Pipe fitting translation machine tool platform of piping erection Download PDF

Info

Publication number
CN206130304U
CN206130304U CN201621213657.7U CN201621213657U CN206130304U CN 206130304 U CN206130304 U CN 206130304U CN 201621213657 U CN201621213657 U CN 201621213657U CN 206130304 U CN206130304 U CN 206130304U
Authority
CN
China
Prior art keywords
pipeline
pipe
pipe fitting
pedestal platform
rail bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621213657.7U
Other languages
Chinese (zh)
Inventor
杨飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201621213657.7U priority Critical patent/CN206130304U/en
Application granted granted Critical
Publication of CN206130304U publication Critical patent/CN206130304U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model relates to a pipe fitting translation machine tool platform of piping erection. Base platform both sides respectively be equipped with guiding rail bar, press from both sides the frid frame and stand on the base bench, and both sides connect through slider and guiding rail bar looks grooves in it, double -layered frid on be equipped with the pin, base bench top portion is equipped with locating hole, pin and locating hole phase -match, base platform one end end be fixed with the arc staple bolt through Z word worker piece, arc staple bolt semi -ring shape go up in the puncture have a nail, double -layered frid top be fixed with the heating jacket, pipeline one end is detained in the heating jacket in the end, pipeline other end end frame stands on on the nail of arc staple bolt, the utility model discloses simple structure, assembly are easily, be applicable to the outdoor installation of moulding the tubulation and saying, the butt joint of fusing between pipeline and the pipeline can be realized at the pipeline mouth of pipe of short time internal heating installation to the hot melt equipment that has integrateed in the equipment, this equipment steadiness is good in addition, is convenient for use under the outdoor adverse circumstances.

Description

A kind of pipe fitting translation mechanical stage of Pipe installing
Technical field
The utility model is related to a kind of pipe fitting translation mechanical stage of Pipe installing.
Background technology
Pipe installing is that full electromechanical equipment quotes new technology, and Pipe installing includes conventional data, tubing, pipe fitting, method Orchid, the connection of Pipe installing basic operation technology, pipeline, support and compensator installation, valve, building water supply and drainage Pipe installing, confession Hot systems are installed, pipeline pressure test and cleaning, common industrial Pipe installing, non-ferrous metal pipe and stainless steel pipes are installed, commonly used The anti-corrosion of nonmetal pipeline and corrosion protective lining Pipe installing, instrument piping installation and pipeline and thermal insulation.Traditional Pipe installing step Suddenly:1st, tubing transport, the barrier that should be cleared up on road.Car transport must have heavy industry or loader to coordinate;Transported in hand truck fashion Must rise and fall during handling consistent by pipe colligation firmly;Not handy hand being transported with rolling bar and directly adjusting rolling bar, pipe rolls front Must not someone.When tower crane is toward eminence fortune pipe, this code derrick crane pertinent regulations should be observed.Material is stacked to put and surely puts jail, no Must huddle and leave about.2nd, scoop tube material cut, ground, when picking flash, striking welding slag, operating personnel should wear safety goggles, and opposite forbids to have People.When the 3rd, simmering pipe, in Guan Shangying colligations firmly, operating personnel's steel wire rope must not stand in the inboard of steel wire rope or arbitrarily across steel wire Rope.Anchor and the stake that don't bother about must be firm.4th, during pipeline purging, outlet should set special messenger's monitoring.In purging and process of the test In, must not be installed or be overhauled.When the 5th, enduring pitch, pertinent regulations in " wasting lamp oil by not sleeping at night " in this code should be observed.When the 6th, standpipe being installed, Should file an application to general contract unit before the bar-mat reinforcement of reserved opening of pipe or security protection cover plate is opened, handling hole makes After knot formality.Can remove. end of operation should recover reserved opening security protection cover plate, cover tightly jail.7th, install During cooling tower standpipe, the ring flange of last root pipe that upper end is connected with cooling tower.Again with cooling tower plastics method after must welding Blue disk connection.Before standpipe welding is installed, it is necessary to application fire syndrome, and sets special messenger and see fire, get fire-fighting equipment, the hole of hoistway ready Asbestos cloth is watered using water and block up tight, forbid Mars to drop to next layer.8th, trench or moist place pipe laying, lighting voltage must not More than 12V.Electric weld handle line forbids exposed and breakage. and operating personnel must wear insulated shoes, wear insulation (electric welding) gloves.9th, pipeline string During dynamic and counterpart, action will be coordinated, and hand must not be placed on the mouth of pipe and joint.10th, outdoors heating pipeline installation, pipe trench earthwork construction The pertinent regulations in this code " shoveling " should be observed.11st, the rust cleaning and mopping of tubing, should be carried out before the mounting.During disconnected tubing, Tubing should be clipped in pipe pressure twist, not handy parallel jaw;Pipe applications support or hand rest are lived.During the sawed-off tubing of emery wheel, Pressure should be uniform, must not overexert, and operating personnel should stand in the side of grinding wheel direction of rotation.
The content of the invention
The purpose of this utility model is to provide a kind of pipe fitting translation mechanical stage of Pipe installing.
The utility model solves its above-mentioned technical problem and adopts following technical scheme:A kind of pipe fitting of Pipe installing Translation mechanical stage, it is mainly configured with:Pedestal platform, guide rail bar, slide block, clip slot plate, pin, limiting plate, heating mantle, traction are interior Button, arc anchor ear, support nail, Z-shaped work block, location hole, pipeline, described pedestal platform both sides are respectively provided with guide rail bar, clip slot grillage Stand on pedestal platform, and its interior both sides is connect by slide block with guide rail bar phase groove;Described clip slot plate is provided with pin, pedestal platform top Portion is provided with location hole, and pin matches with location hole;Described pedestal platform one end end is fixed with arc anchor ear by Z-shaped work block, It is interior on described arc anchor ear semi-circular to be punctured with support nail;
Described clip slot top of the plate portion is fixed with heating mantle, and pipeline one end is buckled in heating mantle in end, pipeline other end end frame Stand on the support nail of arc anchor ear;
Described pipe end end inner support has button in traction.
Further, the described end of pedestal platform one is provided with limiting plate.
Further, described support nail is provided with steel ball with pipeline outer wall contact position.
Further, button is held at inner-walls of duct mouth by the way of interior hydraulic buckling in described traction.
Further, described guide rail bar is provided with rule.
Further, wheel is housed under pedestal platform.
The beneficial effects of the utility model:Simple structure, assembling are easy;Suitable for the installation of outdoor modeling tubing giving sufficient strength;Equipment In be integrated with hot melting equipment, can at short notice heat the pipeline mouth of pipe of installation, realize that the fusion between pipeline and pipeline is right Connect;In addition this equipment steadiness is good, is easy to be used under outdoor adverse circumstances.
Description of the drawings
Fig. 1 translates mechanical stage overall structure figure for a kind of pipe fitting of Pipe installing of the utility model.
Fig. 2 translates mechanical stage detonation configuration figure for a kind of pipe fitting of Pipe installing of the utility model.
1- pedestals platform in figure, 2- guide rail bars, 3- slide blocks, 4- clip slot plates, 5- pins, 6- limiting plates, 7- heating mantles, 8- leads Draw interior button, 9- arc anchor ears, 10- support nails, 11-Z word work blocks, 12- location holes, 13- pipelines.
Specific embodiment
Below in conjunction with the accompanying drawings 1-2 makes a detailed explanation to specific embodiment of the present utility model.
Embodiment:A kind of pipe fitting translation mechanical stage of Pipe installing, it is mainly configured with:Pedestal platform 1, guide rail bar 2, slide block 3rd, clip slot plate 4, pin 5, limiting plate 6, heating mantle 7, the interior button 8, arc anchor ear 9 of traction, support nail 10, Z-shaped work block 11, location hole 12nd, pipeline 13, the described both sides of pedestal platform 1 are respectively provided with guide rail bar 2, and clip slot plate 4 is erected on pedestal platform 1, and its interior both sides is logical Cross slide block 3 to connect with the phase groove of guide rail bar 2;Described clip slot plate 4 is provided with pin 5, and the top of pedestal platform 1 is provided with location hole 12, pin 5 Match with location hole 12;The described one end of pedestal platform 1 end is fixed with arc anchor ear 9 by Z-shaped work block 11, and described arc is embraced Bind round and interior on 9 semi-circulars be punctured with support nail 10;
The described top of clip slot plate 4 is fixed with heating mantle 7, and the one end of pipeline 13 is buckled in heating mantle 7 in end, and pipeline 13 is another End end is erected on the support nail 10 of arc anchor ear 9;
The described end of pipeline 13 end inner support has button 8 in traction.
The described end of pedestal platform 1 one is provided with limiting plate 6.
Steel ball is provided with described support nail 10 and the wall contacts of pipeline 13.
Button 8 is held at the inwall mouth of pipeline 13 by the way of interior hydraulic buckling in described traction.
Described guide rail bar 2 is provided with rule.
Described pedestal platform is equipped with wheel 1 time.
Describe for above-mentioned invention, whole implementation process carries out following elaboration:This plant equipment is for outdoor Modeling tubing giving sufficient strength is installed and used, and its major function is after field lofting, specified location, heating tempreature bulb to be translated according to line bitmap Mouth, the process for intercepting design length;Implementation steps are:Lifting pipeline to be mounted will be needed in pedestal platform by small-sized lifting machine On 1, one end end of pipeline 13 is buckled in heating mantle 7 during lifting, other end is then held on propping up for arc anchor ear 9 On nail 10.Complete to be proceeded by after above-mentioned steps:The first step translates specific bit, and the preliminary of wheel is housed by pedestal platform 1 time The embedment position of this pipe laying is determined according to setting-out drawing.The second step heating hot melt mouth of pipe, opens the electricity in heating mantle 7 Heated filament is in hot melt state using 13 mouthfuls of walls of pipeline.3rd step buckles into button 8 in traction in the other end of pipeline 13, by external force Traction pipeline 13 so that pipeline 13 is overall to be pulled out, and because guide rail bar 2 is provided with rule, is pulled out under external force traction The length of pipeline 13 can be learnt by the rule in guide rail bar 2, and according to design drawing, sawed-off pipeline 13 is to obtain design length Require.Need pin 5 to be buckled in location hole 12 before sawed-off pipeline 13, to reach the steadiness of an entirety.
General principle of the present utility model, principal character and advantage of the present utility model has been shown and described above.One's own profession The technical staff of industry it should be appreciated that the utility model is not restricted to the described embodiments, described in above-described embodiment and specification Simply illustrate principle of the present utility model, on the premise of without departing from the utility model spirit and scope, the utility model is also Various changes and modifications are had, these changes and improvements are both fallen within the range of claimed the utility model.The utility model Claimed scope is by appending claims and its equivalent thereof.

Claims (6)

1. a kind of pipe fitting of Pipe installing translates mechanical stage, and it is mainly configured with:Pedestal platform(1), guide rail bar(2), slide block(3)、 Clip slot plate(4), pin(5), limiting plate(6), heating mantle(7), traction in button(8), arc anchor ear(9), support nail(10), Z-shaped Work block(11), location hole(12), pipeline(13), it is characterised in that:Pedestal platform(1)Both sides are respectively provided with guide rail bar(2), clip slot plate (4)Erect in pedestal platform(1)On, and its interior both sides passes through slide block(3)With guide rail bar(2)Phase groove connects;Described clip slot plate(4)On It is provided with pin(5), pedestal platform(1)Top is provided with location hole(12), pin(5)With location hole(12)Match;Described pedestal Platform(1)One end end passes through Z-shaped work block(11)It is fixed with arc anchor ear(9), described arc anchor ear(9)It is interior on semi-circular to be punctured with Support nail(10);
Described clip slot plate(4)Top is fixed with heating mantle(7), pipeline(13)One end is buckled in heating mantle in end(7)It is interior, pipeline (13)Other end end is erected in arc anchor ear(9)Support nail(10)On;
Described pipeline(13)The last inner support in end has button in traction(8).
2. a kind of pipe fitting of Pipe installing according to claim 1 translates mechanical stage, it is characterised in that described pedestal platform (1)One end is provided with limiting plate(6).
3. a kind of pipe fitting of Pipe installing according to claim 1 translates mechanical stage, it is characterised in that described support nail (10)With pipeline(13)Steel ball is provided with wall contacts.
4. a kind of pipe fitting of Pipe installing according to claim 1 translates mechanical stage, it is characterised in that in described traction Button(8)Pipeline is held on by the way of interior hydraulic buckling(13)At inwall mouth.
5. a kind of pipe fitting of Pipe installing according to claim 1 translates mechanical stage, it is characterised in that described guide rail bar (2)It is provided with rule.
6. a kind of pipe fitting of Pipe installing according to claim 1 translates mechanical stage, it is characterised in that described pedestal platform (1)Wheel is housed down.
CN201621213657.7U 2016-11-10 2016-11-10 Pipe fitting translation machine tool platform of piping erection Expired - Fee Related CN206130304U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621213657.7U CN206130304U (en) 2016-11-10 2016-11-10 Pipe fitting translation machine tool platform of piping erection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621213657.7U CN206130304U (en) 2016-11-10 2016-11-10 Pipe fitting translation machine tool platform of piping erection

Publications (1)

Publication Number Publication Date
CN206130304U true CN206130304U (en) 2017-04-26

Family

ID=58578547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621213657.7U Expired - Fee Related CN206130304U (en) 2016-11-10 2016-11-10 Pipe fitting translation machine tool platform of piping erection

Country Status (1)

Country Link
CN (1) CN206130304U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106402488A (en) * 2016-11-10 2017-02-15 杨飞 Pipe fitting horizontal movement mechanical table for pipeline installation
WO2018170636A1 (en) * 2017-03-18 2018-09-27 深圳市方鹏科技有限公司 Pipe installation robot
CN110985751A (en) * 2019-12-10 2020-04-10 何卫统 Indoor natural gas pipeline paving construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106402488A (en) * 2016-11-10 2017-02-15 杨飞 Pipe fitting horizontal movement mechanical table for pipeline installation
CN106402488B (en) * 2016-11-10 2018-05-15 路明 A kind of pipe fitting translation mechanical stage of Pipe installing
WO2018170636A1 (en) * 2017-03-18 2018-09-27 深圳市方鹏科技有限公司 Pipe installation robot
CN110985751A (en) * 2019-12-10 2020-04-10 何卫统 Indoor natural gas pipeline paving construction method

Similar Documents

Publication Publication Date Title
CN206130304U (en) Pipe fitting translation machine tool platform of piping erection
CN106402488B (en) A kind of pipe fitting translation mechanical stage of Pipe installing
CN107386674A (en) The permanent life line system of the double wireropes of metal Roof
CN104564130A (en) Anti-deformation fast escape tube
CN209226402U (en) Hoisting sling for removing large-diameter negative ring pipe piece
CN111981215A (en) Large-diameter double-rubber-ring socket anticorrosive steel pipe and mounting method thereof
CN204532415U (en) A kind of fast-escape pipe with deixis
CN207145867U (en) The commissure external anti-corrosion layer protection structure of long range horizontal directional drilling water supply line
CN102513977B (en) A kind of Double-safety hand-operated machine
CN208996078U (en) A kind of underground pipe gallery tension rope joint protection box
CN205577835U (en) Mechanical type muffjoint vertical ladder
CN204532417U (en) A kind of resistance to deformation fast-escape pipe
CN108729643A (en) A kind of overhanging type discharging platform steel wire rope drawknot tool
CN201258758Y (en) Simple emergency rescuing interface for tunneling operation
CN206857965U (en) The mobile device of casing elevator
CN2359386Y (en) Suspension scaffold
CN209256153U (en) A kind of flame receiving hopper of zinc-plated square tube as skeletal support
CN206693655U (en) A kind of over-water construction anti-drop net
CN109024681A (en) A kind of underground pipe gallery tension rope joint protection box
CN204299200U (en) Protector
CN206104949U (en) Roof drilling equipment
CN201623405U (en) Simple and convenient electric shock prevention temporary cable supporting frame
CN201891269U (en) Welding protective structure for high-altitude steel structure
CN214170617U (en) Ground connection structure of tunnel lining embedded channel
CN207194428U (en) A kind of building scaffold wall attaching parts

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170426

Termination date: 20171110