CN206023986U - A kind of Arch Bridge Construction monitoring system with real-time monitoring and control - Google Patents

A kind of Arch Bridge Construction monitoring system with real-time monitoring and control Download PDF

Info

Publication number
CN206023986U
CN206023986U CN201620894959.9U CN201620894959U CN206023986U CN 206023986 U CN206023986 U CN 206023986U CN 201620894959 U CN201620894959 U CN 201620894959U CN 206023986 U CN206023986 U CN 206023986U
Authority
CN
China
Prior art keywords
surveillance equipment
job site
watch
infrared surveillance
dog
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620894959.9U
Other languages
Chinese (zh)
Inventor
周会军
黄玉萍
凌建军
韩森
王新妍
杜儒林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Building Installation Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Building Installation Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Building Installation Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201620894959.9U priority Critical patent/CN206023986U/en
Application granted granted Critical
Publication of CN206023986U publication Critical patent/CN206023986U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Warehouses Or Storage Devices (AREA)
  • Alarm Systems (AREA)

Abstract

The utility model discloses a kind of Arch Bridge Construction monitoring system with real-time monitoring and control, including job site infrared surveillance equipment, emergency controller, warehouse watch-dog, transport of materials watch-dog and connection rotating shaft, the front surface of the job site infrared surveillance equipment is provided with louvre, and the right side middle position of job site infrared surveillance equipment is provided with power supply connector, netting twine connector is provided with the job site infrared surveillance equipment below power supply connector, and the connection rotating shaft installs the lower section middle position of infrared surveillance equipment at the construction field (site).This utility model is scientific and reasonable for structure, job site infrared surveillance equipment can be in real time by the picture transmission of job site to Control Room, remote control room can pass through warehouse watch-dog and transport of materials watch-dog monitors material storehouse and transport routes real time status simultaneously, improve the scope of monitoring, VRAM is easy to store monitor video, is easy to the later stage to check.

Description

A kind of Arch Bridge Construction monitoring system with real-time monitoring and control
Technical field
This utility model belongs to bridge monitoring technical field, and in particular to a kind of Arch Bridge Construction with real-time monitoring and control Monitoring system.
Background technology
Monitoring system is to apply one of most systems in safety-protection system, the building site monitoring system being more suitable on the market now System is handheld video communication equipment, and video monitoring is main flow now.From earliest simulation monitoring to burning hot digital supervision a few years ago Network Video Surveillance in the ascendant till now, there occurs earth-shaking change again.Progressively unify global today in IP technology, we It is necessary to re-recognize video monitoring system developing history.From the technical point of view, video monitoring system development is divided into first For analog video monitoring system (CCTV), " PC+ multimedia cards " digital video monitor system (DVR) is based on to the second filial generation, to the Three generations is based entirely on IP network video monitoring system (IPVS).
Existing bridge monitoring device single function, monitoring system imperfection can not notify scene in time when occurring unexpected The problem that workmen withdraws in time, is this it is proposed that a kind of Arch Bridge Construction monitoring system with real-time monitoring and control.
Utility model content
The purpose of this utility model is to provide a kind of Arch Bridge Construction monitoring system with real-time monitoring and control, to solve Bridge monitoring device single function is proposed in above-mentioned background technology, and monitoring system imperfection can not be notified in time when occurring unexpected The problem that site operation personnel withdraw in time.
For achieving the above object, this utility model provides following technical scheme:A kind of arch bridge with real-time monitoring and control Construction monitoring system, including job site infrared surveillance equipment, emergency controller, warehouse watch-dog, transport of materials watch-dog and company Switch through axle, the front surface of the job site infrared surveillance equipment is provided with louvre, and the right side of job site infrared surveillance equipment Middle position is provided with power supply connector, is provided with the job site infrared surveillance equipment below power supply connector Netting twine connector, the connection rotating shaft install the lower section middle position of infrared surveillance equipment at the construction field (site), and connection rotating shaft Lower section is provided with fixed connecting rod, the job site infrared surveillance equipment, transport of materials watch-dog and warehouse watch-dog Jun Yu roads By device by network connection, with remote control room by network connection, the inside of the remote control room is arranged the router There are video display unitss, and the inside of remote control room is additionally provided with VRAM, the emergency controller is installed in long-range control The inside of room processed, and emergency controller is logical with job site infrared surveillance equipment, warehouse watch-dog and transport of materials watch-dog respectively Cross the connection of emergency notice siren.
Preferably, the job site infrared surveillance equipment is fixedly connected by fixed connecting rod with body of wall.
Preferably, rain visor is provided with above the left side of the job site infrared surveillance equipment.
Preferably, the fixed connecting rod is fixedly connected by rotating shaft with connection rotating shaft.
Preferably, the transport of materials watch-dog is at least provided with ten, and ten transport of materials watch-dogs are respectively mounted On each transport routes.
Compared with prior art, the beneficial effects of the utility model are:This utility model is scientific and reasonable for structure, using safety Convenient, job site infrared surveillance equipment can be in real time by the picture transmission of job site to Control Room, while remote control room can Material storehouse and transport routes real time status are monitored by warehouse watch-dog and transport of materials watch-dog, improve the model of monitoring Enclose, VRAM is easy to store monitor video, is easy to the later stage to check, emergency controller can at the time of emergency and Shi Tongzhi workmens, while emergency notice siren is easy to notify workmen to withdraw.
Description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is watch-dog schematic diagram of the present utility model;
In figure:1- job sites infrared surveillance equipment, 2- routers, 3- remote control rooms, 4- video display unitss, 5- videos are deposited Reservoir, 6- emergency controllers, 7- emergency notice sirens, 8- warehouses watch-dog, 9- transport of materials watch-dogs, 10- louvres, 11- connection rotating shafts, 12- power supply connectors, 13- netting twine connectors, 14- fixed connecting rods.
Specific embodiment
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of this utility model, rather than whole Embodiment.Embodiment in based on this utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment for being obtained, belongs to the scope of this utility model protection.
Fig. 1 and Fig. 2 is referred to, this utility model provides a kind of technical scheme:A kind of arch bridge with real-time monitoring and control Construction monitoring system, including job site infrared surveillance equipment 1, emergency controller 6, warehouse watch-dog 8, transport of materials watch-dog 9 With connection rotating shaft 11, the front surface of job site infrared surveillance equipment 1 is provided with louvre 10, and job site infrared surveillance equipment 1 Right side middle position be provided with power supply connector 12, on job site infrared surveillance equipment 1 under power supply connector 12 Side is provided with netting twine connector 13, and connection rotating shaft 11 installs the lower section middle position of infrared surveillance equipment 1 at the construction field (site), and connects The lower section for switching through axle 11 is provided with fixed connecting rod 14, job site infrared surveillance equipment 1, transport of materials watch-dog 9 and warehouse prison Control device 8 with router 2 by network connection, router 2 and remote control room 3 by network connection, remote control room 3 interior Portion is provided with video display unitss 4, and the inside of remote control room 3 is additionally provided with VRAM 5, and emergency controller 6 is arranged on The inside of remote control room 3, and emergency controller 6 respectively with job site infrared surveillance equipment 1, warehouse watch-dog 8 and material transport Defeated watch-dog 9 is connected by emergency notice siren 7.
Job site infrared surveillance equipment 1 is fixedly connected by fixed connecting rod 14 with body of wall.Job site infrared surveillance equipment 1 Left side above be provided with rain visor.Fixed connecting rod 14 is fixedly connected by rotating shaft with connection rotating shaft 11.Transport of materials is monitored Device 9 is at least provided with ten, and ten transport of materials watch-dogs 9 are respectively mounted on each transport routes.
Job site infrared surveillance equipment 1 in this utility model is internally provided with array infrared lamp, it is achieved that watch-dog exists Night is monitored, and improves the time span of watch-dog, improves monitoring effect.
Operation principle of the present utility model and use flow process:There should be the Arch Bridge Construction monitoring system of real-time monitoring and control, By fixed connecting rod 14 by job site infrared surveillance equipment 1 installed in the position of required monitoring, while by 8 He of warehouse watch-dog Transport of materials watch-dog 9 is then turn on power supply, and watch-dog is connected with router 2 by network, road installed in correct position By device 2 by information real-time Transmission to remote control room 3, and picture is shown by video display unitss 4, while information passes through VRAM 5 is stored, and when occurring unexpected, is started emergency notice siren 7 using emergency controller 6 and is notified work people Member withdraws, and each watch-dog is to accident picture monitor in real time.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art, Be appreciated that these embodiments can be carried out multiple changes in the case of without departing from principle of the present utility model and spirit, repair Change, replace and modification, scope of the present utility model is defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of Arch Bridge Construction monitoring system with real-time monitoring and control, including job site infrared surveillance equipment (1), meets an urgent need and controls Device (6) processed, warehouse watch-dog (8), transport of materials watch-dog (9) and connection rotating shaft (11), it is characterised in that:The job site The front surface of infrared surveillance equipment (1) is provided with louvre (10), and the right side middle position of job site infrared surveillance equipment (1) Power supply connector (12) is provided with, described job site infrared surveillance equipment (1) upper lower section near power supply connector (12) is arranged There are netting twine connector (13), described connection rotating shaft (11) that the lower section middle position of infrared surveillance equipment (1) at the construction field (site) is installed, And fixed connecting rod (14) below connection rotating shaft (11), is provided with, job site infrared surveillance equipment (1), transport of materials are supervised Control device (9) and warehouse watch-dog (8) are with router (2) by network connection, router (2) and remote control room (3) By network connection, remote control room (3) are internally provided with video display unitss (4), and the inside of remote control room (3) VRAM (5) is additionally provided with, described emergency controller (6) are installed in the inside of remote control room (3), and emergency controller (6) warned by emergency notice with job site infrared surveillance equipment (1), warehouse watch-dog (8) and transport of materials watch-dog (9) respectively Report device (7) connection.
2. a kind of Arch Bridge Construction monitoring system with real-time monitoring and control according to claim 1, it is characterised in that:Institute State job site infrared surveillance equipment (1) to be fixedly connected by fixed connecting rod (14) with body of wall.
3. a kind of Arch Bridge Construction monitoring system with real-time monitoring and control according to claim 1, it is characterised in that:Institute Rain visor is provided with above the left side for stating job site infrared surveillance equipment (1).
4. a kind of Arch Bridge Construction monitoring system with real-time monitoring and control according to claim 1, it is characterised in that:Institute State fixed connecting rod (14) to be fixedly connected by rotating shaft with connection rotating shaft (11).
5. a kind of Arch Bridge Construction monitoring system with real-time monitoring and control according to claim 1, it is characterised in that:Institute Transport of materials watch-dog (9) is stated at least provided with ten, and ten transport of materials watch-dogs (9) are respectively mounted each transport routes On.
CN201620894959.9U 2016-08-16 2016-08-16 A kind of Arch Bridge Construction monitoring system with real-time monitoring and control Expired - Fee Related CN206023986U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620894959.9U CN206023986U (en) 2016-08-16 2016-08-16 A kind of Arch Bridge Construction monitoring system with real-time monitoring and control

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620894959.9U CN206023986U (en) 2016-08-16 2016-08-16 A kind of Arch Bridge Construction monitoring system with real-time monitoring and control

Publications (1)

Publication Number Publication Date
CN206023986U true CN206023986U (en) 2017-03-15

Family

ID=58249047

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620894959.9U Expired - Fee Related CN206023986U (en) 2016-08-16 2016-08-16 A kind of Arch Bridge Construction monitoring system with real-time monitoring and control

Country Status (1)

Country Link
CN (1) CN206023986U (en)

Similar Documents

Publication Publication Date Title
CN206162874U (en) Highway electronic monitoring device based on internet technology
CN104994346A (en) Intelligent construction safety management monitoring system and image alarm processing method thereof
CN103217950A (en) Automatic long-distance diagnosis system for public security outdoor electronic equipment failure
CN205300648U (en) A big dipper communication device for forest supervision
CN107158621A (en) A kind of fire-fighting robot system
CN202189450U (en) Security monitoring and commanding system for civil aviation airport
CN107580201A (en) A kind of active video monitoring system for merging distributed sensor and its application
CN204013876U (en) A kind of intelligent security watch-dog
CN116823135A (en) Management method and device based on intelligent park
CN209051596U (en) A kind of flame unmanned plane
CN110490782A (en) Urban waterlogging traffic dispersion and command system based on GIS-Geographic Information System
CN203224235U (en) Tower inclination monitoring device
CN206023986U (en) A kind of Arch Bridge Construction monitoring system with real-time monitoring and control
CN204334824U (en) A kind of display screen wireless supervisory control system
CN208707801U (en) The multi-party supervision site ingress/egress points of one kind monitors environmental surveillance mobile device automatically
CN207182038U (en) A kind of tunnel monitoring system
CN203825460U (en) Highway tunnel fire-fighting system
CN105187804A (en) Method for monitoring a plenty of remote sports building hardware in centralized manner cross Internet
CN206331558U (en) Smart travel is supervised and safety emergency management interlinked command system
CN204884030U (en) Transmission line prevents outer broken intelligent monitoring system
CN209341107U (en) A kind of safety monitoring device that can remotely connect
CN204859694U (en) Multi -functional street lamp control system
CN208766833U (en) Intelligent highway road conditions real-time monitoring safe-guard system
CN206364930U (en) A kind of video monitoring maintenance equipment
CN113891184A (en) 5G online monitoring system and method for power transmission line

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170315