CN206189454U - Piping lane - Google Patents

Piping lane Download PDF

Info

Publication number
CN206189454U
CN206189454U CN201621172169.6U CN201621172169U CN206189454U CN 206189454 U CN206189454 U CN 206189454U CN 201621172169 U CN201621172169 U CN 201621172169U CN 206189454 U CN206189454 U CN 206189454U
Authority
CN
China
Prior art keywords
plate
cast
top board
piping lane
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621172169.6U
Other languages
Chinese (zh)
Inventor
谢亮胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuyou Zhizao Technology Investment Co., Ltd
Original Assignee
China Mingsheng Drawin Technology Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mingsheng Drawin Technology Investment Co Ltd filed Critical China Mingsheng Drawin Technology Investment Co Ltd
Priority to CN201621172169.6U priority Critical patent/CN206189454U/en
Application granted granted Critical
Publication of CN206189454U publication Critical patent/CN206189454U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model belongs to municipal architecture engineering field, the utility model discloses a piping lane, constitute by the concatenation of a plurality of tube couplings, the tube coupling includes the bottom plate, curb plate and roof, curb plate bottom is pre -buried to have the connecting sleeve, the bottom plate is cast -in -place bottom plate, be equipped with the splice bar in the cast -in -place bottom plate, splice bar and connecting sleeve fixed connection, the curb plate includes interior plate and outer panel, form U type mouth between interior plate and the outer panel, the roof is including prefabricated roof and cast -in -place layer, prefabricated roof setting is in the interior plate top, cast -in -place layer pours at the top surface of prefabricated roof and extends to U type mouth bottom. The utility model discloses a prefabricated and the cast -in -place mode that combines together is assembled, and structural integrity is good, the connection cost is lower, and waterproof quality obviously promotes, and the transportation and the on -the -spot hoist and mount degree of difficulty of member all reduce, and the efficiency of construction improves greatly, and construction cycle is short.

Description

A kind of piping lane
Technical field
The utility model belongs to civic building engineering field, and in particular to a kind of piping lane.
Background technology
Traditional underground pipe gallery construction is typically the following two kinds mode:One is field cast-in-place, and two is prefabrication;Scene is existing The all working for pouring formula underground pipe gallery is completed at the scene, so side wall and top board are intended to configuration template, not only causes a large amount of moulds The waste of plate, while long construction period, to ensure the operating space of construction, earthwork excavated volume is big, and backfill amount is also larger, causes life The construction period extended while the increase for producing cost, all raw material transports to scene with bulk form, and the making at scene is right The ecological environment on periphery can also shine into destruction and pollute, and the mode of cast-in-site is high to artificial requirement of vibrating, and vibrates unreal, piping lane The possibility that micro-crack occurs in later stage is larger, can leave leakage hidden trouble.Prefabricated piping lane spliced at the scene by the prefabricated tube coupling of more piece and Into, this kind of mode causes the splicing seams of piping lane more, and the waterproof requirement at splicing seams is high, and difficulty is big, for city integrated piping lane, Using full prefabrication system, prefabricated piping lane weight is likely to be breached tens tons, causes factory to manufacture difficult, logistics transportation difficult and live Installation difficulty, and construction cost is high.Existing prefabricated piping lane flank wall plate waterproofing node is reached anti-by using waterproof material closure Water purpose, waterproof type is single, and when seepage occurs in waterproofing node, the cost of overhaul is high, difficulty is big.
In sum, the excellent piping lane of a kind of cost savings of exploitation, easy construction, water resistance is needed badly.
Utility model content
The purpose of this utility model is to provide the excellent piping lane of a kind of cost savings, easy construction, water resistance.
Above-mentioned purpose is to be achieved through the following technical solutions:A kind of piping lane, is spliced to form by multiple tube couplings, the tube coupling bag Base plate, side plate and top board are included, the side plate bottom is embedded with branch sleeve, and the base plate is cast-in-place base plate, the cast-in-place base plate Dowel is inside provided with, the dowel is fixedly connected with branch sleeve, the side plate includes interior plate and outer panel, the inner side U-shaped mouth is formed between plate and outer panel, the top board includes prefabricated top board and in-situ layer, and the prefabricated top board is arranged on interior plate Top, the in-situ layer is cast in the top surface of prefabricated top board and extends to U-shaped mouth bottom.The utility model each tube coupling has many It is combined into cast-in-place part again after individual prefabricated component assembly, such tube coupling component is greatly simplified, while reducing production difficulty, fortune Defeated and live hoisting difficulty is reduced, cost-effective, at the same using it is prefabricated and it is cast-in-place be combined by the way of carry out assembly, side Plate is connected with cast-in-place base plate by branch sleeve and dowel, while being poured in U-shaped mouth between interior plate and outer panel In-situ layer is integral, and structural integrity is good, link cost is relatively low, and waterproof is carried out using in-situ layer at splicing seams, and water resistance is excellent Different, on the other hand, efficiency of construction is greatly improved, short construction period, and relative to cast-in-place pattern, the amount of casting and compacting of concrete substantially subtracts It is few, reduce the workload of site operation.
Further, the either flush of the cast-in-place base plate in or higher than the U-shaped mouth bottom surface.Tube coupling splicing seams are mainly U-shaped intraoral in-situ layer plays waterproof action, the either flush of cast-in-place base plate in or higher than the U-shaped mouth bottom surface, in this way, existing Base plate is poured by the bottom splicing seams covering of the U-shaped mouth of tube coupling, splicing seams seepage of the water along the U-shaped mouth bottom of side plate can be prevented effectively from, carried Water resistance high.
Further, it is described it is U-shaped it is intraoral be provided with the first seal plate, the both sides of first seal plate are located at the tube coupling respectively Between splicing seams both sides.It is arranged such, between the tube coupling and waterproof effect of splicing seams can be increased.
Further, institute first states seal plate for steel plate, and reinforced mesh is welded with first seal plate.It is arranged such, In-situ layer pours rear steel plate for sealing water and is anchored in in-situ layer together with reinforced mesh, the setting of reinforced mesh, considerably increases only Anchor force of the water steel plate in in-situ layer.
Further, the side plate is provided with recess with the connection end of cast-in-place base plate.It is arranged such, increases and survey this and cast-in-place base plate Contact area, that is, increase the cohesive force for surveying this and cast-in-place base plate, improve the globality of piping lane.
Further, the second seal plate is provided with the recess, the second seal plate side is anchored in side plate, opposite side It is anchored in cast-in-place base plate.In this way, can effectively prevent water from being penetrated into the bottom of the connecting sewing of cast-in-place base plate along side plate, piping lane is improved Waterproof effect.
Further, the prefabricated top board and interior plate are connected by template, and the side of the template is connected to prefabricated top board Bottom, opposite side is connected to the inner side of interior plate..In this way, the breach of prefabricated top board and interior plate is blocked, anti-leak-stopping Slurry;It is preferred that, prefabricated top board and interior plate are embedded with branch sleeve in prefabrication process, and template is fixed by bolt with branch sleeve Connection, in this way, not only connect reliable, while after piping lane is molded, being reused after template is removable.It is preferred that, the outer panel Top surface of the top surface higher than the interior plate.
Further, the prefabricated top board is embedded with structure muscle, and the structure muscle at least stretches out the top surface and anchor of prefabricated top board Gu in in-situ layer.It is arranged such, prefabricated top board is more preferable with the globality of in-situ layer, and the intensity of in-situ layer is bigger, can be effective Increase the ability of resistance to compression and the shearing resistance of in-situ layer.
Further, the side plate is provided with girder rib, the girder rib connection interior plate and outer panel and is exposed at U-shaped mouth It is interior.Interior plate is connected with outer panel by girder rib, and the globality between interior plate and outer panel is more preferable, while being exposed at U-shaped Intraoral girder rib is anchored in in-situ layer after in-situ layer is poured, three's good integrity, while increased U-shaped intraoral in-situ layer Intensity.
Further, the interior plate is provided with prefabricated top board and stretches out reinforcing bar, and reinforcing bar is stretched out along inner side in the interior plate Plate top surface stretches out, and the reinforcing bar that stretches out in the prefabricated top board extend out to interior plate top along the two sides of prefabricated top board.In this way, can Increase the globality of interior plate, prefabricated top board and in-situ layer.
Further, the piping lane is longitudinally provided with prestressing force and wears muscle hole, and the prestressing force is equipped with presstressed reinforcing steel in wearing muscle hole. In this way, before cast-in-place, tensioning is carried out by tube coupling by using prestress wire so that longitudinally disposed more piece tube coupling and Prefabricated intermediate plate is closely coupled, and the gap between longitudinally disposed tube coupling and between prefabricated intermediate plate is reduced as far as possible, makes Obtain its Mosaic face to be closely adjacent to, improve the globality and water proofing property of piping lane.
Further, the prestressing force wears the inside angle part that muscle hole sets base plate and side plate junction.
Further, the piping lane is divided into multiple pipe rooms, and at least one pipe room is drip chamber, and the top of the drip chamber is filter Net, the drip chamber is located at the bottom of the piping lane;The drip chamber is provided with emergency outlet.In this way, water can be prevented letting out Piping lane reclaimed water is separated in time during leakage is discharged, it is to avoid all kinds of pipelines and the normal of equipment are used in water influence piping lane.
Brief description of the drawings
The accompanying drawing for constituting a part of the present utility model is used for providing being further understood to of the present utility model, and this practicality is new The schematic description and description of type is used to explain the utility model, does not constitute to improper restriction of the present utility model.
Fig. 1 is the structural representation of the piping lane involved by a kind of implementation method of the utility model;
Fig. 2 is the vertical cross section figure of the tube coupling involved by a kind of implementation method of the utility model;
Fig. 3 is the connecting node schematic diagram of the side plate involved by a kind of implementation method of the utility model and base plate;
Fig. 4 is the splash guard arrangement schematic diagram involved by a kind of implementation method of the utility model;
Fig. 5 is the template arrangement states schematic diagram involved by a kind of implementation method of the utility model.
In figure:
The prefabricated top board of 1 tube coupling, 2 base plate, 3 side plate 4
The in-situ layer of 6 interior plate of 5U types mouthful, 7 outer panel 8
The reinforced mesh of 9 structure muscle, 10 11 first seal plate of girder rib 12
The bolt of 13 splicing seams, 14 template, 15 branch sleeve 16
The dowel of 17 second seal plate, 18 recess 19
Specific embodiment
The utility model is described in detail below in conjunction with the accompanying drawings, the description of this part be only it is exemplary and explanatory, There should not be any restriction effect to protection domain of the present utility model.Additionally, those skilled in the art's retouching according to presents State, respective combination can be carried out to the feature in embodiment in presents and in different embodiments.
The utility model embodiment is as follows, reference picture 1~3, and a kind of piping lane is spliced to form by multiple tube couplings 1, the tube coupling 1 includes base plate 2, side plate 3 and top board, and the bottom of the side plate 3 is embedded with branch sleeve 15, and the base plate 2 is cast-in-place base plate 2, institute State in cast-in-place base plate 2 and be provided with dowel 19, the dowel 19 is fixedly connected with branch sleeve 15, the side plate 3 includes inner side Plate 6 and outer panel 7, form U-shaped mouth 5 between the interior plate 6 and outer panel 7, the top board includes prefabricated top board 4 and in-situ layer 8, the prefabricated top board 4 is arranged on the top of interior plate 6, and the in-situ layer 8 is cast in the top surface of prefabricated top board 4 and extends to U-shaped 5 bottoms of mouth.The utility model each tube coupling 1 is combined into cast-in-place part again after having multiple prefabricated components assembly, such tube coupling 1 Component is greatly simplified, and while reducing production difficulty, the hoisting difficulty at transport and scene is reduced, cost-effective, while adopting Assembly is carried out with the prefabricated and cast-in-place mode being combined, side plate 3 is connected with cast-in-place base plate 2 by branch sleeve 15 and dowel 19 Connect, while being poured in U-shaped mouth 5 between interior plate 6 and outer panel 7, in-situ layer 8 is integral, structural integrity is good, connect into This is relatively low, and waterproof is carried out using in-situ layer 8 at splicing seams 13, and water resistance is excellent, and on the other hand, efficiency of construction is greatly improved, Short construction period, relative to cast-in-place pattern, the amount of casting and compacting of concrete is significantly reduced, and reduces the workload of site operation.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 1~3, the top of the cast-in-place base plate 2 Face flushes in or higher than the bottom surface of the U-shaped mouth 5.In-situ layer 8 in the splicing seams 13 of tube coupling 1 mainly U-shaped mouth 5 plays waterproof work With the either flush of, cast-in-place base plate 2 in or higher than the U-shaped mouth 5 bottom surface, in this way, cast-in-place base plate 2 is by tube coupling 1U types mouthful 5 Bottom splicing seams 13 are covered, and can be prevented effectively from splicing seams 13 seepage of the water along 5 bottoms of side plate 3U types mouthful, improve water resistance.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 4 is provided with first in the U-shaped mouth 5 Seal plate 11, the both sides of first seal plate 11 are located at the both sides of the splicing seams 13 between the tube coupling 1 respectively.So set Put, between the tube coupling 1 and waterproof effect of splicing seams 13 can be increased.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 4, institute first states seal plate for steel plate, Reinforced mesh 12 is welded with first seal plate 11.It is arranged such, in-situ layer 8 pours rear steel plate for sealing water and reinforced mesh 12 It is anchored at together in in-situ layer 8, the setting of reinforced mesh 12, considerably increases anchor force of the steel plate for sealing water in in-situ layer 8.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 3, the side plate 3 and cast-in-place base plate 2 Connection end be provided with recess 18.It is arranged such, increases and survey this contact area with cast-in-place base plate 2, that is, increases and survey this and cast-in-place bottom The cohesive force of plate 2, improves the globality of piping lane.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 3 is provided with second in the recess 18 Seal plate 17, the side of the second seal plate 17 is anchored in side plate 3, and opposite side is anchored in cast-in-place base plate 2.In this way, can have Effect prevents water from being penetrated into the bottom of the connecting sewing of cast-in-place base plate 2 along side plate 3, improves the waterproof effect of piping lane.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 5, the prefabricated top board 4 and interior plate 6 are connected by template 14, and the side of the template 14 is connected to the bottom of prefabricated top board 4, and opposite side is connected to the interior of interior plate 6 Side..In this way, the breach of prefabricated top board 4 and interior plate 6 is blocked, mortar leakage prevention;It is preferred that, prefabricated top board 4 and interior plate 6 Branch sleeve 15 is embedded with prefabrication process, template 14 is fixedly connected by bolt 16 with branch sleeve 15, in this way, not only connecting Reliability is connect, while after piping lane is molded, being reused after template 14 is removable.It is preferred that, the top surface of the outer panel 7 is interior higher than described The top surface of side plate 6.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 2 and Fig. 5, the prefabricated top board 4 is pre- Structure muscle 9 is embedded with, the structure muscle 9 at least stretches out the top surface of prefabricated top board 4 and is anchored in in-situ layer 8.It is arranged such, it is prefabricated Top board 4 is more preferable with the globality of in-situ layer 8, and the intensity of in-situ layer 8 is bigger, can be effectively increased the resistance to compression and shearing resistance of in-situ layer 8 Ability.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 2 and Fig. 5, the side plate 3 is provided with purlin Frame muscle 10, the connection interior plate 6 of the girder rib 10 and outer panel 7 are simultaneously exposed in U-shaped mouth 5.Interior plate 6 passes through with outer panel 7 Girder rib 10 is connected, and the globality between interior plate 6 and outer panel 7 is more preferable, while the girder rib 10 being exposed in U-shaped mouth 5 exists In-situ layer 8 is anchored in in-situ layer 8 after pouring, three's good integrity, while increased the intensity of in-situ layer 8 in U-shaped mouth 5.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Fig. 5, the interior plate 6 and prefabricated top board 4 are provided with and stretch out reinforcing bar, and the reinforcing bar that stretches out in the interior plate 6 stretches out along the top surface of interior plate 6, stretching out in the prefabricated top board 4 Reinforcing bar extend out to the top of interior plate 6 along the two sides of prefabricated top board 4.In this way, interior plate 6, prefabricated top board 4 and in-situ layer can be increased 8 globality.
On the basis of above-described embodiment, in another embodiment of the utility model, the piping lane is longitudinally provided with prestressing force and wears muscle Hole, the prestressing force is equipped with presstressed reinforcing steel in wearing muscle hole.In this way, before cast-in-place, by using prestress wire by pipe Section 1 carries out tensioning so that longitudinally disposed more piece tube coupling 1 and prefabricated intermediate plate is closely coupled, longitudinal direction is reduced as far as possible and is set Gap between the tube coupling 1 put and between prefabricated intermediate plate so that its Mosaic face is closely adjacent to, improve piping lane globality and Water proofing property.
On the basis of above-described embodiment, in another embodiment of the utility model, the prestressing force wear muscle hole set base plate 2 with The inside angle part of the junction of side plate 3.
On the basis of above-described embodiment, in another embodiment of the utility model, the piping lane is divided into multiple pipe rooms, at least one Individual pipe room is drip chamber, and the top of the drip chamber is filter screen, and the drip chamber is located at the bottom of the piping lane;The drip chamber It is provided with emergency outlet.Discharged in this way, can prevent piping lane reclaimed water is separated in time when water is leaked, it is to avoid water influence pipe All kinds of pipelines and the normal of equipment are used in corridor.
The above is only preferred embodiment of the present utility model, it is noted that for the common skill of the art For art personnel, on the premise of the utility model principle is not departed from, some improvements and modifications can also be made, these improve and Retouching also should be regarded as protection domain of the present utility model.

Claims (10)

1. a kind of piping lane, is spliced to form by multiple tube couplings, and the tube coupling includes base plate, side plate and top board, it is characterised in that described Side plate bottom is embedded with branch sleeve, and the base plate is cast-in-place base plate, and dowel, the dowel are provided with the cast-in-place base plate It is fixedly connected with branch sleeve, the side plate includes interior plate and outer panel, forms U-shaped between the interior plate and outer panel Mouthful, the top board includes prefabricated top board and in-situ layer, and the prefabricated top board is arranged on interior plate top, and the in-situ layer is cast in The top surface of prefabricated top board simultaneously extends to U-shaped mouth bottom.
2. piping lane according to claim 1, its characteristic is, the either flush of the cast-in-place base plate is in or higher than the U The bottom surface of type mouthful.
3. piping lane according to claim 1, its characteristic is, it is described it is U-shaped it is intraoral be provided with the first seal plate, described first stops The both sides of water plate are located at the both sides of the splicing seams between the tube coupling respectively.
4. piping lane according to claim 3, it is characterised in that the seal plate is steel plate, is welded with the seal plate Reinforced mesh.
5. piping lane according to claim 3, its characteristic is that the side plate is provided with recess with the connection end of cast-in-place base plate.
6. piping lane according to claim 5, its characteristic is that the second seal plate is provided with the recess, and described second stops Water plate side is anchored in side plate, and opposite side is anchored in cast-in-place base plate.
7. the piping lane according to claim 1~6 any one, its characteristic is that the prefabricated top board and interior plate pass through Template is connected, and the side of the template is connected to prefabricated top board bottom, and opposite side is connected to the inner side of interior plate.
8. piping lane according to claim 7, it is characterised in that the prefabricated top board is embedded with structure muscle, the structure muscle At least stretch out the top surface of prefabricated top board and be anchored in in-situ layer.
9. piping lane according to claim 8, it is characterised in that the side plate is provided with girder rib, in the girder rib connection Side plate and outer panel are simultaneously exposed at U-shaped intraoral.
10. piping lane according to claim 9, it is characterised in that the interior plate is provided with prefabricated top board and stretches out reinforcing bar, institute The reinforcing bar that stretches out stated in interior plate is stretched out along inner side plate top surface, and both sides of the reinforcing bar along prefabricated top board are stretched out in the prefabricated top board Face extend out to interior plate top.
CN201621172169.6U 2016-11-02 2016-11-02 Piping lane Active CN206189454U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621172169.6U CN206189454U (en) 2016-11-02 2016-11-02 Piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621172169.6U CN206189454U (en) 2016-11-02 2016-11-02 Piping lane

Publications (1)

Publication Number Publication Date
CN206189454U true CN206189454U (en) 2017-05-24

Family

ID=58733266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621172169.6U Active CN206189454U (en) 2016-11-02 2016-11-02 Piping lane

Country Status (1)

Country Link
CN (1) CN206189454U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107130634A (en) * 2017-06-28 2017-09-05 中建科技湖南有限公司 A kind of noncontact attachment structure of the prefabricated piping lane of split-type
CN107882060A (en) * 2017-12-17 2018-04-06 中铁四局集团市政工程有限公司 Two prefabricated cabin assembly Pipe racks of superposed type and its construction method
CN109811791A (en) * 2017-11-19 2019-05-28 青岛中科坤泰装配建筑科技有限公司 A kind of prefabricated assembled pipe gallery
CN109811790A (en) * 2017-11-19 2019-05-28 青岛中科坤泰管廊有限公司 A kind of prefabricated assembled pipe gallery

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107130634A (en) * 2017-06-28 2017-09-05 中建科技湖南有限公司 A kind of noncontact attachment structure of the prefabricated piping lane of split-type
CN109811791A (en) * 2017-11-19 2019-05-28 青岛中科坤泰装配建筑科技有限公司 A kind of prefabricated assembled pipe gallery
CN109811790A (en) * 2017-11-19 2019-05-28 青岛中科坤泰管廊有限公司 A kind of prefabricated assembled pipe gallery
CN107882060A (en) * 2017-12-17 2018-04-06 中铁四局集团市政工程有限公司 Two prefabricated cabin assembly Pipe racks of superposed type and its construction method

Similar Documents

Publication Publication Date Title
CN206189455U (en) Piping lane
CN106677787B (en) Vertical shaft repairing and reinforcement structure and repairing and reinforcement construction method
CN206189454U (en) Piping lane
CN105862916A (en) Superimposed assembled type underground pipe gallery system and construction and manufacturing process
CN105839667B (en) The construction manufacture craft of complete prefabricated overlapping assembled underground pipe gallery
CN105839666A (en) Total-prefabricated superimposed assembly type underground pipe gallery and connecting node thereof
CN205662947U (en) Coincide assembled underground pipe gallery system
CN104805866A (en) Prefabricated comprehensive pipe gallery and construction method
CN104831752B (en) Prefabricated inspection well and construction method thereof
CN109024679A (en) A kind of supporting and the integrated system of Pipe rack and construction method
CN204753627U (en) Prefabricated comprehensive piping lane
CN107816117A (en) A kind of large-scale pressure current box culvert is not cut off the water outer restorative procedure
CN113668612A (en) Modular combined prefabricated electric power working well and construction method thereof
CN209873873U (en) Prefabricated assembled power pipeline working well
CN206693265U (en) A kind of installation node of piping lane
CN110295624A (en) Crossroad underground pedestrian walk and pipe gallery build structure and its construction method jointly
CN207553135U (en) A kind of pipe gallery
CN206189458U (en) Multi -deck formula piping lane
CN206189456U (en) Three cabin piping lanes
CN111636875A (en) Construction method of vertical shaft locking ring for underground excavation construction of subway
CN206815373U (en) A kind of piping lane
CN212582739U (en) Prefabricated grout of concrete seals assembled inspection shaft
CN209686448U (en) A kind of prefabricated assembled pipe gallery of sheet hydrant and its piping lane unit
KR20050017815A (en) Construction and design method about center wall of two arch tunnel excavation method
CN209686449U (en) A kind of prefabricated assembled pipe gallery of sheet hydrant and its piping lane unit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: China Civil Architecture Friends Technology (Jiaozhou) Co., Ltd.

Assignor: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT CO., LTD.

Contract record no.: 2018430000023

Denomination of utility model: Integrally movable mould frame for pipe rack cast-in-site construction

Granted publication date: 20170524

License type: Common License

Record date: 20190102

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Nanning Zhongmin zhuyou Intelligent Manufacturing Technology Co., Ltd

Assignor: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT CO., LTD.

Contract record no.: X2019430000004

Denomination of utility model: Integrally movable mould frame for pipe rack cast-in-site construction

Granted publication date: 20170524

License type: Common License

Record date: 20191105

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Xiangxi Zhongmin zhuyou Technology Co., Ltd

Assignor: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT CO., LTD.

Contract record no.: X2020430000002

Denomination of utility model: Integrally movable mould frame for pipe rack cast-in-site construction

Granted publication date: 20170524

License type: Common License

Record date: 20200305

EE01 Entry into force of recordation of patent licensing contract
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 5 / F, office building 2, Zhongmin zhuyou Co., Ltd., No. 10, Zhongshi Road, shaping street, Kaifu District, Changsha City, Hunan Province, 410000

Patentee after: Zhuyou Zhizao Technology Investment Co., Ltd

Address before: 410205 comprehensive building in Hunan province Changsha Kaifu District, No. 30 Xingang Road, Changsha Jinxia bonded logistics center room 2005

Patentee before: CHINA MINGSHENG DRAWIN TECHNOLOGY INVESTMENT Ltd.

EE01 Entry into force of recordation of patent licensing contract

Assignee: Nantong Zhongmin zhuyou Zhizao Technology Co., Ltd

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2020980007488

Denomination of utility model: A kind of pipe gallery

Granted publication date: 20170524

License type: Common License

Record date: 20201105

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hunan Yuanfeng Construction Engineering Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980000884

Denomination of utility model: A kind of pipe gallery

Granted publication date: 20170524

License type: Common License

Record date: 20210203

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hunan Hailong Construction Engineering Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980001039

Denomination of utility model: A kind of pipe gallery

Granted publication date: 20170524

License type: Common License

Record date: 20210207

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Henan fengque Construction Engineering Co.,Ltd.

Assignor: Zhuyou Zhizao Technology Investment Co., Ltd

Contract record no.: X2021980010621

Denomination of utility model: Pipe gallery

Granted publication date: 20170524

License type: Common License

Record date: 20211019

EE01 Entry into force of recordation of patent licensing contract