CN206233484U - Arc railing and its field fabrication fixed support - Google Patents

Arc railing and its field fabrication fixed support Download PDF

Info

Publication number
CN206233484U
CN206233484U CN201620733315.1U CN201620733315U CN206233484U CN 206233484 U CN206233484 U CN 206233484U CN 201620733315 U CN201620733315 U CN 201620733315U CN 206233484 U CN206233484 U CN 206233484U
Authority
CN
China
Prior art keywords
vertical rod
arc
fixed part
pedestal
railing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620733315.1U
Other languages
Chinese (zh)
Inventor
邱峰
林其双
栾和罡
李栋坤
周婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201620733315.1U priority Critical patent/CN206233484U/en
Application granted granted Critical
Publication of CN206233484U publication Critical patent/CN206233484U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a kind of arc railing, including pedestal, vertical rod and arc cross bar, and vertical rod is installed in pedestal and curved arrangement, arc cross bar lateral connection vertical rod, and arc cross bar is a single piece.Additionally provide a kind of arc railing field fabrication fixed support, for making above-mentioned camber line railing, including pedestal fixed part, vertical rod fixed part and connecting portion, connecting portion difference linker seat fixed part and vertical rod fixed part, pedestal fixed part is used for fixed pedestal, and vertical rod fixed part is used to fix vertical rod.Arc railing of the present utility model is simple for production, integral installation effect is good, without secondary rectification, time saving province's wealth is laborsaving, and arc railing field fabrication fixed support is easy to operate, vertical rod can be avoided to produce loosening during the field fabrication of arc railing, ensure that arc railing makes smooth, design ingenious, it is simple for structure, low cost of manufacture, is suitable to large-scale promotion application.

Description

Arc railing and its field fabrication fixed support
Technical field
The utility model is related to railing tools technical field, more particularly to arc railing tools technical field, Specifically refer to a kind of arc railing and its field fabrication fixed support.
Background technology
The structure of railing generally includes pedestal, vertical rod and cross bar, vertical rod be plugged in pedestal and in straight or arc or its Its shaped formation, cross bar lateral connection vertical rod.
Made using factory more than current railing, field erected method, but for polymorphic structures such as arc railings, it is this to do Method mainly has following shortcoming:One is that accurate measurement setting-out, setting-out workload must be carried out to live structure before factory makes Greatly;Two is that factory makes and easily causes and deviation occur with live structure, causes vertical rod embedded part to misplace, cross bar radian and structure differ Cause, influence integral installation effect;Three is that factory makes cross bar segmentation setting-out, is segmented blanking, and joint is easily caused when assembled at the scene Circular arc has some setbacks, and influences installation effect, it usually needs secondary rectification, time-intensive, expensive is laborious.
Accordingly, it is desirable to provide a kind of arc railing, its is simple for production, and integral installation effect is good, time saving without secondary rectification Save wealth laborsaving.
Utility model content
In order to overcome above-mentioned shortcoming of the prior art, a purpose of the present utility model is to provide a kind of arc column Bar, its is simple for production, and integral installation effect is good, and without secondary rectification, time saving province's wealth is laborsaving, is suitable to large-scale promotion application.
Another object of the present utility model is to provide a kind of arc railing, and its design is ingenious, simple for structure, manufacturing cost It is low, it is suitable to large-scale promotion application.
Another object of the present utility model is to provide a kind of arc railing field fabrication fixed support, and its is easy to operate, Vertical rod can be avoided to produce loosening during the field fabrication of arc railing, it is ensured that arc railing makes smooth, is suitable to push away on a large scale Wide application.
Another object of the present utility model is to provide a kind of arc railing field fabrication fixed support, and its design is ingenious, Simple for structure, low cost of manufacture is suitable to large-scale promotion application.
To achieve the above objectives, in first aspect of the present utility model, there is provided a kind of arc railing, including pedestal, vertical rod With arc cross bar, the vertical rod installs in the susceptor and curved arrangement, vertical rod described in the arc cross bar lateral connection, It is characterized in, the arc cross bar is a single piece.
It is preferred that the arc cross bar is formed by a straight-bar bending.
It is preferred that the arc cross bar and the vertical rod are steel pipe, the pedestal is concrete pedestal.
In second aspect of the present utility model, there is provided a kind of arc railing makes fixed support, made for scene Make above-mentioned camber line railing, be characterized in, including pedestal fixed part, vertical rod fixed part and connecting portion, the connecting portion connects respectively The pedestal fixed part and the vertical rod fixed part are connect, the pedestal fixed part is used to fix the pedestal, and the vertical rod is fixed Portion is used to fix the vertical rod.
It is preferred that the pedestal fixed part is inverted U-shaped fixed part, the inverted U-shaped fixed part is used to grip the base Seat.
More preferably, the arc railing field fabrication fixed support also includes cushion block, and the cushion block is located at described inverted U-shaped solid Determine to be used for against the pedestal in portion.
Further, the cushion block is wedge.
Further, the cushion block is wooden unit.
It is preferred that the vertical rod fixed part is horizontal bars, the horizontal bars are used to fix the vertical rod.
It is preferred that the connecting portion is vertical bar, the vertical bar connects the pedestal fixed part and described respectively Vertical rod fixed part.
The beneficial effects of the utility model are essentially consisted in:
1st, arc railing of the present utility model includes pedestal, vertical rod and arc cross bar, and the vertical rod is installed in the pedestal In and curved arrangement, vertical rod described in the arc cross bar lateral connection, the arc cross bar is a single piece, by by one Root straight-bar one end is welded and fixed with the vertical rod on most side, and free end carries out tensioning, rear in place to be welded with remaining vertical rod Connect, the fabrication and installation of arc railing can be completed while forming arc cross bar, simple for production, integral installation effect is good, without Secondary rectification, time saving province's wealth is laborsaving, is suitable to large-scale promotion application.
2nd, arc railing of the present utility model includes pedestal, vertical rod and arc cross bar, and the vertical rod is installed in the pedestal In and curved arrangement, vertical rod described in the arc cross bar lateral connection, the arc cross bar is a single piece, by by one Root straight-bar one end is welded and fixed with the vertical rod on most side, and free end carries out tensioning, rear in place to be welded with remaining vertical rod Connect, the fabrication and installation of arc railing can be completed while forming arc cross bar, design ingenious, simple for structure, low cost of manufacture, It is suitable to large-scale promotion application.
3rd, arc railing field fabrication fixed support of the present utility model is used to make above-mentioned camber line railing, including Pedestal fixed part, vertical rod fixed part and connecting portion, the connecting portion connects the pedestal fixed part respectively and the vertical rod is fixed Portion, the pedestal fixed part is used to fix the pedestal, and the vertical rod fixed part is used to fix the vertical rod, therefore operation letter Just, vertical rod can be avoided to produce loosening during the field fabrication of arc railing, it is ensured that arc railing makes smooth, is suitable to extensive Popularization and application.
4th, arc railing field fabrication fixed support of the present utility model is used to make above-mentioned camber line railing, including Pedestal fixed part, vertical rod fixed part and connecting portion, the connecting portion connects the pedestal fixed part respectively and the vertical rod is fixed Portion, the pedestal fixed part is used to fix the pedestal, and the vertical rod fixed part is used to fix the vertical rod, designs ingenious, knot Structure is succinct, and low cost of manufacture is suitable to large-scale promotion application.
These and other objects of the present utility model, feature and advantage, by following detailed descriptions, accompanying drawing and right will Try to achieve to fully demonstrate, and can be achieved by means, device and the combinations thereof specially pointed out in appended claims.
Brief description of the drawings
Fig. 1 is the schematic diagram in top down perspective of a specific embodiment of arc railing of the present utility model.
Fig. 2 is the manufacturing process schematic diagram in top down perspective of the specific embodiment shown in Fig. 1.
Fig. 3 is the schematic cross-sectional view of the manufacturing process shown in Fig. 2.
(symbol description)
1 pedestal;2 vertical rods;3 arc cross bars;4 straight-bars;5 pedestal fixed parts;6 vertical rod fixed parts;7 connecting portions;8 cushion blocks.
Specific embodiment
In order to be more clearly understood that technology contents of the present utility model, described in detail especially exemplified by following examples.
Refer to shown in Fig. 1 to Fig. 3, arc railing of the present utility model includes pedestal 1, vertical rod 2 and arc cross bar 3, institute State vertical rod 2 to be installed in the pedestal 1 and curved arrangement, vertical rod 2, the arc described in the lateral connection of arc cross bar 3 Cross bar 3 is a single piece.
That is, the arc cross bar 3 is an entirety, non-segmentation is spliced, and is integrated part.
The arc cross bar 3 can be formed using any suitable part, shown in Figure 2, of the present utility model In one specific embodiment, the arc cross bar 3 is formed by a bending of straight-bar 4.
The arc cross bar 3, the vertical rod 2 and the pedestal 1 can be any suitable parts, refer to Fig. 1 to Fig. 3 Shown, in a specific embodiment of the present utility model, the arc cross bar 3 and the vertical rod 2 are steel pipe, the pedestal 1 It is concrete pedestal.
When making above-mentioned arc railing at the scene, as shown in Fig. 2 installation method is carried out as follows:Vertical rod 2 is installed in pedestal 1 In and curved arrangement, one end of straight-bar 4 is welded and fixed with the vertical rod 2 on most side, free end carries out tensioning, it is in place after Welded with remaining vertical rod 2, the fabrication and installation of arc railing can be completed while forming arc cross bar 3.
But, there is problems with this arc railing fabrication and installation method:Because arc cross bar 3 passes through the one end of straight-bar 4 It is fixed, welded with vertical rod 2 after free end tensioning camber and formed, it is adjustment radian, free end needs to move back and forth, easily causes Vertical rod 2 after welding loosens.
Therefore, the utility model additionally provides a kind of arc railing field fabrication fixed support, for avoiding vertical rod 2 in arc Loosening is produced during the field fabrication of shape railing, it is ensured that arc railing makes smooth.
Shown in Figure 3, arc railing of the present utility model makes fixed support, above-mentioned for making Camber line railing, including pedestal fixed part 5, vertical rod fixed part 6 and connecting portion 7, the connecting portion 7 connect the pedestal and fix respectively Portion 5 and the vertical rod fixed part 6, the pedestal fixed part 5 are used to fix the pedestal 1, and the vertical rod fixed part 6 is used to fix The vertical rod 2.
The pedestal fixed part 5 can be suitably composed with any, shown in Figure 3, of the present utility model one In specific embodiment, the pedestal fixed part 5 is inverted U-shaped fixed part, and the inverted U-shaped fixed part is used to grip the pedestal 1。
It is shown in Figure 3 in order to more consolidate, in a specific embodiment of the present utility model, the arc railing Field fabrication fixed support also includes that cushion block 8, the cushion block 8 are used for against the pedestal 1 in being located at the inverted U-shaped fixed part.
The cushion block 8 can have any suitable shape, shown in Figure 3, specific real of the present utility model one Apply in example, the cushion block 8 is wedge.
The cushion block 8 can be any suitable cushion block, shown in Figure 3, in of the present utility model one specific implementation In example, the cushion block 8 is wooden unit.
The vertical rod fixed part 6 can be suitably composed with any, shown in Figure 3, of the present utility model one In specific embodiment, the vertical rod fixed part 6 is horizontal bars, and the horizontal bars are used to fix the vertical rod 2.
The horizontal bars are fixed the vertical rod 2 and can use any suitable structure, specific of the present utility model one In embodiment, the horizontal bars are welded and fixed the vertical rod 2, such as spot welding.
The connecting portion 7 can be suitably composed with any, shown in Figure 3, specific of the present utility model one In embodiment, the connecting portion 7 is vertical bar, and the vertical bar connects the pedestal fixed part 5 and the vertical rod respectively Fixed part 6.
When making fixed support field fabrication arc railing using above-mentioned arc railing, with pedestal 1 for coagulation soil matrix As a example by seat, concrete pedestal is poured into a mould first, vertical rod 2 is embedded in concrete pedestal and curved arrangement, then by inverted U-shaped Fixed part is mobile so as to be clamped in concrete pedestal in inverted U-shaped fixed part from top to down from concrete pedestal top, then will Cushion block 8 is padded between inverted U-shaped fixed part and concrete pedestal, so as to grip concrete pedestal, then by vertical rod fixed part 6 It is fixed with vertical rod 2, then one end of straight-bar 4 is welded and fixed with the vertical rod 2 on most side, free end carries out tensioning, just Welded with remaining vertical rod 2 behind position, the fabrication and installation of arc railing can be completed while forming arc cross bar 3.
Therefore, arc railing field fabrication fixed support of the present utility model can be used for the field fabrication of arc railing, keep away Exempt to make railing in factory and live structural failure causes secondary rectification, and globality is preferable.
Advantage of the present utility model and good effect mainly have:
1) install simple, can gather materials on the spot;
2) arc is smooth attractive in appearance.
To sum up, arc railing of the present utility model is simple for production, and integral installation effect is good, without secondary rectification, time saving province Wealth is laborsaving, and arc railing field fabrication fixed support is easy to operate, and vertical rod can be avoided to be produced during the field fabrication of arc railing It is raw to loosen, it is ensured that arc railing makes smooth, designs ingenious, simple for structure, low cost of manufacture, is suitable to large-scale promotion application.
As can be seen here, the purpose of this utility model is achieved completely and effectively.Function of the present utility model and Structural principle is shown and is illustrated in embodiment, and under without departing substantially from the principle, implementation method can make any modification.Institute So that the utility model includes all variant embodiments based on claim spirit and right.

Claims (7)

1. a kind of arc railing field fabrication fixed support, pedestal, vertical rod and arc cross bar are included for making, described vertical Bar is installed in the susceptor and curved arrangement, vertical rod described in the arc cross bar lateral connection, and the arc cross bar is one Unitarily formed camber line railing, it is characterised in that including pedestal fixed part, vertical rod fixed part and connecting portion, the connecting portion difference The pedestal fixed part and the vertical rod fixed part are connected, the pedestal fixed part is used to fix the pedestal, and the vertical rod is consolidated Portion is determined for fixing the vertical rod.
2. arc railing as claimed in claim 1 makes fixed support, it is characterised in that the pedestal fixed part is for U-shaped fixed part, the inverted U-shaped fixed part is used to grip the pedestal.
3. arc railing as claimed in claim 2 makes fixed support, it is characterised in that arc railing scene system Making fixed support also includes that cushion block, the cushion block are used for against the pedestal in being located at the inverted U-shaped fixed part.
4. arc railing as claimed in claim 3 makes fixed support, it is characterised in that the cushion block is wedge.
5. arc railing as claimed in claim 3 makes fixed support, it is characterised in that the cushion block is wooden unit.
6. arc railing as claimed in claim 1 makes fixed support, it is characterised in that the vertical rod fixed part is water Flat rod member, the horizontal bars are used to fix the vertical rod.
7. arc railing as claimed in claim 1 makes fixed support, it is characterised in that the connecting portion is vertical bar Part, the vertical bar connects the pedestal fixed part and the vertical rod fixed part respectively.
CN201620733315.1U 2016-07-13 2016-07-13 Arc railing and its field fabrication fixed support Expired - Fee Related CN206233484U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620733315.1U CN206233484U (en) 2016-07-13 2016-07-13 Arc railing and its field fabrication fixed support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620733315.1U CN206233484U (en) 2016-07-13 2016-07-13 Arc railing and its field fabrication fixed support

Publications (1)

Publication Number Publication Date
CN206233484U true CN206233484U (en) 2017-06-09

Family

ID=58989043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620733315.1U Expired - Fee Related CN206233484U (en) 2016-07-13 2016-07-13 Arc railing and its field fabrication fixed support

Country Status (1)

Country Link
CN (1) CN206233484U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915181A (en) * 2018-07-12 2018-11-30 苏州美瑞德建筑装饰有限公司 Zhongting overhangs curve globoidal glass railing mounting structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108915181A (en) * 2018-07-12 2018-11-30 苏州美瑞德建筑装饰有限公司 Zhongting overhangs curve globoidal glass railing mounting structure
CN108915181B (en) * 2018-07-12 2023-11-03 苏州美瑞德建筑装饰有限公司 Atrium overhanging curve cambered surface glass railing mounting structure

Similar Documents

Publication Publication Date Title
CN206306252U (en) A kind of prefabricated small box girder reinforcing bar colligation moulding bed
CN203160267U (en) Split adjustable positioning device of embedded bolts of tower crane foundation
CN204738236U (en) Pier vertical reinforcement installation mould
CN204960342U (en) But height -adjusting's roof beam reinforcement supports instrument
CN206233484U (en) Arc railing and its field fabrication fixed support
CN102912977A (en) Mold used for pouring shaped stair
CN102926537B (en) Device for fixing root of external wall formwork
CN200940348Y (en) Hozirontal regulating part for curtain wall skeleton
CN202925679U (en) Concrete embedded part structure
CN211312114U (en) Found along stone concrete back and integrative casting die of sleeper beam
CN205369919U (en) Purlin is enclosed to multi -functional bracket appearance frame template
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
CN206839006U (en) A kind of processing unit (plant) of bridge reinforcement cage transverse steel circle
CN204139162U (en) Concrete tubular pile pile splicing structure
CN211817943U (en) Fixing device of template
CN204199441U (en) Vierendeel girder reinforcing bar and steel pipe column are in the syndeton of Nodes
CN103104099A (en) Method for constructing wall pulling steel bars in frame column and structure thereof
CN104763152A (en) Construction method for flower-basket-shaped support of steel structure water tower
CN201433567Y (en) Post type embedded part positioning device
CN201620599U (en) Rock wall crane beam concrete surface brace-free form of underground plant
CN205918142U (en) Aligning device is assembled to shear force wall
CN202767371U (en) Split head bar special for prestress
CN204826683U (en) H shaped steel frock clamp device
CN204715752U (en) Side form block
CN202990422U (en) Die for pouring and shaping stairs

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170609