CN206003565U - A kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding - Google Patents
A kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding Download PDFInfo
- Publication number
- CN206003565U CN206003565U CN201620948258.9U CN201620948258U CN206003565U CN 206003565 U CN206003565 U CN 206003565U CN 201620948258 U CN201620948258 U CN 201620948258U CN 206003565 U CN206003565 U CN 206003565U
- Authority
- CN
- China
- Prior art keywords
- pyrocondensation
- plant
- furnace chamber
- processing unit
- sleeve pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding, including base, this base has a table top, described processing unit (plant) also includes:The mobile support of frock being installed on base table top and pyrocondensation furnace chamber, the mobile support of frock can move to pyrocondensation furnace chamber, uniformly it is placed with several cambered surface harness fixing frames on the mobile support of frock, the two ends of each cambered surface harness fixing frame are each provided with a wire harness hold-down mechanism, pyrocondensation furnace chamber top is provided with samming hot blast knife, and warm air knife is circumscribed with hot-air blower by pipeline;This utility model cambered surface harness fixing frame can fix many wire harness, can process several cambered surface harness fixing frames simultaneously, compares with manually single process, and tens times of ground of efficiency improve.The method tightened using cambered surface, strands are easy to shakeout arrangement it is not required that follow-up repairing is intervened, than the overall process of manual method repeatedly roll prevent from shakeouing out of shape laborsaving save time a lot.
Description
Technical field
This utility model belongs to wire harness processing technique field, and the sleeve pipe pyrocondensation shakeouing molding particularly to a kind of multi cord adds
Frock is put.
Background technology
Wire harness processing is the pith during auto parts and components manufacture, with computerized, motorized automobile development, automobile
The manufacturing industry scale of wire harness increases rapid.In order to adapt to the efficient cabling requirement of small space in automobile, electrical equipment etc., a lot
It is frequently necessary to wire harness advance comprising in wire harness processing.Multi cord as one of main forming technique shakeouts molding, existing skill
In art, workman manually must shakeout strands, puts molding heat-shrink tube, and then side is blown to heat-shrink tube heat gun, while being spread out with pair of rollers
Flat strands roll so that during pyrocondensation, strands are adjacent all the time divides, until the flat molding of heat-shrink tube.This technique every
Line is required for completely artificial operation and controls, high labor intensive, and hot environment is severe, and quality conformance there is no guarantee that.
Utility model content
This utility model provides a kind of multi cord to shakeout the sleeve pipe pyrocondensation processing unit (plant) of molding, many in prior art to solve
Strand bundle shakeouts in pyrocondensation molding manual problem entirely.
For achieving the above object, the technical solution adopted in the utility model is:
A kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding, including base 8, this base 8 has a table top, institute
State processing unit (plant) also to include:The mobile support 3 of frock being installed on base 8 table top and pyrocondensation furnace chamber 5, described frock moves support
3 can move to pyrocondensation furnace chamber 5, and the mobile support 3 of described frock is uniformly placed with several cambered surface harness fixing frames 2,
The two ends of each cambered surface harness fixing frame 2 are each provided with a wire harness hold-down mechanism 1, and described pyrocondensation furnace chamber 5 top is provided with all
Warm air knife 4, warm air knife 4 is circumscribed with hot-air blower 6 by pipeline 9.
Preferably, described processing unit (plant) also includes one end and connects pyrocondensation furnace chamber 5 side wall, the other end and warm air knife 4 and heat
The exhaust outlet 7 that 6 pipelines 9 of blower fan communicate.
Preferably, described pipeline 9 is thermal-insulating sealing pipeline.
Preferably, described base 8 table top is provided with the rail for mobile support 3 movement to the inside of pyrocondensation furnace chamber 5 of frock
Road 11.
Preferably, described cambered surface harness fixing frame 2 be cambered plate, be used for shakeouing and tighten wire harness, wire harness tight in cambered plate
Convex side.
Preferably, described wire harness hold-down mechanism 1 can move on cambered surface harness fixing frame 2 and lock, wire harness compacting machine
Structure 1 is used for the two ends of fixed beam.
Preferably, described wire harness hold-down mechanism 1 adopts exotic material.
Preferably, inside the air knife mouth be aligned pyrocondensation furnace chamber 5 of described samming hot blast knife 4.
Preferably, described pyrocondensation furnace chamber 5 is a heat insulating box, described pyrocondensation furnace chamber 5 is provided with and moves for frock
The opening 10 that support 3 enters.
Compared with prior art, this utility model has advantages below:
This utility model cambered surface harness fixing frame can fix many wire harness, and every table apparatus can process one or number simultaneously
Individual cambered surface harness fixing frame, compares with manually single process, and tens times of ground of efficiency improve.The method tightened using cambered surface, strands
Be easy to shakeout arrangement it is not required that follow-up repairing is intervened, than the overall process of manual method repeatedly roll prevent from shakeouing out of shape
Laborsaving save time a lot.The samming pyrocondensation purging automatically controlling, pyrocondensation quality increases substantially.Compared with manually, purging hot blast has
Effect is collected in pyrocondensation furnace chamber so that the high temperature feature of working environment significantly improves.So that whole working (machining) efficiency and quality have
It is obviously improved.
This device has been liberated traditional multi cord and has been shakeout the manual a large amount of manpowers flattening in pyrocondensation one by one, line in pyrocondensation
Restraint the quality shakeout to be remarkably improved, considerably reduce cost of labor, improve this kind of common wire harness pyrocondensation processing
Automaticity.
Brief description
Fig. 1 is structural representation of the present utility model;
Fig. 2 is another structural representation of the present utility model;
Wherein:1- wire harness hold-down mechanism, 2- cambered surface harness fixing frame, 3- frock moves support, 4- samming hot blast knife, 5- heat
Contracting furnace chamber, 6- hot-air blower, 7- exhaust outlet, 8- base, 9- pipeline, 10- opening, 11- track.
Specific embodiment
With reference to embodiment, this utility model is further described.
Wire harness hold-down mechanism 1 in this utility model adopts exotic material, and described exotic material is in prior art
It is capable of resistant to elevated temperatures material.
As illustrated in fig. 1 and 2, a kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding, including base 8, on this base 8
There is a table top, described processing unit (plant) also includes:The mobile support 3 of frock being installed on base 8 table top and pyrocondensation furnace chamber 5, institute
State the mobile support 3 of frock can move to pyrocondensation furnace chamber 5, the mobile support 3 of described frock is uniformly placed with several arcs
Face harness fixing frame 2, the two ends of each cambered surface harness fixing frame 2 are each provided with a wire harness hold-down mechanism 1, described pyrocondensation furnace chamber
5 tops are provided with samming hot blast knife 4, and warm air knife 4 is circumscribed with hot-air blower 6 by thermal-insulating sealing pipeline 9.
Described processing unit (plant) also includes one end and connects pyrocondensation furnace chamber 5 side wall, between the other end and warm air knife 4 and hot-air blower 6
The exhaust outlet 7 that thermal-insulating sealing pipeline 9 communicates.Described exhaust outlet 7 can also be without connecting with thermal-insulating sealing pipeline 9, and connect hot blast and receive
Acquisition means.
Track 11 for mobile support 3 movement to the inside of pyrocondensation furnace chamber 5 of frock is provided with described base 8 table top.
Described cambered surface harness fixing frame 2 is cambered plate, is used for shakeouing and tightens wire harness, the tight convex surface in cambered plate of wire harness
Side.
Described wire harness hold-down mechanism 1 can move on cambered surface harness fixing frame 2 and lock, and wire harness hold-down mechanism 1 is used for
The two ends of fixed beam.
Inside the air knife mouth be aligned pyrocondensation furnace chamber 5 of described samming hot blast knife 4.
Described pyrocondensation furnace chamber 5 is a heat insulating box, described pyrocondensation furnace chamber 5 is provided with and enters for the mobile support 3 of frock
The opening 10 entering.
Cambered surface harness fixing frame 2 described in the utility model is placed on the mobile support 3 of frock, and frock moves support 3 and heat
Contracting furnace chamber 5 is arranged on a base 8, frock mobile support 3 translation turnover pyrocondensation furnace chamber 5, and samming hot blast knife 4 is fixed on pyrocondensation
On furnace chamber 5, in the air knife mouth be aligned pyrocondensation furnace chamber 5 of samming hot blast knife 4, hot-air blower 6 and samming hot blast knife 4 pass through thermal-insulating sealing pipe
Road 9 connects.Put every strand on the multi cord of heat-shrinkable T bush by parallel adjacent spread out after, tighten fixation using hold-down mechanism 1
On the convex side of a cambered surface harness fixing frame 2.Several cambered surface harness fixing frames 2 can male and fomale(M&F) be relatively simultaneously at certain intervals
Row arrangement, is placed on the mobile support 3 of frock so that simultaneously tens of wire harness can be processed simultaneously.The high-temperature hot-air of hot-air blower 6
Form one and be blown into along the equally distributed high temperature air curtain of air knife mouth direction temperature by samming hot blast knife 4 and there is heat insulating function
Pyrocondensation furnace chamber 5, the mobile support 3 of frock is in pyrocondensation furnace chamber 5 by controlling speed to be close to through samming hot blast knife 4 so that high warm air
Curtain sweeps to the other end from cable one end, and samming hot blast knife 4 inswept part heat-shrink tube on cable shrinks immediately, is in divide and tightens
After the multi cord pyrocondensation of state, state maintains.The mobile support 3 of frock completes pyrocondensation backed off after random pyrocondensation furnace chamber 5, takes off arc above
Face harness fixing frame 2, changes another batch of cambered surface harness fixing frame 2, starts next fabrication cycles.In pyrocondensation furnace chamber, hot blast is permissible
Discharged by exhaust outlet 7 or recycle.
Described wire harness hold-down mechanism 1 is arranged on cambered surface harness fixing frame 2 two ends, can shakeout cable and be tightened in wire harness and fix
On the cambered surface convex surface of frame 2, this hold-down mechanism is that a Quick-clamped unclamps frock.Using exotic material, adopt with cable contact face
With high temperature resistant soft anti-slip material to prevent impression, by cable length or terminal types adjusting position or fixture can be changed.Adopt
The method tightened with cambered surface, strands are easy to shakeout arrangement it is not required that follow-up repairing is intervened.This makes to shakeout molding arrangement
Work greatly simplified and quick.
The high-temperature hot-air of hot-air blower 6 delivers to samming hot blast knife 4 by thermal-insulating sealing pipeline 9, forms one along air knife mouth
Direction temperature equally distributed high temperature air curtain.Samming air knife 4 ensure that the process consistency that many wire harness are processed simultaneously.
Samming hot blast knife 4 is placed on pyrocondensation furnace chamber 5, and inside air knife mouth be aligned pyrocondensation furnace chamber 5, pyrocondensation furnace chamber 5 is one
There is the semiclosed casing of thermal insulation protection.All hot-working are confined in a hemi-closure space so that the temperature of working environment
It is obviously improved.
Frock moves support 3 and presses and controls speed and pyrocondensation furnace chamber 5 to produce relative motion so that frock moves on support 3
Cable passes through in pyrocondensation furnace chamber 5 and is close to through samming hot blast knife 4.The control of pyrocondensation distance and speed ensure that
The optimization of quality and concordance.
Cambered surface harness fixing frame 2 above the mobile support 3 of frock can be with quick-replaceable.This makes work efficiency more carry
High.
In pyrocondensation furnace chamber 5, hot blast can be discharged or be recycled by exhaust outlet 7.Focusing on of waste gas ensure that work
Environment is affected by high-temperature hot-air less, is simultaneously achieved hot air circulation utilization, energy saving.
Using method of the present utility model, be loaded with shakeout arrange wire harness a cambered surface harness fixing frame 2 put
Move on support 3 to a frock, the mobile support 3 of frock is pressed setting speed by a tool motor transmission mechanism and entered pyrocondensation furnace chamber
5 opening 10, the constant speed in pyrocondensation furnace chamber 5 of the cambered surface harness fixing frame 2 on the mobile support 3 of frock skims over samming hot blast knife 4, all
Warm air knife mouth direction vertical with wire harness orientation on cambered surface harness fixing frame 2 so that samming hot blast knife 4 pyrocondensation movement from
One end of all wire harness starts, and synchronizing moving is to the other end.Frock mobile support 3 removal pyrocondensation furnace chamber 5 after the completion of pyrocondensation is mobile.
Operator takes off the cambered surface harness fixing frame 2 completing pyrocondensation, puts the cambered surface harness fixing frame that another is already prepared to wire harness
2, start next round processing.Meanwhile, take off, from previous cambered surface harness fixing frame 2, the wire harness machining, and prepare to descend next
The wire harness of wheel.
The above be only preferred implementation of the present utility model it should be pointed out that:Common skill for the art
For art personnel, on the premise of without departing from this utility model principle, some improvements and modifications can also be made, these improve and
Retouching also should be regarded as protection domain of the present utility model.
Claims (9)
1. a kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding, including base, this base has a table top, its feature
It is:Also include:The mobile support of frock being installed on base table top and pyrocondensation furnace chamber, the mobile support of described frock can move
To pyrocondensation furnace chamber, the mobile support of described frock is uniformly placed with several cambered surface harness fixing frames, each cambered surface wire harness
The two ends of fixed mount are each provided with a wire harness hold-down mechanism, and described pyrocondensation furnace chamber top is provided with samming hot blast knife, warm wind
Knife is circumscribed with hot-air blower by pipeline.
2. multi cord according to claim 1 shakeout molding sleeve pipe pyrocondensation processing unit (plant) it is characterised in that:Also include one
End connects pyrocondensation oven cavity side wall, the exhaust outlet that between the other end and warm air knife and hot-air blower, pipeline communicates.
3. multi cord according to claim 2 shakeout molding sleeve pipe pyrocondensation processing unit (plant) it is characterised in that:Described pipeline
For thermal-insulating sealing pipeline.
4. multi cord according to claim 1 shakeout molding sleeve pipe pyrocondensation processing unit (plant) it is characterised in that:Described base
Track for the mobile support movement to the inside of pyrocondensation furnace chamber of frock is provided with table top.
5. multi cord according to claim 1 shakeout molding sleeve pipe pyrocondensation processing unit (plant) it is characterised in that:Described cambered surface
Harness fixing frame is cambered plate, is used for shakeouing and tightens wire harness, the tight convex side in cambered plate of wire harness.
6. multi cord according to claim 1 shakeout molding sleeve pipe pyrocondensation processing unit (plant) it is characterised in that:Described wire harness
Hold-down mechanism can move on cambered surface harness fixing frame and lock, and wire harness hold-down mechanism is used for the two ends of fixed beam.
7. multi cord according to claim 1 shakeout molding sleeve pipe pyrocondensation processing unit (plant) it is characterised in that:Described wire harness
Hold-down mechanism adopts exotic material.
8. multi cord according to claim 1 shakeout molding sleeve pipe pyrocondensation processing unit (plant) it is characterised in that:Described samming
Inside the air knife mouth be aligned pyrocondensation furnace chamber of hot blast knife.
9. multi cord according to claim 1 shakeout molding sleeve pipe pyrocondensation processing unit (plant) it is characterised in that:Described pyrocondensation
Furnace chamber is a heat insulating box, and described pyrocondensation furnace chamber is provided with the opening entering for the mobile support of frock.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620948258.9U CN206003565U (en) | 2016-08-26 | 2016-08-26 | A kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620948258.9U CN206003565U (en) | 2016-08-26 | 2016-08-26 | A kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206003565U true CN206003565U (en) | 2017-03-08 |
Family
ID=58197178
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620948258.9U Active CN206003565U (en) | 2016-08-26 | 2016-08-26 | A kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206003565U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112092355A (en) * | 2019-07-11 | 2020-12-18 | 铜陵博康机电有限公司 | Operation method of wire harness end part and heat shrinkable tube forming device |
-
2016
- 2016-08-26 CN CN201620948258.9U patent/CN206003565U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112092355A (en) * | 2019-07-11 | 2020-12-18 | 铜陵博康机电有限公司 | Operation method of wire harness end part and heat shrinkable tube forming device |
CN112092355B (en) * | 2019-07-11 | 2023-04-07 | 铜陵博康机电有限公司 | Operation method of wire harness end part and heat shrinkable tube forming device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206003565U (en) | A kind of multi cord shakeouts the sleeve pipe pyrocondensation processing unit (plant) of molding | |
CN205951279U (en) | Plastic pipe flaring production line | |
CN105710258A (en) | Power strip cable bundling machine | |
CN208529376U (en) | The steam-cured mechanism of track plates flow production line and system | |
CN103515824A (en) | Automatic rolling toasting thermal shrinkage jacketing machine | |
CN219664092U (en) | Waterproof material board brushing device | |
CN210907593U (en) | Full-automatic hot spinning steel bottle shaping transfer device | |
CN107275680A (en) | A kind of automatic pre- roasting device of battery core | |
CN106273393B (en) | The full-automatic flange system of composite glass steel pipe | |
CN210116171U (en) | Pyrocondensation pipe firing equipment | |
CN109623672B (en) | Operation method of oil drum refurbishing pretreatment production line | |
CN209035383U (en) | A kind of automobile control arm forging line | |
CN205463068U (en) | Automatic dry and cool off machine people | |
CN206589368U (en) | A kind of automatic pipebender of plastic tube | |
CN111872204B (en) | Novel joint bolt forming device | |
CN206335849U (en) | A kind of multi cord shakeouts the processing unit (plant) of thermoforming | |
CN209005999U (en) | The automatic plastic-spraying equipment of high pressure copper bar | |
CN212218288U (en) | Pneumatic clamp for pipes | |
CN205551323U (en) | Insert winding displacement binding machine | |
CN203521856U (en) | Automatic rolling toasting thermal shrinkage jacketing machine | |
CN102962276B (en) | The taking off modular system and utilize it to carry out taking off the method for mould of wire-drawing die | |
CN201892427U (en) | Vacuum impregnating and curing equipment | |
CN207449050U (en) | Screw rod cleaning device | |
CN206879132U (en) | Steel moulds converting electromagnetic radiation automatic thermal shrinkage control system | |
CN206505987U (en) | A kind of automatic concordant battery conveying line of achievable battery |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |