CN205975367U - Bridge aerial working platform device - Google Patents

Bridge aerial working platform device Download PDF

Info

Publication number
CN205975367U
CN205975367U CN201620845397.9U CN201620845397U CN205975367U CN 205975367 U CN205975367 U CN 205975367U CN 201620845397 U CN201620845397 U CN 201620845397U CN 205975367 U CN205975367 U CN 205975367U
Authority
CN
China
Prior art keywords
hanging basket
bridge
master console
sliding
connecting shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620845397.9U
Other languages
Chinese (zh)
Inventor
贾美玲
李吴杰
王琴
丁昕璐
周燕燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Xiangda Construction Co Ltd
Original Assignee
Zhejiang Xiangda Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Xiangda Construction Co Ltd filed Critical Zhejiang Xiangda Construction Co Ltd
Priority to CN201620845397.9U priority Critical patent/CN205975367U/en
Application granted granted Critical
Publication of CN205975367U publication Critical patent/CN205975367U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses a bridge aerial working platform device, including the staff's that is used for standing hanging flower basket with arrange the main control console on the bridge in, be equipped with the dismouting subassembly between hanging flower basket and the main control console, the dismouting subassembly include along bridge beam width degree direction and main control console be the complex sliding component that slides, with sliding component one end be normal running fit and be connected in the hanging flower basket near the connecting axle on one side of the main control console, articulate the actuating lever of keeping away from connecting axle one end in the hanging flower basket, the actuating lever atress rotates and drives the hanging flower basket in the staff and overturns to main control console top or bridge side below round the connecting axle. The utility model provides a setting of hanging flower basket position can be accomplished fast, a bridge aerial working platform device of the operation degree of difficulty is reduced.

Description

A kind of bridge high altitude operation stage apparatus
Technical field
This utility model is related to aerial platform field, particularly to a kind of bridge high altitude operation stage apparatus.
Background technology
In bridge construction or maintenance, generally require the side to bridge and carry out job execution, such as maintenance, cabling, peace Dress ornament materials etc..
The patent document of China Patent Publication No. CN 105735140A discloses a kind of bridge side aerial work platform dress Put, including I shape guide rail, mobile suspension beam, hanging basket assembly and platform walking actuation means, the riser of I shape guide rail sets It is equipped with bar-shaped trough, two described mobile beam one end that hang are arranged in bar-shaped trough, positioned at the mobile suspension Liang Shangjun of riser both sides It is provided with rail wheel, rail wheel drives the mobile beam that hangs to move along along I shape guide rail two siding track;Two mobile suspension beams are another One end is hung with hanging basket assembly and is connected;Platform walking actuation means drive mobile suspension beam to suspended on hanging basket assembly and lead in I shape Walk on rail.Hanging basket assembly in technique scheme is fixed, and when mounting operation platform, by whole hanging basket Put to the lower section of bridge, the construction of this hanging basket is fixed, lead to disassembly process trouble complicated.
Utility model content
The purpose of this utility model is to provide a kind of bridge high altitude operation stage apparatus, by removable component, can facilitate Ground overturns hanging basket to bridge side-lower from master console or hanging basket is overturn to above master console from bridge side, quickly Complete the setting of hanging basket position, reduce operation easier.
Above-mentioned technical purpose of the present utility model technical scheme is that:A kind of bridge high altitude operation Stage apparatus, including for the hanging basket of the staff that stands with the master console, described hanging basket and the master console that are placed on bridge Between be provided with removable component, described removable component include along bridge width direction and master console be in sliding cooperation sliding component, It is rotating and is connected to the connecting shaft near master console side for the hanging basket with sliding component one end, be articulated with hanging basket away from being connected The drive rod of axle one end, described drive rod stress rotates in staff and drives hanging basket to overturn to master console around connecting shaft Top or bridge side-lower.
By adopting technique scheme, when needing using hanging basket, first with sliding component, whole hanging basket is transported to bridge The outside of beam, then hanging basket is made around connecting shaft to the operation of drive rod by flip-flop movement by staff, by whole hanging basket Overturn to the side-lower of bridge, thus staff just can be made to smoothly enter in hanging basket being operated;When completing maintenance mans After work, first pass through drive rod hanging basket is deviated from one end of connecting shaft and exert a force, pulled up, so that hanging basket can be around Connecting shaft up to be overturn so as to conflict on sliding component, then move sliding component again, just can be the space of whole device Reduce;Whole disassembly process fast and easy, reduces the time before work, reduces operation easier, improves disassembly efficiency.
This utility model is further arranged to:Described sliding component include socket-connecting and in sliding the first extension rod of cooperation and Second extension rod, described first extension rod and master console are in that sliding coordinates, and described second extension rod deviates from master console one end It is rotating with connecting shaft.
By adopting technique scheme, the second extension rod can be stretched out in the first extension rod, such that it is able to increase The distance between hanging basket and master console, hanging basket are successfully moved to the outside of bridge, will not be by the guardrail width institute of bridge Impact, when using, can adjust the spacing between master console and hanging basket, after not using, reduce accounting for of whole device Use space.
This utility model is further arranged to:Described second extension rod socket-connects and sliding is combined with connecting rod, described hangs It is in the socket that grafting coordinates that basket deviate from connecting shaft side wall to be provided with connecting rod.
By adopting technique scheme, the second extension rod can be stretched out a segment distance using connecting rod, and Insert it in the side wall of hanging basket, thus using the first extension rod, the second extension rod and connecting rod, can by master console and Hanging basket is stably connected with, and relies on connecting rod to hanging basket away from the fixation of connecting shaft side, makes hanging basket keep horizontal equilibrium, will not Because there is the upset of wide-angle the reason connecting shaft, and improve safety when operator station stands in hanging basket, Increase the stability of equilibrium between hanging basket and master console.
This utility model is further arranged to:Described master console is provided with the slide rail being set in parallel with its width, Described sliding component is embedded and is slidably connected to slide rail.
By adopting technique scheme, rely on slide rail, whole sliding component all can be slid onto inside it, such that it is able to Reduce taking up room of whole device;And rely on slide rail that the movement of sliding component is played with guide and limit effect, so that hanging basket is being slided Along specified track motion, the deviation of position can will not occur in dynamic process so that its more stably with main control Platform is connected;The annexation of sliding cooperation, makes the process of mobile whole hanging basket convenient, simple to operate.
This utility model is further arranged to:Described connecting shaft outer wall is provided with the baffle element being vertically arranged, described stop Body sidewall and hanging basket are in setting of conflicting near connecting shaft side.
By adopting technique scheme, rely on baffle element that hanging basket is acted near the conflict of the side wall of connecting shaft one end, The position of hanging basket can be carried out spacing, make hanging basket keep, in being vertically arranged, excessive angle will not being rotated in switching process, Also the balanced action of hanging basket can be improved;And, the position of hanging basket in the switching process to hanging basket, is determined without relying upon drive rod Put, directly overturned, simple to operation.
This utility model is further arranged to:Described drive rod is deviated from one end hinged with hanging basket and is joined in rotation with connecting shaft Close, described drive rod is hinged with gangbar near one end hinged with hanging basket, and described gangbar is hinged with away from drive rod one end Rotating bar, described rotating bar is deviated from gangbar one end and is rotating with master console, and described rotating bar and drive rod are in isometric Setting.
By adopting technique scheme, when needing to carry out turning operation to hanging basket, because rotating bar with drive rod is in Isometric, so rotating bar, gangbar and drive rod may make up a parallelogram, rotating bar only need to be rotated by staff 180 degree, with regard to relying on the gangbar being in hinged with it to drive drive rod to carry out 180 degree rotation around connecting shaft, and then with regard to energy Drive rod is made to drive hanging basket to deviate from the side of connecting shaft to be overturn around the axial direction of connecting shaft, will hang away from one end of connecting shaft Basket overturns from bridge side to the top of master console, thus completing expansion and the folding of whole device;It is different from and only rely on A piece drive rod, needs staff will adjust position and the force journey of drive rod according to the flip angle of actual hanging basket Degree, this scheme, only need staff to rotate 180 degree to rotating bar, can be achieved with the upset to hanging basket.
This utility model is further arranged to:Described gangbar include in socket and sliding cooperation the first expansion link and the Two expansion links, it is in that sliding coordinates that described rotating bar deviates from gangbar one end along master console width and master console.
By adopting technique scheme, the socket telescopic action of dependence the first expansion link and the second expansion link and rotation Sliding cooperation between bar one end and master console, makes hanging basket during the drive of sliding component, drive rod, gangbar and rotation Bar will not move interference and fracture, can according to actual hanging basket and master console the distance between adjusting gangbar The length and rotating bar position on master console.
This utility model is further arranged to:Described rotating bar deviates from gangbar one end and is coaxially connected with worm gear, described snail Wheel engagement is provided with worm screw, and described worm screw is in rotate to be connected with master console, and described worm screw is connected with handwheel.
By adopting technique scheme, drive rotating bar to be rotated using the worm and gear being meshed, rely on snail Self-locking action between worm and gear, can only drive worm gear wheel by worm screw, worm gear reverse drive worm screw rotates, so that rotating Bar and gangbar can play stable interconnection function to hanging basket, and a pulling force work is played in one end that hanging basket is deviated from connecting shaft With so as to the deflection of wide-angle will not occur.
This utility model is further arranged to:Described hanging basket is connected with conflict bar, described conflict along its width sliding Bar contacts at side wall of bridge away from hanging basket one end, is connected with securing member between described conflict bar and hanging basket.
By adopting technique scheme, when in staff standing to hanging basket, by conflict bar along hanging basket width Direction is moved so as to conflict to the side wall of bridge, and is fixedly connected conflict bar and hanging basket using securing member, thus Can provide hanging basket one conflict power deviating from bridge, enable stable being connected on master console of hanging basket, improve and entirely hang The stability of equilibrium of basket, improves the operational stability of staff.
This utility model is further arranged to:It is connected with horizontal cat ladder, described hanging basket between described hanging basket and master console It is provided with vertical cat ladder, described horizontal cat ladder is connected in sliding along bridge width direction with master console width.
By adopting technique scheme, facilitate staff and enter in workbench from bridge, and can also be right Workbench plays fence protective effect, and the phorogenesis using horizontal cat ladder and master console, can coordinate removable component Move.
In sum, this utility model has the advantages that:
One:In conjunction with the grafting of connecting rod and socket, conflict bar and side wall of bridge conflict and worm and gear to driving The reverse self-locking effect of bar, improves the connective stability of hanging basket, and the balance and master console between, improves whole The security performance of device;
It two:Using rotating bar, gangbar, drive rod and the sliding component that can stretch, can more easily exert a force In hanging basket, realize the rotary movement of hanging basket, make whole operation process simple and quick, improve efficiency.
Brief description
Fig. 1 is the structural representation of the present embodiment;
Fig. 2 is the structural representation of the present embodiment, major embodiment hanging basket;
Fig. 3 is the structural representation of the present embodiment, major embodiment screw rod;
Fig. 4 is the I portion enlarged drawing of Fig. 3, major embodiment slide block;
Fig. 5 is II portion enlarged drawing, major embodiment worm gear and the worm screw of Fig. 2.
Reference:1st, master console;111st, roller;2nd, slide rail;3rd, the first extension rod;31st, clamping screw;4th, screw rod; 41st, slide block;5th, mobile bar;6th, the second extension rod;7th, connecting shaft;8th, baffle element;9th, connecting rod;10th, hanging basket;101st, montant; 102nd, stock;103rd, wide bar;104th, workbench;11st, socket;12nd, conflict bar;121st, conflict and take turns;122nd, securing member;13rd, level Cat ladder;14th, vertical cat ladder;15th, direction recess;16th, pedestal;17th, worm screw;18th, worm gear;19th, rotating bar;20th, gangbar;201、 First expansion link;202nd, the second expansion link;203rd, fastening bolt;204th, waist type groove;21st, drive rod;22nd, handwheel.
Specific embodiment
Below in conjunction with accompanying drawing, this utility model is described in further detail.
A kind of bridge high altitude operation stage apparatus, with reference to shown in Fig. 1, including a cuboid master console 1, master console 1 has larger quality;It is respectively connected with roller 111 at four angles of master console 1 bottom, master console 1 is positioned over bridge floor On.
With reference to shown in Fig. 2, it is equipped with and bridge width in master console 1 two side edge perpendicular with bridge length direction The slide rail 2 that direction is set in parallel;Slide rail 2 is a chute through master console 1 width;It is embedded in slide rail 2 And sliding is connected with cuboid first extension rod 3 along its length;In conjunction with shown in Fig. 3-4, also set in master console 1 There is the screw rod 4 being set in parallel with its length direction, the end of screw rod 4 is in rotate to be connected with the side wall of master console 1;Screw rod 4 Wear and be threaded with a slide block 41, slide block 41 is connected in sliding along master console 1 width with master console 1, sliding The upper surface of block 41 and the first extension rod 3 bottom surface phase welding;It is connected with movement between first extension rod 3 of master console 1 both sides Bar 5.
With reference to shown in Fig. 2, the first extension rod 3 is in hollow setting, is socketed with cuboid second extension rod inside it 6, the second extension rod 6 can slide in the first extension rod 3 along the width of master console 1;Deviate from the first extension rod 3 The threaded one end of master console 1 is connected with clamping screw 31;The one end deviating from master console 1 in the second extension rod 6 rotates and connects There is a connecting shaft 7;It is vertically connected with a block length cube baffle element in the lower surface near connecting shaft 7 one end for second extension rod 6 8;Second extension rod 6 is also in that hollow is arranged, and is socketed with a cuboid connecting rod 9, connecting rod 9 can be along master control inside it The width of platform 1 processed slides in the second extension rod 6.
With reference to shown in Fig. 2, it is hinged with a hanging basket 10 in the end of connecting shaft 7, whole hanging basket 10 is in cuboid, hanging basket 10 include four is in the montant 101 that is vertically arranged and is connected between montant 101 bottom and the workbench 104 in level; It is connected between four montant 101 ends and constitute a rectangle;It is connected with and bridge length side between wherein two montants 101 To the stock 102 being set in parallel, then another two is the wide bar 103 being set in parallel with bridge width direction;Wherein near even The stock 102 of spindle 7 side is in conflict to arrange with baffle element 8 surface when hanging basket 10 is located at bridge side;Hanging basket 10 away from It is in the socket 11 that grafting is arranged that montant 101 side of connecting shaft 7 is provided with connecting rod 9, to increase hanging basket for fixed connecting rod 9 10 stability of equilibrium;Two wide bars 103 of hanging basket 10 lower section are arranged all in hollow, are socketed and along bridge in wide bar 103 Width sliding be connected with conflict bar 12, conflict bar 12 is rotatably connected to conflict wheel 121 away from one end of hanging basket 10, conflict Wheel 121 rolls the side wall being connected to bridge;It is connected near the threaded one end of connecting shaft 7 in the wide bar 103 of socket conflict bar 12 Securing member 122, securing member 122 pushes against and is used for locking conflict bar 12 and wide bar 103 in conflict bar 12;In hanging basket 10 and master console It is connected with the cat ladder in level, horizontal cat ladder 13 is in that sliding coordinates along the width of bridge with master console 1, level between 1 Cat ladder 13 includes socket-connecting and two sections of sliding cooperation;The montant 101 that hanging basket 10 deviates from connecting shaft 7 side is provided with vertically Cat ladder 14.
In order to overturn to hanging basket 10, in conjunction with shown in Fig. 2 and Fig. 5, it is provided with and it in the upper surface of master console 1 The direction recess 15 that width is set in parallel, sliding in direction recess 15 is connected with a pedestal 16, on pedestal 16 It is rotatably connected to a worm screw 17, the axial direction of worm screw 17 is set in parallel with the width of master console 1;The end of worm screw 17 It is coaxially connected with a handwheel 22;Worm screw 17 engagement is provided with a worm gear 18, and worm gear 18 is rotationally connected with pedestal 16;Worm gear 18 It is coaxially connected with a rotating bar 19;In conjunction with shown in Fig. 3, rotating bar 19 is hinged with a gangbar away from one end of worm gear 18 20, gangbar 20 includes two and socket-connects and the first expansion link 201 of sliding cooperation and the second expansion link 202, the first expansion link 201 is in hinged with rotating bar 19 and the setting in hollow, and the second expansion link 202 is socketed on the first expansion link 201 and deviates from first and stretch It is in isometric drive rod 21 that one end of contracting bar 201 is hinged with one with rotating bar 19;First expansion link 201 deviates from rotating bar 19 Threaded one end is connected with fastening bolt 203, and the second expansion link 202 is provided with for fastening bolt 203 of conflicting along its length direction Waist type groove 204;The hinged place of drive rod 21 and the second expansion link 202 and hanging basket 10 are also in hinged away from the side of connecting shaft 7 Setting;Drive rod 21 is deviated from and is rotating with the stock 101 of hanging basket 10 with one end of the second expansion link 202 hinged place, drives Bar 21 is in be coaxially disposed with the pin joint of stock 101 with connecting shaft 7.
The operation principle of the present embodiment is:
When needing bridge side is keeped in repair, first the second extension rod 6 is pulled out from the first extension rod 3, and use Clamping screw 31 is fastened, and the hanging basket 10 being articulated with the second extension rod 6 one end is also moved and away from master console 1 simultaneously, Second expansion link 202 of gangbar 20 is drawn out from the first expansion link 201, is fixed both using fastening bolt 203, Meanwhile, wherein a section of horizontal cat ladder 13 is also pulled out;Rotate screw rod 4, make slide block 41 with the first extension rod 3 from master console Sliding in 1 and go out, simultaneously pedestal 16 along master console 1 width move, the other end of horizontal cat ladder 13 is also from master control Skid off in platform 1 processed;It is rotated further by handwheel 22, drive worm gear 18 to rotate by worm screw 17, so that rotating bar 19 is rotated around pedestal 16 180 °, rely on drive rod 21 to rotate 180 ° around connecting shaft 7, hanging basket 10 also rotates around connecting shaft 7 near bridge side simultaneously 180 °, make hanging basket 10 from the upper surface of the second extension rod 6 overturn to bridge side and in being vertically arranged;Staff is by level Cat ladder 13 and vertical cat ladder 14 can be stood on workbench 104, now, connecting rod 9 is extracted out from the second extension rod 6, and And be plugged in socket 11, then conflict bar 12 is extracted out from hanging basket 10, so that conflict wheel 121 is conflicted to side wall of bridge, and profit Fastened with securing member 122.
After completing maintenance, staff, first with vertical cat ladder 14 and horizontal cat ladder 13, climbs to bridge from workbench 104 On face;First rotate handwheel, using worm gear 18 worm screw 17, rotating bar 19 rotated 180 °, meanwhile, drive rod 21 and hanging basket 10 all around Connecting shaft 7 and rotate 180 °, hanging basket 10 turns to the upper surface of the second extension rod 6 from bridge side;Then, rotate screw rod 4, utilize First extension rod 3 sliding is entered in master console 1 by slide block 41, and also sliding enters master console 1, pedestal simultaneously to horizontal cat ladder 13 16 move toward the direction deviating from hanging basket 10 on master console 1, then the second expansion link 202 sliding is entered into the first expansion link In 201, hanging basket 10 is made to move to the top of master console 1, thus completing the dismounting of hanging basket 10.
This specific embodiment is only that it is not to restriction of the present utility model, ability to explanation of the present utility model Field technique personnel can make to the present embodiment after reading this specification as needed does not have the modification of creative contribution, but As long as all being protected by Patent Law in right of the present utility model.

Claims (10)

1. a kind of bridge high altitude operation stage apparatus, including the hanging basket for the staff that stands(10)With the master being placed on bridge Control station(1), it is characterized in that:Described hanging basket(10)With master console(1)Between be provided with removable component, described removable component includes Along bridge width direction and master console(1)In sliding, the sliding component of cooperation is rotating with sliding component one end and is connected to Hanging basket(10)Near master console(1)The connecting shaft of side(7), be articulated with hanging basket(10)Away from connecting shaft(7)The driving of one end Bar(21), described drive rod(21)Stress rotates in staff and drives hanging basket(10)Around connecting shaft(7)Overturn to master control Platform processed(1)Top or bridge side-lower.
2. a kind of bridge high altitude operation stage apparatus according to claim 1, is characterized in that:Described sliding component includes being nested The first extension rod connecing and coordinating in sliding(3)With the second extension rod(6), described first extension rod(3)With master console(1)It is in Sliding coordinates, described second extension rod(6)Deviate from master console(1)One end and connecting shaft(7)It is rotating.
3. a kind of bridge high altitude operation stage apparatus according to claim 2, is characterized in that:Described second extension rod(6) Socket-connect and sliding is combined with connecting rod(9), described hanging basket(10)Deviate from connecting shaft(7)Side wall is provided with and connecting rod(9)In slotting Connect the socket of cooperation(11).
4., according to claim 1 or 2 or 3 or a kind of described bridge high altitude operation stage apparatus, it is characterized in that:Described main control Platform(1)It is provided with the slide rail being set in parallel with its width(2), described sliding component is embedded and is slidably connected to slide rail(2).
5. a kind of bridge high altitude operation stage apparatus according to claim 1, is characterized in that:Described connecting shaft(7)Outer wall It is provided with the baffle element being vertically arranged(8), described baffle element(8)Side wall and hanging basket(10)Near connecting shaft(7)Side is in conflict Setting.
6. a kind of bridge high altitude operation stage apparatus according to claim 1, is characterized in that:Described drive rod(21)Deviate from With hanging basket(10)Hinged one end and connecting shaft(7)It is rotating, described drive rod(21)Near and hanging basket(10)Hinged One end is hinged with gangbar(20), described gangbar(20)Away from drive rod(21)One end is hinged with rotating bar(19), described turn Lever(19)Deviate from gangbar(20)One end and master console(1)It is rotating, described rotating bar(19)With drive rod(21) In isometric setting.
7. a kind of bridge high altitude operation stage apparatus according to claim 6, is characterized in that:Described gangbar(20)Including In the first expansion link being socketed and sliding coordinates(201)With the second expansion link(202), described rotating bar(19)Deviate from gangbar (20)One end is along master console(1)Width and master console(1)Coordinate in sliding.
8. a kind of bridge high altitude operation stage apparatus according to claim 6, is characterized in that:Described rotating bar(19)Deviate from Gangbar(20)One end is coaxially connected with worm gear(18), described worm gear(18)Engagement is provided with worm screw(17), described worm screw(17) With master console(1)Connect in rotating, described worm screw(17)It is connected with handwheel(22).
9. a kind of bridge high altitude operation stage apparatus according to claim 1, is characterized in that:Described hanging basket(10)Wide along it Degree direction sliding is connected with conflict bar(12), described conflict bar(12)Away from hanging basket(10)One end contacts at side wall of bridge, described Conflict bar(12)With hanging basket(10)Between be connected with securing member(122).
10. a kind of bridge high altitude operation stage apparatus according to claim 1, is characterized in that:Described hanging basket(10)With master Control station(1)Between be connected with horizontal cat ladder(13), described hanging basket(10)It is provided with vertical cat ladder(14), described horizontal cat ladder(13) Along bridge width direction and master console(1)Width is in that sliding connects.
CN201620845397.9U 2016-08-06 2016-08-06 Bridge aerial working platform device Withdrawn - After Issue CN205975367U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620845397.9U CN205975367U (en) 2016-08-06 2016-08-06 Bridge aerial working platform device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620845397.9U CN205975367U (en) 2016-08-06 2016-08-06 Bridge aerial working platform device

Publications (1)

Publication Number Publication Date
CN205975367U true CN205975367U (en) 2017-02-22

Family

ID=58029128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620845397.9U Withdrawn - After Issue CN205975367U (en) 2016-08-06 2016-08-06 Bridge aerial working platform device

Country Status (1)

Country Link
CN (1) CN205975367U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476562A (en) * 2017-09-13 2017-12-15 许昌学院 A kind of novel building hanging basket
CN109468963A (en) * 2019-01-08 2019-03-15 云南省建设投资控股集团有限公司 Bridge high altitude operation hanging basket and bridge high-altitude construction method
CN109706841A (en) * 2019-01-08 2019-05-03 广西路桥工程集团有限公司 A kind of movable hanging basket and its construction method facilitating high-strength bolt construction
CN109750601A (en) * 2019-01-16 2019-05-14 四川同风源建设工程有限公司 A kind of highway bridge avris construction operation platform
CN111877179A (en) * 2020-08-11 2020-11-03 郑琮 Safe aerial work platform for bridge construction

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476562A (en) * 2017-09-13 2017-12-15 许昌学院 A kind of novel building hanging basket
CN109468963A (en) * 2019-01-08 2019-03-15 云南省建设投资控股集团有限公司 Bridge high altitude operation hanging basket and bridge high-altitude construction method
CN109706841A (en) * 2019-01-08 2019-05-03 广西路桥工程集团有限公司 A kind of movable hanging basket and its construction method facilitating high-strength bolt construction
CN109706841B (en) * 2019-01-08 2020-09-18 广西路桥工程集团有限公司 Construction method of movable hanging basket convenient for high-strength bolt construction
CN109468963B (en) * 2019-01-08 2024-07-05 云南省建设投资控股集团有限公司 Hanging basket for overhead operation of bridge and overhead construction method of bridge
CN109750601A (en) * 2019-01-16 2019-05-14 四川同风源建设工程有限公司 A kind of highway bridge avris construction operation platform
CN109750601B (en) * 2019-01-16 2020-08-07 四川同风源建设工程有限公司 Highway bridge avris construction work platform
CN111877179A (en) * 2020-08-11 2020-11-03 郑琮 Safe aerial work platform for bridge construction
CN111877179B (en) * 2020-08-11 2021-04-13 唐晖 Safe aerial work platform for bridge construction

Similar Documents

Publication Publication Date Title
CN205975367U (en) Bridge aerial working platform device
CN101752804B (en) Two-arm swing obstacle-clearing type line walking robot body
CN107268969B (en) A kind of scaffold structure for high altitude operation
CN107237487A (en) A kind of movable Scaffold
CN112249999A (en) Electric lifting type aerial work platform
CN106002927B (en) A kind of construction transportation industrial robot based on redundancy four-degree-of-freedom
CN109237212B (en) Gantry crane removes base
CN105344714B (en) A kind of milling train Quick roll-changing device
CN208791125U (en) The extension job platform of aerial work platform
CN207583301U (en) A kind of voluntarily double ladder
CN208815871U (en) A kind of lifting ladder for building easy to use
CN106837379B (en) A kind of construction method in tunnel and its tunnel lining trolley of use
CN101214905A (en) Upright column single-beam portable hoisting and transporting machine
CN209670301U (en) A kind of scaffold with stress monitoring protection
CN209538731U (en) A kind of protective fence of construction stair
CN108049315B (en) A kind of travelling bridge for the guardrail construction that builds a bridge
CN217947606U (en) Aerial operation vehicle
CN106629470B (en) Lift level-sensing device apparatus for examination and repair
CN208310397U (en) A kind of color steel plate warning fence
CN106639620B (en) Canopy device
CN213476647U (en) Construction hanging basket suspension device for steel structure gallery bridge
CN209670368U (en) Building engineering construction platform
CN208603647U (en) A kind of construction lift
KR101116258B1 (en) Revolving Support of Table Form
CN106337652A (en) Electric power maintenance ladder

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170222

Effective date of abandoning: 20211216

AV01 Patent right actively abandoned

Granted publication date: 20170222

Effective date of abandoning: 20211216