CN206143608U - Assembled T beam bridge hogging moment district anchorage sealing system - Google Patents

Assembled T beam bridge hogging moment district anchorage sealing system Download PDF

Info

Publication number
CN206143608U
CN206143608U CN201621147428.XU CN201621147428U CN206143608U CN 206143608 U CN206143608 U CN 206143608U CN 201621147428 U CN201621147428 U CN 201621147428U CN 206143608 U CN206143608 U CN 206143608U
Authority
CN
China
Prior art keywords
built
notch
sealing
covering anchorage
hogging moment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621147428.XU
Other languages
Chinese (zh)
Inventor
毛敏
韩之江
刘志华
赵雷
申雁鹏
汪永强
郭文龙
吕立宁
陈栋栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Province Transport Science Research Institute
Shanxi Jiaoke Highway Survey and Design Institute
Original Assignee
Shanxi Province Transport Science Research Institute
Shanxi Jiaoke Highway Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Province Transport Science Research Institute, Shanxi Jiaoke Highway Survey and Design Institute filed Critical Shanxi Province Transport Science Research Institute
Priority to CN201621147428.XU priority Critical patent/CN206143608U/en
Application granted granted Critical
Publication of CN206143608U publication Critical patent/CN206143608U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model belongs to the technical field of bridge engineering, particularly, relate to an assembled T beam bridge hogging moment district anchorage sealing system. The anchorage sealing system is including built -in notch, anchorage sealing concrete, crack control reinforcing bar net piece, built -in notch prefabrication is on the T roof beam, steel strand wires one end is passed built -in notch and is buried underground in the T roof beam, and another pot head has anchor clamps and fixed with the ground tackle, be equipped with crack control reinforcing bar net piece in the built -in notch to fill the anchorage sealing concrete. Compared with the prior art, assembled T beam bridge hogging moment district anchorage sealing system built -in through making the anchorage sealing district, remove processes such as the template is strutted, the ligature of crack control reinforcing bar net piece from, improved anchorage sealing concrete pouring quality when reducing to construct the process, practice thrift construction cost.

Description

A kind of fabricated T beam bridge hogging moment area sealing off and covering anchorage system
Technical field
This utility model belongs to technical field of bridge engineering, it particularly relates to a kind of fabricated T beam bridge hogging moment area envelope Anchor system.
Background technology
As expressway construction is shifted from Plain to mountain area, increasing fabricated T beam bridge obtains engineer applied.Mesh Front fabricated T beam bridge main beam structure major part is used《Bridges and culverts universal design drawing》In standard drawing, wherein hogging moment steel What twisted wire anchorage zone adopted is the cast-in-place concrete sealing off and covering anchorage that apparent size is about 400mm × 400mm × 150mm, and the program need to Hogging moment tooth plate area vertical muscle is exposed into about 100mm when T is beam prefabricated, during so as to cast-in-place sealing off and covering anchorage concrete, fix reinforced mesh; And surrounding needs template support when sealing off and covering anchorage concrete is poured.From the point of view of long-term Construction practices, this kind of sealing off and covering anchorage method is because of behaviour Make narrow space, template support, reinforcing bar colligation are difficult, it is difficult to ensure that the quality of sealing off and covering anchorage concrete, and construction cost is higher.
The content of the invention
To solve problem above, this utility model provides a kind of fabricated T beam bridge hogging moment area easy, efficiently, economic Sealing off and covering anchorage system.
A kind of fabricated T beam bridge hogging moment area sealing off and covering anchorage system described in the utility model, the sealing off and covering anchorage system includes built-in Notch 1, sealing off and covering anchorage concrete 2, anticracking reinforced mesh 3;The built-in notch 1 is prefabricated on T beams;5 one end of steel strand wires passes through built-in Notch 1 is simultaneously embedded in T beams, and the other end is cased with fixture and is fixed with anchorage 4;Anticracking reinforced mesh 3 is provided with built-in notch 1, And fill sealing off and covering anchorage concrete 2.
A kind of fabricated T beam bridge hogging moment area sealing off and covering anchorage system described in the utility model, the anticracking reinforced mesh 3 are parallel It is located at 1 surface 3cm of built-in notch.
A kind of fabricated T beam bridge hogging moment area sealing off and covering anchorage system described in the utility model, 1 inner space of built-in notch For inner small and outside big landing shape.
A kind of fabricated T beam bridge hogging moment area sealing off and covering anchorage system described in the utility model, the sealing off and covering anchorage concrete 2 are low stream Dynamic degree or half stiff pea gravel concreten.
Compared with prior art, fabricated T beam bridge hogging moment area sealing off and covering anchorage system described in the utility model is by making sealing off and covering anchorage Area is built-in, removes the operations such as template support, anticracking reinforced mesh colligation from, improves sealing off and covering anchorage concrete while reducing working procedure Pouring quality, saves construction cost.
Description of the drawings:
Fig. 1:Fabricated T beam bridge hogging moment area sealing off and covering anchorage system schematic;Fig. 2:Built-in notch profile;Fig. 3:Built-in notch Elevation;Fig. 4:Anticracking reinforced mesh figure;The built-in notches of 1-, 2- sealing off and covering anchorage concrete, 3- anticracking reinforced mesh, 4- anchorages, 5- steel Twisted wire.
Specific embodiment
With reference to specific embodiment fabricated T beam bridge hogging moment area sealing off and covering anchorage system described in the utility model is made into One step is illustrated, but protection domain of the present utility model is not limited to this.
Embodiment 1
A kind of fabricated T beam bridge hogging moment area sealing off and covering anchorage system, including built-in notch 1, sealing off and covering anchorage concrete 2, anticracking bar-mat reinforcement Piece 3;The built-in notch 1 is jointly prefabricated when T beams make;It is mixed with the sealing off and covering anchorage after steel strand tension, pipeline pneumatic mortar are finished Solidifying soil 2 closes built-in notch 1.Sealing off and covering anchorage concrete 2 is poured to away from 1 surface 3cm of built-in notch or so Shi An in the built-in notch 1 Anticracking reinforced mesh 3 is put, then proceedes to pour sealing off and covering anchorage concrete 2 to 1 surface of built-in notch, and receipts slurry of wiping one's face.The built-in groove 1 inner space of mouth is inner small and outside big landing shape.The sealing off and covering anchorage concrete 2 is low fluidity or half stiff pea gravel concreten. By the reinforced mesh 3, prefabrication also live can be processed, during placement and away from 1 surface 3cm of built-in notch or so section surrounding Hold out against.The built-in notch 1 does not need template support when pouring sealing off and covering anchorage concrete 2.
It is when Liang Chang carries out T beams and makes, common prefabricated together with built-in notch 1,1 inner surface of built-in notch is repaiied after form removal It is whole, and to 1 inner side dabbing of built-in notch to be well combined with rear pouring concrete.Before the sealing off and covering anchorage of hogging moment area, carefully in cleaning Put debris in notch 1, and moistening of sprinkling water.Remove 1 inside excessive moisture after-pouring of built-in notch, half stiff microlith sealing off and covering anchorage concrete 2 It is closely knit to away from built-in notch surface about 3cm or so, being plugged and pounded with spatula, then cutting suitable precast reinforced mesh sheet is put into built-in Notch 1 is simultaneously held out against with surrounding, is continued to pour half stiff microlith sealing off and covering anchorage concrete 2 to notch surface, is plugged and pounded with spatula again closely knit It is afterwards that surface is floating, and carry out watering health preserving.

Claims (4)

1. a kind of fabricated T beam bridge hogging moment area sealing off and covering anchorage system, it is characterised in that the sealing off and covering anchorage system include built-in notch (1), Sealing off and covering anchorage concrete (2), anticracking reinforced mesh (3);The built-in notch (1) is prefabricated on T beams;Steel strand wires (5) one end passes through interior Put notch (1) and be embedded in T beams, the other end is cased with fixture and is fixed with anchorage (4);Anticracking steel is provided with built-in notch (1) Muscle mesh sheet (3), and fill sealing off and covering anchorage concrete (2).
2. fabricated T beam bridge hogging moment area sealing off and covering anchorage system according to claim 1, it is characterised in that the anticracking reinforcing bar Mesh sheet (3) is parallel to be located at built-in notch (1) surface 3cm.
3. fabricated T beam bridge hogging moment area sealing off and covering anchorage system according to claim 1, it is characterised in that the built-in notch (1) inner space is inner small and outside big landing shape.
4. fabricated T beam bridge hogging moment area sealing off and covering anchorage system according to claim 1, it is characterised in that the sealing off and covering anchorage coagulation Native (2) are pea gravel concreten.
CN201621147428.XU 2016-10-21 2016-10-21 Assembled T beam bridge hogging moment district anchorage sealing system Expired - Fee Related CN206143608U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621147428.XU CN206143608U (en) 2016-10-21 2016-10-21 Assembled T beam bridge hogging moment district anchorage sealing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621147428.XU CN206143608U (en) 2016-10-21 2016-10-21 Assembled T beam bridge hogging moment district anchorage sealing system

Publications (1)

Publication Number Publication Date
CN206143608U true CN206143608U (en) 2017-05-03

Family

ID=58623222

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621147428.XU Expired - Fee Related CN206143608U (en) 2016-10-21 2016-10-21 Assembled T beam bridge hogging moment district anchorage sealing system

Country Status (1)

Country Link
CN (1) CN206143608U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505444A (en) * 2018-04-03 2018-09-07 中交路桥华东工程有限公司 A kind of T beams pier top continuous segment hogging moment tooth block sealing end mold
CN111287090A (en) * 2020-02-25 2020-06-16 陕西建工机械施工集团有限公司 External grouting anchor sealing device for large-section cast-in-situ box girder beam end anchor and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505444A (en) * 2018-04-03 2018-09-07 中交路桥华东工程有限公司 A kind of T beams pier top continuous segment hogging moment tooth block sealing end mold
CN108505444B (en) * 2018-04-03 2019-09-24 中交路桥华东工程有限公司 A kind of T beam pier top continuous segment hogging moment tooth block sealing end mold
CN111287090A (en) * 2020-02-25 2020-06-16 陕西建工机械施工集团有限公司 External grouting anchor sealing device for large-section cast-in-situ box girder beam end anchor and construction method

Similar Documents

Publication Publication Date Title
CN105804410B (en) Prefabricated concrete structure is vertically connected with dividing storehouse slip casing by pressure method
CN104895581B (en) Structure and its restorative procedure are quickly repaired in a kind of tunnel-liner based on Carbon Fibre Textile
CN108797292A (en) A kind of cement concrete cracks breakage raggle formula patching
CN205662837U (en) Overhead bridge transformation structure
CN105089693B (en) One kind improves gob side entry retaining wall and connects top method
CN105714635B (en) A kind of concrete drainage pavement and its construction, method for repairing and mending
CN109611102A (en) Construction of the flyover method is worn under a kind of cold excavation
CN204983669U (en) Constructional column be connected with collar tie beam pour device
CN107090777A (en) A kind of T beam manufacture methods for reducing blibbing
CN205088671U (en) Precast concrete drainage stake
CN104533451A (en) Tunnel advance pre-supporting technology used in discrete gravelly soil and broken surrounding rock
CN107524471A (en) A kind of tunnel end plugging construction method
CN206143608U (en) Assembled T beam bridge hogging moment district anchorage sealing system
CN105926470A (en) Transformation method of elevated bridge
CN103938869A (en) Construction method for line pipes and line boxes in MS building block rear building wall body
CN107338729A (en) A kind of prestress pipe anti-blocking device and construction method
CN106760004A (en) A kind of construction method of the uniform joint bar in guide trough structure surface
CN104805864B (en) The cementing Waterproof Construction Technique that closes of basement top-down method exterior wall tongue and groove and sealing
CN104500836A (en) Trenchless quick repair method of urban underground pipelines
CN103526953A (en) Method for processing roof panels insufficient in bearing capacity
CN204691782U (en) A kind of Tunnel Second Lining surface Defects Treatment structure
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN204825887U (en) Prestressed anchorage cable
CN205116582U (en) Stretch out protection architecture of roofing pipeline
CN204238264U (en) A kind of sole plate post-poured strip structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170503

Termination date: 20181021