CN206204969U - Reservoir submerges area's brick mixed building terrace lift structure - Google Patents
Reservoir submerges area's brick mixed building terrace lift structure Download PDFInfo
- Publication number
- CN206204969U CN206204969U CN201621290679.3U CN201621290679U CN206204969U CN 206204969 U CN206204969 U CN 206204969U CN 201621290679 U CN201621290679 U CN 201621290679U CN 206204969 U CN206204969 U CN 206204969U
- Authority
- CN
- China
- Prior art keywords
- brick mixed
- mixed building
- reservoir
- barricade
- area
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Landscapes
- Steps, Ramps, And Handrails (AREA)
Abstract
The utility model is related to a kind of reservoir submergence area's brick mixed building terrace lift structure.The utility model includes brick mixed building that number of floor levels is at least two-layer, the surrounding of brick mixed building builds the barricade of stone masonry or concrete structure by laying bricks or stones, there is interval between barricade and brick mixed building, sand horsestone compacting reclamation district is set on the outside of barricade, inner side is set to the artificial landfill of sand horsestone, and the artificial landfill of sand horsestone is distributed in the outer wall body both sides of brick mixed building simultaneously, the apical side height of barricade, sand horsestone is compacted the apical side height of reclamation district, the apical side height of the artificial landfill of sand horsestone is above the design high-water that reservoir submerges area, gear coping is provided with the panel of reinforced concrete structure, panel has the extension towards brick mixed building, set between the outer wall body outside of its extension and brick mixed building and fill out sealing.The utility model can recover the use function that reservoir submerges area's brick mixed building, mitigate society and the economic pressures of relocation of people from reservoir areas.
Description
Technical field
The utility model is related to a kind of reservoir submergence area's brick mixed building terrace lift structure, it is adaptable to which reservoir submergence area's brick is mixed
The reconstruction project of building.
Background technology
With the abundant area large medium-size station of China's water resource, the construction of reservoir, cause after reservoir filling underground water and
River lake stage lifting, a large amount of relatively low houses of original physical features are submerged, and a large amount of immigrants need to carry out Relocation and Settlement.Meanwhile, also there is phase
When the house for closing on reservoir area of quantity, do not influenceed by storehouse water logging, ground floor flashing, interior are poured water, even one layer in Gao Shui
Flooded completely during position.By the way of grade is raised, former grade is promoted to the height of two layers of original building, can be extensive
The use function in area house is submerged again, mitigates society, the economic pressures of immigration allocation, with quite extensive promotional value.So
And, brick mix structure form is generally used positioned at the house in submergence area, wall is vertical load-carrying members, it is impossible to undertake horizontal direction water
Soil pressure, therefore fill compaction operation directly can not be carried out in existed building periphery, operation is banketed due to the interior space in interior
Limitation is difficult to be compacted.It is domestic at present to throw the house that bottom is submerged aside due to the limitation of above-mentioned contradiction, carry out weight on highland
Build.
Utility model content
Technical problem to be solved in the utility model is:A kind of reservoir submergence area brick mixed building terrace lifting knot is provided
Structure, can recover the use function that reservoir submerges area's brick mixed building, mitigate society and the economic pressures of relocation of people from reservoir areas.
For the technical scheme that solution above-mentioned technical problem the utility model is used is:Reservoir submerges area's brick mixed building terrace
Lift structure, including the brick mixed building that number of floor levels is at least two-layer, the surrounding of brick mixed building have built stone masonry or concrete knot by laying bricks or stones
The barricade of structure, has interval between barricade and brick mixed building, sand horsestone compacting reclamation district, inner side are set on the outside of barricade and are set
It is the artificial landfill of sand horsestone, and the artificial landfill of sand horsestone is distributed in the outer wall body both sides of brick mixed building simultaneously, barricade
Apical side height, the apical side height of sand horsestone compacting reclamation district, the apical side height of the artificial landfill of sand horsestone are above reservoir submergence
The design high-water in area, gear coping is provided with the panel of reinforced concrete structure, and panel has prolonging towards brick mixed building
Set between the outer wall body outside of extending portion, its extension and brick mixed building and fill out sealing.
It is further:Brick mixed building is above panel and the floor nearest apart from panel is provided with door.
It is further:Door is reconstructed by the window opening of floor where it and obtained.
It is further:The stair of marking time of the floor for connecting brick mixed building, building of marking time are provided with the top of panel
Ladder is located at one end of panel positioned at one end of brick mixed building higher than it.
It is further:Mark time and be provided with using waterproof roll between stair top and the outer wall body outside of brick mixed building
Waterproof portion.
It is further:The apical side height of the artificial landfill of sand horsestone is less than the apical side height of barricade, the artificial heap of sand horsestone
The top surface for filling out area is provided with floor damp-proof course.
It is further:The top surface of sand horsestone compacting reclamation district flushes setting with the top surface of panel.
The beneficial effects of the utility model are:Using barricade by the way of panel is combined, by all skirts of brick mixed building
Close, while being filled using the compacting of sand horsestone on the outside of barricade, artificial heap back-up sand is carried out on the inside of barricade and in brick mixed building room
Horsestone, grade is raised, so as to the use functional rehabilitation by former brick mixed building higher than water level part.Original brick mix structure is not
Water And Earth Pressures are undertaken, the packing requirement banketed to interior is relatively low, is easy to landfill to construct, while barricade isolation grade landfill
The vibrations of compacting and pressure, and reduce barricade to the unique deformation on the inside of outer wall body.The utility model simple structure, it is easy to apply
Work, cost is relatively low.
Brief description of the drawings
Fig. 1 is the architectural section before terrace is raised;
Fig. 2 is the schematic diagram in terrace lifting construction;
Fig. 3 is the architectural section after terrace is raised;
Fig. 4 is the layer plane figure of building one after terrace is raised;
Fig. 5 is the building first floor plan after terrace is raised;
Marked in figure:1- brick mixed buildings, 2- barricades, 3- sand horsestone compacting reclamation district, the artificial landfill of 4- sand horsestones, 5- faces
Plate, 6- mark time stair, 7- waterproofs portion, 8- floor damp-proof courses, 9- design high-waters, 10- originals grade, mono- layer of 11- indoorly
Face, the floor faces of 12- bis-, 13- building foundations, mono- layer of door opening of 14-.
Specific embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
As shown in Fig. 1~Fig. 5, the utility model includes the brick mixed building 1 that number of floor levels is at least two-layer, brick mixed building 1
Surrounding builds the barricade 2 of stone masonry or concrete structure by laying bricks or stones, has interval, the outside of barricade 2 between barricade 2 and brick mixed building 1
It is set to sand horsestone compacting reclamation district 3, inner side and is set to the artificial landfill 4 of sand horsestone, and sand horsestone artificial landfill 4 same time-division
It is distributed in the outer wall body both sides of brick mixed building 1, the apical side height of barricade 2, the apical side height of sand horsestone compacting reclamation district 3, sand folder
The apical side height of the artificial landfill 4 of stone is above the design high-water 9 that reservoir submerges area, and the top of barricade 2 is provided with reinforcing bar and mixes
The panel 5 of Xtah Crude Clay structure, panel 5 has the outer wall body of the extension towards brick mixed building 1, its extension and brick mixed building 1
Set between outside and fill out sealing.
The utility model should be selected in dry season construction, and construction procedure is as follows:When dry season water level declines, in brick mixed building
Made a circle outside 1 exterior wall, build the barricade 2 of stone masonry or concrete structure by laying bricks or stones.But it is different from usual barricade, it is of the present utility model
Banketed the both sides of barricade 2.Artificial landfill is used near the side of brick mixed building 1, the exterior wall of brick mixed building 1 is inside and outside to be filled simultaneously;
Barricade opposite side is filled using the compacting of sand horsestone, it is desirable to which compacting factor is not less than the requirement of grade related specifications, due to barricade
Obstruct, grade lifting compacting construction it is smaller to the existing wall influence of brick mixed building 1, compacting filling soil pressure is by barricade 2
Undertake.Simultaneously as the soil body is filled in the existing exterior wall both sides of brick mixed building 1 simultaneously, and water can be by former one layer of door opening and substrate
Wall both sides are flowed to, the horizontal pressure force that wall undertakes is reduced.
During using stone masonry barricade, as barricade is constantly built by laying bricks or stones, barricade both sides synchronously carry out fill construction.Building side is filled out
Soil when construction to higher than maximum water level certain distance after, carry out it is smooth, thereon build floor damp-proof course 8, this layer can as partly
Storage cellar is used.Being banketed due to barricade both sides can reduce barricade tilt displacement deformation.Proceed barricade to build by laying bricks or stones, keep off
Wall outside is banketed and carries out compacting construction, until reach close to original building apart from nearest one layer of design high-water floor flooring highly
When (usually second layer flooring), carry out smooth, complete to fill, below water level isolation to indoor terrace.
Then the panel 5 for carrying out armored concrete at the top of barricade 2 is constructed, and the panel 5 is mixed with existing brick to barricade
Space between construction wall is closed, and gap is clogged using Bituminous hemp fiber between panel and existing building wall, so as to subtract
Influence of the small barricade deformation to building.The root of panel 5 carries out thickening to be poured with barricade being integrated, from without toppling.Sand is pressed from both sides
The top surface of stone compacting reclamation district 3 flushes setting with the top surface of panel 5.When newly grade sedimentation and deformation is filled, to outdoor ground
Level ground carries out benefit and fills out, and does not influence existing building.
The utility model is raised by by grade, so as to former brick mixed building is extensive higher than the use function of water level part
It is multiple.Use for convenience, brick mixed building 1 is positioned at the top of panel 5 and the floor nearest apart from panel 5 is provided with door.Door is preferably
Reconstructed by the window opening of floor where it and obtained, the destruction to original wall body can be reduced.
In addition, using for convenience, the top of panel 5 is provided with the stair of marking time of the floor for connecting brick mixed building 1
6, stair 6 of marking time are located at one end of panel 5 positioned at one end of brick mixed building 1 higher than it.Mark time the top of stair 6 and brick mixed building 1
Outer wall body outside between waterproof portion 7 is provided with using waterproof roll.
Claims (7)
1. reservoir submergence area's brick mixed building terrace lift structure, including the brick mixed building (1) that number of floor levels is at least two-layer, its feature
It is:The surrounding of brick mixed building (1) builds the barricade (2) of stone masonry or concrete structure, barricade (2) and brick mixed building (1) by laying bricks or stones
Between there is interval, the compacting of sand horsestone reclamation district (3), inner side are set on the outside of barricade (2) and are set to the artificial landfill of sand horsestone
Area (4), and the artificial landfill of sand horsestone (4) is while be distributed in the outer wall body both sides of brick mixed building (1), the top surface of barricade (2)
Highly, the apical side height of sand horsestone compacting reclamation district (3), the apical side height of the artificial landfill of sand horsestone (4) are above reservoir leaching
Do not have the design high-water (9) in area, the panel (5) of reinforced concrete structure is provided with the top of barricade (2), panel (5) is with court
To the extension of brick mixed building (1), set between the outer wall body outside of its extension and brick mixed building (1) and fill out sealing.
2. reservoir as claimed in claim 1 submerges area's brick mixed building terrace lift structure, it is characterised in that:Brick mixed building (1)
Positioned at panel (5) top and the floor nearest apart from panel (5) is provided with door.
3. reservoir as claimed in claim 2 submerges area's brick mixed building terrace lift structure, it is characterised in that:Door is by where it
The window opening reconstruction of floor is obtained.
4. reservoir as claimed in claim 1 submerges area's brick mixed building terrace lift structure, it is characterised in that:The top of panel (5)
Portion is provided with the stair of marking time (6) of the floor for connecting brick mixed building (1), and stair of marking time (6) are positioned at brick mixed building (1)
One end is located at one end of panel (5) higher than it.
5. reservoir as claimed in claim 4 submerges area's brick mixed building terrace lift structure, it is characterised in that:Mark time stair (6)
Waterproof portion (7) is provided with using waterproof roll between the outer wall body outside of top and brick mixed building (1).
6. the reservoir as described in any one in Claims 1 to 5 submerges area's brick mixed building terrace lift structure, and its feature exists
In:The apical side height of the artificial landfill of sand horsestone (4) is less than the apical side height of barricade (2), the top of the artificial landfill of sand horsestone (4)
Face is provided with floor damp-proof course (8).
7. the reservoir as described in any one in Claims 1 to 5 submerges area's brick mixed building terrace lift structure, and its feature exists
In:The top surface of sand horsestone compacting reclamation district (3) flushes setting with the top surface of panel (5).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621290679.3U CN206204969U (en) | 2016-11-29 | 2016-11-29 | Reservoir submerges area's brick mixed building terrace lift structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621290679.3U CN206204969U (en) | 2016-11-29 | 2016-11-29 | Reservoir submerges area's brick mixed building terrace lift structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206204969U true CN206204969U (en) | 2017-05-31 |
Family
ID=58747801
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621290679.3U Withdrawn - After Issue CN206204969U (en) | 2016-11-29 | 2016-11-29 | Reservoir submerges area's brick mixed building terrace lift structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206204969U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106498958A (en) * | 2016-11-29 | 2017-03-15 | 中国电建集团成都勘测设计研究院有限公司 | Reservoir submergence area brick mixed building terrace lift structure and technique |
-
2016
- 2016-11-29 CN CN201621290679.3U patent/CN206204969U/en not_active Withdrawn - After Issue
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106498958A (en) * | 2016-11-29 | 2017-03-15 | 中国电建集团成都勘测设计研究院有限公司 | Reservoir submergence area brick mixed building terrace lift structure and technique |
CN106498958B (en) * | 2016-11-29 | 2018-05-04 | 中国电建集团成都勘测设计研究院有限公司 | Reservoir submerges area's brick mixed building terrace lift structure and technique |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102277867B (en) | Construction method for collapsible loess foundation | |
CN103741714B (en) | Underground engineering full sheltered reverse excavation construction method | |
CN105002913B (en) | A kind of highly permeable stratum deep basal pit back cover water sealing structure and its construction method | |
CN201883450U (en) | Coastal deep-foundation anti-seepage waterproof basement structure | |
CN105256810B (en) | Construction method for round underground continuous wall two-in-one structure | |
CN110258538B (en) | Soil nail reinforced buffer type manual hole digging pile and construction method thereof | |
CN204343339U (en) | A kind of temporary support columns waterproof base plate | |
CN103938634B (en) | A kind of deep foundation pit supporting structure and construction method | |
CN101806055B (en) | Vacuum pre-pressed joint rigid pile composite foundation reinforcing method | |
CN104846841A (en) | Anti-floating construction method for basements without uplift piles | |
CN207079718U (en) | A kind of basement waterproofing structure | |
CN204982908U (en) | Elevartor shaft deep basal pit seepage prevention structure | |
CN110080248A (en) | Nearly depth of water foundation pit supporting construction | |
CN206204969U (en) | Reservoir submerges area's brick mixed building terrace lift structure | |
CN103469828A (en) | Construction method of hydrophobic structure of post-cast strip of bottom plate of basement | |
CN112726682A (en) | Construction method for preventing water scattering and cracking in combination of high water level area and waterproof curtain | |
CN1155606A (en) | Foundation side wall as basement wall and construction method thereof | |
CN208501761U (en) | A kind of sedimentation reinforcing jacking leveling structure suitable for industrial premises independence pile foundation | |
CN110670613A (en) | Anti-seepage structure of foundation pit elevator shaft and construction method thereof | |
CN106498958B (en) | Reservoir submerges area's brick mixed building terrace lift structure and technique | |
CN207331699U (en) | One kind cheats reinforced concrete barricade composite supporting construction in hole | |
CN105544621A (en) | Building structure for lowering designed anti-floating water level of heap slope building | |
CN205530218U (en) | Slip casting composite foundation suitable for high -rise building structural strengthening is rectified | |
CN211547830U (en) | Structure for preventing ground from being wetted | |
CN205062744U (en) | Half gravity type two -stage view anti -flood wall on half cantilever |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20170531 Effective date of abandoning: 20180504 |