CN206233057U - A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time - Google Patents

A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time Download PDF

Info

Publication number
CN206233057U
CN206233057U CN201621222832.9U CN201621222832U CN206233057U CN 206233057 U CN206233057 U CN 206233057U CN 201621222832 U CN201621222832 U CN 201621222832U CN 206233057 U CN206233057 U CN 206233057U
Authority
CN
China
Prior art keywords
road surface
drainage
drain
construction time
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621222832.9U
Other languages
Chinese (zh)
Inventor
宋亮
杨新龙
王吉运
王璐
李程
马建勇
周建娇
赵奇峰
赵鹏
张飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Traffic programme prospective design academy of Xinjiang Uygur Autonomous Regions
Original Assignee
宋亮
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 宋亮 filed Critical 宋亮
Priority to CN201621222832.9U priority Critical patent/CN206233057U/en
Application granted granted Critical
Publication of CN206233057U publication Critical patent/CN206233057U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of road surface temporary drainage structure for being adapted to the highway extension project construction time, including existing road surface structare layer, new pavement structure sheaf, described existing road surface structare layer and the joining place of new pavement structure sheaf are provided with multiple drainage arrangements, drainage arrangement includes drain-pipe cover, drain-pipe cover has vertical drainage pipe, described vertical drainage pipe end is connected with transverse drain, and transverse drain is placed in newly-built roadbed bottom.The utility model sets road surface temporary drainage device by new-old pavement joining place, ensure that construction time existing road surface drainage is unimpeded, the highway reconstruction and expansion engineering construction phase is avoided due to surface gathered water problem caused by impeded drainage, solve due to oozing caused subgrade and pavement disease under ponding, improve construction quality, and low cost, easy construction, with good use value.

Description

A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time
Technical field
The utility model belongs to highway construction road surface temporary drainage field, and in particular to one kind is applied to highway monoblock type Roadbed spells the road surface temporary drainage structure of reorganization and expansion construction time wide.
Background technology
With the sustainable growth of China's rapid economic development and the volume of traffic, the highway that early stage builds the traffic capacity, The aspects such as service level, operation security manifest deficiency increasingly, and increasing area has the tight demand of highway reconstruction and expansion. Integral subgrade spells reconstruction and extension project wide for guarantee has a good transport and communication network, frequently with semi-enclosed construction organization, in construction, when existing road Face with spell wide portion new pavement simultaneously be open to traffic when, due to new pavement absolute altitude be higher than existing grade elevation, therefore existing road surface without The smooth draining of method, it is more likely that cause rainwater to enter road surface, roadbed, causes it to produce disease.This problem is not obtained well Solve, when particularly construction time rainfall is larger, it is impossible to ensure the construction quality of high-quality, to highway life-span in later stage and operation security Very big hidden danger is buried.
The content of the invention
In view of the shortcomings of the prior art, the purpose of this utility model is to provide one kind to be applied suitable for highway reconstruction and expansion The road surface temporary drainage structure of duration, prevents rain water-harvesting in the range of existing road surface, forms rainwater infiltration, sends out existing road surface Sick evil.
In order to solve the above technical problems, the utility model is adopted the following technical scheme that being achieved:
A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time, including existing road surface structare layer, New pavement structure sheaf, described new pavement structure sheaf is higher than existing road surface structare layer, described existing road surface structare layer and The joining place of new pavement structure sheaf is provided with multiple drainage arrangements;
Described drainage arrangement includes drain-pipe cover, and drain-pipe cover has vertical drainage pipe, described vertical drainage pipe End is connected with transverse drain, and described drain-pipe cover surface is located at same level highly with existing pavement structure layer surface.
The utility model also has following distinguishing feature:
Distance between described each two drainage arrangement is 50~2000m.
Described transverse drain transverse direction ratio of slope is 2%~5%.
The length of described vertical drainage pipe is:Road surface structare layer thickness+roadbed thickness≤vertical drainage length of tube≤road Face Laminate construction thickness+roadbed thickness+30cm.
The utility model has the following technical effect that:
The utility model by new-old pavement joining place set road surface temporary drainage device, it is ensured that the construction time existing road surface Draining is unimpeded, it is to avoid the highway reconstruction and expansion engineering construction phase due to surface gathered water problem caused by impeded drainage, solve due to Ooze caused subgrade and pavement disease under ponding, improve construction quality, and cost is relatively low, easy construction, with using valency well Value.
Brief description of the drawings
Fig. 1 is the utility model overall structure schematic cross-sectional view.
Fig. 2 is the utility model overall structure floor map.
Fig. 3 is the utility model drain-pipe cover schematic diagram.
Fig. 4 is that the utility model drain-pipe cover is connected schematic diagram with vertical drainage pipe.
Note:Accompanying drawing unit is in terms of millimeter.
The implication of each label is in figure:The existing road surface structare layers of 1-, 2- new pavement structure sheafs, 3- drainage arrangements, (3- 1)-drain-pipe cover, (3-2)-vertical drainage pipe, (3-3)-transverse drain.
Explanation is further explained in detail to particular content of the present utility model below in conjunction with accompanying drawing.
Specific embodiment
Specific embodiment of the utility model given below is, it is necessary to explanation is that the utility model is not limited to following tool Body embodiment, all equivalents done on the basis of technical scheme each fall within protection domain of the present utility model.
Embodiment:
Above-mentioned technical proposal is deferred to, with reference to Fig. 1 to Fig. 4, the present embodiment provides one kind and is adapted to highway extension project to be applied The road surface temporary drainage structure of duration, including existing road surface structare layer 1, new pavement structure sheaf 2, described existing pavement structure The joining place of layer 1 and new pavement structure sheaf 2 is provided with multiple drainage arrangements 3.
Drainage arrangement 3 includes that drain-pipe cover 3-1, drain-pipe cover 3-1 have vertical drainage pipe 3-2, described vertical row Water pipe 3-2 ends are connected with transverse drain 3-3, and transverse drain 3-3 is placed in newly-built roadbed bottom, and transverse drain arrangement is prolonged Extend roadbed outside, transverse drain and the steel pipe that vertical drainage pipe is a diameter of 200mm, the table of described drain-pipe cover 3-1 Face is located at same level highly with the surface of existing road surface structare layer 1.
Distance between each two drainage arrangement 3 is 1000m, it is to avoid save material while ponding problem.
Transverse drain 3-3 transverse direction ratios of slope are 3%, smooth with water supply and sewage.
The length of vertical drainage pipe 3-2 is 2m, if the length of vertical drainage pipe 3-2 is too small and can reduce roadbed globality and increase Big traffic load will increase cost to the active force of drainpipe, length increase.

Claims (4)

1. a kind of road surface temporary drainage structure for being adapted to the highway extension project construction time, including existing road surface structare layer (1) With new pavement structure sheaf (2), described new pavement structure sheaf (2) is higher than existing road surface structare layer (1), it is characterised in that Along being provided with multiple drainage arrangements at road direction between described existing road surface structare layer (1) and new pavement structure sheaf (2) (3);
Described drainage arrangement (3) includes drain-pipe cover (3-1), and drain-pipe cover (3-1) has vertical drainage pipe (3-2), institute Vertical drainage pipe (3-2) end stated is connected with transverse drain (3-3), the surface of described drain-pipe cover (3-1) with it is existing Road surface structare layer (1) surface is located at same level highly.
2. the road surface temporary drainage structure of highway extension project construction time is adapted to as claimed in claim 1, and its feature exists In the distance between described each two drainage arrangement (3) is 50~2000m.
3. the road surface temporary drainage structure of highway extension project construction time is adapted to as claimed in claim 1, and its feature exists In described transverse drain (3-3) is downward-sloping to extend to new pavement roadbed outside, the transverse direction of transverse drain (3-3) Ratio of slope is 2%~5%.
4. the road surface temporary drainage structure of highway extension project construction time is adapted to as claimed in claim 1, and its feature exists In the length of described vertical drainage pipe (3-2) is:Road surface structare layer thickness+roadbed thickness≤vertical drainage length of tube≤road Face Laminate construction thickness+roadbed thickness+30cm.
CN201621222832.9U 2016-11-14 2016-11-14 A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time Active CN206233057U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621222832.9U CN206233057U (en) 2016-11-14 2016-11-14 A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621222832.9U CN206233057U (en) 2016-11-14 2016-11-14 A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time

Publications (1)

Publication Number Publication Date
CN206233057U true CN206233057U (en) 2017-06-09

Family

ID=58991308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621222832.9U Active CN206233057U (en) 2016-11-14 2016-11-14 A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time

Country Status (1)

Country Link
CN (1) CN206233057U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107893471A (en) * 2017-11-15 2018-04-10 孟宪山 Expressway Extension Project construction time Pavement surface drainage system
CN111705590A (en) * 2020-06-28 2020-09-25 山东省交通规划设计院有限公司 Drainage system and method for road surface in traffic protection stage of highway reconstruction and extension project
CN111894104A (en) * 2020-06-10 2020-11-06 河北交通职业技术学院 Drainage system for expressway reconstruction and expansion construction and drainage method thereof
CN114561849A (en) * 2022-03-16 2022-05-31 池州市交通规划设计院 Drainage system and construction method for road surface in traffic protection stage of highway reconstruction and extension project
CN114960900A (en) * 2022-08-01 2022-08-30 四川省亚通工程咨询有限公司 Drainage pipeline for highway reconstruction and extension project

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107893471A (en) * 2017-11-15 2018-04-10 孟宪山 Expressway Extension Project construction time Pavement surface drainage system
CN107893471B (en) * 2017-11-15 2018-08-31 孟宪山 Expressway Extension Project construction time Pavement surface drainage system
CN111894104A (en) * 2020-06-10 2020-11-06 河北交通职业技术学院 Drainage system for expressway reconstruction and expansion construction and drainage method thereof
CN111894104B (en) * 2020-06-10 2022-02-01 河北交通职业技术学院 Drainage system for expressway reconstruction and expansion construction and drainage method thereof
CN111705590A (en) * 2020-06-28 2020-09-25 山东省交通规划设计院有限公司 Drainage system and method for road surface in traffic protection stage of highway reconstruction and extension project
CN111705590B (en) * 2020-06-28 2021-10-19 山东省交通规划设计院集团有限公司 Drainage system and method for road surface in traffic protection stage of highway reconstruction and extension project
CN114561849A (en) * 2022-03-16 2022-05-31 池州市交通规划设计院 Drainage system and construction method for road surface in traffic protection stage of highway reconstruction and extension project
CN114561849B (en) * 2022-03-16 2023-12-12 池州市交通规划设计院 Drainage system and construction method for road surface in road reconstruction and expansion engineering passage-keeping stage
CN114960900A (en) * 2022-08-01 2022-08-30 四川省亚通工程咨询有限公司 Drainage pipeline for highway reconstruction and extension project
CN114960900B (en) * 2022-08-01 2022-11-01 四川省亚通工程咨询有限公司 Drainage pipeline for highway reconstruction and extension project

Similar Documents

Publication Publication Date Title
CN206233057U (en) A kind of road surface temporary drainage structure for being adapted to the highway extension project construction time
CN205276099U (en) Drainage formula brick that permeates water
CN206352331U (en) The concave herbaceous field structure of sponge the idea of the city
CN106320433A (en) Urban road rainwater collection structure
CN105970764B (en) A kind of laying method of drainage pavement
CN207143648U (en) A kind of ubbase drain system of embedding careless brick surface layer
CN201502019U (en) Permeable ground structure
CN109826065A (en) A kind of high-fill roadbed guard system and its construction method
CN206655077U (en) A kind of porous base course brick suitable for porous pavement and the basic road surface using the brick
CN203475267U (en) Curb for water-permeable asphalt greenway pavement
CN107842038A (en) A kind of pipe gallery node location road subtracts sink device
CN203546559U (en) Reverse seepage preventing sidewalk brick capable of draining water
CN206256336U (en) A kind of pervious concrete pavement structure that can be purified water
CN206971571U (en) Bluish-green roof structure applied to sponge urban construction
CN206034231U (en) Colored elasticity concrete that permeates water
CN205399132U (en) Linear curb drainage pipe culvert
CN206346091U (en) Water permeable sidewalk
CN205529758U (en) Sub -surface
CN104631279A (en) Space utilization road surface unit
CN211815262U (en) Brick permeates water convenient to drainage
CN209144602U (en) A kind of concrete prefabricated people's line width road
CN210657848U (en) Permeable brick laying structure
CN203498724U (en) Routing table drainage system in construction period of expressway reconstruction and extension project
CN106758678A (en) Multifunctional permeable water storage brick
CN206800107U (en) A kind of T-shaped collector pipe

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190329

Address after: 830006 No. 12 Cangfanggou Road, Shaibak District, Urumqi City, Xinjiang Uygur Autonomous Region

Patentee after: Traffic programme prospective design academy of Xinjiang Uygur Autonomous Regions

Address before: 830006 No. 12 Cangfanggou Road, Urumqi City, Xinjiang Uygur Autonomous Region

Patentee before: Song Liang

TR01 Transfer of patent right