Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621309403.5U
Other languages
Chinese (zh)
Inventor
孟志强
石志祥
马家亮
闫珊珊
张旭
曲学峰
杨珍
高政
朱巧芬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei University of Engineering
Original Assignee
Hebei University of Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei University of Engineering filed Critical Hebei University of Engineering
Priority to CN201621309403.5U priority Critical patent/CN206246131U/en
Application granted granted Critical
Publication of CN206246131U publication Critical patent/CN206246131U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses prefabricated steel supporting construction in a kind of tunnel, including tunnel matrix, concrete ejection basic unit is provided with tunnel matrix inwall, silica gel waterproof layer is provided with the inwall of concrete ejection basic unit, fine sand layer is provided with silica gel waterproof layer inwall, prefabricated steel is provided with fine sand layer inwall, internal layer of silica gel is provided with the inner surface of prefabricated steel, be provided with inner concrete injection basic unit in internal layer of silica gel on wall;It is provided with some segmental arcs I being uniformly arranged and some segmental arcs II being uniformly arranged, segmental arc I and the interval setting of segmental arc II in the prefabricated steel, the arc opening of segmental arc I and segmental arc II is in opposite direction;Some stators are provided with the inner surface of the prefabricated steel.The drawbacks of overcoming prior art the utility model has the advantage of it, reasonable in design is novel.

Description

Prefabricated steel supporting construction in a kind of tunnel
Technical field
The utility model is related to prefabricated steel supporting construction in a kind of tunnel, belongs to field of civil engineering.
Background technology
Tunnel is the engineering works being embedded in stratum, is a kind of form of human use's underground space.Tunnel can divide It is traffic tunnel, Hydraulic Tunnel, municipal tunnel, mining tunnel.The tunnel that Organisation for Economic Co-operation and Development in 1970 is held Meeting combines various factors, is to tunnel definition:" act on any method regulation shape with certain purposes, in subsurface Cavern of the basal area more than 2 ㎡ that shape and size are built." with China's expanding economy and the expansion of infrastructure construction scale Greatly, Tunnel Engineering has turned into the important engineering in the mega projects such as highway, railway, municipal administration;And due to surrounding enviroment, geology bar Part is limited, or in order to better meet the growing magnitude of traffic flow, transportation condition, or to pursue the spacious effect of large space Really, the tunnel of shallow buried covered excavation big cross section form is increasing, and in construction, due to the influence of tunnel matrix, it is propped up in these tunnels When support structure is not enough, the service life in tunnel and support strength be difficult to reach requirement.
Utility model content
In view of the shortcomings of the prior art, technical problem to be solved in the utility model is to provide in a kind of tunnel Prefabricated steel supporting construction, support effect is good, improves the service life in tunnel.
In order to solve the above technical problems, the utility model is adopted the technical scheme that, prefabricated steel support in a kind of tunnel Structure, including tunnel matrix, are provided with concrete ejection basic unit on tunnel matrix inwall, set on the inwall of concrete ejection basic unit Silica gel waterproof layer is equipped with, fine sand layer is provided with silica gel waterproof layer inwall, prefabricated steel, pre-manufactured steel are provided with fine sand layer inwall Internal layer of silica gel is provided with the inner surface of plate, inner concrete injection basic unit is provided with internal layer of silica gel on wall;It is described pre- Some segmental arcs I being uniformly arranged and some segmental arcs II being uniformly arranged, segmental arc I and segmental arc II are provided with steel plate processed The arc opening of interval setting, segmental arc I and segmental arc II is in opposite direction;It is provided with the inner surface of the prefabricated steel some Stator, is fixedly connected with anchor pole on stator, anchor pole passes through prefabricated steel, fine sand layer, silica gel waterproof layer, concrete ejection base The tail end of anchor pole is arranged at tunnel Medium Culture after layer.
Optimization, prefabricated steel supporting construction in above-mentioned tunnel is provided with some nylon wires, Buddhist nun in the silica gel waterproof layer Some nylon balls are provided with imperial line.
Optimization, prefabricated steel supporting construction in above-mentioned tunnel is provided with some hangnails on the anchor pole.
Optimization, prefabricated steel supporting construction in above-mentioned tunnel is provided with steel pipe in the inner concrete injection basic unit Support.
The drawbacks of overcoming prior art the utility model has the advantage of it, reasonable in design is novel.The application's Design by the support of prefabricated steel, improve the support force of support of tunnel structure.When tunnel matrix deforms and has influence on After concrete ejection basic unit deforms it, to fine sand layer, fine sand layer serves to buffer to be made the displacement transfer of concrete ejection basic unit With, the shape of fine sand layer is sexually revised by the flowing of fine sand to adapt to the deformation of concrete ejection basic unit, but it is thin during this Layer of sand can produce larger internal stress on certain section, and the upper of prefabricated steel is provided with segmental arc I and segmental arc II, when fine sand layer office When portion's internal stress changes, the internal stress of fine sand layer is put aside by the elastic deformation of segmental arc I and segmental arc II, prevent it to be transferred to In inner concrete injection basic unit, prevent inner concrete from spraying basic unit and deform and crackle.Between segmental arc I and segmental arc II Every setting, the arc opening of segmental arc I and segmental arc II is in opposite direction, so can be different by segmental arc I and segmental arc II The elastic deformation in the direction planted agent force direction complicated to adapt to fine sand layer.Anchor pole can fix the position of prefabricated steel, prevent it There is position skew because of elastic deformation, influence the support in tunnel.Some nylon wires are provided with silica gel waterproof layer, silicon is increased The tensile capacity of glue waterproof layer, the setting of nylon ball causes nylon wire and silica gel waterproof layer internal friction, improve nylon wire for The supporting function of silica gel waterproof layer.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is stator of the present utility model and anchor structure schematic diagram;
In figure:1 is tunnel matrix, 2 is concrete ejection basic unit, 3 is silica gel waterproof layer, 4 is nylon wire, 5 is nylon ball, 6 it is fine sand layer, 7 be prefabricated steel, 8 be internal layer of silica gel, 9 be inner concrete injection basic unit, 10 is that segmental arc I, 11 is arc Shape section II, 12 is stator, 13 is anchor pole, 14 is steel pipe support.
Specific embodiment
Technical characterstic of the invention is expanded on further with specific embodiment below in conjunction with the accompanying drawings.
The utility model is prefabricated steel supporting construction in a kind of tunnel, including tunnel matrix sets on tunnel matrix inwall Concrete ejection basic unit is equipped with, silica gel waterproof layer is provided with the inwall of concrete ejection basic unit, set on silica gel waterproof layer inwall Fine sand layer is equipped with, prefabricated steel is provided with fine sand layer inwall, internal layer of silica gel is provided with the inner surface of prefabricated steel, it is internal Inner concrete injection basic unit is provided with layer of silica gel on wall;Some segmental arcs being uniformly arranged are provided with the prefabricated steel I and some segmental arcs II being uniformly arranged, segmental arc I and the interval setting of segmental arc II, the arc of segmental arc I and segmental arc II is opened Mouth is in opposite direction;Some stators are provided with the inner surface of the prefabricated steel, anchor pole, anchor pole are fixedly connected with stator The tail end of anchor pole is arranged at tunnel Medium Culture after through prefabricated steel, fine sand layer, silica gel waterproof layer, concrete ejection basic unit.Institute State and some nylon wires are provided with silica gel waterproof layer, some nylon balls are provided with nylon wire.It is provided with the anchor pole some Hangnail.Steel pipe support is provided with the inner concrete injection basic unit.
The drawbacks of overcoming prior art the utility model has the advantage of it, reasonable in design is novel.The application's Design by the support of prefabricated steel, improve the support force of support of tunnel structure.When tunnel matrix deforms and has influence on After concrete ejection basic unit deforms it, to fine sand layer, fine sand layer serves to buffer to be made the displacement transfer of concrete ejection basic unit With, the shape of fine sand layer is sexually revised by the flowing of fine sand to adapt to the deformation of concrete ejection basic unit, but it is thin during this Layer of sand can produce larger internal stress on certain section, and the upper of prefabricated steel is provided with segmental arc I and segmental arc II, when fine sand layer office When portion's internal stress changes, the internal stress of fine sand layer is put aside by the elastic deformation of segmental arc I and segmental arc II, prevent it to be transferred to In inner concrete injection basic unit, prevent inner concrete from spraying basic unit and deform and crackle.Between segmental arc I and segmental arc II Every setting, the arc opening of segmental arc I and segmental arc II is in opposite direction, so can be different by segmental arc I and segmental arc II The elastic deformation in the direction planted agent force direction complicated to adapt to fine sand layer.Anchor pole can fix the position of prefabricated steel, prevent it There is position skew because of elastic deformation, influence the support in tunnel.Some nylon wires are provided with silica gel waterproof layer, silicon is increased The tensile capacity of glue waterproof layer, the setting of nylon ball causes nylon wire and silica gel waterproof layer internal friction, improve nylon wire for The supporting function of silica gel waterproof layer.
Certainly, described above is not that, to limitation of the present utility model, the utility model is also not limited to the example above, this The those of ordinary skill of technical field, in essential scope of the present utility model, change, remodeling, addition or the replacement made, all Protection domain of the present utility model should be belonged to.

Claims (4)

1. prefabricated steel supporting construction in a kind of tunnel, it is characterised in that:Including tunnel matrix, it is provided with tunnel matrix inwall Concrete ejection basic unit, is provided with silica gel waterproof layer on the inwall of concrete ejection basic unit, be provided with silica gel waterproof layer inwall Fine sand layer, is provided with prefabricated steel on fine sand layer inwall, internal layer of silica gel, internal silica gel are provided with the inner surface of prefabricated steel Inner concrete injection basic unit is provided with layer on wall;Some Hes of segmental arc I being uniformly arranged are provided with the prefabricated steel The arc opening of some segmental arcs II being uniformly arranged, segmental arc I and the interval setting of segmental arc II, segmental arc I and segmental arc II In the opposite direction;Some stators are provided with the inner surface of the prefabricated steel, anchor pole is fixedly connected with stator, anchor pole is worn The tail end for crossing anchor pole after prefabricated steel, fine sand layer, silica gel waterproof layer, concrete ejection basic unit is arranged at tunnel Medium Culture.
2. prefabricated steel supporting construction in tunnel according to claim 1, it is characterised in that:Set in the silica gel waterproof layer Some nylon wires are equipped with, some nylon balls are provided with nylon wire.
3. prefabricated steel supporting construction in tunnel according to claim 1, it is characterised in that:If being provided with the anchor pole Dry hangnail.
4. prefabricated steel supporting construction in tunnel according to claim 1, it is characterised in that:The inner concrete injection Steel pipe support is provided with basic unit.
CN201621309403.5U 2016-12-01 2016-12-01 Prefabricated steel supporting construction in a kind of tunnel Withdrawn - After Issue CN206246131U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621309403.5U CN206246131U (en) 2016-12-01 2016-12-01 Prefabricated steel supporting construction in a kind of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621309403.5U CN206246131U (en) 2016-12-01 2016-12-01 Prefabricated steel supporting construction in a kind of tunnel

Publications (1)

Publication Number Publication Date
CN206246131U true CN206246131U (en) 2017-06-13

Family

ID=59005195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621309403.5U Withdrawn - After Issue CN206246131U (en) 2016-12-01 2016-12-01 Prefabricated steel supporting construction in a kind of tunnel

Country Status (1)

Country Link
CN (1) CN206246131U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401612A (en) * 2016-12-01 2017-02-15 河北工程大学 Precast steel plate supporting structure in tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106401612A (en) * 2016-12-01 2017-02-15 河北工程大学 Precast steel plate supporting structure in tunnel

Similar Documents

Publication Publication Date Title
CN106837408B (en) A kind of coal seam stope advantage gas migration channel staged construction method
CN206942764U (en) The supplementary structure of assembly and disassembly shield machine or TBM development machines in a kind of hole
CN102852533A (en) High-strength three-dimensional support system of yielding type restriction concrete lagging jack
CN204139197U (en) Bottom enlarging prestress anchoring pile wind energy conversion system basis
CN110145329A (en) A kind of deep soft rock circular tunnel method for protecting support
CN206246131U (en) Prefabricated steel supporting construction in a kind of tunnel
CN103774649B (en) Anti-mouth prevents the prestressed anchor extracted from anchor hole
CN106285775A (en) Cover goaf filling under a kind of structures and expand bag and construction method
CN204343306U (en) Tunnel, landslide integration Reinforcement device
CN110984857B (en) Grouting reinforcement drilling device capable of being adjusted in two directions
CN206205897U (en) A kind of support of tunnel structure
CN204456124U (en) One is slip casing by pressure pipe repeatedly
CN209041758U (en) A kind of major diameter bell and spigot water supply concrete pipe suspension protection system
CN204357447U (en) A kind of prefabricated pipe section for shield tunnel lining cutting stratum grouting device behind
CN103195449B (en) Large-span heavy-load open cut tunnel prestressed reinforced concrete liner structure
CN202090352U (en) Deep foundation pit bracing system with steel pipe piles-self-drilling type pre-stress anchor rods
CN106401612B (en) Prefabricated steel support construction in a kind of tunnel
CN206205896U (en) A kind of tunnel anti-collapse supporting construction
CN106368717B (en) A kind of tunnel anti-collapse supporting construction
CN202187288U (en) Compound tunnel anchorage
CN206337561U (en) A kind of anchor pole for being used to improve retaining wall bearing capacity
CN206694056U (en) A kind of mine anchor rod with Telescopic
CN201627585U (en) Grout stopping device for large pipe shed
CN203546685U (en) Optimized tunnel structure
CN201554033U (en) Tower crane foundation for deep foundation ditch

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20170613

Effective date of abandoning: 20181214

AV01 Patent right actively abandoned