CN206110186U - Double -deck gate control well suitable for river regulation engineering - Google Patents

Double -deck gate control well suitable for river regulation engineering Download PDF

Info

Publication number
CN206110186U
CN206110186U CN201620933740.5U CN201620933740U CN206110186U CN 206110186 U CN206110186 U CN 206110186U CN 201620933740 U CN201620933740 U CN 201620933740U CN 206110186 U CN206110186 U CN 206110186U
Authority
CN
China
Prior art keywords
gate
well
river
double
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620933740.5U
Other languages
Chinese (zh)
Inventor
李骏飞
余涛
姚诚毅
陈覃
游浩荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Architectural Design and Research Institute of Guangdong Province
Original Assignee
Architectural Design and Research Institute of Guangdong Province
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Architectural Design and Research Institute of Guangdong Province filed Critical Architectural Design and Research Institute of Guangdong Province
Priority to CN201620933740.5U priority Critical patent/CN206110186U/en
Application granted granted Critical
Publication of CN206110186U publication Critical patent/CN206110186U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a double -deck gate control well suitable for river regulation engineering, including the well body that is equipped with the well head, still including lifting lift up part spare, the well body include last operating layer and under the accuse water layer, the accuse water layer is equipped with water inlet and delivery port, is equipped with height -adjusting's gate from top to bottom on the delivery port, the aperture area of delivery port changes along with the lift altitude variation of gate, is equipped with the controller in the operating layer, the controller with lift lift up part spare and be connected, act lift up part spare is followed operating layer and is stretched into the accuse water layer and interior and be connected with the gate for lift up part spare is lifted to the controller accessible makes the gate go up and down. The delivery port is used for and accesss to the pipe connection that gushes in the river, and the water inlet is connected with urban wastewater pipe. During dry season, let the complete shutoff of general who has surrendered's delivery port under the gate, the sewage in city can not get into during the river gushes. And when rainy season, if the internal water level of well is higher than a certain numerical value of the water level that gushes in the river, make the gate blowdown of rising, if the water level that gush in the river is higher than a certain numerical value of the internal water level of well, make the waterlogging that the gate descends and prevent to flow backward and lead to.

Description

A kind of double-deck gate suitable for river controlling projects controls well
Technical field
This utility model is related to a kind of double-deck gate suitable for river controlling projects and controls well.
Background technology
Water is important natural resourcess, economic resources, social resources and the Ecological basis key element of urban development, and water is in city Shuttle and flow, there is important function for urban ecological function and safety and stability is maintained.In Rapid-Urbanization and industrialized In process, because cities and towns capital construction is seriously delayed, urban river course becomes industrial wastewater, sanitary sewage and farmland water-break collection The main thoroughfare of middle blowdown, pollutant discharge amount is big and spatial distribution is concentrated, and river is dirty only than high, and water body self-purification ability is weak, holds Anoxia and eutrophication are easily caused, black and odorous water is formed.City black and odorous water has become a kind of urban disease, and all cities are almost None is escaped by luck.
Recently live to build portion, Chinese Ministry of Environmental Protection to combine and print and distribute《The notice of situation is investigated with regard to announcing National urban black and odorous water》, lead to Cross development black and odorous water investigation of knowing the real situation to find, by 2 months 2016, in Chinese 295 regions and above city, except 77 cities It was found that outside black and odorous water, 218 cities investigate out 1861 black and odorous waters, the i.e. whole nation and exceed seventy percent city and investigate out black smelly water Body.
City black and odorous water is the water environmental problems that common people have strong complaints, and not only compromises human settlement environment in city, also sternly Ghost image rings city image, administers black and odorous water very urgent.State Council's initiation in 2015《Water prevention and cure of pollution action plan》In Municipality directly under the Central Government, provincial capital, cities specifically designated in the state plan built-up areas substantially eliminate black and odorous water before explicitly pointing out for the end of the year 2017;Before the year two thousand twenty bottom Region and above completed region of the city black and odorous water are controlled within 10%;The year two thousand thirty completed region of the city black and odorous water is totally obtained Eliminate.
Preferably to instruct local government to carry out black and odorous water renovation, house town and country construction portion takes the lead in time can same ring The ministries and commissions such as guarantor portion, Ministry of Water Resources, the Ministry of Agriculture work out《City black and odorous water renovation guide》,《Guide》According to various technologies Function is divided and proposes the basic measures that four classes renovate black and odorous water, including dirty, endogenous control, restoration of the ecosystem and running water are cut in control source Circulating technology.It is crucial wherein to control the dirty technology in source section.
Bank lays the one way in which that wastewater interception pipe is that dirty technology is cut in black-odor river control source.For the ease of maintenance and clearly Reason pipeline, typically at a certain distance or in specific position(At conduit section change, at gradient change, intersection, elevation change At change)Inspection shaft is set.Due to the restriction of land used condition, inspection shaft is usually arranged under the car lane of urban road.For The discharge of sewage that control wastewater interception pipe is collected, often gushes side and arranges electric gate valve in the nearly river of inspection shaft.Conventional inspection shaft is due to electricity Dynamic gate control section is exposed outside, not only affects traffic, and exist get rusty, the hidden danger such as antitheft.
The reason for river gushes black smelly includes point-source pollution, pollution of area source, endogenous pollution and other pollutions.
Wherein, point-source pollution refers to the various polluter for entering urban water-body with point source pattern, mainly includes that floss hole is straight Blowdown water, interflow tubing giving sufficient strength rainy season overflow, separate system storm sewer early-stage rainwater or non-irrigated flowing water, unconventional water source moisturizing etc..
Pollution of area source is referred to non-point source(Spread source)Form enters the various polluter of urban water-body, mainly including all kinds of Pollution of pollutional load, combination area of city and country area distributing livestock breeding wastewater entrained by precipitation etc., generally has obvious Region and seasonal variation characteristics.
It is endogenous be primarily referred to as various floating things in pollutant contained in urban water-body bed mud and water body, float, The putrefaction that bank rubbish, the water plant do not cleared up or wawter bloom algae etc. are formed.
Other polluter mainly include exceeded urban wastewater treatment firm tail water, industrial undertaking's accidental release, fall foliage Deng generally falling into seasonal or provisional polluter.Fall foliage problem is more obvious in northern area, and fallen leaves are entered after water body To gradually rot and sink under water, it is possible to create black smelly bed mud.
Utility model content
The technical problems to be solved in the utility model is:There is provided a kind of double-deck gate suitable for river controlling projects to control Well.
This utility model solves the solution of its technical problem:
A kind of double-deck gate suitable for river controlling projects controls well, including the well body for being provided with well head, also including lifting Part, the operation layer that well body is included in and the control water layer under, control water layer is provided with water inlet and outlet, and outlet is provided with Can height up and down gate, the aperture area of outlet changes with the adjustable height of gate and changes, be provided with operation layer Controller, controller is connected with lifting part, and lifting part puts in from operation layer and be connected in control water layer and with gate so that control Device can make gate lift by lifting part.
Used as the further improvement of such scheme, the gate is circle.
As the further improvement of such scheme, guide holder is provided with control water layer, the guide holder is provided with pilot hole, lifting Part passes through the guide holder.
As the further improvement of such scheme, ladder is provided with below well head, the ladder is extended to from well head Control water layer.
Used as the further improvement of such scheme, controller is provided with gear, and lifting part is connected with the gear, controls Device is additionally provided with operation handle, and operation handle is connected with the gear.
Used as the further improvement of such scheme, controller is provided with electric module, and the electric module connects with control module Connect.
As the further improvement of such scheme, in control water layer water-level gauge is provided with.
Used as the further improvement of such scheme, the control module is PLC.
The beneficial effects of the utility model are:A kind of double-deck gate suitable for river controlling projects controls well, including setting There is the well body of well head, also including lifting part, the operation layer that well body is included in and the control water layer under, control water layer is provided with into water Mouthful and outlet, outlet be provided with can height up and down gate, the aperture area of outlet with gate adjustable height Change and change, controller is provided with operation layer, controller is connected with lifting part, and lifting part puts in control water layer from operation layer It is interior and be connected with gate so that controller can make gate lift by lifting part.Outlet be for lead to the pipe that river is gushed Road connection, and water inlet is connected with urban sewage pipe.During dry season, general who has surrendered's outlet under gate is allowed to block completely, city During the sewage in city will not gush into river.And at rainy season, if the water level in well body is higher than a certain numerical value of water level that river is gushed, make gate Rise blowdown, if the water level that river is gushed is higher than a certain numerical value of water level in well body, making gate decline prevents from pouring in down a chimney and caused waterlogging. This utility model is used for the regulation and control of sewage.
Description of the drawings
Technical scheme in order to be illustrated more clearly that this utility model embodiment, below will be to needed for embodiment description The accompanying drawing to be used is briefly described.Obviously, described accompanying drawing is a part of embodiment of the present utility model, rather than entirely Portion's embodiment, those skilled in the art on the premise of not paying creative work, can be obtaining it according to these accompanying drawings His design and accompanying drawing.
Fig. 1 is the cross-sectional schematic in the main view direction of this utility model embodiment;
Fig. 2 is the cross-sectional schematic of the right apparent direction of this utility model embodiment.
Specific embodiment
The technique effect of design of the present utility model, concrete structure and generation is carried out below with reference to embodiment and accompanying drawing Clearly and completely describe, to be completely understood by the purpose of this utility model, feature and effect.Obviously, described embodiment It is a part of embodiment of the present utility model, rather than whole embodiments, based on embodiment of the present utility model, the skill of this area The other embodiment that art personnel are obtained on the premise of not paying creative work, belongs to the model of this utility model protection Enclose.In addition, all connection/annexations being previously mentioned in text, not singly refer to that component directly connects, and refer to can be according to concrete reality Situation is applied, by adding or reducing couple auxiliary more excellent draw bail is constituted.Each technology in this utility model is special Levy, can be with combination of interactions on the premise of not conflicting conflict.
See figures.1.and.2, this is one embodiment of the present utility model, specifically:
A kind of double-deck gate suitable for river controlling projects controls well, including the well body for being provided with well head, also including lifting Part 21, the operation layer 11 that well body is included in and the control water layer 12 under, control water layer 12 is provided with water inlet and outlet 121, Outlet 121 be provided with can height up and down gate 2, the aperture area of outlet 121 changes with the adjustable height of gate 2 And change, controller 3 is provided with operation layer 11, controller 3 is connected with lifting part 21, and lifting part 21 puts in from operation layer 11 It is connected in control water layer 12 and with gate 2 so that controller 3 can make gate 2 lift by lifting part 21.Outlet be for Lead to what the pipeline for gushing in river connected, and water inlet is connected with urban sewage pipe.During dry season, general who has surrendered's outlet under gate is allowed Block completely, during the sewage in city will not gush into river.And at rainy season, if the water level in well body is a certain higher than the water level that river is gushed Numerical value, makes gate rise blowdown, if the water level that gushes of river is higher than a certain numerical value of water level in well body, make gate decline prevent from pouring in down a chimney and Caused waterlogging.
Lead to the pipeline connection gushed in river and be generally prefabricated circular pipe, so outlet 121 is also circle, therefore the gate 2 are circle.
For the ease of being oriented to the intensity for improving gate simultaneously, in control water layer 12 guide holder 122, the guide holder 122 are provided with Pilot hole is provided with, lifting part 21 passes through the guide holder 122.
For the ease of clearing up the mud of well body bottom, ladder is provided with below well head, the ladder extends always from well head To control water layer 12.
In order to the height of gate of the present embodiment can be controlled manually, controller 3 is provided with gear, lifting part 21 with The gear connection, controller 3 is additionally provided with operation handle 22, and operation handle 22 is connected with the gear.
The controller 3 of the present embodiment is provided with electric module, and the electric module is connected with control module.By control module with Control centre networks, and control centre can just remotely control gate.
In order to provide accurate waterlevel data to control centre, in control water layer 12 water-level gauge is provided with.Can certainly be by water Position meter is connected with control module, and allows control module to be preloaded with intelligent control program, makes the main retention of excessive fluid position of water table ratio in well body high Self-shooter is allowed to be opened during 0.5m, and the main retention of excessive fluid position of the water table ratio in well body allows gate to be automatically switched off when low.
Preferably, the control module is PLC.
Better embodiment of the present utility model is illustrated above, but this utility model be not limited to it is described Embodiment, those of ordinary skill in the art can also make a variety of equivalents and become on the premise of without prejudice to this utility model spirit Type or replacement, the modification of these equivalents or replacement are all contained in the application claim limited range.

Claims (8)

1. a kind of double-deck gate suitable for river controlling projects controls well, including the well body for being provided with well head, it is characterised in that:Also Including lifting part(21), the operation layer that well body is included in(11)With the control water layer under(12), control water layer(12)Be provided with into The mouth of a river and outlet(121), outlet(121)Be provided with can height up and down gate(2), outlet(121)Opening Area is with gate(2)Adjustable height change and change, operation layer(11)Inside it is provided with controller(3), controller(3)With lifting portion Part(21)Connection, lifts part(21)From operation layer(11)Put in control water layer(12)Interior and and gate(2)Connection so that controller (3)Can be by lifting part(21)Make gate(2)Lifting.
2. a kind of double-deck gate suitable for river controlling projects according to claim 1 controls well, it is characterised in that:Institute State gate(2)For circle.
3. a kind of double-deck gate suitable for river controlling projects according to claim 1 controls well, it is characterised in that:Control Water layer(12)Inside it is provided with guide holder(122), the guide holder(122)Pilot hole is provided with, part is lifted(21)Through the guiding Seat(122).
4. a kind of double-deck gate suitable for river controlling projects according to claim 1 controls well, it is characterised in that:Well The lower section of mouth is provided with ladder, and the ladder extends to control water layer from well head(12).
5. a kind of double-deck gate suitable for river controlling projects according to claim 1 controls well, it is characterised in that:Control Device processed(3)Gear is provided with, part is lifted(21)It is connected with the gear, controller(3)It is additionally provided with operation handle(22), operation Handle(22)It is connected with the gear.
6. a kind of double-deck gate suitable for river controlling projects according to claim 1 controls well, it is characterised in that:Control Device processed(3)Electric module is provided with, the electric module is connected with control module.
7. a kind of double-deck gate suitable for river controlling projects according to claim 6 controls well, it is characterised in that:Control Water layer(12)Inside it is provided with water-level gauge.
8. a kind of double-deck gate suitable for river controlling projects according to claim 6 controls well, it is characterised in that:Institute Control module is stated for PLC.
CN201620933740.5U 2016-08-24 2016-08-24 Double -deck gate control well suitable for river regulation engineering Active CN206110186U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620933740.5U CN206110186U (en) 2016-08-24 2016-08-24 Double -deck gate control well suitable for river regulation engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620933740.5U CN206110186U (en) 2016-08-24 2016-08-24 Double -deck gate control well suitable for river regulation engineering

Publications (1)

Publication Number Publication Date
CN206110186U true CN206110186U (en) 2017-04-19

Family

ID=58512896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620933740.5U Active CN206110186U (en) 2016-08-24 2016-08-24 Double -deck gate control well suitable for river regulation engineering

Country Status (1)

Country Link
CN (1) CN206110186U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593379A (en) * 2019-08-30 2019-12-20 南京庞瑞科技有限公司 Intelligent sewage well based on Internet of things technology
CN115059029A (en) * 2022-06-24 2022-09-16 中铁建安工程设计院有限公司 Semicircular curved surface sewage interception gate

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593379A (en) * 2019-08-30 2019-12-20 南京庞瑞科技有限公司 Intelligent sewage well based on Internet of things technology
CN115059029A (en) * 2022-06-24 2022-09-16 中铁建安工程设计院有限公司 Semicircular curved surface sewage interception gate
CN115059029B (en) * 2022-06-24 2024-01-16 中铁建安工程设计院有限公司 Semicircular curved surface dirt interception gate

Similar Documents

Publication Publication Date Title
CN103821222B (en) Take into account early-stage rainwater and the rain dirty mixing water overflow storage pond facility of flood peak reduction
CN107605006B (en) Drainage system and drainage control method
CN105198085B (en) A kind of staged horizontal drowned flow artificial wet land combined system and its application
CN203834623U (en) Single building balcony sewage and rainwater shunting device
CN109457789A (en) Primary rainwater closure well
CN206110186U (en) Double -deck gate control well suitable for river regulation engineering
CN207567889U (en) Residential quarters Rainwater collection system
CN202990090U (en) Control device for controlling to flow equally under condition of water level change
CN209538351U (en) A kind of rain perforaled strainer with initial stage rain sewage diversion function
CN205012279U (en) River system system of light green ground of shore view
CN204982781U (en) Water simply cuts dirty device
CN108457178B (en) Environmental protection collection and purification system for river bridge deck sewage/wastewater
CN103437281A (en) Bridge deck runoff collection treatment and emergency system
CN203383144U (en) Bridge floor runoff collection, treatment and emergency system
CN110029721A (en) A kind of combine with the pipe culvert of blowdown and first rain Regulation Function cuts dirty structure
CN206114639U (en) Lab scale test device is reinforceed to self purification of water body ability
CN206128001U (en) Prefabricated dirt lateral that cuts suitable for black and odorous water body administers
CN205637031U (en) Burst online processing discharge system that dams
CN207243686U (en) A kind of overpass rain processing system
CN207871715U (en) Rural rainwater purification pond
CN106638889A (en) Un-obvious initial rain characteristic online fragment treatment discharge system under combined system or mixed system and control method of discharge system
CN202718232U (en) Buoy flow-limiting valve for combined system sewage intercepting well
CN106193262A (en) A kind of rain dirt mixed flow pipeline Vatch basin
CN107879564B (en) In-situ treatment system for river drain outlet
CN205776648U (en) Rainwater division based on combined system pipe network discarding system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant