CN206094126U - Electric stove evaporative cooling flue's cooling zone - Google Patents

Electric stove evaporative cooling flue's cooling zone Download PDF

Info

Publication number
CN206094126U
CN206094126U CN201620825738.6U CN201620825738U CN206094126U CN 206094126 U CN206094126 U CN 206094126U CN 201620825738 U CN201620825738 U CN 201620825738U CN 206094126 U CN206094126 U CN 206094126U
Authority
CN
China
Prior art keywords
flue
water
return
cooling
water inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620825738.6U
Other languages
Chinese (zh)
Inventor
王中建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Bengang Steel Plates Co Ltd
Original Assignee
Bengang Steel Plates Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bengang Steel Plates Co Ltd filed Critical Bengang Steel Plates Co Ltd
Priority to CN201620825738.6U priority Critical patent/CN206094126U/en
Application granted granted Critical
Publication of CN206094126U publication Critical patent/CN206094126U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The utility model relates to an auxiliary assembly of electric stove, concretely relates to electric stove evaporative cooling flue's cooling zone. Including anterior segment, back end and flange, the anterior segment passes through with the back end flange joint together, the anterior segment is inside to be set up and is on a parallel with the flue axis and carries out the water cold wall pipe no. 1 that extends, the back end is inside to be set up and is on a parallel with the flue axis and carries out the water cold wall pipe no. 2 that extends, the water inlet manifold that the anterior segment passes through inlet tube no. 1 and circulating water pump is connected, and the flue return water rising main with the steam pocket is connected through wet return no. 1, the water inlet manifold that the back end passes through inlet tube no. 2 and circulating water pump is connected, and the flue return water rising main with the steam pocket is connected through wet return no. 2, circulating water pump passes through the return main and is connected with the steam pocket. The utility model discloses make the high -temperature area of flue relatively independent, can be at the short time in line processing after it breaks down to but the commute decreases the position and in time changes, reduces maintenance work volume and maintenance cost.

Description

A kind of cooling section of electric furnace gasification cooling flue
Technical field
The utility model is related to a kind of auxiliary equipment of electric furnace, and in particular to a kind of cooling of electric furnace gasification cooling flue Section.
Background technology
The gasification cooling flue of electric furnace is one of the necessaries for realizing energy recovery and green production, and it is used for electricity The flue gas produced in stove steelmaking process is cooled down and reclaimed.First paragraph of the current domestic gasification cooling flue from electric furnace side (i.e. cooling section) is an entirety, and such design have ignored the Temperature Distribution in flue, and flue is extended to from import to inner side The position on arc top is high-temperature area, and maximum temperature can reach 1300 DEG C, following position be in gentle low-temperature region, temperature exists Between 800 DEG C -1000 DEG C.The service life of normal gasification cooling flue was up to 4 years, and the life-span of high-temperature area can be only sustained at 2 years, damageable zone is not carried out independently to consider, relatively reduce the service life of flue.
Utility model content
The utility model provides a kind of cooling section of electric furnace gasification cooling flue so that the high-temperature area of flue is relatively only It is vertical, can process at short notice after it breaks down, and damageable zone can in time be changed, reduce maintenance load and Maintenance cost.
The technical solution of the utility model is as follows:
A kind of cooling section of electric furnace gasification cooling flue, including leading portion, back segment and flange, the leading portion passes through institute with back segment State flange to link together, the water screen tube one that flue axis is extended, the back segment are arranged parallel to inside the leading portion Inside is arranged parallel to the water screen tube two that flue axis is extended;The leading portion is entered by water inlet pipe one and water circulating pump Supply mains connects, and is connected with the flue backwater rising main of drum by return pipe one;The back segment passes through water inlet pipe two and follows The water inlet manifold connection of ring water pump, is connected by return pipe two with the flue backwater rising main of drum;Water circulating pump passes through back Supply mains is connected with drum.
The cooling section of described electric furnace gasification cooling flue, its preferred version is that the flange is by asbestos seal.
The cooling section of described electric furnace gasification cooling flue, its preferred version is, the caliber of water inlet pipe one and water inlet pipe two At least 150mm.
The cooling section of described electric furnace gasification cooling flue, its preferred version is, the caliber of return pipe one and return pipe two At least 200mm.
The cooling section of described electric furnace gasification cooling flue, its preferred version is that the caliber of return main is at least 300mm。
The beneficial effects of the utility model are:
1st, the utility model carries out subsection setup by the cooling section of electric furnace gasification cooling flue so that flue from import to The position (i.e. high-temperature area) that inner side extends to arc top is relatively independent, can process at short notice after it breaks down, and can Damageable zone is changed in time, maintenance load and maintenance cost is reduced.
2nd, the cooling water pipeline in the utility model is optimised, and the leading portion of cooling section, back segment are carried out individually with water circulation, Circulated into short distance single group by over long distances multigroup loop optimization so that its cooling effect ensured, extend the use of flue Life-span.
Description of the drawings
Fig. 1 is the cooling section structural representation of electric furnace gasification cooling flue;
Fig. 2 is Section A-A schematic diagram in Fig. 1;
Fig. 3 is the circulation waterway schematic diagram of electric furnace gasification cooling flue.
Specific embodiment
As shown in Figures 1 to 3, a kind of cooling section of electric furnace gasification cooling flue, including leading portion 1, back segment 3 and flange 2, it is described Leading portion 1 is linked together with back segment 3 by the flange 2, and the flange 2 is by asbestos seal;The inside of the leading portion 1 arranges parallel In the water screen tube one that flue axis is extended, the water-cooled that flue axis is extended is arranged parallel to inside the back segment 3 Wall pipe 24;The leading portion 1 is connected by water inlet pipe 1 with the water inlet manifold 13 of water circulating pump 5, by return pipe 1 and vapour The flue backwater rising main 14 of bag 6 connects;The back segment 3 is connected by water inlet pipe 2 10 with the water inlet manifold 13 of water circulating pump 5 Connect, be connected with the flue backwater rising main 14 of drum 6 by return pipe 2 12;The caliber of water inlet pipe 1 and water inlet pipe 2 10 Caliber for 150mm, return pipe 11 and return pipe 2 12 is 200mm;Water circulating pump 5 is connected by return main 15 with drum 6, The caliber of return main is 300mm;Flow control valve 1 is set on water inlet pipe 1, flow control valve is set on water inlet pipe 2 10 28, the inflow that flow control valve 1 controls water inlet pipe one when using is 270m3/ h, the control water inlet pipe of flow control valve 28 Two inflow is 200m3/ h, to ensure to strengthen the cooling effect of the leading portion 1;The number of water screen tube one and water screen tube 24 Amount is all 108;The overall length of water screen tube one is 8 meters, realizes that short distance single group is circulated, and its cooling effect is ensured.

Claims (5)

1. a kind of cooling section of electric furnace gasification cooling flue, it is characterised in that including leading portion, back segment and flange, the leading portion with Back segment is linked together by the flange, and the water screen tube that flue axis is extended is arranged parallel to inside the leading portion One, the water screen tube two that flue axis is extended is arranged parallel to inside the back segment;The leading portion by water inlet pipe one with The water inlet manifold connection of water circulating pump, is connected by return pipe one with the flue backwater rising main of drum;The back segment passes through Water inlet pipe two is connected with the water inlet manifold of water circulating pump, is connected with the flue backwater rising main of drum by return pipe two;Follow Ring water pump is connected by return main with drum.
2. the cooling section of electric furnace gasification cooling flue according to claim 1, it is characterised in that the flange is close by asbestos Envelope.
3. the cooling section of electric furnace gasification cooling flue according to claim 1, it is characterised in that water inlet pipe one and water inlet pipe Two caliber is at least 150mm.
4. the cooling section of electric furnace gasification cooling flue according to claim 1, it is characterised in that return pipe one and return pipe Two caliber is at least 200mm.
5. the cooling section of electric furnace gasification cooling flue according to claim 1, it is characterised in that the caliber of return main is extremely It is less 300mm.
CN201620825738.6U 2016-07-29 2016-07-29 Electric stove evaporative cooling flue's cooling zone Expired - Fee Related CN206094126U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620825738.6U CN206094126U (en) 2016-07-29 2016-07-29 Electric stove evaporative cooling flue's cooling zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620825738.6U CN206094126U (en) 2016-07-29 2016-07-29 Electric stove evaporative cooling flue's cooling zone

Publications (1)

Publication Number Publication Date
CN206094126U true CN206094126U (en) 2017-04-12

Family

ID=58467670

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620825738.6U Expired - Fee Related CN206094126U (en) 2016-07-29 2016-07-29 Electric stove evaporative cooling flue's cooling zone

Country Status (1)

Country Link
CN (1) CN206094126U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106090963A (en) * 2016-07-29 2016-11-09 本钢板材股份有限公司 A kind of cooling section of electric furnace gasification cooling flue

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106090963A (en) * 2016-07-29 2016-11-09 本钢板材股份有限公司 A kind of cooling section of electric furnace gasification cooling flue

Similar Documents

Publication Publication Date Title
CN103657329B (en) A kind of yellow phosphoric tail gas centralized Control reclaims and purifier
CN209540854U (en) A kind of power generation station-service boiler overheating cooling device
CN204730670U (en) A kind of residual heat and energy comprehensive utilization TRT
CN206094126U (en) Electric stove evaporative cooling flue's cooling zone
CN106090963A (en) A kind of cooling section of electric furnace gasification cooling flue
CN208536582U (en) A kind of electric arc furnaces spray cooling device
CN104653242B (en) A kind of Direct Air-cooled Unit waste-heat recovery device
CN204026622U (en) Steam boiler
CN207567275U (en) Vaporize latter end flue compulsory circulative cooling system
CN103697451B (en) A kind of high-temperature atmospheric steam generator
CN108413779A (en) A kind of split type, curved flue of mixed type electric furnace entrance
CN206204344U (en) A kind of blast furnace slag flushing water circulation system
CN206073125U (en) A kind of Direct Air-Cooled tower waste heat circulation system
CN205261518U (en) Steaming system
CN102878818A (en) Heat supply system using waste heat in self-absorption type negative-pressure adjustable heat carrier furnace
CN209027307U (en) A kind of split type, curved flue of mixed type electric furnace entrance
CN204514069U (en) A kind of afterheat heat exchanger based on cement kiln head waste gas
CN104344726B (en) Vanadium goods raw material preheating system
CN209431389U (en) A kind of waste incineration and generating electricity heat energy recycling system of air compressor
CN209279132U (en) A kind of boiler province's coal-firing device
CN104807338A (en) Coal gas, converter steam and sintering waste heat combined power generation device and waste heat utilization method
CN206958585U (en) A kind of blast furnace blower Lubricating oil heating device
CN206771303U (en) A kind of natural gas steam generator
CN109442369A (en) A kind of energy conservation and environmental protection steam boiler for dual purpose
CN205079635U (en) Finned tube cooling water steam heat recovery system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170412

Termination date: 20180729