CN205955208U - Multi -functional split bolt sleeve pipe - Google Patents

Multi -functional split bolt sleeve pipe Download PDF

Info

Publication number
CN205955208U
CN205955208U CN201620968610.5U CN201620968610U CN205955208U CN 205955208 U CN205955208 U CN 205955208U CN 201620968610 U CN201620968610 U CN 201620968610U CN 205955208 U CN205955208 U CN 205955208U
Authority
CN
China
Prior art keywords
pvc
sleeve pipe
template
supporting block
internal supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620968610.5U
Other languages
Chinese (zh)
Inventor
刘永涛
苑庆涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201620968610.5U priority Critical patent/CN205955208U/en
Application granted granted Critical
Publication of CN205955208U publication Critical patent/CN205955208U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a multi -functional split bolt sleeve pipe belongs to the architectural engineering technology field, include bracer in the template of being made by the cement mortar that excels in, PVC sleeve pipe and rubber packing pad, the bracer is the cuboid in the template, and its lateral wall is provided with the reinforcing bar and places the recess, the center of cuboid is provided with PVC sleeve pipe hole along length direction, the PVC sleeve pipe sets up in PVC tube hole hole, and with bracer zonulae occludens in the template, PVC sheathed tube both ends set up rubber packing pad, the rubber packing pad dimensions equals the dimensions of the interior bracer terminal surface of template, and rubber packing pad central point puts and is provided with the bolt hole, sets up the boss bolt hole hole week, and rubber packing pad passes through the boss block at two tip of PVC sheathed tube. The utility model discloses template internal stay, PVC pipe and protective layer cushion can be substituted simultaneously in the shear wall template construction, the efficiency of construction has been promoted in the time of convenient greatly.

Description

A kind of multi-functional Split bolt sleeve
Technical field
This utility model is related to construction engineering technical field, specifically a kind of multi-functional Split bolt sleeve.
Background technology
Concrete shear wall structure construction when, for ensure shear wall cross section size, generally the template in shear wall both sides it Between template internal stay is set, template internal stay is many to be made using materials such as cement mortar or pea gravel concretens;Meanwhile, it is reduces cost, The split bolt reinforcing non-waterproof shear wall is typically repeated and is used in turn, setting PVC sleeve pipe facilitate concreting after to drawing spiral shell Bolt takes out;And, for ensureing shear force wall reinforcing steel bar protective layer thickness, shear wall construction is respectively provided with cushion block of concrete bar protective layer.
During shear wall site operation, template internal stay, pvc pipe, protective layer cushion block are all to place respectively, and this form of construction work disappears Consumption is artificial in a large number, increased construction workload simultaneously, inefficient.
Content of the invention
Technical assignment of the present utility model is for above weak point, provides a kind of multi-functional Split bolt sleeve, can Alternate template internal stay, pvc pipe and protective layer cushion block, greatly improve efficiency of construction while convenience simultaneously.
This utility model solves its technical problem and be employed technical scheme comprise that:
A kind of multi-functional Split bolt sleeve, including the template internal supporting block being made up of high-strength cement mortar, PVC sleeve pipe and rubber Glue sealing gasket,
Template internal supporting block be cuboid, its side wall be provided with reinforcing bar place groove, described cuboid centrally along length side To being provided with PVC sleeve pipe hole, PVC sleeve pipe hole runs through template internal supporting block;
PVC sleeve pipe is arranged in pvc pipe hole, is closely connected with template internal supporting block, and length is equal to the length of template internal supporting block Degree, the two ends setting rubber gasket of PVC sleeve pipe;
Rubber gasket overall size is equal to the overall size of template internal supporting block end face, and rubber gasket center is arranged There are bolt hole, bolt hole hole week setting boss, described boss external diameter is equal to the internal diameter of PVC sleeve pipe, and rubber gasket passes through boss It is fastened on two ends of PVC sleeve pipe.
Preferably, the section of template internal supporting block is square.
Further, the length of side of square sectional is more than or equal to 30mm, less than or equal to 45mm, according to shear wall's thickness not With the size of design high-strength cement mortar template bracer.
Preferably, template internal supporting block two sides are provided with two reinforcing bars and place groove, and size sets according to steel-bar arrangement Meter, makes full use of its cushion block function.
Further, the reinforcing bar of template internal supporting block two sides is placed groove and is symmetrical arranged.
Preferably, the internal diameter of PVC sleeve pipe is more than or equal to 12mm, less than or equal to 14mm, is designed according to construction requirement.
Compared to the prior art a kind of multi-functional Split bolt sleeve of the present utility model, has the advantages that:
The function of Split bolt sleeve, shear force wall reinforcing steel bar cushion block and template internal stay can be had concurrently, in shear wall coagulation simultaneously Efficiency is greatly promoted in native template construction, only just alternative original right using multi-functional Split bolt sleeve of the present utility model Draw bolt sleeve, shear force wall reinforcing steel bar cushion block and template internal stay;
In construction can the construction of effectively save xoncrete structure shear wall formwork when artificial, accelerating construction progress, effectively Save work, when, this utility model has that reasonable in design, structure is simple, easy to process, has good use value.
Brief description
Fig. 1 is this utility model multi-functional Split bolt sleeve horizontal profile schematic diagram;
Fig. 2 is this utility model multi-functional Split bolt sleeve longitdinal cross-section diagram.
In figure:1st, template internal supporting block, 2, PVC sleeve pipe hole, 3, reinforcing bar place groove, 4, PVC sleeve pipe, 5, rubber seal Pad, 6, boss.
Specific embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
A kind of multi-functional Split bolt sleeve, including the template internal supporting block 1 being made up of high-strength cement mortar, PVC sleeve pipe 4 and Rubber gasket 5,
Template internal supporting block 1 is foursquare cuboid for section, and the length of side of described square sectional is more than or equal to 30mm, Less than or equal to 45mm, different according to shear wall's thickness, the size of design high-strength cement mortar template bracer 1.
Template internal supporting block 1 side wall is provided with reinforcing bar and places groove 3, and template internal supporting block 1 two sides are provided with two reinforcing bars Place groove 3, and the reinforcing bar of two sides is placed groove 3 and is symmetrical arranged, size designs according to steel-bar arrangement, makes full use of its pad Block function.
The center of template internal supporting block 1 is provided with PVC sleeve pipe hole 2 along its length, and PVC sleeve pipe hole 2 runs through in template Bracer 1.PVC sleeve pipe 4 is arranged in pvc pipe hole 2, and outer wall is closely connected with template internal supporting block 1, and the length of PVC sleeve pipe 4 is equal to The length of template internal supporting block 1, the internal diameter of PVC sleeve pipe is more than or equal to 12mm, less than or equal to 14mm, is designed according to construction requirement. The two ends setting rubber gasket 5 of PVC sleeve pipe 4.
Rubber gasket 5 overall size is equal to the overall size of template internal supporting block 1 end face, rubber gasket 5 center It is provided with bolt hole, bolt hole hole week setting boss 6, described boss 6 external diameter is equal to the internal diameter of PVC sleeve pipe 4, rubber gasket 5 It is fastened on two ends of PVC sleeve pipe 4 by boss 6.
During prefabricated processing template internal supporting block 1, PVC sleeve pipe 4 is centrally disposed position, pours into a mould high-strength cement mortar, molding Afterwards, rubber gasket 5 is fastened on two ends of PVC sleeve pipe 4 by boss 6.During use, by the position of template scheme design Lay, and shear force wall reinforcing steel bar is put into reinforcing bar and place in groove 3, to play thickness of protection tier effect;After form removal, by rubber Sealing gasket 5 takes off, and bolt hole closure can be made smooth attractive in appearance.
By specific embodiment above, described those skilled in the art can readily realize this utility model.But It is it should be appreciated that this utility model is not limited to above-mentioned specific embodiment.On the basis of disclosed embodiment, described Those skilled in the art can the different technical characteristic of combination in any, thus realizing different technical schemes.
In addition to technical characteristic described in except description, it is the known technology of those skilled in the art.

Claims (6)

1. a kind of multi-functional Split bolt sleeve is it is characterised in that include template internal supporting block, the PVC being made up of high-strength cement mortar Sleeve pipe and rubber gasket,
Template internal supporting block is cuboid, and its side wall is provided with reinforcing bar and places groove, and the center of described cuboid sets along its length It is equipped with PVC sleeve pipe hole, PVC sleeve pipe hole runs through template internal supporting block;
PVC sleeve pipe is arranged in pvc pipe hole, is closely connected with template internal supporting block, and length is equal to the length of template internal supporting block, The two ends setting rubber gasket of PVC sleeve pipe;
Rubber gasket overall size is equal to the overall size of template internal supporting block end face, and rubber gasket center is provided with spiral shell Keyhole, bolt hole hole week setting boss, described boss external diameter is equal to the internal diameter of PVC sleeve pipe, and rubber gasket is engaged by boss Two ends in PVC sleeve pipe.
2. a kind of multi-functional Split bolt sleeve according to claim 1 is it is characterised in that the section of template internal supporting block is Square.
3. a kind of multi-functional Split bolt sleeve according to claim 2 is it is characterised in that the length of side of square sectional is big In equal to 30mm, less than or equal to 45mm.
4. a kind of multi-functional Split bolt sleeve according to claim 1 or 2 or 3 is it is characterised in that template internal supporting block two Side is provided with two reinforcing bars and places groove.
5. a kind of multi-functional Split bolt sleeve according to claim 4 is it is characterised in that template internal supporting block two sides Reinforcing bar is placed groove and is symmetrical arranged.
6. a kind of multi-functional Split bolt sleeve according to claim 1 it is characterised in that PVC sleeve pipe internal diameter be more than etc. In 12mm, less than or equal to 14mm.
CN201620968610.5U 2016-08-30 2016-08-30 Multi -functional split bolt sleeve pipe Active CN205955208U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620968610.5U CN205955208U (en) 2016-08-30 2016-08-30 Multi -functional split bolt sleeve pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620968610.5U CN205955208U (en) 2016-08-30 2016-08-30 Multi -functional split bolt sleeve pipe

Publications (1)

Publication Number Publication Date
CN205955208U true CN205955208U (en) 2017-02-15

Family

ID=57981167

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620968610.5U Active CN205955208U (en) 2016-08-30 2016-08-30 Multi -functional split bolt sleeve pipe

Country Status (1)

Country Link
CN (1) CN205955208U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944461A (en) * 2019-04-13 2019-06-28 周登楷 A kind of skyscraper coupling beam horizontal hole plugging structure and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944461A (en) * 2019-04-13 2019-06-28 周登楷 A kind of skyscraper coupling beam horizontal hole plugging structure and its construction method

Similar Documents

Publication Publication Date Title
CN104975652B (en) A kind of precast concrete docks attachment structure
CN205955208U (en) Multi -functional split bolt sleeve pipe
CN204691782U (en) A kind of Tunnel Second Lining surface Defects Treatment structure
CN206267179U (en) A kind of flexible cladding soil nail wall protective slope structure
CN205530340U (en) Precast concrete retaining wall block
CN207513190U (en) A kind of wall pouring can
CN204174820U (en) The building block of a kind of constructional column template
CN207920144U (en) A kind of sliding and shock isolation device of no collar tie beam masonry structure
CN203129402U (en) Self-insulating building block
CN204703363U (en) Energy-saving wall heat insulation building block
CN202658765U (en) Keel framework concrete anti-crack filling wall
CN204552128U (en) A kind of novel wall-building machine
CN205046743U (en) Building block of wall crown wedge
CN202658766U (en) Reinforced concrete tying belt structure
CN206916995U (en) A kind of masonry structure of new ribs building block
CN201762890U (en) Positioning strip for steel bar and template of reinforced concrete wall
CN202925541U (en) Concrete wall body pile and protection wall
CN205591415U (en) Non - standard building block
CN204626772U (en) A kind of rapidly-assembled double L-shaped lightweight inner partition wall plate
CN204626973U (en) A kind of sealing up screw for building
CN204825796U (en) Plastics ditch
CN206429129U (en) A kind of windowsill prefabricated component and the antiseep exterior wall windowsill using the prefabricated component
CN206571030U (en) A kind of novel environment friendly density building block brick
CN206941943U (en) A kind of insulation blocks with quick positioning mechanism
CN207048166U (en) A kind of new compact-type building block brick

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant