CN206189458U CN201621175945.8U CN201621175945U CN206189458U CN 206189458 U CN206189458 U CN 206189458U CN 201621175945 U CN201621175945 U CN 201621175945U CN 206189458 U CN206189458 U CN 206189458U
Authority
CN
China
Prior art keywords
prefabricated
tube coupling
prefabricated tube
plate
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621175945.8U
Other languages
Chinese (zh)
Inventor
向辉兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuyou Zhizao Technology Investment Co., Ltd
Original Assignee
China Mingsheng Drawin Technology Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mingsheng Drawin Technology Investment Co Ltd filed Critical China Mingsheng Drawin Technology Investment Co Ltd
Priority to CN201621175945.8U priority Critical patent/CN206189458U/en
Application granted granted Critical
Publication of CN206189458U publication Critical patent/CN206189458U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model belongs to municipal architecture engineering field discloses a multi -deck formula piping lane, and first cabin and second cabin are formed by the vertical concatenation of the prefabricated tube coupling of the first prefabricated tube coupling of multisection and second respectively, and settings of transversely aliging of first prefabricated tube coupling and the prefabricated tube coupling of second is equipped with one row at least prefabricated intermediate lamella between first prefabricated tube coupling and the second prefabrication tube coupling, and first prefabricated tube coupling and second prefabrication tube coupling include interior plate and outer panel, interior plate upper portion and the both sides on prefabricated intermediate lamella upper portion all are equipped with first connecting portion, the outer panel lower part and the both sides of prefabricated intermediate lamella lower part all are equipped with the second connecting portion, and first connecting portion link to each other through the coincide roof, and the second connecting portion link to each other through cast -in -place bottom plate. The utility model discloses structural integrity is good, it is lower to connect the cost, and transportation, the hoist and mount degree of difficulty of member reduce, and the efficiency of construction improves, and construction cycle is short, and site work measure reductions, water repellent's degree of difficulty reduction, and the seal plate can prevent effectively that year post -construction of a specified duration from stitching crack and water seepage's a problem.

Description

A kind of many cabin formula piping lanes
Technical field
The utility model belongs to civic building engineering field, and in particular to a kind of many cabin formula piping lanes.
Background technology
Traditional underground pipe gallery construction is typically the following two kinds mode:One is field cast-in-place, and two is prefabrication;Scene is existing The all working for pouring formula underground pipe gallery is completed at the scene, so side wall and top board are intended to configuration template, not only causes a large amount of moulds The waste of plate, while long construction period, to ensure the operating space of construction, earthwork excavated volume is big, and backfill amount is also larger, causes life The construction period extended while the increase for producing cost, all raw material transports to scene with bulk form, and the making at scene is right The ecological environment on periphery can also shine into destruction and pollute, and requirement is high to manually vibrating for the mode of cast-in-site, and vibrate unreal piping lane The possibility that micro-crack occurs in later stage is larger, can leave leakage hidden trouble.Prefabricated piping lane spliced at the scene by the prefabricated tube coupling of more piece and Into, this kind of mode causes the splicing seams of piping lane more, and the waterproof requirement at splicing seams is high, and difficulty is big, for city integrated piping lane, Using full prefabrication system, prefabricated piping lane weight is likely to be breached tens tons, causes factory to manufacture difficult, logistics transportation difficult and live Installation difficulty, and construction cost is high.
In sum, the excellent composite type piping lane of a kind of cost savings of exploitation, easy construction, water resistance is needed badly.
Utility model content
The purpose of this utility model is to provide the excellent many cabin formula piping lanes of a kind of cost savings, easy construction, water resistance.
Above-mentioned purpose is to be achieved through the following technical solutions:A kind of many cabin formula piping lanes, at least including the first cabin and the second cabin, First cabin and the second cabin are respectively by the prefabricated tube coupling of more piece first and the second prefabricated tube coupling is longitudinal spliced forms, and described first is pre- Tubulation section and the second prefabricated laterally aligned setting of tube coupling, at least one is provided between the first prefabricated tube coupling and the second prefabricated tube coupling Prefabricated intermediate plate is arranged, the first prefabricated tube coupling and the second prefabricated tube coupling include interior plate and outer panel, the interior plate top And the both sides on the prefabricated intermediate plate top are equipped with first connecting portion, the outer panel bottom and the prefabricated intermediate plate The both sides of bottom are equipped with second connecting portion, and the first connecting portion is connected by overlapping top board, and the second connecting portion passes through Cast-in-place base plate is connected.
Big, the weight weight for large-scale synthesis formula piping lane volume, prefabrication difficulty is big, and cost of transportation is high, and on-site consolidation is difficult Problem, the utility model using it is prefabricated and it is cast-in-place be combined by the way of, on the one hand the first prefabricated tube coupling and the second prefabricated tube coupling By the way of prefabrication on-site consolidation, behind the first cabin and the second cabin configuration, using prefabricated intermediate plate as connection bridge, bottom Portion carries out cast-in-place connection, and the cast-in-place of casting top slab, and then the cabin in the middle of configuration, this practicality are carried out after the hoisting prefabricated top board in top New structure good integrity, link cost are relatively low, and scene drops without formwork supporting plate, the transport of component and the hoisting difficulty at scene Low, efficiency of construction is greatly improved, short construction period, and the amount of casting and compacting of concrete is significantly reduced, and reduces the workload of site operation, By the way of part is cast-in-place, the construction joint of component is also significantly reduced, the difficulty reduction of water-proofing treatment, the machine that infiltration hidden danger occurs Rate is smaller.
Further, the prefabricated intermediate plate is provided with U-shaped mouth, and the overlapping top board includes prefabricated top board and casting top slab, institute State casting top slab and extend to U-shaped mouth bottom.It is arranged such, one side casting top slab is more preferable with the globality of prefabricated intermediate plate, separately On the one hand the joint face of the two is thoroughly covered by casting top slab, eliminates infiltration hidden danger.
Further, the overlapping top board includes prefabricated top board and casting top slab, and the casting top slab is prefabricated with described first It is provided with seal plate at tube coupling, the connecting sewing of the second prefabricated tube coupling, it is the cast-in-place base plate and the described first prefabricated tube coupling, second prefabricated Seal plate is provided with the connecting sewing of tube coupling and prefabricated intermediate plate.Seal plate is set at above-mentioned splicing seams, can effectively prevent older The problem of construction joint crack and water leakage, can reach permanent waterproof effect afterwards.
Further, the first connecting portion is support bracket, and the both sides of the prefabricated top board are overlapped on are arranged on horizontal stroke respectively To on the support bracket being disposed adjacent.Prefabricated tube coupling after prefabricated top board is shelved on support bracket, is being entered using support bracket The quantity of scene support and the usage amount of end template can be reduced in the casting process of row casting top slab.
Further, the casting top slab sets with the seal plate at the connecting sewing of the first prefabricated tube coupling and the second prefabricated tube coupling Put in the top of support bracket, the seal plate side is anchored in the interior plate of the first prefabricated tube coupling or the second prefabricated tube coupling, Opposite side is anchored in casting top slab.In this way, water can effectively be prevented along casting top slab and the first prefabricated tube coupling and the second prefabricated pipe The top of the connecting sewing of section is penetrated into, and improves the waterproof effect of piping lane.
Further, the second connecting portion is base plate of encorbelmenting, and the base plate of encorbelmenting is provided with recessed with the connection end of cast-in-place base plate Mouthful.It is arranged such, increases encorbelment base plate and the contact area of cast-in-place base plate, that is, increases encorbelment base plate and the bonding of cast-in-place base plate Power, improves the globality of piping lane.
Further, the cast-in-place base plate sets with the seal plate at the connecting sewing of the first prefabricated tube coupling and the second prefabricated tube coupling Put in the recess, the seal plate side is anchored in base plate of encorbelmenting, and opposite side is anchored in cast-in-place base plate.In this way, can Effectively prevent water from being penetrated into along the bottom of casting top slab and the connecting sewing of the first prefabricated tube coupling and the second prefabricated tube coupling, improve piping lane Waterproof effect.It is preferred that, splash guard also is provided with the recess of the base plate of encorbelmenting of prefabricated intermediate plate, so cast-in-place base plate and bottom of encorbelmenting The connecting sewing of plate takes splash guard and carries out water-proofing treatment.
Further, it is provided with dowel in the cast-in-place base plate and casting top slab, the first prefabricated tube coupling and second prefabricated Sleeve is provided with tube coupling, the sleeve is fixedly connected with dowel.Prefabricated piping lane uses sleeve connection with cast-in-place part, makes prefabricated Piping lane and cast-in-place part are connected as a single entity, and globality is strengthened.The sleeve can be screw thread mouth, one in the dowel insertion sleeve It is the end of thread to hold, and the two uses grout sleeve, dowel to connect using grouting with grout sleeve using threaded connection, or sleeve Connect.It is preferred that, sleeve also is provided with prefabricated intermediate plate, and be connected with the dowel in cast-in-place base plate and/or casting top slab.
Further, the prefabricated top board is provided with structure muscle, and the structure muscle stretches out the top surface of prefabricated top board and is anchored at existing In pouring top board.It is arranged such, prefabricated top board is more preferable with the globality of casting top slab, and the intensity of casting top slab is bigger, can be effective Increase the ability of resistance to compression and the shearing resistance of casting top slab.
Further, the top board top of the described first prefabricated tube coupling and/or the second prefabricated tube coupling is provided with bar-mat reinforcement, described cast-in-place Top board extends to the top board top of the first prefabricated tube coupling and/or the second prefabricated tube coupling.It is arranged such, equivalent in whole piping lane Top is provided with one layer of in-situ layer, and not only globality is more preferable, and in-situ layer covers horizontal seam connector of the present utility model, significantly Increased the water proofing property of piping lane.
Further, the described first prefabricated tube coupling, the second prefabricated tube coupling and the prefabricated intermediate plate are provided with anchor rib, described Anchor rib one end is anchored in the first prefabricated tube coupling, the second prefabricated tube coupling or prefabricated intermediate plate, and the other end is anchored at casting top slab In.It is arranged such, globality of the present utility model is more preferable.
Further, the top board of the described second prefabricated tube coupling is less than the top board of the described first prefabricated tube coupling, and described second is prefabricated The side plate near the first prefabricated tube coupling of tube coupling extends to the top board top of the second prefabricated tube coupling.It is arranged such, when second prefabricated When the space requirement of tube coupling is not high, accordingly reduce the sectional dimension of component, the difficulty reduction of production, the transport of component and scene Hoisting difficulty reduce.In such cases, the first connecting portion of the second prefabricated tube coupling should be with the first of the first prefabricated tube coupling Connecting portion alignment is set.
Further, the described first prefabricated tube coupling, the second prefabricated tube coupling and prefabricated intermediate plate are longitudinally provided with prestressing force and wear muscle hole, The prestressing force is equipped with presstressed reinforcing steel in wearing muscle hole.In this way, applying certain stress by presstressed reinforcing steel so that longitudinal direction sets The prefabricated tube coupling of more piece put and prefabricated intermediate plate are closely coupled, reduce as far as possible between longitudinally disposed prefabricated tube coupling and Gap between prefabricated intermediate plate so that its Mosaic face is closely adjacent to, improves the globality and water proofing property of piping lane.
Further, the prefabricated intermediate plate is provided with tensioning and stamps, and the prestressing force on the prefabricated intermediate plate is worn muscle hole and is arranged on The tensioning is stamped.
Further, the prestressing force of the first prefabricated tube coupling and the second prefabricated tube coupling wears muscle hole and is arranged on the first prefabricated tube coupling and The corner inner side of two prefabricated tube couplings.
Brief description of the drawings
The accompanying drawing for constituting a part of the present utility model is used for providing being further understood to of the present utility model, and this practicality is new The schematic description and description of type is used to explain the utility model, does not constitute to improper restriction of the present utility model.
Fig. 1 is the horizontal section schematic diagram of four cabin piping lanes involved by a kind of implementation method of the utility model;
Fig. 2 is the generalized section of the first prefabricated tube coupling involved by a kind of implementation method of the utility model;
Fig. 3 is the generalized section of the second prefabricated tube coupling involved by a kind of implementation method of the utility model;
Fig. 4 and Fig. 5 are respectively the generalized section of the prefabricated intermediate plate involved by a kind of implementation method of the utility model;
Fig. 6 is the connecting node schematic diagram of overlapping top board and the first prefabricated tube coupling involved in Fig. 1;
Fig. 7 is the connecting node schematic diagram of cast-in-place base plate and the first prefabricated tube coupling involved in Fig. 1;
Fig. 8 is the connecting node schematic diagram of overlapping top board and the second prefabricated tube coupling involved in Fig. 1;
Fig. 9 is the connecting node schematic diagram of overlapping top board and prefabricated intermediate plate involved in Fig. 1.
In figure:
The prefabricated tube coupling of 1 first cabin, 2 second cabin, 3 prefabricated intermediate plate 4 first
The prefabricated top board of 5 second prefabricated tube coupling, 6 interior plate, 7 outer panel 8
9 10 cast-in-place base plate of casting top slab, 11 seal plate 12 supports bracket
13 encorbelment the sleeve of 14 recess of base plate, 15 dowel 16
The prestressing force of 17 structure muscle, 18 bar-mat reinforcement, 19 anchor rib 20 wears muscle hole
22 U-shaped mouths are stamped in 21 tensioning
Specific embodiment
The utility model is described in detail below in conjunction with the accompanying drawings, the description of this part be only it is exemplary and explanatory, There should not be any restriction effect to protection domain of the present utility model.Additionally, those skilled in the art's retouching according to presents State, respective combination can be carried out to the feature in embodiment in presents and in different embodiments.
The utility model embodiment is as follows, reference picture 1:A kind of many cabin formula piping lanes, at least including the first cabin 1 and the second cabin 2, The cabin 2 of first cabin 1 and second is formed by the prefabricated tube coupling 5 of the prefabricated tube coupling of more piece first 4 and second is longitudinal spliced respectively, and described One prefabricated tube coupling 4 and the laterally aligned setting of the second prefabricated tube coupling 5, set between the prefabricated tube coupling 5 of the first prefabricated tube coupling 4 and second There is the prefabricated intermediate plate 3 of an at least row, the prefabricated tube coupling 5 of the first prefabricated tube coupling 4 and second includes interior plate 6 and outer panel 7, institute The both sides for stating the top of interior plate 6 and the top of prefabricated intermediate plate 3 are equipped with first connecting portion, the bottom of the outer panel 7 with And the both sides of the bottom of prefabricated intermediate plate 3 are equipped with second connecting portion, the first connecting portion is connected by overlapping top board, institute Second connecting portion is stated to be connected by cast-in-place base plate 10.
Big, the weight weight for large-scale synthesis formula piping lane volume, prefabrication difficulty is big, and cost of transportation is high, and on-site consolidation is difficult Problem, the utility model using it is prefabricated and it is cast-in-place be combined by the way of, on the one hand the first prefabricated tube coupling 4 and the second prefabricated tube coupling 5 by the way of prefabrication on-site consolidation, behind the first cabin 1 and the configuration of the second cabin 2, using prefabricated intermediate plate 3 as connecting bridge Beam, bottom carries out cast-in-place connection, and the cast-in-place of casting top slab 9, and then the cabin in the middle of configuration are carried out after the hoisting prefabricated top board 8 in top Room, the utility model structural integrity is good, link cost is relatively low, and scene is without formwork supporting plate, the transport of component and hanging for scene Dress difficulty is reduced, and efficiency of construction is greatly improved, short construction period, and the amount of casting and compacting of concrete is significantly reduced, and reduction scene is applied The workload of work, by the way of part is cast-in-place, the construction joint of component is also significantly reduced, the difficulty reduction of water-proofing treatment, infiltration The probability that hidden danger occurs is smaller.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 5, the prefabricated intermediate plate 3 is provided with U Type mouthful 22, the overlapping top board includes prefabricated top board 8 and casting top slab 9, and the casting top slab 9 extends to the bottom of U-shaped mouth 22.Such as This is set, and one side casting top slab 9 is more preferable with the globality of prefabricated intermediate plate 3, and on the other hand the joint face of the two is thoroughly showed Pour top board 9 to cover, eliminate infiltration hidden danger.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 6, Fig. 8 and Fig. 9, the overlapping top board Including prefabricated top board 8 and casting top slab 9, the casting top slab 9 and the described first prefabricated tube coupling 4, the connection of the second prefabricated tube coupling 5 Seal plate 11, the cast-in-place base plate 10 and the described first prefabricated tube coupling 4, the second prefabricated tube coupling 5 and prefabricated intermediate plate 3 are provided with seam Connecting sewing at be provided with seal plate 11.Seal plate 11 is set at above-mentioned splicing seams, and construction joint ftractures long afterwards can effectively to prevent year The problem of infiltration, can reach permanent waterproof effect.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 2~6, the first connecting portion is branch Support bracket 12, the both sides of the prefabricated top board 8 are overlapped on the support bracket 12 for being arranged on laterally adjacent setting respectively.Prefabricated pipe Be shelved on for prefabricated top board 8 after supporting on bracket 12, in the casting process for carrying out casting top slab 9 by section using support bracket 12 The quantity of scene support and the usage amount of end template can be reduced.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 2~9, the casting top slab 9 and the Seal plate 11 at the connecting sewing of one prefabricated tube coupling 4 and the second prefabricated tube coupling 5 is arranged on the top of support bracket 12, described to stop The side of water plate 11 is anchored in the interior plate 6 of the first prefabricated prefabricated tube coupling 5 of tube coupling 4 or the second, and opposite side is anchored at casting top slab 9 In.In this way, can effectively prevent from being oozed at the top of connecting sewing of the water along casting top slab 9 with the first prefabricated tube coupling 4 and the second prefabricated tube coupling 5 Enter, improve the waterproof effect of piping lane.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 2~5, the second connecting portion is outstanding Base plate 13 is chosen, the base plate 13 of encorbelmenting is provided with recess 14 with the connection end of cast-in-place base plate 10.It is arranged such, increases base plate 13 of encorbelmenting With the contact area of cast-in-place base plate 10, that is, increase encorbelment base plate 13 and the cohesive force of cast-in-place base plate 10, improve the globality of piping lane.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1 and Fig. 7, the cast-in-place base plate 10 with Seal plate 11 at the connecting sewing of the first prefabricated tube coupling 4 and the second prefabricated tube coupling 5 is arranged in the recess 14, the sealing The side of plate 11 is anchored in base plate 13 of encorbelmenting, and opposite side is anchored in cast-in-place base plate 10.In this way, water can effectively be prevented along cast-in-place top The bottom of the connecting sewing of the prefabricated tube coupling 4 of plate 9 and first and the second prefabricated tube coupling 5 is penetrated into, and improves the waterproof effect of piping lane.It is preferred that, Splash guard also is provided with the recess 14 of the base plate 13 of encorbelmenting of prefabricated intermediate plate 3, so cast-in-place base plate 10 and base plate 13 of encorbelmenting Connecting sewing takes splash guard and carries out water-proofing treatment.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1 and Fig. 6~9, the cast-in-place base plate 10 and casting top slab 9 in be provided with dowel 15, be provided with sleeve 16 in the prefabricated tube coupling 5 of the first prefabricated tube coupling 4 and second, it is described Sleeve 16 is fixedly connected with dowel 15.Prefabricated piping lane is connected with cast-in-place part using sleeve 16, makes prefabricated piping lane and cast-in-place portion Divide and be connected as a single entity, globality is strengthened.The sleeve 16 can be screw thread mouth, and one end is spiral shell in the insertion sleeve 16 of the dowel 15 Line end, the two uses grout sleeve 16, dowel 15 to connect using grouting with grout sleeve 16 using threaded connection, or sleeve 16 Connect.It is preferred that, also be provided with sleeve 16 in prefabricated intermediate plate 3, and with cast-in-place base plate 10 and/or casting top slab 9 in the phase of dowel 15 Even.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1, the prefabricated top board 8 is provided with structure Muscle 17, the structure muscle 17 stretches out the top surface of prefabricated top board 8 and is anchored in casting top slab 9.Be arranged such, prefabricated top board 8 with More preferably, and the intensity of casting top slab 9 is bigger the globality of casting top slab 9, can be effectively increased the resistance to compression and shearing resistance of casting top slab 9 Ability.
On the basis of above-described embodiment, in another embodiment of the utility model, first is prefabricated as described in Fig. 1, Fig. 6 and Fig. 8 The top board top of the prefabricated tube coupling 5 of tube coupling 4 and/or second is provided with bar-mat reinforcement 18, and the casting top slab 9 extends to the first prefabricated tube coupling 4 and/or second prefabricated tube coupling 5 top board top.Be arranged such, equivalent to the top of whole piping lane be provided with one layer it is cast-in-place Layer, not only globality is more preferable, and in-situ layer covers horizontal seam connector of the present utility model, considerably increases the waterproof of piping lane Property.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1, Fig. 6 and Fig. 8, described first is prefabricated Tube coupling 4, the second prefabricated tube coupling 5 and the prefabricated intermediate plate 3 are provided with anchor rib 19, and the one end of the anchor rib 19 is anchored at first In prefabricated tube coupling 4, the second prefabricated tube coupling 5 or prefabricated intermediate plate 3, the other end is anchored in casting top slab 9.It is arranged such, this reality It is more preferable with new globality.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1 and Fig. 3, the second prefabricated tube coupling 5 top board is less than the top board of the described first prefabricated tube coupling 4, the side plate near the first prefabricated tube coupling 4 of the second prefabricated tube coupling 5 Extend to the top board top of the second prefabricated tube coupling 5.It is arranged such, when the space requirement of the second prefabricated tube coupling 5 is not high, accordingly subtracts The sectional dimension of primary structural component, the difficulty reduction of production, the transport of component and the hoisting difficulty at scene are reduced.This kind of situation Under, the first connecting portion of the second prefabricated tube coupling 5 should align setting with the first connecting portion of the first prefabricated tube coupling 4.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1~5, the first prefabricated tube coupling 4, Second prefabricated tube coupling 5 and the longitudinal direction of prefabricated intermediate plate 3 are provided with prestressing force and wear muscle hole 20, and the prestressing force is worn and be equipped with muscle hole 20 pre- Stress rib.In this way, applying certain stress by presstressed reinforcing steel so that the prefabricated tube coupling of longitudinally disposed more piece and it is prefabricated in Between plate 3 it is closely coupled, the gap between longitudinally disposed prefabricated tube coupling and between prefabricated intermediate plate 3 is reduced as far as possible, make Obtain its Mosaic face to be closely adjacent to, improve the globality and water proofing property of piping lane.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 4, the prefabricated intermediate plate 3 is provided with to be opened Drawing stamps 21, and the prestressing force on the prefabricated intermediate plate 3 wears muscle hole 20 and is arranged on the tensioning and stamps on 21.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 2 and Fig. 3, the He of the first prefabricated tube coupling 4 The prestressing force of the second prefabricated tube coupling 5 wears the corner inner side that muscle hole 20 is arranged on the first prefabricated tube coupling 4 and the second prefabricated tube coupling 5.
The above is only preferred embodiment of the present utility model, it is noted that for the common skill of the art For art personnel, on the premise of the utility model principle is not departed from, some improvements and modifications can also be made, these improve and Retouching also should be regarded as protection domain of the present utility model.

Claims (10)

1. a kind of many cabin formula piping lanes, at least including the first cabin and the second cabin, first cabin and the second cabin are respectively by more piece first Prefabricated tube coupling and the second prefabricated tube coupling is longitudinal spliced forms, the first prefabricated tube coupling and the second prefabricated tube coupling is laterally aligned sets Put, it is characterised in that at least prefabricated intermediate plate of a row, described are provided between the first prefabricated tube coupling and the second prefabricated tube coupling One prefabricated tube coupling and the second prefabricated tube coupling include interior plate and outer panel, on the interior plate top and the prefabricated intermediate plate The both sides in portion are equipped with first connecting portion, and the both sides of the outer panel bottom and the prefabricated intermediate plate bottom are equipped with second Connecting portion, the first connecting portion is connected by overlapping top board, and the second connecting portion is connected by cast-in-place base plate.
2. many cabin formula piping lanes according to claim 1, it is characterised in that the prefabricated intermediate plate is provided with U-shaped mouth, described folded Closing top board includes prefabricated top board and casting top slab, and the casting top slab extends to U-shaped mouth bottom.
3. many cabin formula piping lanes according to claim 1, it is characterised in that the overlapping top board includes prefabricated top board and cast-in-place Top board, seal plate is provided with the casting top slab and the described first prefabricated tube coupling, the connecting sewing of the second prefabricated tube coupling, described cast-in-place Seal plate is provided with base plate and the connecting sewing of the described first prefabricated tube coupling, the second prefabricated tube coupling and prefabricated intermediate plate.
4. many cabin formula piping lanes according to claim 3, it is characterised in that the first connecting portion is support bracket, described The both sides of prefabricated top board are overlapped on the support bracket for being arranged on laterally adjacent setting respectively.
5. many cabin formula piping lanes according to claim 4, it is characterised in that the casting top slab and the first prefabricated tube coupling and Seal plate at the connecting sewing of the second prefabricated tube coupling is arranged on the top of support bracket, and it is pre- that the seal plate side is anchored at first In the interior plate of tubulation section or the second prefabricated tube coupling, opposite side is anchored in casting top slab.
6. many cabin formula piping lanes according to claim 5, it is characterised in that the second connecting portion is base plate of encorbelmenting, described Base plate of encorbelmenting is provided with recess, the cast-in-place base plate and the first prefabricated tube coupling and the second prefabricated tube coupling with the connection end of cast-in-place base plate Connecting sewing at seal plate be arranged in the recess, the seal plate side is anchored in base plate of encorbelmenting, opposite side anchoring In cast-in-place base plate.
7. many cabin formula piping lanes according to claim 2~6 any one, it is characterised in that the cast-in-place base plate and cast-in-place Dowel is provided with top board, sleeve is provided with the first prefabricated tube coupling and the second prefabricated tube coupling, the sleeve is consolidated with dowel Fixed connection.
8. many cabin formula piping lanes according to claim 7, it is characterised in that the prefabricated top board is provided with structure muscle, the knot Structure muscle stretches out the top surface of prefabricated top board and is anchored in casting top slab.
9. many cabin formula piping lanes according to claim 7, it is characterised in that the first prefabricated tube coupling and/or second prefabricated The top board top of tube coupling is provided with bar-mat reinforcement, and the casting top slab extends to the top of the first prefabricated tube coupling and/or the second prefabricated tube coupling Plate top, the first prefabricated tube coupling, the second prefabricated tube coupling and the prefabricated intermediate plate are provided with anchor rib, the anchor rib one End is anchored in the first prefabricated tube coupling, the second prefabricated tube coupling or prefabricated intermediate plate, and the other end is anchored in casting top slab.
10. many cabin formula piping lanes according to claim 7, it is characterised in that the prefabricated intermediate plate is provided with tensioning and stamps, described First prefabricated tube coupling, the tensioning of the corner inner side of the second prefabricated tube coupling and prefabricated intermediate plate are stamped longitudinal direction and are provided with prestressing force and wear muscle hole, The prestressing force is equipped with presstressed reinforcing steel in wearing muscle hole.
CN201621175945.8U 2016-11-02 2016-11-02 Multi -deck formula piping lane Active CN206189458U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621175945.8U CN206189458U (en) 2016-11-02 2016-11-02 Multi -deck formula piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621175945.8U CN206189458U (en) 2016-11-02 2016-11-02 Multi -deck formula piping lane

Publications (1)

Publication Number Publication Date
CN206189458U true CN206189458U (en) 2017-05-24

Family

ID=58733410

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621175945.8U Active CN206189458U (en) 2016-11-02 2016-11-02 Multi -deck formula piping lane

Country Status (1)

Country Link
CN (1) CN206189458U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555159A (en) * 2018-12-31 2019-04-02 上海城建预制构件有限公司 A kind of prefabricated pipe gallery method for stretching
CN111851328A (en) * 2020-07-06 2020-10-30 海门市帕源路桥建设有限公司 Modular, standardized prefabricating and assembling construction process for box culvert concrete structural steel bars

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555159A (en) * 2018-12-31 2019-04-02 上海城建预制构件有限公司 A kind of prefabricated pipe gallery method for stretching
CN111851328A (en) * 2020-07-06 2020-10-30 海门市帕源路桥建设有限公司 Modular, standardized prefabricating and assembling construction process for box culvert concrete structural steel bars
CN111851328B (en) * 2020-07-06 2021-08-27 海门市帕源路桥建设有限公司 Modular, standardized prefabricating and assembling construction process for box culvert concrete structural steel bars

Similar Documents

Publication Publication Date Title
CN206189455U (en) Piping lane
CN207700443U (en) Exterior wall plate level has muscle grouted joint structure at a kind of fabricated shear wall architecture storey
CN206722878U (en) A kind of mining light-duty filling counterfort
CN105862916A (en) Superimposed assembled type underground pipe gallery system and construction and manufacturing process
CN102691365B (en) Connecting structure for assembly type concrete shear wall edge member
CN105839666A (en) Total-prefabricated superimposed assembly type underground pipe gallery and connecting node thereof
CN208363127U (en) A kind of retaining wall structure of combined type high-speed rail platform
CN206337641U (en) Transverse joint connecting node between a kind of prefabricated board wall layers
CN104878854A (en) Prefabricated shear wall horizontal abutted seam buckle welding built-up connection device
CN206189454U (en) Piping lane
CN108360901A (en) Novel low layer assembled wallboard structure energy dissipating bolt joint
CN108589982A (en) A kind of assembled composite wall structure and its construction method being welded to connect indirectly based on reinforcing bar
CN109024870A (en) The connection structure and its construction method of assembled underground structure vertical member
CN107806114A (en) Basement roof closes late poured band structure and construction method in advance
CN208072706U (en) A kind of connection structure of the prefabricated steel shear wall horizontal joint of slip installation
CN109972630A (en) A kind of foundation pit enclosure structure and its construction method of the assembly of PC component
CN206189458U (en) Multi -deck formula piping lane
CN108625506A (en) A kind of connection method of the prefabricated combined wall board being welded to connect key based on mild steel plate and its construction method
CN106677162B (en) A kind of stiffness composite precast slab stake building enclosure
CN108374493A (en) Novel low layer assembled wallboard structure energy dissipating steel plate welding node
CN206693265U (en) A kind of installation node of piping lane
CN208633847U (en) A kind of corrugated steel supporting construction suitable for circular arch stalk formula tunnel full-section excavation
CN108240037A (en) Transverse joint connecting node between a kind of prefabricated board wall layers
CN206189456U (en) Three cabin piping lanes
CN109972627A (en) A kind of fashioned iron assembled foundation pit enclosure structure and its construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: China Civil Architecture Friends Technology (Jiaozhou) Co., Ltd.

Assignor: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT CO., LTD.

Contract record no.: 2018430000023

Denomination of utility model: Multi -deck formula piping lane

Granted publication date: 20170524

License type: Common License

Record date: 20190102

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Nanning Zhongmin zhuyou Intelligent Manufacturing Technology Co., Ltd

Assignor: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT CO., LTD.

Contract record no.: X2019430000004

Denomination of utility model: Multi -deck formula piping lane

Granted publication date: 20170524

License type: Common License

Record date: 20191105

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Xiangxi Zhongmin zhuyou Technology Co., Ltd

Assignor: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT CO., LTD.

Contract record no.: X2020430000002

Denomination of utility model: Multi -deck formula piping lane

Granted publication date: 20170524

License type: Common License

Record date: 20200305

EE01 Entry into force of recordation of patent licensing contract
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 5 / F, office building 2, Zhongmin zhuyou Co., Ltd., No. 10, Zhongshi Road, shaping street, Kaifu District, Changsha City, Hunan Province, 410000

Patentee after: Zhuyou Zhizao Technology Investment Co., Ltd

Address before: 410205 comprehensive building in Hunan province Changsha Kaifu District, No. 30 Xingang Road, Changsha Jinxia bonded logistics center room 2005

Patentee before: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT Ltd.

EE01 Entry into force of recordation of patent licensing contract

Assignee: Nantong Zhongmin zhuyou Zhizao Technology Co., Ltd

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2020980007488

Denomination of utility model: A multi cabin pipe gallery

Granted publication date: 20170524

License type: Common License

Record date: 20201105

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hunan Yuanfeng Construction Engineering Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980000884

Denomination of utility model: A multi cabin pipe gallery

Granted publication date: 20170524

License type: Common License

Record date: 20210203

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hunan Hailong Construction Engineering Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980001039

Denomination of utility model: A multi cabin pipe gallery

Granted publication date: 20170524

License type: Common License

Record date: 20210207

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Henan fengque Construction Engineering Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980010621

Denomination of utility model: A multi compartment pipe gallery

Granted publication date: 20170524

License type: Common License