CN206023059U - Combined paying off pulley hanger - Google Patents

Combined paying off pulley hanger Download PDF

Info

Publication number
CN206023059U
CN206023059U CN201621074747.2U CN201621074747U CN206023059U CN 206023059 U CN206023059 U CN 206023059U CN 201621074747 U CN201621074747 U CN 201621074747U CN 206023059 U CN206023059 U CN 206023059U
Authority
CN
China
Prior art keywords
tie
connecting plate
plate
pulley hanger
pay
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621074747.2U
Other languages
Chinese (zh)
Inventor
尹泉军
吴自强
张志远
石战旗
景胜利
吴彬员
李星
俞文
张鑫梦
段永亮
强勇
杨文辉
崔明生
马学华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Hebei Electric Power Co Ltd
Hebei Power Transmission and Transformation Co Ltd
State Grid Corp of China SGCC
Original Assignee
State Grid Hebei Electric Power Co Ltd
Hebei Power Transmission and Transformation Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Hebei Electric Power Co Ltd, Hebei Power Transmission and Transformation Co Ltd, State Grid Corp of China SGCC filed Critical State Grid Hebei Electric Power Co Ltd
Priority to CN201621074747.2U priority Critical patent/CN206023059U/en
Application granted granted Critical
Publication of CN206023059U publication Critical patent/CN206023059U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses combined paying off pulley hanger, belongs to technical field of electric power construction.The releasing pulley hanger includes that tie-beam, tie-beam include tie-beam, lower tie-beam, left tie-beam, right tie-beam by connecting plate connection composition isosceles trapezoidal structure, tie-beam.Connecting plate includes connecting plate one, connecting plate two, connecting plate three, connecting plate four;The two ends of upper tie-beam are fixedly connected with one end of left tie-beam and one end of right tie-beam respectively by connecting plate one, and the two ends of lower tie-beam are fixedly connected with the other end of the other end and right tie-beam of left tie-beam respectively by connecting plate two;The centre position fixed connecting plate three of upper tie-beam, lower tie-beam centre position fixed connecting plate four;The connecting plate one at the left and right two ends of upper tie-beam is connected by buttress brace one also between connecting plate three.This utility model intensity high stability more preferably, arranges the suspension requirement that multiple hanging points can meet multiple releasing pulleys, it is possible to increase unwrapping wire efficiency.

Description

组合式放线滑车挂架Combined pay-off tackle hanger

技术领域technical field

本实用新型涉及组合式放线滑车挂架,属于电力工程施工设备领域。The utility model relates to a combined pay-off pulley hanger, which belongs to the field of electric power engineering construction equipment.

背景技术Background technique

近年来,国家电网公司全面落实大气污染防治项目,大力推进特高压电网建设,因此对大截面导线的放线施工工艺要求很高。目前国内最大截面的导线放线施工工艺原则上采用3ד一牵2”方式进行张力放线,大截面导线的展放施工对施工机具的性能要求高,放线滑车悬挂方式的选择,对工程进度、效率及施工质量有重要影响。目前,多个放线滑车进行放线时需要在铁塔上预留施工孔,这样要实现多个放线滑车悬挂,调整滑车高度一致的工作量大,并且使用的配套工具很多,操作很不方便。In recent years, the State Grid Corporation of China has comprehensively implemented air pollution prevention and control projects and vigorously promoted the construction of UHV power grids. Therefore, the requirements for the laying-out construction technology of large-section conductors are very high. At present, the construction technology of the largest cross-section wire in China is in principle 3 × "one pull 2" method for tension pay-off. The construction of large cross-section wires has high requirements on the performance of construction tools. It has an important impact on the progress, efficiency and construction quality of the project. At present, it is necessary to reserve construction holes on the iron tower when multiple pay-off tackles are paid out. In this way, it is necessary to realize the suspension of multiple pay-off tackles and adjust the height of the tackles to be consistent. The workload is large, and there are many supporting tools used, which is very inconvenient to operate. .

实用新型内容Utility model content

本实用新型的目的是提供一种结构简单、方便使用,能满足多个放线滑车同时悬挂的组合式放线滑车挂架。The purpose of the utility model is to provide a combined pay-off tackle hanger which is simple in structure, convenient to use, and capable of simultaneously hanging multiple pay-off tackle.

为了实现上述目的,本实用新型采用的技术方案是:In order to achieve the above object, the technical solution adopted by the utility model is:

一种组合式放线滑车挂架,包括连接梁,连接梁通过连接板连接组成等腰梯形结构,连接梁包括上连接梁、下连接梁、左连接梁和右连接梁,连接板包括连接板一、连接板二、连接板三、连接板四;上连接梁的两端通过连接板一分别与左连接梁的一端和右连接梁的一端固定连接,下连接梁的两端通过连接板二分别与左连接梁的另一端和右连接梁的另一端固定连接;上连接梁的中间位置固定连接板三,下连接梁中间位置固定连接板四;上连接梁的左右两端的连接板一还与连接板四之间通过加强梁一连接。A combined pay-off tackle hanger, comprising a connecting beam, the connecting beam is connected through a connecting plate to form an isosceles trapezoidal structure, the connecting beam includes an upper connecting beam, a lower connecting beam, a left connecting beam and a right connecting beam, and the connecting plate includes a connecting plate One, connecting plate two, connecting plate three, connecting plate four; the two ends of the upper connecting beam are fixedly connected with one end of the left connecting beam and one end of the right connecting beam respectively through connecting plate one, and the two ends of the lower connecting beam pass through connecting plate two The other end of the left connecting beam and the other end of the right connecting beam are respectively fixedly connected; the middle position of the upper connecting beam is fixed with the connecting plate three, and the middle position of the lower connecting beam is fixed with the connecting plate four; the connecting plate one at the left and right ends of the upper connecting beam is also It is connected with the connecting plate 4 through the reinforcing beam 1.

进一步的,连接梁与连接板之间通过焊接连接。Further, the connecting beam and the connecting plate are connected by welding.

进一步的,连接梁的端部和连接板上设置用于连接的孔,连接梁和连接板之间通过螺栓连接。Further, the end of the connecting beam and the connecting plate are provided with holes for connection, and the connecting beam and the connecting plate are connected by bolts.

进一步的,下连接梁长度方向上的1/4处和3/4使用螺栓固定连接板三。Further, bolts are used to fix the connecting plate three at 1/4 and 3/4 of the lower connecting beam in the length direction.

进一步的,上连接梁中间位置的连接板三和下连接梁中间位置的连接板四之间通过加强梁二连接。Further, the third connecting plate at the middle position of the upper connecting beam and the fourth connecting plate at the middle position of the lower connecting beam are connected through the second reinforcing beam.

进一步的,连接梁和加强梁由位于连接板两侧且均与连接板固定连接的两块角铁组成。Further, the connecting beam and the reinforcing beam are composed of two angle irons located on both sides of the connecting plate and fixedly connected with the connecting plate.

进一步的,下连接梁上在位于连接板四的两侧分别设置一个可移动挂板。Further, a movable hanging plate is respectively arranged on both sides of the connecting plate four on the lower connecting beam.

由于采用了上述技术方案,本实用新型取得的技术效果有:Owing to adopting above-mentioned technical scheme, the technical effect that the utility model obtains has:

本实用新型的组合式放线滑车挂架使用连接板和连接梁连接成更加稳固的等腰梯形挂架,能够保证挂架的强度。The combined pay-off block hanger of the utility model is connected with a connecting plate and a connecting beam to form a more stable isosceles trapezoidal hanger, which can ensure the strength of the hanger.

本实用新型设置了多个挂点可以一次性满足多个放线滑车的悬挂要求,能够提高放线的效率。The utility model is provided with a plurality of hanging points, which can meet the suspension requirements of a plurality of pay-off tackles at one time, and can improve the efficiency of pay-off.

本实用新型在下连接梁上设置了附加的连接板固定点,可以根据需求加装连接板,以便增加放线滑车。The utility model is provided with additional connecting plate fixing points on the lower connecting beam, and the connecting plate can be installed according to the demand, so as to increase the pay-off block.

本实用新型的使用简化了放线施工操作流程,减少了牵引板过滑车的冲击力,为现场施工带来极大的方便,确保了架线施工的顺利推进。The use of the utility model simplifies the operation process of setting-out construction, reduces the impact force of the traction plate passing over the block, brings great convenience to on-site construction, and ensures the smooth progress of the setting-out construction.

本实用新型结构简单,方便储存、运输和使用,本实用新型的使用大大提高了放线施工的综合效率。The utility model has a simple structure and is convenient for storage, transportation and use, and the use of the utility model greatly improves the comprehensive efficiency of setting-out construction.

附图说明Description of drawings

图1是本实用新型结构示意图;Fig. 1 is a structural representation of the utility model;

图2是本实用新型实施例2的结构示意图;Fig. 2 is the structural representation of the utility model embodiment 2;

图3是本实用新型实施例3的结构示意图;Fig. 3 is the structural representation of the utility model embodiment 3;

图4是可移动挂板结构示意图;Fig. 4 is a schematic diagram of the structure of the movable hanging board;

图5是连接板一的结构示意图;Fig. 5 is the structural representation of connection plate one;

图6是连接板二的结构示意图;Fig. 6 is the structural representation of connection plate two;

图7是连接板三的结构示意图;Fig. 7 is a schematic structural view of connecting plate three;

图8是连接板四的结构示意图;Fig. 8 is a structural schematic diagram of connecting plate four;

图9是本实用新型实施例2带连接梁以及加强梁截面图的示意图;Fig. 9 is a schematic diagram of a cross-sectional view of a connecting beam and a reinforcing beam in Embodiment 2 of the present utility model;

其中,1、上连接梁,2、下连接梁,3、左连接梁,4、右连接梁,5、加强梁一,6、连接板一,7、连接板二,8、连接板三,9、连接板四,10、加强梁二,11、可移动挂板,11-1紧固螺钉。Among them, 1. Upper connecting beam, 2. Lower connecting beam, 3. Left connecting beam, 4. Right connecting beam, 5. Reinforcing beam 1, 6. Connecting plate 1, 7. Connecting plate 2, 8. Connecting plate 3, 9, connecting plate four, 10, reinforcing beam two, 11, removable hanging plate, 11-1 fastening screw.

具体实施方式detailed description

下面结合附图及具体实施例对本实用新型做进一步详细说明:Below in conjunction with accompanying drawing and specific embodiment the utility model is described in further detail:

实施例1Example 1

本实用新型公开了组合式放线滑车挂架,放线滑车挂架包括连接梁,连接梁之间通过连接板连接组成等腰梯形结构的挂架,连接梁包括上连接梁1、下连接梁2、左连接梁3、右连接梁4,还包括两根加强梁一5,连接板包括连接板一6、连接板二7、连接板三8、连接板四9;上连接梁1的两端通过连接板一6分别与左连接梁3的一端和右连接梁4的一端固定连接,下连接梁2的两端通过连接板二7分别与左连接梁3的另一端和右连接梁4的另一端固定连接;上连接梁1的中间位置固定连接板三8,下连接梁2中间位置固定连接板四9;上连接梁1的左右两端的连接板一6还与连接板三8之间通过加强梁一5连接,具体结构如图1所示。本实用新型的技术方案是将连接梁通过连接板组合连接在一起,放线滑车挂架的外形呈等腰梯形的结构,与矩形挂架相比结构更加稳固,放线滑车挂架的整体抗拉、抗压强度得到提高,并且占用空间小,方便存储和运输。为了进一步增强组合式放线滑车挂架的强度,还可以将上连接梁1中间位置的连接板三8和下连接梁2中间位置的连接板四9使用加强梁二10连接起来。The utility model discloses a combined pay-off tackle hanger. The pay-off tackle hanger includes connecting beams, and the hangers of an isosceles trapezoidal structure are formed by connecting the connecting beams through connecting plates. The connecting beams include an upper connecting beam 1 and a lower connecting beam. 2. The left connecting beam 3 and the right connecting beam 4 also include two reinforcing beams one 5, and the connecting plates include connecting plates one 6, connecting plates two 7, connecting plates three 8, and connecting plates four 9; The ends are respectively fixedly connected to one end of the left connecting beam 3 and one end of the right connecting beam 4 through the connecting plate one 6, and the two ends of the lower connecting beam 2 are respectively connected to the other end of the left connecting beam 3 and the right connecting beam 4 through the connecting plate two 7 The other end of the upper connecting beam 1 is fixedly connected; the middle position of the upper connecting beam 1 is fixed connecting plate three 8, and the middle position of the lower connecting beam 2 is fixed connecting plate four 9; the connecting plate one 6 at the left and right ends of the upper connecting beam 1 is also connected with connecting plate three 8 The rooms are connected by reinforcing beams 1 and 5, and the specific structure is shown in Figure 1. The technical solution of the utility model is to connect the connecting beams together through the connecting plates. The shape of the hanger of the pay-off tackle is an isosceles trapezoidal structure, which is more stable in structure compared with the hanger of a rectangle. The overall resistance of the hanger of the pay-off tackle is The tensile and compressive strengths are improved, and the space occupied is small, which is convenient for storage and transportation. In order to further enhance the strength of the combined pay-off block hanger, the connecting plate three 8 at the middle position of the upper connecting beam 1 and the connecting plate four 9 at the middle position of the lower connecting beam 2 can also be connected using the reinforcing beam two 10.

连接梁之间的连接有三种方式,螺栓连接、焊接连接以及螺栓连接配合焊接连接。There are three ways to connect beams, bolted connection, welded connection and bolted connection with welded connection.

如果采用螺栓连接,可以将放线滑车挂架拆解,方便存储或者运输,特别适用于山区施工,故一般优先选用螺栓连接的方式。If bolt connection is used, the pay-off tackle hanger can be disassembled for easy storage or transportation. It is especially suitable for construction in mountainous areas, so bolt connection is generally preferred.

本实施例可以采用螺栓连接配合焊接的形式,即对五个挂点采用螺栓连接后再进行焊接补强,使挂点的受力更加合理,连接梁和加强梁与连接板之间连接更加牢固。In this embodiment, the form of bolt connection and welding can be adopted, that is, the five hanging points are connected by bolts and then welded for reinforcement, so that the stress of the hanging points is more reasonable, and the connection between the connecting beam and the reinforcing beam and the connecting plate is more firm .

本实用新型中的连接板一6如图5所示,连接板二7如图6所示,连接板三8如图7所示,连接板四9如图8所示。连接板一6、连接板二7、连接板三8、连接板板四9均设置悬挂连接用的悬挂孔。Connecting plate one 6 among the utility model as shown in Figure 5, connecting plate two 7 as shown in Figure 6, connecting plate three 8 as shown in Figure 7, connecting plate four 9 as shown in Figure 8. Connecting plate one 6, connecting plate two 7, connecting plate three 8, connecting plate four 9 all arrange the suspension hole that hangs and connects usefulness.

在实际制作过程中,本实用新型中的连接梁和加强梁通常情况下选用角铁。为了进一步增强本实用新型中组合式放线滑车挂架的强度,将连接梁和加强梁制作成两块角铁的形式,两块角铁位于连接板两侧且均与连接板固定连接,具体形式如图9所示。In the actual production process, the connecting beam and the reinforcing beam in the utility model usually use angle irons. In order to further enhance the strength of the combined pay-off block hanger in the utility model, the connecting beam and the reinforcing beam are made into the form of two angle irons, and the two angle irons are located on both sides of the connecting plate and are fixedly connected with the connecting plate. The form is shown in Figure 9.

实施例2Example 2

本实施例对实施例1进行了改进,改进之处在于:在下连接梁2上增设了连接板固定点,可以根据需求加装连接板三8作为放线滑车的悬挂点,从而在放线施工时方便地增加放线滑车,进一步提高放线效率。连接板固定点在下连接梁2方向上均匀分布,以保证放线施工时组合式放线滑车挂架受力均匀,放线过程平稳。本实施例中增设了两个连接板固定点,其中一个连接板固定点位于下连接梁2长度方向的1/4处,另一个连接板固定点位于下连接梁2长度方向的3/4处,具体结构如图2所示。对于本实施例中的改进,为放线提供了多种选择,施工人员可以根据实际需求情况在下连接梁2的连接板固定点上固定连接板三8作为放线滑车的悬挂点,增加的连接板三8使用螺栓与组合式放线滑车挂架固定连接,以方便安装和拆卸,使用灵活。This embodiment has improved Embodiment 1, and the improvement is that a connecting plate fixing point is added on the lower connecting beam 2, and the connecting plate 3 8 can be added as the suspension point of the pay-off block according to the demand, so that it can be used in the pay-out construction. It is convenient to increase the pay-off block at the time to further improve the pay-off efficiency. The fixed points of the connecting plate are evenly distributed in the direction of the lower connecting beam 2, so as to ensure that the combined pay-off pulley hanger is evenly stressed during the pay-out construction, and the pay-off process is stable. In this embodiment, two connecting plate fixing points are added, one of which is located at 1/4 of the length direction of the lower connecting beam 2, and the other connecting plate fixing point is located at 3/4 of the length direction of the lower connecting beam 2 , the specific structure is shown in Figure 2. For the improvement in this embodiment, a variety of options are provided for the pay-off. The construction personnel can fix the connection plate 3 8 on the connection plate fixed point of the lower connection beam 2 as the suspension point of the pay-off block according to actual needs, and the increased connection Plate 3 8 is fixedly connected with the combined pay-off block hanger by bolts to facilitate installation and disassembly, and to be flexible in use.

本实用新型在制作时将各连接梁的长度适当扩大,以便根据需要在下连接梁上增加3个或4个连接板三8作为放线滑车的悬挂点,做到一个组合式放线滑车挂架满足多种放线要求,从而提高放线施工的效率。When the utility model is manufactured, the length of each connecting beam is appropriately expanded, so that 3 or 4 connecting plates 38 are added on the lower connecting beam as the suspension points of the pay-off tackle according to the needs, so as to achieve a combined pay-off tackle hanger Satisfy a variety of setting-out requirements, thereby improving the efficiency of setting-out construction.

实施例3Example 3

本实用新型对实施例2进行了改进,改进之处在于:将下连接梁2上增设的放线滑车悬挂点设置为可移动挂板11, 由角铁构成的下连接梁2作为可移动挂板11的滑道,本实施例的具体结构如图3所示。本实施例中的可移动挂板11包括挂板连接架以及与挂板连接架固定连接的挂板,可移动挂板11还配有用于将可移动挂板11相对固定在滑道的紧固螺钉11-1以及方便调节距离的两个滚轮;挂板连接架为三面封闭一面半开口的矩形框架,在矩形框架的封闭的长边的中间位置焊接有挂板,本实施例中的可移动挂板11的具体结构如图4所示。在组装时,将可移动挂板11装入滑道,调节好距离使用紧固螺钉11-1紧固。该设置进一步扩大了组合式放线滑车挂架的适用范围,当一组相邻导线之间的的距离发生改变时,可以调节可移动挂板11以适应不同距离的相邻导线,做到了只使用一个组合式放线滑车挂架而能够适用于不同施工现场,并省去了更换组合式滑车挂架的时间,提高了施工效率。The utility model has improved the embodiment 2, and the improvement is that the suspension point of the pay-off block added on the lower connecting beam 2 is set as a movable hanging plate 11, and the lower connecting beam 2 composed of angle iron is used as a movable hanging plate 11. The specific structure of the slideway of the plate 11 in this embodiment is shown in FIG. 3 . The movable hanging plate 11 in this embodiment includes a hanging plate connecting frame and a hanging plate fixedly connected with the hanging plate connecting frame. Screw 11-1 and two rollers for convenient distance adjustment; the hanging plate connecting frame is a rectangular frame with three sides closed and one side half open, and a hanging plate is welded in the middle of the closed long side of the rectangular frame. The concrete structure of hanging board 11 is as shown in Figure 4. When assembling, the movable hanging plate 11 is packed into the slideway, and the distance is adjusted and fastened with the fastening screw 11-1. This setting further expands the scope of application of the combined pay-off block hanger. When the distance between a group of adjacent wires changes, the movable hanging plate 11 can be adjusted to adapt to adjacent wires with different distances. The use of a combined pay-off pulley hanger can be applied to different construction sites, saves the time for replacing the combined pulley hanger, and improves construction efficiency.

本实用新型设计合理,采用稳固的等腰梯形结构,等腰梯形的上部的两个悬挂点可以满足悬垂绝缘子串的悬挂要求,将滑车和悬垂绝缘子串进行同步安装和悬挂,减少了施工安装环节,提高了放线的总体施工效率,保证了铁塔的良好受力,能够保证放线施工安全顺利进行。The utility model has a reasonable design and adopts a stable isosceles trapezoidal structure. The two suspension points on the upper part of the isosceles trapezoid can meet the suspension requirements of the suspension insulator string, and the pulley and the suspension insulator string are installed and suspended synchronously, reducing the construction and installation links. , which improves the overall construction efficiency of setting out, ensures the good force bearing of the iron tower, and can ensure the safe and smooth progress of setting out construction.

本实用新型的使用简化了放线施工操作流程,方便了运输流程,减少了牵引板过滑车的冲击力,为现场施工带来极大的方便,确保了放线线施工的顺利推进。The use of the utility model simplifies the operation process of the pay-off construction, facilitates the transportation process, reduces the impact force of the traction plate passing the block, brings great convenience to the on-site construction, and ensures the smooth progress of the pay-off construction.

Claims (7)

1. a kind of combined paying off pulley hanger, it is characterised in that:Including tie-beam, tie-beam is by connecting plate connection composition etc. Waist trapezium structure, tie-beam include tie-beam(1), lower tie-beam(2), left tie-beam(3)With right tie-beam(4), connecting plate Including connecting plate one(6), connecting plate two(7), connecting plate three(8), connecting plate four(9);Upper tie-beam(1)Two ends by connection Plate one(6)Respectively with left tie-beam(3)One end and right tie-beam(4)One end be fixedly connected, lower tie-beam(2)Two ends lead to Cross connecting plate two(7)Respectively with left tie-beam(3)The other end and right tie-beam(4)The other end be fixedly connected;Upper tie-beam (1)Centre position fixed connecting plate three(8), lower tie-beam(2)Centre position fixed connecting plate four(9);Upper tie-beam(1)'s The connecting plate one at left and right two ends(6)Also with connecting plate four(9)Between pass through buttress brace one(5)Connection.
2. combined paying off pulley hanger according to claim 1, it is characterised in that:Pass through between tie-beam and connecting plate It is welded to connect.
3. combined paying off pulley hanger according to claim 1, it is characterised in that:On the end and connecting plate of tie-beam The hole for connecting is provided for, is bolted between tie-beam and connecting plate.
4. the combined paying off pulley hanger according to any one of Claims 2 or 3, it is characterised in that:Lower tie-beam(2)Long Degree direction on 1/4 at and 3/4 use bolt fixed connecting plate three(8).
5. the combined paying off pulley hanger according to any one of Claims 2 or 3, it is characterised in that:Upper tie-beam(1)In Between position connecting plate three(8)With lower tie-beam(2)The connecting plate four in centre position(9)Between pass through buttress brace two(10)Even Connect.
6. combined paying off pulley hanger according to claim 1, it is characterised in that:Tie-beam and buttress brace are by the company of being located at Fishplate bar both sides and two pieces of angle bar compositions being fixedly connected with connecting plate.
7. combined paying off pulley hanger according to claim 6, it is characterised in that:Lower tie-beam(2)On be located at connect Fishplate bar four(9)Both sides be respectively provided with a removable link plate(11).
CN201621074747.2U 2016-09-23 2016-09-23 Combined paying off pulley hanger Expired - Fee Related CN206023059U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621074747.2U CN206023059U (en) 2016-09-23 2016-09-23 Combined paying off pulley hanger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621074747.2U CN206023059U (en) 2016-09-23 2016-09-23 Combined paying off pulley hanger

Publications (1)

Publication Number Publication Date
CN206023059U true CN206023059U (en) 2017-03-15

Family

ID=58261330

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621074747.2U Expired - Fee Related CN206023059U (en) 2016-09-23 2016-09-23 Combined paying off pulley hanger

Country Status (1)

Country Link
CN (1) CN206023059U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106329386A (en) * 2016-09-23 2017-01-11 国家电网公司 Combined paying-off tackle hanging rack

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106329386A (en) * 2016-09-23 2017-01-11 国家电网公司 Combined paying-off tackle hanging rack

Similar Documents

Publication Publication Date Title
CN106329386A (en) Combined paying-off tackle hanging rack
CN204960368U (en) String formula bearing structure is opened in space
CN203845689U (en) Indoor assembled large-scale equipment hoisting device
CN215185508U (en) UHV insulator string replacement device based on insulating soft sling
CN204778275U (en) But balancing jack -up hoist
CN206023059U (en) Combined paying off pulley hanger
CN204079226U (en) A kind of movable beam string hanging apparatus that can increase rigidity when tubular truss lifts
CN207846810U (en) A kind of novel ceiling applied on steel construction ceiling framework
CN102709856B (en) A kind of UHV transmission line cross yoke plate
CN206148848U (en) Large -tonnage electrified conducting wire's hoisting device
CN202164864U (en) Holding pole equipped with detachable standard section
CN206359109U (en) Tower hanging apparatus and tower hoisting structure
CN209339715U (en) A kind of girdle ring attachment device for electric power pole
CN202899735U (en) Lifting tool for high-pressure iron tower support
CN102923600B (en) Reverse pulley fixing device
CN105366559A (en) Small hoisting machine fixed on channel steel framework
CN206827973U (en) One kind plus drag-line tower crane climbing frame apparatus
CN207069439U (en) 4 × " one leads 2 " wires-erecting pulley hangers
CN206110810U (en) Fixed armful of pole structure of staple bolt that slides
CN205134912U (en) A bed -jig for making open string roof beam
CN210669280U (en) Transmission line stridees across iron tower assembled protection network supporting beam
CN202081693U (en) Straight steel pipe rod of extra-high voltage DC grounding electrode line
CN209244293U (en) Temporary fixing device for movable arched rod
CN221353700U (en) Electric power crossing net sealing device
CN206872268U (en) T beams are revealed all the details suspender

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170315