CN206188204U - Specialized tool is lifted by crane in inspection of turbo generator set axle bush - Google Patents

Specialized tool is lifted by crane in inspection of turbo generator set axle bush Download PDF

Info

Publication number
CN206188204U
CN206188204U CN201621161527.3U CN201621161527U CN206188204U CN 206188204 U CN206188204 U CN 206188204U CN 201621161527 U CN201621161527 U CN 201621161527U CN 206188204 U CN206188204 U CN 206188204U
Authority
CN
China
Prior art keywords
wire rope
shoulder pole
lifting
steel wire
driving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621161527.3U
Other languages
Chinese (zh)
Inventor
赵西文
赵立波
郝长山
李宪法
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ji'nan Fenghui Technology Co Ltd
SEPCO1 Electric Power Construction Co Ltd
Original Assignee
Ji'nan Fenghui Technology Co Ltd
SEPCO1 Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ji'nan Fenghui Technology Co Ltd, SEPCO1 Electric Power Construction Co Ltd filed Critical Ji'nan Fenghui Technology Co Ltd
Priority to CN201621161527.3U priority Critical patent/CN206188204U/en
Application granted granted Critical
Publication of CN206188204U publication Critical patent/CN206188204U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a specialized tool is lifted by crane in inspection of turbo generator set axle bush, include driving, a wire rope, lift by crane shoulder pole, the 2nd wire rope, counter weight and the 3rd wire rope, wherein, drive a vehicle to the lifting machine tool, be provided with the lifting hook in the driving, the middle part of lifting by crane the shoulder pole is provided with the driving hoisting point, and the hoisting point of driving a vehicle passes through the hook connect in a wire rope and the driving, and a wire rope has sufficient length, and when making the lifting hook position of driving a vehicle be higher than the closed tube top, the position of lifting by crane the shoulder pole is less than the closed tube bottom, the counter weight is connected with the one end of lifting by crane the shoulder pole through the 2nd wire rope, and the opposite side that lifts by crane the shoulder pole is connected with the 3rd wire rope, hoisting point and the radius apart from more than or equal to closed tube driving hoisting point between of the 3rd wire rope on lifting by crane the shoulder pole. Lift by crane the one end of shoulder pole and can extend the below that gets into the closed tube, can hoist the bearing frame reel shaft tile of dismantling under the condition that need not dismantle the closed tube.

Description

A kind of turbine generator unit shaft watt checks hoisting special purpose tools
Technical field
The utility model is specifically related to a kind of turbine generator unit shaft watt and checks hoisting special purpose tools.
Background technology
Turbo-generator Set when such as bearing shell occurs abnormal, need to open bearing block during running, by bearing shell disassemble with Afterwards, bearing shell is transported into inspection desk carries out inspection work, and the weight of bearing shell is larger, and lifting and the fortune of driving are needed between maintenance It is defeated.Generally, cross over pipe is provided with above bearing block, and cross over pipe is located at the lower section of driving.The effect of cross over pipe is After the completion of the acting of steam red switch intermediate pressure cylinder rotor, middle pressure steam is entered by mesolow communicating pipe by intermediate pressure cylinder upper air vent Enter to low pressure (LP) cylinder and done work, the effect of mesolow communicating pipe is that therefrom pressure steam ports introduces low by steam under minimum crushing Cylinder pressure.Because the diameter of cross over pipe is generally 3-5 meters, so, if necessary to be lifted to bearing block and bearing shell using driving When, it is necessary to the suspension hook of driving is dropped at bearing block to be removed and bearing shell, but due to the presence of cross over pipe, suspension hook cannot under Drop, cannot also be lifted by other connectors.It is therefore desirable to remove cross over pipe first, then axle is carried out using driving The dismounting and bearing shell service work of bearing.And premature removal cross over pipe, be pressed for time, task weight, workload it is big, vapour can be had a strong impact on The normal work of turbine generator.
Utility model content
For technical problem present in prior art, the utility model provides a kind of turbine generator unit shaft watt and checks Hang specific purpose tool.
In order to solve the above technical problems, the technical solution of the utility model is:
A kind of turbine generator unit shaft watt checks hoisting special purpose tools, including driving, the first steel wire rope, lifts by crane shoulder pole, the Two steel wire ropes, counterweight and the 3rd steel wire rope, wherein,
It is lifting machinery to drive a vehicle, and suspension hook is provided with driving;
Driving suspension centre is provided with the middle part of lifting shoulder pole, driving suspension centre is connected by the first steel wire rope with the suspension hook in driving Connect, the first steel wire rope has enough length, when making the lift hook position of driving higher than cross over pipe top, the position for lifting by crane shoulder pole is low In the bottom of cross over pipe;
Counterweight is connected by the second steel wire rope with one end of lifting shoulder pole, and the opposite side for lifting by crane shoulder pole is connected with the 3rd steel wire Rope, radius of the distance more than or equal to cross over pipe between suspension centre and driving suspension centre of the 3rd steel wire rope on lifting shoulder pole.
Lifting shoulder pole is hung in the lower section of driving by the first steel wire rope, due to the length long enough of the first steel wire rope so that At the top of cross over pipe, the position for lifting by crane shoulder pole may be located at the lower section of cross over pipe to suspension hook, because lifting shoulder pole has certain Length, so, the 3rd steel wire rope one end that is connected with of lifting shoulder pole can be made to extend under cross over pipe lifting shoulder pole rotation Side, and the bearing block and bearing shell of dismounting are hung on the 3rd steel wire rope, just be able to will be torn open in the case of without removing cross over pipe The bearing block and bearing shell for unloading are lifted, and greatly save the cost of overhaul of bearing shell.
Preferably, several fixture blocks are evenly equipped with the lifting shoulder pole, the body of fixture block protrusion lifting shoulder pole is set, second Steel wire rope and the 3rd steel wire rope are respectively positioned between two adjacent fixture blocks with the tie point of lifting shoulder pole.
Due to fixture block lifting shoulder pole on be equally distributed, so the position of fixture block can substantially show lifting shoulder pole Position, the weight of weight and counterweight according to bearing block and bearing shell, you can determine hanging for the second steel wire rope and the 3rd steel wire rope Point, is more convenient operation.Fixture block steel wire rope can also be carried out it is spacing, prevent steel wire rope along lifting shoulder pole slip, it is ensured that The stabilization of hoisting process, it is to avoid cause danger.
Preferably, the lifting shoulder pole is prepared from by I-steel.
Preferably, the lifting shoulder pole is integrally formed with fixture block.
The hoisting method of hoisting special purpose tools is checked using above-mentioned turbine generator unit shaft watt, is comprised the following steps:
1) will lift by crane shoulder pole by the first wire rope suspensioning driving suspension hook on;
2) driving will be lifted by crane at the cross over pipe that shoulder pole is transported at bearing block to be removed, the first steel wire rope is located at cross over pipe Edge, the bottom of the position less than cross over pipe of shoulder pole is lifted by crane in the suspension hook position of driving higher than the top of cross over pipe;
3) rotation lifting shoulder pole, makes one end of the steel wire rope of connection the 3rd of lifting shoulder pole extend into the lower section of cross over pipe, And positioned at the top of bearing block to be removed;
4) bearing block or/and bearing shell of dismounting are lifted on the lower end of the 3rd steel wire rope, adjust the suspension centre of the second steel wire rope, And counterweight is lifted in the lower end of the second steel wire rope, make the bearing block of lifting or/and bearing shell hanging;
5) driving is started, bearing block or/and bearing shell is transported to maintenance department.
Preferably, step 3) in, the one end for being connected with the 3rd steel wire rope for lifting by crane shoulder pole is rotated to the lower section of cross over pipe, The 3rd steel wire rope is set to be located at the surface of bearing block to be removed.
If during the active force tilted upward to rising hanging object to apply, playing hanging object can produce a speed for horizontal direction, i.e., The phenomenon of " swinging long-drawn-out " can occur, when speed is larger, larger impulsive force can be produced, staff and mechanical facility be produced certain Potential safety hazard.When slinging vertically, lifting is steady, and security is good.
Preferably, step 4) in, when the bearing block or/and hanging bearing shell of lifting, lifting shoulder pole is in horizontality.
When lifting by crane shoulder pole and being in horizontality, the weight for having illustrated hanging object and counterweight is identical, lifting system now The stability of system is best.
Advantageous Effects of the present utility model are:
1st, in the utility model, lifting by crane one end of shoulder pole can extend into the lower section of cross over pipe, can be without dismounting In the case of cross over pipe, the bearing block or bearing shell of dismounting are sling, reduce because of other extra works that dismounting brings communicating pipe, contracting Short emergency repair time, substantially increases overhaul efficiency, reduces the cost of overhaul;
2nd, the second steel wire rope of counterweight and the suspension centre of the 3rd steel wire rope can be adjusted in the utility model, can according to rise Horizontal and the 3rd steel wire rope the suspension centre position of bearing block and the weight of bearing shell and the steel wire of weight Reasonable adjustment second of counterweight hung Put, without preparing too many counterweight, with wider applicability.
Brief description of the drawings
Fig. 1 is the structural representation that the utility model lifts by crane shoulder pole.
Wherein, 1 hanging object, is played, the 2, the 3rd steel wire rope, 3, fixture block, 4, driving suspension centre, 5, lifting shoulder pole, 6, counterweight.
Specific embodiment
With reference to specific embodiment, the utility model is described in further detail.
As shown in figure 1, a kind of turbine generator unit shaft watt checks the arrangement and method for construction of hoisting special purpose tools, including driving, the One steel wire rope, lifting shoulder pole 5, the second steel wire rope, the steel wire rope 2 of counterweight 6 and the 3rd, wherein, it is lifting machinery to drive a vehicle, and is set in driving It is equipped with suspension hook;Driving suspension centre 4 is provided with the middle part of lifting shoulder pole, driving suspension centre 4 is by the suspension hook on the first steel wire rope and driving Connection, the first steel wire rope has enough length, when making the lift hook position of driving higher than cross over pipe top, lifts by crane the position of shoulder pole 5 Set low in the bottom of cross over pipe;
The effect of the 3rd steel wire rope 2 be will lifting shoulder pole 5 transfer to the lower section of cross over pipe, its one end extend to bearing block and The surface of bearing shell, by way of vertical lifting, when solving inclination lifting, playing hanging object 1 can produce certain horizontal velocity, The problem of certain potential safety hazard can be produced to neighbouring people or thing.
Counterweight 6 is connected by the second steel wire rope with one end of lifting shoulder pole 5, and the opposite side for lifting by crane shoulder pole 5 is connected with the 3rd Steel wire rope 2, the distance between suspension centre and driving suspension centre 4 of the 3rd steel wire rope 2 on lifting shoulder pole 5 is more than or equal to the half of cross over pipe Footpath.The effect of counterweight 6 herein is to provide downward active force, using lever principle, will play hanging object 1 vacantly, is easy to conveying.
Lifting shoulder pole 5 is hung in the lower section of driving by the first steel wire rope, due to the length long enough of the first steel wire rope so that At the top of cross over pipe, the position for lifting by crane shoulder pole 5 may be located at the lower section of cross over pipe to suspension hook, because lifting shoulder pole 5 has necessarily Length, so, can will lifting shoulder pole 5 rotate, the one end of the 3rd steel wire rope 2 that is connected with of lifting shoulder pole 5 is extended to UNICOM The lower section of pipe, and the bearing block dismantled and bearing shell (playing hanging object 1) are hung on the 3rd steel wire rope 2, just can be without removing connection In the case of siphunculus, the bearing block and bearing shell of dismounting are lifted, greatlyd save the cost of overhaul of bearing shell.
Several fixture blocks 3 are preferred embodiment evenly equipped with the lifting shoulder pole 5 as a kind of, the protrusion of fixture block 3 is lifted by crane The body of shoulder pole 4 is set, and the second steel wire rope and the 3rd steel wire rope 2 are respectively positioned on two adjacent fixture blocks 3 with the tie point of lifting shoulder pole 5 Between.
As the alternative of above-mentioned implementation method, uniform several grooves on lifting shoulder pole 5, the second steel wire rope and the One end system of three steel wire ropes closes in a groove, and groove can not only be defined to the hoisting point position of steel wire rope, can also be effectively Steel wire rope is prevented along the slip of lifting shoulder pole 5, it is to avoid caused danger during lifting.
Due to fixture block 3 lifting shoulder pole 5 on be equally distributed, so the position of fixture block 3 can substantially show lifting The position of shoulder pole 5, according to the weight and the weight of counterweight 6 that play hanging object 1, you can determine the second steel wire rope and the 3rd steel wire rope 2 Suspension centre, be more convenient operation.Fixture block 3 can also carry out steel wire rope spacing, prevent steel wire rope (including the second steel wire rope and the 3rd Steel wire rope) along the slip of lifting shoulder pole 5, it is ensured that the stabilization of hoisting process, it is to avoid cause danger.
Preferably, lifting shoulder pole 5 is prepared from by I-steel, and I-steel has intensity higher, without special processing, Simple structure.Or lifting shoulder pole 5 is integrally formed in a mold with fixture block 3.
The method that hoisting special purpose tools are lifted by crane is checked using above-mentioned turbine generator unit shaft watt, is comprised the following steps:
1) will lift by crane shoulder pole 5 in driving suspension centre 4 by the first wire rope suspensioning driving suspension hook on;
2) driving will be lifted by crane at the cross over pipe that shoulder pole 5 is transported at bearing block to be removed, the first steel wire rope is located at UNICOM The side of pipe, and set against cross over pipe, the position of shoulder pole is lifted by crane in the top of the suspension hook position higher than cross over pipe of driving Less than the bottom of cross over pipe;
3) rotation lifting shoulder pole 5 (due to lifting shoulder pole 5 by the first steel wire rope be in suspended state, can be by manpower Directly the mode of rotation lifting shoulder pole 5 is carried out, it is also possible to lifting shoulder pole 5 is rotated by external force), make lifting shoulder pole 5 The one end for connecting the 3rd steel wire rope 2 extends into the lower section of cross over pipe, and positioned at the top of bearing block to be removed;
4) bearing block or/and bearing shell of dismounting are lifted on the lower end of the 3rd steel wire rope 2;Adjust the suspension centre of the second steel wire rope Position on lifting shoulder pole 5, after adjusting, lifts counterweight 6, in the leverage of counterweight 6 in the lower end of the second steel wire rope Under, make the bearing block of lifting or/and bearing shell hanging;Herein hanging refers to leave supporter, to hanging height without it is special will Ask, i.e., need not require that the flying height of hanging object 1 is equal with the flying height of counterweight 6, it is preferable that when playing hanging object 1 and being hanging, rise Hang shoulder pole 5 and be in horizontality.
5) start driving, bearing block or/and bearing shell be transported to maintenance department, due to now lifting shoulder pole 5 top Through the limitation without cross over pipe, driving can be lifted by crane upwards, and bearing block and bearing shell are placed on inspection rack.
One phase of table mountain Second Power Plant, 2 × 1000MW units engineering #1 units, steam turbine is had by Harbin Turbine Limit company and Toshiba Corp's co-design and the national First pattern of production be overcritical, resuperheat, single shaft, Four cylinders, four steam discharges, condensing turbine;During the test run of unit 168, find #3, #4 bearing bush temperature it is high, unit by forced-stopping machine, Be pressed for time, task weight, through test run headquarter discuss need to assault repairing check bearing shell, due to bearing shell be located at communicating pipe immediately below, profit Lifting is carried out to bearing shell with driving and checks that service work cannot be realized, and remove cross over pipe, additional workload certainly will be increased;Herein In the case of, absorbed all the useful ideas at steam turbine construction, using existence conditions, bearing shell hoisting special purpose tools are designed and produced, smoothly complete To inspecting bearing shell repairing work.
Although above-mentioned be described with reference to accompanying drawing to specific embodiment of the present utility model, not to utility model The limitation of protection domain, one of ordinary skill in the art should be understood that on the basis of the technical solution of the utility model, this area Various modifications or deform still in protection domain of the present utility model that technical staff makes by need not paying creative work It is interior.

Claims (4)

1. a kind of turbine generator unit shaft watt checks hoisting special purpose tools, it is characterised in that:Including driving, the first steel wire rope, rise Shoulder pole, the second steel wire rope, counterweight and the 3rd steel wire rope are hung, wherein,
It is lifting machinery to drive a vehicle, and suspension hook is provided with driving;
Driving suspension centre is provided with the middle part of lifting shoulder pole, driving suspension centre is connected by the first steel wire rope with the suspension hook in driving, the One steel wire rope has enough length, when making the lift hook position of driving higher than cross over pipe top, lifts by crane the position of shoulder pole less than connection The bottom of siphunculus;
Counterweight is connected by the second steel wire rope with one end of lifting shoulder pole, and the opposite side for lifting by crane shoulder pole is connected with the 3rd steel wire rope, Radius of the distance more than or equal to cross over pipe between suspension centre and driving suspension centre of 3rd steel wire rope on lifting shoulder pole.
2. turbine generator unit shaft watt according to claim 1 checks hoisting special purpose tools, it is characterised in that:The lifting Be evenly equipped with several fixture blocks on shoulder pole, the body of fixture block protrusion lifting shoulder pole is set, the second steel wire rope and the 3rd steel wire rope with rise The tie point for hanging shoulder pole is respectively positioned between two adjacent fixture blocks.
3. turbine generator unit shaft watt according to claim 2 checks hoisting special purpose tools, it is characterised in that:The lifting Shoulder pole is integrally formed with fixture block.
4. turbine generator unit shaft watt according to claim 1 checks hoisting special purpose tools, it is characterised in that:The lifting Shoulder pole is prepared from by I-steel.
CN201621161527.3U 2016-11-01 2016-11-01 Specialized tool is lifted by crane in inspection of turbo generator set axle bush Active CN206188204U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621161527.3U CN206188204U (en) 2016-11-01 2016-11-01 Specialized tool is lifted by crane in inspection of turbo generator set axle bush

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621161527.3U CN206188204U (en) 2016-11-01 2016-11-01 Specialized tool is lifted by crane in inspection of turbo generator set axle bush

Publications (1)

Publication Number Publication Date
CN206188204U true CN206188204U (en) 2017-05-24

Family

ID=58732892

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621161527.3U Active CN206188204U (en) 2016-11-01 2016-11-01 Specialized tool is lifted by crane in inspection of turbo generator set axle bush

Country Status (1)

Country Link
CN (1) CN206188204U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106315391A (en) * 2016-11-01 2017-01-11 山东电力建设第工程公司 Special hoisting tool for inspection of bearing bush of steam turbine generator unit and hoisting method
CN107265280A (en) * 2017-08-14 2017-10-20 西山煤电(集团)有限责任公司 Gravity motion hanging beam

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106315391A (en) * 2016-11-01 2017-01-11 山东电力建设第工程公司 Special hoisting tool for inspection of bearing bush of steam turbine generator unit and hoisting method
CN106315391B (en) * 2016-11-01 2018-05-18 中国电建集团山东电力建设第一工程有限公司 A kind of turbine generator unit shaft watt checks hoisting special purpose tools and hoisting method
CN107265280A (en) * 2017-08-14 2017-10-20 西山煤电(集团)有限责任公司 Gravity motion hanging beam

Similar Documents

Publication Publication Date Title
CN201821226U (en) Lifting device of large synchronous motor
CN206188204U (en) Specialized tool is lifted by crane in inspection of turbo generator set axle bush
CN102430923A (en) Method for turning over turning wheel of water turbine in the air
CN206466885U (en) A kind of milling train inner structural member dismounts special hanger
CN106315391B (en) A kind of turbine generator unit shaft watt checks hoisting special purpose tools and hoisting method
CN205603125U (en) Special hoist device that horizontal water tube cooler heat exchange tube was changed
CN203006789U (en) Auxiliary hoisting tool for on-site maintenance of wind turbine generator
CN202744175U (en) Sling used for hoisting precast concrete columns
CN202558444U (en) Steel penstock hoisting balance beam device
CN215666631U (en) Lifting device for hub of wind generating set
CN106829778B (en) A kind of horizontal pump maintenance maintenance unit
CN203127986U (en) Adjustable lifting tool for T joist steel formwork of high-speed rail
CN101776033B (en) Hydraulic dismounting device for vertical-shaft pelton turbine rotating wheel
CN108105041A (en) The device of maintenance gear case and its application on tower
CN208517821U (en) A kind of simple hoisting apparatus for removing box beam beret slice
CN207209896U (en) A kind of large-scale dismountable lower end axle inspection platform
CN110030836A (en) The method and track-type facilities of sintering pallet safe and highly efficient operation in hole for hoist
CN202481941U (en) Balancing device for overhanging steam-turbine bearing bush
CN107304030B (en) Special hoisting device for replacing heat exchange tube of transverse tube cooler and application method thereof
CN213802525U (en) Hoisting device for rotor of large-scale generator motor
CN102756988A (en) Movable sling for mounting expansion joint of comb plate
CN205772813U (en) For 40 tons of door machines built-in decelerator remove and install one suspender
CN102815625A (en) Crane for ocean platform
CN210884893U (en) Hanging bracket for disassembling and assembling high-pressure chamber under travelling beam
CN203048408U (en) Hook