CN206189590U - Full precast prestressed assembly structure - Google Patents

Full precast prestressed assembly structure Download PDF

Info

Publication number
CN206189590U
CN206189590U CN201620706988.8U CN201620706988U CN206189590U CN 206189590 U CN206189590 U CN 206189590U CN 201620706988 U CN201620706988 U CN 201620706988U CN 206189590 U CN206189590 U CN 206189590U
Authority
CN
China
Prior art keywords
post
groove
fabricated construction
prestressed
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620706988.8U
Other languages
Chinese (zh)
Inventor
周赟文
林伟
雷斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang University
Original Assignee
Nanchang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang University filed Critical Nanchang University
Priority to CN201620706988.8U priority Critical patent/CN206189590U/en
Application granted granted Critical
Publication of CN206189590U publication Critical patent/CN206189590U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model belongs to the technical field of the building, a full precast prestressed assembly structure is related to, the main structure body form is frame construction, the post, and the roof beam, the board, door and window, wall body, stair all are the prefabricating production of mill. Set up the groove and the entrance to a cave at required post, roof beam, board according to total design paper, not only guarantee the component quality, can save loaded down with trivial details formwork at the construction field (site) moreover, the maintenance, shortcomings such as dismantlements, reach save labour, efficient, of high quality, the light advantage such as pollution -free of just being under construction. Contrast in more existing assembly structure, the utility model discloses the advantage lies in: whole assembling and stability are good, and equal bearing capacity design value requires down, and required section size is less, and anti -seismic performance can obtain assurance etc.. The utility model discloses the product is green, energy -conserving, the consumption reduction, accords with the requirement of construction industry sustainable development strategy, can extensively be applicable to various many, high layer frame structures, has fine economy and social.

Description

A kind of complete precast prestressed fabricated construction
Technical field
The utility model is related to field of civil engineering, is related to a kind of complete precast prestressed fabricated construction.
Background technology
For a long time, the labor productivity of construction industry improves speed slowly, compared with other industry and the external same industry, mostly Number enterprise construction Technical comparing falls behind, and low construction efficiency, labour intensity is big, and construction quality and security incident are high, engineering Common quality defect is of common occurrence, and construction cost constantly increases.In the process of urbanization and urban modernization, constructional enterprises are necessary From the angle for improving construction efficiency, speed up the work, reduce labourer's working strength, in General Promotion construction technology water Made an effort on flat, approach and catch up with external advanced construction technology level as early as possible.Realize the modernization of construction industry, it is necessary to walk industry The road of change, is relied on scientific and technological advances, and building is realized with design standard, component component, mechanization of building operation, IT application in management The modernization of industry.
The content of the invention
The purpose of this utility model is, there is provided a kind of efficient, convenient, overall good precast construction and assembly method, work Factory's modularization production design, the measure that scene directly carries out being carried out after simply combining some waterproofs can complete major project, Not only ensure component quality, and job site can save cumbersome formwork, maintenance, dismounting, reach time saving, efficiency high, matter Measure, it is light, construct it is pollution-free the advantages of.Substantially reduce the duration and save the resources such as substantial amounts of human and material resources.
In order to solve the above problems and realizing above-mentioned requirements, the utility model takes following technical solution.
(1)A kind of complete precast prestressed fabricated construction, prefabricated node post, is provided with prestress hole in the fabricated construction Road, joint bar hole, joint bar, beam connects prestressed pore passage, styletable groove, post side groove, pre-buried angle steel;Precast beam, is provided with post even pre- Stress duct, beam side groove, beam-ends groove, plate connects hole;Armoured concrete slab, is provided with elbow reinforcing bar, the convex key of reinforcing bar.Exterior wall side Reserved slurry seal groove, post Column border node, bean column node.
(2)Be fixed on beam on column by applying the tectonic sieving of prestressing force and beam to beam mainly by this fabricated construction, Integral post vertical construction prestressing force of the post by the tectonic sieving on Column border node with after the completion of ensures resistance to overturning, and plate is by pre- Stay in elbow reinforcing bar insertion beam, be allowed to be integrally formed cooperative bearing with beam.Precast wall body is then by the convex key of embedded bar on plate It is embedded into structure with chute is set on post, both sides can be set damping spring or properties of lead-core rubber damper on wall Improve anti-seismic performance.
(3)The waterproofing process of this assembling structure is default seam wide, after the completion of overall structure tensioning, is completed to cover with mortar Seam.Due to described seam a width of artificial default, later stage is integrated poured and seam in extruded by residual prestress, it is therefore more pre- than other Structure node water-proofing treatment construction processed is relatively reliable.
(4)This assembling structure applies prestressing force for segmentation, takes measures to be to apply this in the position of required section construction Semi-fixed type anchorage in utility model.Anchorage through-thickness half is located at post side groove, and second half is located in beam-ends groove, To provide intensity jointly with pre-buried angle steel after prestress steel relaxation.
(5)This assembling structure is located at every layer of centre position due to the block position of Column border node, according to structural mechanics for The calculating of frame model understands that every layer of post center is inflection point, bears the position that moment of flexure is 0, and this clever structure uses this Bar specification so that junction is substantially solely subjected to axle power effect, it is to avoid the influence of junction bending moment destruction.
(6)The presstressed reinforcing steel of this assembling structure beam can be prestressing force spiral or steel strand wires form, post prestressing force Muscle should be steel strand wires form.
The utility model has advantages below:
(1)Not only ensure component quality, and cumbersome formwork can be saved at the construction field (site), conserve, dismounting, construction is dirty The shortcomings of dye, reach time saving, efficiency high, quality it is good, it is light the advantages of.
(2)Overall assembling and good stability, under equal design ultimate bearing capacity requirement, required sectional dimension is smaller, resists Shock stability is guaranteed.
(3)Green, energy-conservation, consumption reduction, meet Sustainable Construction Industry strategic requirement.
Brief description of the drawings
Fig. 1 is node post schematic three dimensional views.
Fig. 2 is reinforced beam schematic three dimensional views.
Fig. 3 is the vertical view and schematic side view of reinforced beam.
Fig. 4 is the schematic three dimensional views of armoured concrete slab.
Fig. 5 is Column border node combination diagram.
Fig. 6 is beam column combined joint schematic diagram.
Fig. 7 is beam slab combined joint schematic diagram.
The semifixed end anchorage floor map of Fig. 8.
Fig. 9 integral unit assembling process floor map.
Figure 10 integrally assembles completion schematic diagram.
Wherein 1. node posts, 2. prestressed pore passage, 3. joint bar hole, 4. joint bar, 5. beam connect prestressed pore passage, 6. pre-buried angle Steel, 7. precast beam, 8. post connect prestressed pore passage, 9. plate connects hole, 10. armoured concrete slab, 11. elbow reinforcing bars, 12. reinforcing bars are convex Key, 13. post side grooves, 14. beam-ends grooves, 15. semifixed end anchorages, 16. styletables are recessed.
Specific embodiment
(1)A kind of complete precast prestressed fabricated construction, prefabricated node post 1, is provided with prestressing force in the fabricated construction Duct 2, joint bar hole 3, joint bar 4, beam connects prestressed pore passage 5, styletable groove 17, post side groove 13, pre-buried angle steel 6;Precast beam 7, it is provided with post and connects prestressed pore passage 8, beam side groove 20, beam-ends groove 14, plate connects hole 9;Armoured concrete slab 10, is provided with elbow Reinforcing bar 11, the convex key 12 of reinforcing bar.The reserved slurry seal groove 16 in exterior wall side, post Column border node 18, bean column node 19.
(2)Be fixed on beam on column by applying the tectonic sieving of prestressing force and beam to beam mainly by this fabricated construction, Integral post vertical construction prestressing force of the post by the tectonic sieving on Column border node with after the completion of ensures resistance to overturning, and plate is by pre- Stay in elbow reinforcing bar insertion beam, be allowed to be integrally formed cooperative bearing with beam.Precast wall body is then by the convex key of embedded bar on plate It is embedded into structure with chute is set on post, both sides can be set damping spring or properties of lead-core rubber damper 16 in wall Upper raising anti-seismic performance.
(3)The waterproofing process of this assembling structure is default seam wide, after the completion of overall structure tensioning, is completed to cover with mortar Seam.Due to described seam a width of artificial default, later stage is integrated poured and seam in extruded by residual prestress, it is therefore more pre- than other Structure node water-proofing treatment construction processed is relatively reliable.
(4)This assembling structure applies prestressing force for segmentation, takes measures to be to apply this in the position of required section construction Semi-fixed type anchorage in utility model.Anchorage through-thickness half is located at post side groove 13, and second half is located at beam-ends groove It is to provide intensity jointly with pre-buried angle steel 6 after prestress steel relaxation in 14.
(5)This assembling structure is located at every layer of centre position due to the block position of Column border node, according to structural mechanics for The calculating of frame model understands that every layer of post center is inflection point, bears the position that moment of flexure is 0, and this clever structure uses this Bar specification so that junction is substantially solely subjected to axle power effect, it is to avoid the influence of junction bending moment destruction.
(6)The presstressed reinforcing steel of this assembling structure beam can be prestressing force spiral or steel strand wires form, post prestressing force Muscle should be steel strand wires form.
The utility model is further described below in conjunction with specific embodiment, carries out the architectural design in house, according to Construction drawing carries out pouring for the components such as prefabrication post, beam, wall.After manufacturer's standard maintenance reaches intensity, job site is transported to.
Embodiment 1:Cast-in-situ floor prefabricated PC structure
After the completion of basis pours according to design requirement, in each column foundation centerline, steel strand wires are fixed on the pre- of basis On embedded part, the cylinder for after applies prestressing force and provides fixing end.Afterwards again start lift bottom layer node post, lift it is adjacent across During beam, following two construction technologies are taken:Arrangement is spread from corner to center, or arrangement is spread from center to side.
Corner is to center arrangement:After the completion of corner post 1a assemblings, transport transverse and longitudinal adjacent across beam a, b to floor height Place, one end is erected on post on pre-buried angle steel 6, and the other end is first fixed with equipment.Two adjacent with the longitudinal axis and transverse axis are set up again Root node column 2a, 3a, before this, the beam near corner post on column 2a, 3a connects semifixed anchor is worn on prestressed pore passage 5 Tool.Next connecting prestressed pore passage 5 in beam wears presstressed reinforcing steel, the circle of the semifixed anchorage on the front pillar that presstressed reinforcing steel is needed guiding through Hole.Fixed with anchorage at two ends after the tensioning of two ends, the anchorage is placed in post side groove 13, the beam-ends fixing equipment before releasing is entered The assembling of next group of row.When carrying out the assembling of node post 4, beam c, d first pass through before semifixed anchorage on node post 2a, 3a Presstressed reinforcing steel, roof beam structure one end is erected on the pre-buried angle steel 6 of 2a, 3a post, the other end is fixed with equipment.Again will along beam c, The node post 4a assemblings that d directions have worn semifixed anchorage are in place, and cross girders c, d two ends tensioning is entered afterwards, and anchorage is fixed.One beam Post rectangular cells just assemble completion, then above-mentioned steps are repeated, you can complete the assembling of flood.
Back enters the wet trade of andante again after the completion of this layer of beam column assembling, and setting reinforcing bar and plate at hole 9 is connected in the plate of beam Muscle connects integral cast-in-situ, after the intensity of plate reaches to a certain degree by carry out next layer of assembling.
Adjacent layer be assemblied in complete all components of bottom assembling after, 1b is installed on 1a so that 1a tops insert Muscle hole 3 is mutually twisted with the joint bar 4 of 1b bottoms, completes to fix after the treatment of the cement mortar cementation of fissures, according to the similar dress of ground floor Method of completing the square can equally complete the assembling of the second layer and pouring for plate, be finally completed the prestressing force assembling of agent structure.
After the completion of overall structure assembling, the prestressed stretch-draw anchor of cylinder is carried out on top mode post, complete node Combining closely for post, completes structurally waterproof by the cementation of fissures treatment that the seam default wide of its all outer surfaces carries out cement mortar afterwards.
Center is arranged to side:It is consistent with above-mentioned settled principle, but different with the requirement in place can be adopted based on the duration Take the mode of being implemented as follows:
The column 1a at overall structure center is chosen, all of beam of surrounding connects prestressed pore passage 5 and wears semifixed anchorage, diagonally It is alternately interspersed, on the basis of being placed in.Four erections of beam are carried out simultaneously, and beam a, b, c, d are each passed through the semifixed anchorage muscle at place, It is erected on the pre-buried angle steel 6 of post 1a, the other end is fixed with four equipment.Column 2a, 3a, 4a, 5a of surrounding are leaned on again The beam of nearly post 1a connects semifixed anchorage is worn on prestressed pore passage 5, and is positioned in basis.Next can two ends tensioning beam a, Fixed with anchorage at two ends after b, c, d, the anchorage is placed in post side groove 13.Beam-ends fixing equipment before releasing, completes ten Word cell is assembled.For example above-mentioned step of arrangement afterwards repeats conjunction and can both complete overall assembling to center arrangement method with reference to side With structurally waterproof treatment.
Embodiment 2:Precast floor slab(Band door and window wall)Prefabricated PC structure
Early stage operation is identical with example 1, the assembling until completing post and lintel system.The assembly method of post and lintel system can also be taken Next above-mentioned Bian Xiang centers and center carry out the assembling of prefabricated board and beam again to two kinds of side construction technology, take following method: The plate that the elbow reinforcing bar of prefabricated board is inserted in beam to it is connected into hole 9, two bottom carry out elbow reinforcing bar it is substantially stationary i.e. The combination of beam slab can be completed.If following also prefabricated wall, by wall body construction from top to bottom along post sideslip groove by wall On body insert plate, while the convex key 12 of reinforcing bar on plate plays fixation to the bottom of wall.The overall assembling of bottom is completed, for The assembly method of adjacent layer, adjacent layer can be completed with reference to the beam column assembly method of this layer of beam slab wall assembly method and example one Overall assembling.Until structure is performed integrally assembling.
After the completion of overall structure assembling, the prestressed stretch-draw anchor of cylinder is carried out on top mode post, complete node Combining closely for post, completes structurally waterproof by the cementation of fissures treatment that the seam default wide of its all outer surfaces carries out cement mortar afterwards. This case method can more meet the requirement of quick-assembling, substantially depart from wet trade operation.With good application prospect.

Claims (8)

1. a kind of complete precast prestressed fabricated construction, it is characterised in that:Prefabricated node post is provided with pre- answering in this fabricated construction Power duct, joint bar hole, joint bar, beam connects prestressed pore passage, styletable groove, post side groove, pre-buried angle steel;Precast beam is provided with post company Prestressed pore passage, beam-ends groove, plate connects hole;Armoured concrete slab is provided with elbow reinforcing bar, the convex key of reinforcing bar;Beam passes through duct and post Even along direction alignment and total length insertion where beam, perforate central point is located at beam section neutral axis, enters at two ends prestressed pore passage Row post-tensioned construction is fixed, when when several few, can be along the elongated tensioning of building;When several more, can along one across or it is several Across subsection tension;When the position that all structures are connected with each other is with external environment directly contact, set wide in single element joints It is 100mm, depth is the groove of 20mm, and the packing material of groove is cement mortar or mixed mortar.
2. a kind of complete precast prestressed fabricated construction according to claim 1, it is characterised in that:The armored concrete The often section length of node post 1 is design floor height, wherein every section of the root post bottom one is 1.5 times of floor heights, and bottom segmented column Can be according to general house structure design with basis consolidation design.
3. a kind of complete precast prestressed fabricated construction according to claim 1, it is characterised in that:The prestressed pore passage Need to apply fixing end of the built-in fitting as tensioning at basis in advance, post applies prestressing force and completes laggard in the connection of whole root post OK.
4. a kind of complete precast prestressed fabricated construction according to claim 1, it is characterised in that:The armored concrete Plate, when being inner panel, four end outreach are the half of deck-siding;During for side plate or gusset, armoured concrete slab extension elongation is Deck-siding.
5. a kind of complete precast prestressed fabricated construction according to claim 1, it is characterised in that:It is described it is all of it is pre- should Power duct aperture is 50mm, and common duct is 30mm.
6. a kind of complete precast prestressed fabricated construction according to claim 1, it is characterised in that:It is flat where pre-buried angle steel A circular hole mutually run through with the elbow reinforcing bar of upper plate is opened up in face.
7. a kind of complete precast prestressed fabricated construction according to claim 1, it is characterised in that:Post side groove, beam-ends The groove depth of groove is the half of semi-fixed type anchorage thickness, and fluting shape matches with selected anchorage shape.
8. a kind of complete precast prestressed fabricated construction according to claim 1, it is characterised in that:Semifixed anchorage(15) It is holes anchoring type, wherein a hole has consolidated presstressed reinforcing steel(14), consolidation muscle length is that every span length's degree adds 1m again, as one Across tensioning fixing end;An other hole waits the tensioning of adjacent span prestressed beam muscle.
CN201620706988.8U 2016-07-07 2016-07-07 Full precast prestressed assembly structure Expired - Fee Related CN206189590U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620706988.8U CN206189590U (en) 2016-07-07 2016-07-07 Full precast prestressed assembly structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620706988.8U CN206189590U (en) 2016-07-07 2016-07-07 Full precast prestressed assembly structure

Publications (1)

Publication Number Publication Date
CN206189590U true CN206189590U (en) 2017-05-24

Family

ID=58736329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620706988.8U Expired - Fee Related CN206189590U (en) 2016-07-07 2016-07-07 Full precast prestressed assembly structure

Country Status (1)

Country Link
CN (1) CN206189590U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558606A (en) * 2017-09-09 2018-01-09 山东科技大学 A kind of prefabricated construction construction method
CN107905369A (en) * 2017-12-25 2018-04-13 合肥工业大学 Assembling frame beam-column connection
WO2019196627A1 (en) * 2018-04-11 2019-10-17 蔡瑶生 Method for constructing building frame and building frame
CN113502915A (en) * 2021-07-24 2021-10-15 中机工程有限公司 Assembled concrete building beam column node connecting structure and hoisting process

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107558606A (en) * 2017-09-09 2018-01-09 山东科技大学 A kind of prefabricated construction construction method
CN107905369A (en) * 2017-12-25 2018-04-13 合肥工业大学 Assembling frame beam-column connection
CN107905369B (en) * 2017-12-25 2024-02-23 合肥工业大学 Assembled frame beam column connection node
WO2019196627A1 (en) * 2018-04-11 2019-10-17 蔡瑶生 Method for constructing building frame and building frame
CN113502915A (en) * 2021-07-24 2021-10-15 中机工程有限公司 Assembled concrete building beam column node connecting structure and hoisting process

Similar Documents

Publication Publication Date Title
CN107165272B (en) Prestressed assembled concrete frame node connecting structure and construction method thereof
CN101769008B (en) Method for constructing quake-proof masonry house by utilizing prefabricated constructional column ring beams
CN206189590U (en) Full precast prestressed assembly structure
CN107587605A (en) A kind of complete precast prestressed fabricated construction and its construction method
CN206070562U (en) Subassembly formula underground structure
CN106677339A (en) Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method
CN109469202A (en) Prestressed assembly integral concrete frame structure system and construction method thereof
CN106168035A (en) The subassembly formula construction method of subassembly formula underground structure and underground structure
CN106436893A (en) Fully-prefabricated structure and construction method thereof
CN103711330B (en) A kind of prestressing force assembling precast reinforced concrete frame reinforces the method for existing structure
CN108179809A (en) The connection method of assembled steel tendon concrete frame structure component
CN110700103B (en) Construction method of continuous composite beam
CN107090908B (en) A kind of vertical prefabricated components joint connecting method
CN209443571U (en) A kind of large span fabricated construction self-balancing tenon-prestressing combination connecting node
CN110258789A (en) A kind of beam-column connection and its construction method that energy consumption rod iron is replaceable
CN104314167B (en) Prestressed assembly type building and assembly method thereof
CN109235637A (en) A kind of large span fabricated construction self-balancing tenon-prestressing combination connecting node
CN212613903U (en) Brick-concrete structure old building body composite reinforcement structure
CN106499045A (en) A kind of prefabricated composite construction parapet and construction method
CN108166629A (en) A kind of detachable assembling type steel core concrete column-connected mode and its construction method
CN205475877U (en) Compound outer thermal insulation walling system of assembled self preservation temperature wallboard
CN115029983B (en) Longitudinal and transverse staggered bidirectional prestress assembly road based on post grouting process and construction method
CN206205139U (en) A kind of prefabricated composite construction parapet
CN110284520B (en) Dry-wet hybrid-connection large-span closed frame plate-column assembly system
CN1186509C (en) Post-stretching prestressed concrete arch bar roof and its construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170524

Termination date: 20170707