CN205975619U - Pour into hopper for drilled pile - Google Patents
Pour into hopper for drilled pile Download PDFInfo
- Publication number
- CN205975619U CN205975619U CN201620901418.4U CN201620901418U CN205975619U CN 205975619 U CN205975619 U CN 205975619U CN 201620901418 U CN201620901418 U CN 201620901418U CN 205975619 U CN205975619 U CN 205975619U
- Authority
- CN
- China
- Prior art keywords
- panel
- hopper
- section panel
- conical section
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a pour into hopper for drilled pile, including the hopper body, the hopper body includes square section panel, toper section panel and pipe, and square section panel and toper section panel enclose into the material groove, material groove and pipe intercommunication, and its characterized in that: the pipe bottom outside is equipped with the base, and four angles of base are equipped with the stand, the upper portion and the square section panel fixed connection of stand, the peripheral interval of square section panel and toper section panel is equipped with the horizontal support in a plurality of layers, still be equipped with a plurality of bracings on the base, the upper end of bracing is supported in the horizontal support of toper section panel. The utility model discloses simple structure can hold the concrete that is greater than 16m3 under the fully loaded condition, and stability is good, can not take place deformation.
Description
Technical field
This utility model is related to drilled pile instrument, particularly a kind of bored piles hopper.
Background technology
The general volume of existing concrete hopper is less, fully loaded in the case of can only fill 2m3Concrete, if mixed
The volume of solidifying earth material bucket increases, during pouring reinforcement concrete, often because hopper four pin point point that plate muscle is applied
Load is excessive, thus occurring reinforcing bar deflection to exceed the situation of job specfication allowed band, and then affects pouring quality, and is difficult
Place stabilizing influence construction safety;But in the irrigation process of large-diameter concrete stake, the quantity of first batch of concrete perfusion should expire
Sufficient conduit buried depth first(≥1.0m)With the needs of filling conduit bottom because making a kind of strong hopper of the big bearing capacity of volume,
Perfusion to large-diameter concrete stake is necessary.
Content of the invention
This utility model provides a kind of bored piles hopper, and structure is simple, and bearing capacity is strong it is ensured that major diameter is mixed
The casting quality of solidifying soil stake.
For solving above-mentioned technical problem, the technical solution adopted in the utility model is:
A kind of bored piles hopper, including hopper body, hopper body include square section of panel, conical section panel and
Conduit, square section of panel and conical section panel surround material trough, and material trough is connected with conduit, and conduit bottom outside is provided with base,
Four angles of base are provided with column, and the top of column is fixedly connected with square section of panel, described square section of panel and conical section face
If plate periphery is interval with dried layer cross-brace, described base is additionally provided with some diagonal braces, the upper end of diagonal brace is supported in taper
In the cross-brace of section panel.
Further, the first stiffener being provided with triangle between described conical section panel and column is reinforced, to protect
Card conical section panel and the connective stability of column.
Further, described conduit and the junction of conical section panel, are provided with reinforcing plate and are reinforced, to ensure conical section
The stability of panel and conduit connection and the bearing capacity of conical section panel.
Further, described reinforcing plate includes upper reinforcing plate and lower reinforcing plate, upper reinforcing plate and the conical section of oblique connection
Panel is fixedly connected, and lower reinforcing plate is fixedly connected with conduit.
Further, described column is provided with the preformed hole for lifting, and preformed hole can facilitate hopper is lifted.
Further, the junction of described column and base be symmetrically arranged on two with triangle the second stiffener carry out plus
Gu.
Further, described base and column are made by I-steel, and the robust structure of I-steel can ensure that hopper four
The support force of pin point.
Further, described diagonal brace and cross-brace are made by channel-section steel.
In sum, due to employing technique scheme, the beneficial effects of the utility model are:(1)This utility model
It is provided with column, cross-brace, diagonal brace are reinforced to funnel, thus improve square section of panel and each side of conical section panel
To strength and stability;(2)This utility model be equipped with the first stiffener, the second stiffener and reinforcing plate column with
The connection of square section of panel, column and base is reinforced, thus ensureing the support force of hopper;(3)The letter of this utility model structure
Single, can hold more than 16m in the case of being fully loaded with3Concrete, and good stability, will not deform upon.
Brief description
Fig. 1 is overlooking the structure diagram of the present utility model;
Fig. 2 is the positive structure diagram of Fig. 1;
Fig. 3 is the left view structural representation of Fig. 1;
Fig. 4 is the cross section structure schematic diagram that reinforcing plate is connected with conduit;
Fig. 5 is the left view structural representation of reinforcing plate in Fig. 2.
In figure, cross-brace 1, base 2, conduit 3, column 4, square section of panel 5, conical section panel 6, reinforcing plate 7, above add
Strong plate 7a, lower reinforcing plate 7b, diagonal brace 8, the first stiffener 9, the second stiffener 10, preformed hole 11, suspension ring 12.
Specific embodiment
Below in conjunction with accompanying drawing, the utility model is described in further detail, but protection domain of the present utility model be not limited to
Lower embodiment.
A kind of bored piles hopper, as shown in Fig. 1 ~ 3, including hopper body, hopper body includes square section of panel
5th, conical section panel 6 and conduit 3, square section of panel 5 and conical section panel 6 surround material trough, and material trough is connected with conduit 3, pump
The concrete entering material trough is entered in drilled pile by conduit 3.For improving the support force of hopper, it is provided with conduit 3 bottom outside
Base 2, installs column 4 at four angles of base 2, the top of column 4 is fixedly connected with square section of panel 5, in square section of panel 5
If being interval with dried layer cross-brace 1 with conical section panel 6 periphery, wherein, the cross-brace 1 shown in figure, in square section of face
It is provided with 2 layers on plate 5, conical section panel 6 is provided with 1 layer;Some diagonal braces 8, the upper end of diagonal brace 8 are additionally provided with base 2
It is supported in the cross-brace 1 of conical section panel 6.
Further, for ensureing the connective stability of conical section panel 6 and column 4, conical section panel 6 and column 4 it
Between be provided with the first stiffener 9 of triangle and reinforced, this first stiffener 9 also can improve the support of conical section panel simultaneously
Power.
Further, for ensureing the stability of conical section panel 6 and conduit 3 connection, strengthen the load-bearing of conical section panel 6
Power, in the junction of conduit 3 and conical section panel 6, is provided with reinforcing plate 7, in conjunction with shown in Fig. 4 and Fig. 5, wherein, reinforcing plate 7 is wrapped
Include the upper reinforcing plate 7a and lower reinforcing plate 7b of oblique connection, upper reinforcing plate 7a is fixedly connected with conical section panel 6, upper reinforcing plate 7a
Inner side be close to the outer wall of conical section panel 6, lower reinforcing plate 7b is fixedly connected with conduit 3, and the inner side of lower reinforcing plate 7b is close to
Outer wall in conduit 3.
Further, for convenience hopper is lifted, the preformed hole 11 for lifting is provided with column 4, reserve
Suspension ring are penetrated, you can lift hopper to suitable position by hanging device in hole 11.
For being further ensured that the support force of hopper four pin point, it is symmetrically installed with three in the junction both sides of column 4 and base 2
The second angular stiffener 10 is reinforced, and the supporting construction of triangle can mitigate the support burden of column 4, by the weight of material trough
Amount is uniformly dispersed to base 2.
For enabling hopper to hold more than 16m3Concrete, in installation process, base 2 and column 4 are by I25a I-shaped
Steel is made, and diagonal brace 8 and cross-brace 1 are by [ 20 channel-section steels are made.
Claims (8)
1. a kind of bored piles hopper, including hopper body, hopper body includes square section of panel, conical section panel and leads
Pipe, square section of panel and conical section panel surround material trough, material trough connect with conduit it is characterised in that:Conduit bottom outside
Be provided with base, four angles of base are provided with column, and the top of column is fixedly connected with square section of panel, described square section of panel and
If conical section panel periphery is interval with dried layer cross-brace, described base is additionally provided with some diagonal braces, the upper end of diagonal brace is propped up
Support in the cross-brace of conical section panel.
2. bored piles hopper according to claim 1 it is characterised in that:Between described conical section panel and column
The first stiffener being provided with triangle is reinforced.
3. bored piles hopper according to claim 1 it is characterised in that:Described conduit and the company of conical section panel
Meet place, be provided with reinforcing plate and reinforced.
4. bored piles hopper according to claim 3 it is characterised in that:Described reinforcing plate includes oblique connection
Upper reinforcing plate and lower reinforcing plate, upper reinforcing plate is fixedly connected with conical section panel, and lower reinforcing plate is fixedly connected with conduit.
5. bored piles hopper according to claim 1 it is characterised in that:Described column is provided with for lifting
Preformed hole.
6. bored piles hopper according to claim 1 it is characterised in that:Described column and the junction two of base
The second stiffener that side is arranged with triangle is reinforced.
7. bored piles hopper according to claim 1 it is characterised in that:Described base and column are by I-steel
Make.
8. bored piles hopper according to claim 1 it is characterised in that:Described diagonal brace and cross-brace are by groove
Steel is made.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620901418.4U CN205975619U (en) | 2016-08-19 | 2016-08-19 | Pour into hopper for drilled pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620901418.4U CN205975619U (en) | 2016-08-19 | 2016-08-19 | Pour into hopper for drilled pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205975619U true CN205975619U (en) | 2017-02-22 |
Family
ID=58032338
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620901418.4U Active CN205975619U (en) | 2016-08-19 | 2016-08-19 | Pour into hopper for drilled pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205975619U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113233027A (en) * | 2021-04-22 | 2021-08-10 | 中国电建集团河北省电力勘测设计研究院有限公司 | Cluster formula steel coal storage bucket |
-
2016
- 2016-08-19 CN CN201620901418.4U patent/CN205975619U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113233027A (en) * | 2021-04-22 | 2021-08-10 | 中国电建集团河北省电力勘测设计研究院有限公司 | Cluster formula steel coal storage bucket |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107299643B (en) | Steel lattice column combined type tower crane foundation structure in foundation pit and construction method | |
CN105544587B (en) | The construction method of tower crane is fixed using combined type foundation for tower crane | |
CN207294093U (en) | A kind of large span steel truss integral lifting apparatus | |
CN105113716A (en) | Construction method of large-diameter multi-rib-plate high-dropping self-compacting steel pipe concrete superposed columns | |
CN103469735B (en) | The mounting method of curve ultrahigh hollow column plate type pier top solid section template | |
CN203639095U (en) | Inner-side-column lifting device for reverse installation method | |
CN205975619U (en) | Pour into hopper for drilled pile | |
CN206157792U (en) | Complementary rectification reinforced structure of stake raft | |
CN209603163U (en) | A kind of tower crane bearing platform ruggedized construction | |
CN108277817B (en) | Construction method of high-pile bearing platform tower crane foundation reinforcing structure | |
CN105951683A (en) | Construction method for corbel steel reinforcements of gate pier | |
CN110607801A (en) | Improve fan cushion cap subassembly of stake resistance to plucking bearing capacity | |
CN106193101A (en) | Tower crane steel platform pile foundation and construction method thereof | |
CN206616602U (en) | A kind of outdoor construction elevator strengthening of foundation device | |
CN207144022U (en) | A kind of cross pile foundation reinforcement device | |
CN206562620U (en) | A kind of tower crane lattice column and the attachment structure on concrete bearing platform basis | |
CN102134856B (en) | Tower crane foundation | |
CN211257051U (en) | Improve fan cushion cap subassembly of stake resistance to plucking bearing capacity | |
CN209261225U (en) | A kind of tool for pouring concrete into steel column | |
CN210086236U (en) | Bearing capacity lifting device of cast-in-place pile and cast-in-place pile | |
CN205976692U (en) | Base of communication tower | |
CN203222808U (en) | Foundation processing structure for floating sluice | |
CN208219623U (en) | A kind of reusable foundation pile pile cover | |
CN205421312U (en) | Combined type tower machine basis | |
CN201212146Y (en) | Reinforcement reinforced bar caging of ultralong and overweight concrete filling pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |