201621352800.0U CN201621352800U CN206267033U CN 206267033 U CN206267033 U CN 206267033U CN 201621352800 U CN201621352800 U CN 201621352800U CN 206267033 U CN206267033 U CN 206267033U
Authority
CN
China
Prior art keywords
hanging basket
steel plate
bar
horizon bar
prepressing device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621352800.0U
Other languages
Chinese (zh)
Inventor
饶彪
李旭
范正才
李敏
薛连
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming Railway Construction Co Ltd Of Zhong Tiebaju Group
Kunming Railway Construction Co of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Kunming Railway Construction Co Ltd Of Zhong Tiebaju Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming Railway Construction Co Ltd Of Zhong Tiebaju Group filed Critical Kunming Railway Construction Co Ltd Of Zhong Tiebaju Group
Priority to CN201621352800.0U priority Critical patent/CN206267033U/en
Application granted granted Critical
Publication of CN206267033U publication Critical patent/CN206267033U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of Hanging Basket prepressing device, belong to technical field of bridge construction, including Hanging Basket, in 0# sections termination, correspondence per pass web is provided with pre-embedded steel slab, pre-embedded steel slab is made up of upper and lower corresponding upper steel plate and lower steel plate, on lower steel plate the vertical bridge of welding one to horizon bar, a hound is welded on upper steel plate and three-legged structure is formed by welding with horizon bar;Horizontal, vertical bridge is installed on Hanging Basket bottom girder to distribution beam, in every Pin hanging basket main truss correspondence web position, very heavy horizon bar and the vertical bridge of peaking at is installed between distribution beam.The utility model precompressed is simple to operate, safe, and work efficiency is high, economy is convenient.

Description

A kind of Hanging Basket prepressing device
Technical field
The utility model belongs to technical field of bridge construction.
Background technology
In technical field of bridge construction, cantilever pouring realizes that sections pours case by the use of Hanging Basket system as support and template system Beam pouring construction, the precompressed elastic settlement value of hanging basket main truss is to determine the significant data of section box girder mould absolute altitude, direct shadow Sound arrives into the linear quality of bridge, therefore must carry out precompressed acquisition elastic settlement value to Hanging Basket after Hanging Basket installation.
Precompressed for Hanging Basket before coming into operation, current way has sandbag method, reinforcing bar accumulation load method and adopting water tank method.Tool Gymnastics is made to be to lift sandbag or preloading reinforcing bar on the end template of Hanging Basket, or one group of water tank of preloading, then according to design requirement Progressively load and unload, to eliminate inelastic deformation, and measure the elastic deformation amount of Hanging Basket, this way is primarily present following asking Topic:
1st, the experiment preparation time is big compared with long, loading difficulty, preloading height is high, relatively costly;
2nd, being limited to and close on existing line by place is influenceed, and high to site requirements, crane operation is extremely difficult, construction operation Difficulty is big;
3rd, work high above the ground, heap loading height is high, and squeeze time is long, there is security risk very high.
For T structure box girder cantilever sections it is larger, bridge pier is higher in the case of, the piling prepressing workload of prior art is big, heap Load process and uninstall process time are more long, and preloading and uninstall process security risk are high, are unfavorable for that the duration ensures.
For the problem of conventional prestressing technology, prior art proposes some improvement projects:
China Patent No.:201120053596.3, the utility model discloses a kind of cantilever casting prepressing system of hanging basket, its It is characterized in, for the Hanging Basket being fixed on by cantilever in the beam body for having poured, anchor ingot to be fixedly installed below Hanging Basket, in Hanging Basket Bed die and anchor ingot between the prepressing units being made up of hydraulic jack and vertical lacing wire are set.The utility model system is substituted The pre-pressing system that useful sandbag, reinforcing bar or water tank are implemented, its loading and discharge time are short, simple to operate, without the long period Prepare, experiment is easy to be quick;Miscellaneous equipment need not be put into, experimentation cost is low, hydraulic jack precompressed loading force is accurate and easily-controllable System.
China Patent No.:201220423823.1, the utility model is related to field of bridge construction, and specially a kind of cantilever is poured Build construction hanging basket prepressing device, solve existing Hanging Basket precompressed institute and have that complex procedures, site requirements be high, difficulty of construction using method The problems such as big and security risk is high, including extend through and be arranged on main truss cradle crossbeam and positioned at two main truss cradles Hydraulic jack is installed in the back-pressure fining twisted steel suspension rod of both sides, back-pressure fining twisted steel suspension rod upper end, and top penetrates hydraulic pressure thousand Jin top axle center punching duct and with screw cap anchoring, lower end is embedded in cantilever continuous beam two grades of cushion caps of main pier, is externally provided with protection Sleeve pipe, back-pressure fining twisted steel downrod lower end end is welded with backing plate.It is simple structure, reasonable in design, solve traditional Hanging Basket pre- The drawbacks of pressure, save working space, it is to avoid using the complicated procedures of forming and potential safety hazard of piling prepressing, improve work effect Rate, it is ensured that the safe mass of construction, reduces construction cost, accelerates project progress.
Although prior art is improved to a certain extent, prior art still suffers from structure, complex operation, efficiency The problem of low and high cost.
Utility model content
The purpose of this utility model is:A kind of Hanging Basket prepressing device is proposed, precompressed is simple to operate, safe, work efficiency It is high, economical convenient.
The utility model purpose is realized by following technical proposals:
A kind of Hanging Basket prepressing device, including Hanging Basket, in construction of bridge T structure beam 0# sections termination, correspondence per pass web is provided with pre-buried steel Plate, pre-embedded steel slab is fixed by anchor bar and finish rolling deformed bar, and anchor bar is relatively short and is weldingly fixed on pre-buried steel Plate inner side, finish rolling deformed bar is relatively long and is fastened on pre-embedded steel slab outside by nut;Pre-embedded steel slab is by corresponding up and down Upper steel plate and lower steel plate are constituted, welded on lower steel plate a vertical bridge to horizon bar, a hound and and water are welded on upper steel plate Flat bar is formed by welding three-legged structure;Horizontal, vertical bridge is installed on Hanging Basket bottom girder to distribution beam, in every Pin hanging basket main truss correspondence Web position, is provided with very heavy horizon bar and the vertical bridge of peaking between distribution beam, and jack position correspondence hound and level At bar node.
Alternatively, horizon bar and hound are welded to form by double joint I-steel make-up.
Alternatively, horizon bar and hound into 26.5 degree of angles.
Alternatively, one piece of reinforcement is welded below the horizon bar of hound jack position corresponding with horizontal bar node Steel plate.
Alternatively, lower steel plate bottom is not less than 1.3m, upper lower steel plate spacing 3m away from box beam base plate bottom distance.
The foregoing main scheme of the utility model and its each further selection scheme can be with independent assortments to form multiple schemes, For the utility model can be used and claimed scheme;And the utility model, (each non conflicting selection) selection between and and Can also independent assortment between other selections.Those skilled in the art after the utility model scheme is understood according to prior art and Common knowledge can understand there is multiple combination, be the claimed technical scheme of the utility model, and exhaustion is not done herein.
The course of work is:This patent is by the way that in 0# sections termination web pre-embedded steel slab, weld horizontal bar and hound are upper Counter-force fulcrum, is lower counter-force to distribution beam using Hanging Basket bed die skeleton platform (Hanging Basket bottom girder) and horizontal, the vertical bridge installed thereon Fulcrum, very heavy to peak at loading precompressed Hanging Basket between upper and lower counter-force fulcrum, quick with loading and unloading, security and economy are obvious The characteristics of.Wherein, the embedding pattern of pre-embedded steel slab, is combined mode and effectively improves 0# using fining twisted steel and anchor bar Sections web end stress so that the fulcrum preloading structure of counter-force up and down in this patent using simple triangle skeleton is able into Work(, prepressing structure is formed without supporting constructions such as complicated anchor cable, suspension rods.
The beneficial effects of the utility model:The utility model greatly reduces the workload of precompressed, preferably improves and apply Work operation intensity, improves security risk, embodies excellent economy.
Brief description of the drawings
Fig. 1 is the use state apparatus structure schematic diagram of the utility model embodiment;
Fig. 2 is pre-embedded steel slab, horizon bar and the hound arrangement schematic diagram of the embodiment of the present invention;
Fig. 3 is pre-embedded steel slab, horizon bar and the hound mounting structure schematic diagram of the embodiment of the present invention;
Wherein 1, horizon bar 2, hound 3, upper steel plate 4, finish rolling deformed bar 5, jack 6, vertical bridge are to distribution beam 7th, direction across bridge distribution beam 8, lower steel plate 9, Hanging Basket bottom girder 10, anchor bar 11, hanging basket main truss 12, construction of bridge T structure beam 0# Sections.
Specific embodiment
Following non-limiting examples are used to illustrate the utility model.
With reference to shown in Fig. 1-3, a kind of Hanging Basket prepressing device, including Hanging Basket, in the termination of construction of bridge T structure beam 0# sections 12, correspondence is every Road web is provided with pre-embedded steel slab, and pre-embedded steel slab is made up of upper and lower corresponding upper steel plate 3 and lower steel plate 8, and upper and lower steel plate 3,8 leads to Cross anchor bar 10 and finish rolling deformed bar 4 is fixed, anchor bar 10 is relatively short and is weldingly fixed in upper and lower steel plate 3,8 Side, finish rolling deformed bar 4 is relatively long and is fastened on the outside of upper and lower steel plate 3,8 by nut;The vertical bridge of welding one on lower steel plate 8 To horizon bar 1, welded on upper steel plate 3 and a hound 2 and be formed by welding three-legged structure with horizon bar 1;In Hanging Basket bottom girder 9 On horizontal, vertical bridge is installed to distribution beam 7,6, in the corresponding web position of every Pin hanging basket main truss 11, jack 5 is installed in level Bar 1 and vertical bridge are between distribution beam 6, and (hound 2 and level at the position of jack 5 correspondence hound 2 and the node of horizon bar 1 Bar 1 is welded and fixed place, it is illustrated that in be located at the middle part of horizon bar 1 and keep right position).Alternatively, as shown in this embodiment, horizon bar 1 It is formed by welding by double joint I40a make-ups, hound 2 is formed by welding by double joint I40a make-ups, the thickness of upper and lower steel plate 3,8 20mm, finish rolling Spiral 4 is Φ 25mm, and it is I40b to indulge bridge to distribution beam 6, and direction across bridge distribution beam 7 is I40b.The bottom of lower steel plate 8 is away from box beam base plate Bottom distance is not less than 1.3m, upper and lower steel plate 3,8 spacing 3m, horizon bar 1 and 2 one-tenth of hound, 26.5 degree angles, in hound 2 and One piece of reinforcement steel plate (not shown) of the lower section of horizon bar 1 welding of correspondence jack 5 position at the node of horizon bar 1.
The preloading method of foregoing Hanging Basket prepressing device, comprises the following steps successively:
The first step, correspondence per pass web installs pre-embedded steel slab (upper and lower steel plate 3,8) before construction of bridge T structure beam 0# sections 12 is poured With anchor bar 10 and finish rolling deformed bar 4;
Second step, tightens the nut of finish rolling deformed bar 4, and the horizon bar 1 and hound 2 that will be processed are lifted and pre-embedded steel slab (upper and lower steel plate 3,8) is welded;
3rd step, installs horizontal, vertical bridge to distribution beam 7,6 on Hanging Basket bottom girder 9;
4th step, in the corresponding web position of every Pin hanging basket main truss 11, install jack 5 in horizon bar 1 and vertical bridge to point With between beam 6;
5th step, connects the pipeline between jack 5 and oil pump and debugs, hierarchical loading precompressed Hanging Basket;
6th step, precompressed terminates, and removes jack 5 and cuts off horizon bar 1 and hound 2.
Preferred embodiment of the present utility model is the foregoing is only, is not used to limit the utility model, it is all at this Any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (5)

1. a kind of Hanging Basket prepressing device, including Hanging Basket, it is characterised in that:In construction of bridge T structure beam 0# sections termination correspondence per pass web Pre-embedded steel slab is provided with, pre-embedded steel slab is fixed by anchor bar and finish rolling deformed bar, anchor bar is relatively short and welds solid Pre-embedded steel slab inner side is scheduled on, finish rolling deformed bar is relatively long and is fastened on pre-embedded steel slab outside by nut;Pre-embedded steel slab by Upper and lower corresponding upper steel plate and lower steel plate composition, welded on lower steel plate a vertical bridge to horizon bar, one is welded on upper steel plate tiltedly Strut is simultaneously formed by welding three-legged structure with horizon bar;Horizontal, vertical bridge is installed on Hanging Basket bottom girder to distribution beam, in every Pin Hanging Baskets Main couple correspondence web position, is provided with very heavy horizon bar and the vertical bridge of peaking between distribution beam, and jack position correspondence is oblique At strut and horizontal bar node.
2. Hanging Basket prepressing device as claimed in claim 1, it is characterised in that:Horizon bar and hound are by double joint I-steel pair Button is welded to form.
3. Hanging Basket prepressing device as claimed in claim 1, it is characterised in that:Horizon bar and hound into 26.5 degree of angles.
4. Hanging Basket prepressing device as claimed in claim 1, it is characterised in that:It is corresponding very heavy with horizontal bar node in hound Push up one block of reinforcement steel plate of horizon bar lower section welding of position.
5. Hanging Basket prepressing device as claimed in claim 1, it is characterised in that:Lower steel plate bottom is not less than away from box beam base plate bottom distance 1.3m, upper lower steel plate spacing 3m.
CN201621352800.0U 2016-12-09 2016-12-09 A kind of Hanging Basket prepressing device Active CN206267033U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621352800.0U CN206267033U (en) 2016-12-09 2016-12-09 A kind of Hanging Basket prepressing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621352800.0U CN206267033U (en) 2016-12-09 2016-12-09 A kind of Hanging Basket prepressing device

Publications (1)

Publication Number Publication Date
CN206267033U true CN206267033U (en) 2017-06-20

Family

ID=59044160

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621352800.0U Active CN206267033U (en) 2016-12-09 2016-12-09 A kind of Hanging Basket prepressing device

Country Status (1)

Country Link
CN (1) CN206267033U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106702906A (en) * 2016-12-09 2017-05-24 中铁八局集团昆明铁路建设有限公司 Pre-pressing device for hanging baskets and pre-pressing method thereof
CN109371846A (en) * 2018-11-28 2019-02-22 中交第二航务工程局有限公司 A kind of assembled Multifunction side is across cast-in-place support and its construction method
CN111764307A (en) * 2020-08-06 2020-10-13 中国建筑一局(集团)有限公司 Reaction frame structure and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106702906A (en) * 2016-12-09 2017-05-24 中铁八局集团昆明铁路建设有限公司 Pre-pressing device for hanging baskets and pre-pressing method thereof
CN109371846A (en) * 2018-11-28 2019-02-22 中交第二航务工程局有限公司 A kind of assembled Multifunction side is across cast-in-place support and its construction method
CN111764307A (en) * 2020-08-06 2020-10-13 中国建筑一局(集团)有限公司 Reaction frame structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN106702906A (en) Pre-pressing device for hanging baskets and pre-pressing method thereof
CN206267033U (en) A kind of Hanging Basket prepressing device
CN203546626U (en) Suspender replacing device for concrete-filled steel tube arch bridge
CN103882813B (en) For calf support platform and the building method thereof of bridge pier and straining beam synchronous construction
CN201574359U (en) Hanging basket equivalent preloading device used in high-pier large-span bridge construction
CN104695336B (en) The double-deck first up and then down stand construction method of Cast-in-situ Beam
CN205604088U (en) But bent cap quick adjustment support
CN204849607U (en) A continuous beam string basket pre -compaction device for bridge construction
CN203096598U (en) Outer cladding type steel-concrete combined structure beam bridge overturn-resistant device
CN103952982B (en) Bridge box and beam Hanging Basket anchorage rod-pulling type jack prepressing device and preloading method
CN110359374A (en) A kind of Hanging Basket precompressed counter-force bracket and its construction method
CN104831639B (en) A kind of ultra-wide nonprismatic continuous beam 0# block consolidation and releasing construction method
CN204589822U (en) The two cantilever bent cap anchor ear Construction Support system of a kind of solely post
CN110485264A (en) A kind of center pier great cantilever bent cap and its construction method
CN205223871U (en) Suspension bridge bridge tower overarm brace pre -compaction device
CN202830785U (en) High pier bridge cantilever casting concrete 0 # block pier top bracket
CN104846750B (en) A kind of prestressing force friction-type thick pillar beam support and change method with seam
CN209194353U (en) It is a kind of to ride integral type bracket suitable for the construction of Bridge High-pier 0# block
CN204080649U (en) The supporting shelf bracket of a kind of cantilever bridge No. 0 block
CN104233961B (en) A kind of supporting shelf bracket of No. 0 block of cantilever bridge
CN108547226B (en) Tower column support for determining cable-free zone of inclined tower of cable-stayed bridge
CN206607506U (en) A kind of through type adds the capping construction support of passive stress trapezoid block
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN205116231U (en) Independent strutting arrangement in basement post -cast strip
CN110939261A (en) Disc-buckle type double-row outer scaffold cantilever structure and construction method thereof