CN206110078U CN201620978863.0U CN201620978863U CN206110078U CN 206110078 U CN206110078 U CN 206110078U CN 201620978863 U CN201620978863 U CN 201620978863U CN 206110078 U CN206110078 U CN 206110078U
Authority
CN
China
Prior art keywords
flashboard
iron wall
spud pile
built
floodgate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620978863.0U
Other languages
Chinese (zh)
Inventor
卞正奎
鲁秀国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620978863.0U priority Critical patent/CN206110078U/en
Application granted granted Critical
Publication of CN206110078U publication Critical patent/CN206110078U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a floodgate is detained flood fighting of style iron wall and is built stifled dyke device that lacks, formula iron wall is detained for the floodgate to the device, including flashboard, spud pile and sleeve pipe, flashboard one side fixed connection spud pile, flashboard opposite side fixedly connected with sleeve pipe, the sleeve pipe is equipped with the breach, the flashboard passes the breach and will overlap the pipe box and locate on the spud pile, regular spread has the through -hole on the spud pile, be equipped with on the flashboard and press the recess that shakes. The utility model discloses a floodgate is detained flood fighting of style iron wall and is built stifled dyke device that lacks can stop up the breach that inrushes fast, the anxious situation of the rivers security implementation that does, the quick realization piping, the processing of breaching a dyke, it provides convenient security assurances to increase for the dyke heap, and simple process does not need a large amount of manpowers, material resources, as long as carry out the fixed mounting that formula iron wall was detained to the floodgate as required, can form the new flood -fighting line of defence one, and the shock resistance promotes by a wide margin.

Description

Stifled scarce dike device is built in a kind of lock button iron wall flood fighting
Technical field
The utility model is related to the field of fighting flood and relieve victims, and stifled scarce dike device is built in specifically a kind of lock button iron wall flood fighting.
Background technology
China territory is vast, with a varied topography, climate variability, population Relatively centralized and rivers and lakes bank wide geographic area.Often All can there is different degrees of flood in different regions in the summer and autumn in year, and it seriously threatens these regional industrial or agricultural Production and the safety of people's lives and properties.The Chinese government always pays much attention to Water Capital Construction, all put into every year a large amount of manpowers, Material resources, financial resources are used to reinforce flood bank, but flood bank major part is soil is built, and through winter spring break is freezed Afterwards structure becomes loose, and nest is done in the cave of building of animal, can not timely be safeguarded in addition, occurs as soon as after flood occurs Piping, breach a dyke, the phenomenon of levee body too short, once there is above-mentioned emergency, such as not in time take blocking reinforcement measure, will Cause serious consequence.And existing means to save the situation, remain original, simply the straw bag that filling mud is blocked is made into plastics volume Knit bag, moreover substantial amounts of person property is needed using this original method, often to lean on substantial amounts of personnel to dig where far Soil fills bag and pickaback comes, and greatly, Jing often that personnel are overworked and the even dead event that falls down to the ground of suffering a shock to labour intensity occurs, in addition Because the big stream of water is anxious, usually casts earth bag and just washed away by flood, and if flood can not timely obtain becoming if blocking disconnected downstream in a moment Into a vast expanse of water.It is this for the existing means of such situation mainly also line up wall to slow down flood velocity hand in hand by human body Method is very big to personnel hazard's property, is accidentally swept away by flood and will result in casualties, the too urgent breach of some current or Do not stint and the jumboes such as vehicle are put in water, to slow down current.
It is thing very thorny in flood fighting for piping occur in dykes and dams, if being caused to lack the thing of dike by piping or unrestrained dike etc. Therefore, even more very thorny thing is not directed at present piping, preferably solution of breaching a dyke, and does so needing badly and looking for one kind Method solves the above problems.
Utility model content
The purpose of this utility model is to overcome above-mentioned the deficiencies in the prior art, and the technology for solving presently, there are lacks Fall into, the utility model provides a kind of lock button iron wall flood fighting and builds stifled scarce dike device.
The technical scheme that the utility model is adopted is:
Stifled scarce dike device is built in a kind of lock button iron wall flood fighting, and described device is lock button iron wall, including flashboard, spud pile and Sleeve pipe, the flashboard side is fixedly connected spud pile, and the flashboard opposite side is fixedly connected with sleeve pipe, and described sleeve pipe is provided with scarce Mouthful, the flashboard is located at casing pipe sleeve on spud pile through breach.
Further, it is regularly arranged on the spud pile to have through hole.
Further, the flashboard is provided with the groove that pressure is shaken.
Further, the groove is airplane-shaped, can be carried out with the pressure situation of shaking of spud pile according to flashboard Two-end coupling annular tube Adjustment.
The beneficial effects of the utility model are:Stifled scarce dike device is built in lock button iron wall flood fighting disclosed in the utility model,
1st, can quickly block the breach for inrushing, the more anxious situation of current also can security implementation, quickly realize to piping, breach a dyke Process;
2nd, offer easily safety assurance, process is simple are increased for dike heap, it is not necessary to a large amount of human and material resources, as long as according to Need the fixed installation for carrying out lock button iron wall, you can form one new flood fighting defence line, and shock resistance is substantially improved.
The utility model is described in further detail below in conjunction with the accompanying drawings.
Description of the drawings
Fig. 1 is that the structural representation after stifled scarce dike device is installed is built in the utility model lock button iron wall flood fighting.
Fig. 2 is that the overlooking the structure diagram after stifled scarce dike device is installed is built in the utility model lock button iron wall flood fighting.
Fig. 3 is that the cross-sectional view after stifled scarce dike device is installed is built in the utility model lock button iron wall flood fighting.
In figure, 1- flashboard 2- spud pile 3- sleeve pipes.
Specific embodiment
In order to deepen, to understanding of the present utility model, the utility model to be made further in detail with reference to the accompanying drawings and examples Thin explanation.Following examples are only used for clearly illustrating the technical solution of the utility model, and can not be limited with this Protection domain of the present utility model.
As shown in figure 1, stifled scarce dike device is built in the utility model lock button iron wall flood fighting, device is lock button iron wall, flashboard, Spud pile and sleeve pipe, flashboard side is fixedly connected spud pile, and flashboard opposite side is fixedly connected with sleeve pipe, and described sleeve pipe is provided with scarce Mouthful, flashboard is located at casing pipe sleeve on spud pile through breach.
Further, it is regularly arranged on spud pile to have through hole.
Further, flashboard is provided with the groove that pressure is shaken.
Further, the groove is airplane-shaped, can be carried out with the pressure situation of shaking of spud pile according to flashboard Two-end coupling annular tube Adjustment.
Specific embodiment of the utility model is generally to survey the length and water depth of the heap that breached a dyke;U-shaped is made with water proof cloth Shape, prevents the continuous of breach from bursting;The lock button iron wall being prefabricated into is transported to into scene;First a spud pile is fixed on into dike heap, First is formed across Tie Bi;After the first depth needed for the spud pile of iron wall is embedded in dike heap, second is carried out across construction;Second Across casing pipe sleeve first on the spud pile of iron wall after carry out pressure and shake, with recessed in the middle of the vibration head alignment flashboard of excavator Groove, presses down into vertical configuration and shakes, and pushes ahead in order;For the region for being separated is banketed;To installing fixation Gap foaming and intumescing body or cement between sleeve pipe firmly and spud pile is implemented to tamp;When both sides are constructed simultaneously, it is right to reach Place is met, takes water proof cloth U-shaped in inwall, built-in sand hill breaks and lives leak, is banketed, order of banketing is first outside, interior afterwards Side.
If current are more anxious, the position of lock button iron wall cannot be fixed, and outhauler post can be arranged in water, by outhauler Post, on lock button iron wall hoist ropes is fixed, for the position of lock button iron wall is fixed as needed.
When both sides are constructed simultaneously, joint is reached, a lock button iron wall can be configured according to the distance of joint measurement, Carry out closing up fixation.
Further, lock button iron wall is arranged in isosceles triangle, can each other form support, and compressive resistance is strong.
It is noted that embodiment described above is to the illustrative and not limiting of technical solutions of the utility model, affiliated skill The equivalent of art field those of ordinary skill or other modifications made according to prior art, as long as not new beyond this practicality The thinking and scope of type technical scheme, should be included within the interest field required by the utility model.

Claims (4)

1. stifled scarce dike device is built in a kind of lock button iron wall flood fighting, it is characterised in that:Described device is lock button iron wall, including lock Plate, spud pile and sleeve pipe, the flashboard side is fixedly connected spud pile, and the flashboard opposite side is fixedly connected with sleeve pipe, described Sleeve pipe is provided with breach, and the flashboard is located at casing pipe sleeve on spud pile through breach.
2. stifled scarce dike device is built in a kind of lock button iron wall flood fighting according to claim 1, it is characterised in that:The spud pile It is above regularly arranged to have through hole.
3. stifled scarce dike device is built in a kind of lock button iron wall flood fighting according to claim 1, it is characterised in that:On the flashboard It is provided with the groove that pressure is shaken.
4. stifled scarce dike device is built in a kind of lock button iron wall flood fighting according to claim 3, it is characterised in that:The groove is Airplane-shaped.
CN201620978863.0U 2016-08-26 2016-08-26 Floodgate is detained flood fighting of style iron wall and is built stifled dyke device that lacks Expired - Fee Related CN206110078U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620978863.0U CN206110078U (en) 2016-08-26 2016-08-26 Floodgate is detained flood fighting of style iron wall and is built stifled dyke device that lacks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620978863.0U CN206110078U (en) 2016-08-26 2016-08-26 Floodgate is detained flood fighting of style iron wall and is built stifled dyke device that lacks

Publications (1)

Publication Number Publication Date
CN206110078U true CN206110078U (en) 2017-04-19

Family

ID=58513796

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620978863.0U Expired - Fee Related CN206110078U (en) 2016-08-26 2016-08-26 Floodgate is detained flood fighting of style iron wall and is built stifled dyke device that lacks

Country Status (1)

Country Link
CN (1) CN206110078U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284204A (en) * 2016-08-26 2017-01-04 卞正奎 The quick device of a kind of fill heap of fighting flood and relieve victims, protect and technique
CN114277731A (en) * 2022-01-17 2022-04-05 南京工业大学 Quick plugging device of dyke breach

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284204A (en) * 2016-08-26 2017-01-04 卞正奎 The quick device of a kind of fill heap of fighting flood and relieve victims, protect and technique
CN106284204B (en) * 2016-08-26 2018-07-10 卞正奎 A kind of quick device and technique of fill heap of fighting flood and relieve victims, protect
CN114277731A (en) * 2022-01-17 2022-04-05 南京工业大学 Quick plugging device of dyke breach
CN114277731B (en) * 2022-01-17 2022-09-27 南京工业大学 Quick plugging device of dyke breach

Similar Documents

Publication Publication Date Title
CN108978585B (en) Flood control dykes and dams of scour protection
CN206015612U (en) A kind of quick and safe device of closure piping
CN205102879U (en) Weir of simultaneous observation hillside surface runoff and interflow
CN206110078U (en) Floodgate is detained flood fighting of style iron wall and is built stifled dyke device that lacks
CN205742175U (en) A kind of steel construction protection wall of bored pile
CN100342090C (en) Technology for securing landslip with swelled ground
CN106284204B (en) A kind of quick device and technique of fill heap of fighting flood and relieve victims, protect
CN205999897U (en) A kind of seepage proof curtain using dewatering well borders on the river foundation ditch
CN107044131A (en) A kind of anti-seepage method of deep covering layer
CN109024476A (en) Base self collapsing levee dam geotechnique's woven fabric very floodway is washed in a pan in cross flow
CN209456974U (en) A kind of articulated hinge concrete block system
CN208039303U (en) A kind of Construction of Civil Engineering retaining wall
CN216075134U (en) Rich water district faces lake sandy soil deep basal pit hillside top construction road structure
CN206477308U (en) A kind of compatible ready-package river levee in dike road
CN205557473U (en) Remote control type floodwall dam gate
CN209958291U (en) Anti-overflow dam capable of being assembled and disassembled instantly
CN206110077U (en) Impervious water conservancy floodwall
CN213867663U (en) Earth and rockfill dam post-drainage and leakage measurement arrangement system
CN205000346U (en) Slope frame for slope reinforcement and water drainage
CN212052585U (en) Ecological bank protection is used in hydraulic engineering construction with water level monitoring function
CN209760164U (en) Small landscape retaining dam with fishway
CN208777263U (en) A kind of permeable three bars concrete interlocking armour
CN214143539U (en) Slope protection for antiseep water conservancy flood control
CN213773205U (en) Hydraulic engineering bank protection device
CN210658250U (en) Novel debris flow blocking dam capable of effectively reducing uplift pressure of dam foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170419

Termination date: 20210826

CF01 Termination of patent right due to non-payment of annual fee