CN205822125U - The interim breakwater structure of packaged type - Google Patents

The interim breakwater structure of packaged type Download PDF

Info

Publication number
CN205822125U
CN205822125U CN201620498615.6U CN201620498615U CN205822125U CN 205822125 U CN205822125 U CN 205822125U CN 201620498615 U CN201620498615 U CN 201620498615U CN 205822125 U CN205822125 U CN 205822125U
Authority
CN
China
Prior art keywords
steel
type
sitting type
upright
structure framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620498615.6U
Other languages
Chinese (zh)
Inventor
李志云
阚卫明
张晓晗
陈洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN PORT ENGINEERING DESIGN&CONSULTING Co Ltd OF CCCC FIRST HARBOR ENGINEERING Co Ltd
CCCC First Harbor Engineering Co Ltd
Original Assignee
TIANJIN PORT ENGINEERING DESIGN&CONSULTING Co Ltd OF CCCC FIRST HARBOR ENGINEERING Co Ltd
CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN PORT ENGINEERING DESIGN&CONSULTING Co Ltd OF CCCC FIRST HARBOR ENGINEERING Co Ltd, CCCC First Harbor Engineering Co Ltd filed Critical TIANJIN PORT ENGINEERING DESIGN&CONSULTING Co Ltd OF CCCC FIRST HARBOR ENGINEERING Co Ltd
Priority to CN201620498615.6U priority Critical patent/CN205822125U/en
Application granted granted Critical
Publication of CN205822125U publication Critical patent/CN205822125U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Abstract

A kind of interim breakwater structure of packaged type, including the upright steel structure framework of bottom-sitting type, many horizontal plank barricades, many short steel plates, many short steel pipes stakes and air bag;The upright steel structure framework of described bottom-sitting type is made up of base, many vertical supportings and Duo Gen diagonal brace;Described horizontal plank is horizontal is inserted in the upright steel structure framework of bottom-sitting type formation exposed throughout type barricade;Described short steel plate is welded on bottom the upright steel structure framework of bottom-sitting type side by side;What described short steel pipes stake was positioned at bottom-sitting type upright steel structure framework both sides and vertical supporting intersects at welding hole reserved on angle point;Equipped with air bag in the cavity of described bottom-sitting type upright steel structure framework left and right.This utility model, in the sea situation of conventional coastal waters wave height, can effectively reduce the wave impact on offshore engineering, increase construction operation natural law, and structural safety is stable, for ease of maintenaince, can be mass, recycle, reduce construction costs.

Description

The interim breakwater structure of packaged type
Technical field
This utility model is that one relates to civil engineering, building, mining technique field, faces particularly to a kind of packaged type Time breakwater structure.
Background technology
There is more than 1.8 ten thousand kilometer of coastline in China, along with the fast development of China's Coastal Areas urban construction, the maritime affairs in coastal waters Engineering is the most more many, but when being engaged in offshore engineering, wave is the most prominent on the impact of engineering construction, governs the reality of engineering Execute the design with scheme, it is possible to find a kind of moveable anti-ripple measure to screen for job site temporarily, increase construction operation Natural law, shorten the construction period seem particularly significant.
At present interim breakwater many employings floating breakwater, is developed so far, and kind is the most various, is generally divided into three major types: Floating box type breakwater, float-type breakwater, floating raft type breakwater.Dominant structural moieties includes wave absorption buoyancy aid and anchor system, device, profit The principle being concentrated mainly on water body top layer with wave energy carries out energy dissipating.The effect of energy dissipation of floating breakwater is main and W/L (buoyancy aid width Degree/wavelength) and h/d (float/depth of water) be correlated with, therefore for different marine sites, need to be according to the different wave condition in scene Design different floating breakwater physical dimensions.In addition cable and the anchorage of floating breakwater is prone to destroy under the wave action, If cable destroys, buoyancy aid is the most floating, then may endanger boats and ships and offshore structure, and wave absorption buoyancy aid once destroys, and safeguards more Difficulty.The most also minority floating breakwater is had to use steel-pipe pile etc. to be fixed, although the wind that anchor system, device destroys can be avoided Danger, but its foundation cost is higher, and piling pile pulling difficulty is bigger, it is difficult to as temporary structure cycle applications.
Summary of the invention
The purpose of this utility model is the deficiency for existing floating breakwater, it is provided that a kind of for greater coasting area can Portable interim breakwater structure, this structure, in the sea situation of conventional coastal waters wave height, can effectively reduce wave to offshore engineering Impact, increase construction operation natural law, and structural safety is stable, for ease of maintenaince, can be mass, recycle, reduce engineering Cost.
As above conceiving, the technical solution of the utility model is: a kind of interim breakwater structure of packaged type, its feature exists In: include the upright steel structure framework of bottom-sitting type, many horizontal plank barricades, many short steel plates, many short steel pipes stakes and air bag;Institute State the upright steel structure framework of bottom-sitting type to be made up of base, many vertical supportings and Duo Gen diagonal brace;Described horizontal plank is horizontal is inserted in seat Formula upright steel structure framework in the end is formed exposed throughout type barricade;Described short steel plate is welded at the bottom of the upright steel structure framework of bottom-sitting type side by side Portion;Described short steel pipes stake is positioned at the welding hole reserved on angle point that intersects of bottom-sitting type upright steel structure framework both sides and vertical supporting Place;Equipped with air bag in the cavity of described bottom-sitting type upright steel structure framework left and right.
The base of the upright steel structure framework of described bottom-sitting type is made up of channel-section steel 14a, many vertical supportings are by Two bors d's oeuveres I-steel 2.5 meters of compositions of longitudinal pitch are fixed on base, and reserve welding hole with the intersection of base, reserved level between vertical supporting The fixing steel plate that plank barricade inserts, diagonal brace is fixed between longitudinal bracing and base.
It is fixed with under the upright steel structure framework of described bottom-sitting type and does sill plate.
Described short steel plate elongated layout three road, and be welded on bottom the upright steel structure framework of bottom-sitting type.
Towards a diameter of 500mm of steel-pipe pile of wave direction in described short steel pipes stake, a length of 4.2m of stake, longitudinal pitch is 2.5m, The a diameter of 299mm of steel-pipe pile, a length of 2.5m of stake of back of the body wave direction, longitudinal pitch is 2.5m.
Described horizontal plank barricade is by the horizontal fixing steel plate being inserted in the upright steel structure framework of bottom-sitting type of root.
This utility model has such advantages as and good effect:
1, this utility model is a kind of wave trap being applied in coastal ocean engineering, and its structure is light, permissible Row is lifted up into the most mobile, with the sea situation of reply different waters difference wave direction with air bag transportation by driving or ship.
Horizontal plank barricade the most of the present utility model can be with independent assortment in terms of vertical location and width, to adapt to difference Depth of water difference period of wave and the complicated sea situation of different wave height, can effectively reflect or crush wave, and wave dissipation effect is notable.
3. this utility model sits the end in sea bed, it is difficult to floating by wave stroke, can avoid structure because ripple condition surpasss the expectation And the secondary harm that operation boats and ships, offshore structure etc. are caused, and keep in repair more convenient.
4. this utility model is made up of shaped steel and timber, simple in construction, can on-the-spot produce in batches, and single linear meter(lin.m.) cost is low Honest and clean, reusable edible, as constructing, interim anti-ripple measure can be substantially reduced engineering cost, increases effective operation natural law, and shortening is executed The work duration.
5. this utility model uses cancelled structure, it is allowed to water body exchange inside and outside port, environmentally friendly.
Accompanying drawing explanation
Fig. 1 is structure section figure of the present utility model;
Fig. 2 is structural plan of the present utility model figure;
Fig. 3 is structural facades figure of the present utility model.
In figure, 1 is the upright steel structure framework of bottom-sitting type;2 is horizontal plank barricade;3 is short steel plate;4 is short steel pipes stake;5 are Sit sill plate;6 is air bag;7 come unrestrained direction.
Detailed description of the invention
Below in conjunction with the accompanying drawings the interim breakwater structure of packaged type of utility model is illustrated.
Case study on implementation:
Under mean depth 4.5m, the sea situation of wave height 1.5m, as shown in Figure 1, 2, 3: a kind of interim breakwater of packaged type Structure, including the upright steel structure framework of bottom-sitting type 1, horizontal plank barricade 2, short steel plate 3, short steel pipes stake 4, sits sill plate 5, air bag 6.The upright steel structure framework of described bottom-sitting type is made up of base, many vertical supportings and Duo Gen diagonal brace.Described horizontal plank Barricade is horizontal to be inserted in the upright steel structure framework of bottom-sitting type formation exposed throughout type barricade and carries out disappearing wave, to reduce the transmitted wave at dike rear Height, horizontal plank barricade can the most freely position, to adapt to different water depth difference period of wave and different wave height Complicated sea situation.Described short steel plate is welded on bottom the upright steel structure framework of bottom-sitting type side by side, to strengthen it at severe sea condition Under holistic arrestment slippage stabilization.Described short steel pipes stake is positioned at the both sides of the upright steel structure framework of bottom-sitting type and the friendship of vertical supporting At welding hole reserved on fork angle point, set, to strengthen its entirety under severe sea condition after steel structure framework positions Stability against overturning.Under the conditions of sea situation is preferable, the air bag described in the cavity of steel structure framework left and right can be inflated, exit, and enters The flexible transportation by driving of row and location.The described sill plate that does is fixed under the upright steel structure framework of bottom-sitting type, to strengthen its integrated carrying Ability.
Further, described bottom-sitting type upright steel structure framework 1 base is made up of channel-section steel 14a, width 10 meters, single structure 7.5 linear meter(lin.m.)s are long, reserved welding hole 510mm on both sides intersect angle point.Vertical supporting is by Two bors d's oeuveres I-steel 32a longitudinal pitch 2.5 Meter Zu Cheng, long 6m, the fixing steel plate of reserved fender beam between I-steel.Diagonal brace is made up of channel-section steel 14, longitudinal pitch 2.5m.
Further, described short steel plate 3, a length of 1.9m of plate, thickness is 10mm, elongated layout three road, is welded on described The upright steel structure framework of bottom-sitting type, can rely on overall deadweight to insert soft soil foundation.
Further, the upright steel structure framework of bottom-sitting type 1 and short steel plate 3 are pre-erection, integral prefabricated part list linear meter(lin.m.) Weight 1.34t, can preferably can use ship to lift up into row location with air bag transportation by driving.
Further, described horizontal plank barricade 2 is by the horizontal location steel being inserted in the upright steel structure framework of bottom-sitting type 1 of root On plate, its location has gap, and overall air permeability rate is 25%, can effectively reflect or crush wave energy dissipating, and can reduce wave Horizontal force to structure.
Further, described short steel pipes stake 4 sets, wherein towards wave direction behind described steel structure framework 1 location The a diameter of 500mm of steel-pipe pile, a length of 4.2m of stake, longitudinal pitch is 2.5m, and a diameter of 299mm of steel-pipe pile of back of the body wave direction, stake is a length of 2.5m, longitudinal pitch is 2.5m, and simple boat machine equipment can be used to plug flexibly.
Further, when sea situation is relatively good, preferably can carry out transportation by driving with air bag 6, the volume of unilateral air bag is 5.02m3
Further, when sea bed geology is poor, level paving can insert between the channel-section steel under the upright steel structure framework of bottom-sitting type 1 20mm thickness does sill plate 5, to strengthen its integrated carrying ability.
Using method of the present utility model: making the upright steel structure framework of prefabrication bottom-sitting type 1 and short steel plate 3, and It is transported to scene, survey engineering marine site ripple condition and the depth of water, assembles horizontal plank barricade 2 the most as required and sit sill plate 5, Use air bag 6 transportation by driving to main wave direction upstream position, need the temporary wave direction of shielding to carry out positioning sinking according to construction.Finally In preformed hole, squeeze into short steel pipes stake 4, install.
Although preferred structure size of the present utility model being described above in conjunction with accompanying drawing, but this utility model being also Difference is limited to above-mentioned physical dimension, and those of ordinary skill in the art is under enlightenment of the present utility model, without departing from book In the case of utility model objective and scope of the claimed protection, it is also possible to make a lot of form, these belong to this practicality Within novel protection domain.

Claims (6)

1. the interim breakwater structure of packaged type, it is characterised in that: include the upright steel structure framework of bottom-sitting type, many levels Plank barricade, many short steel plates, many short steel pipes stakes and air bag;The upright steel structure framework of described bottom-sitting type by base, many erect To supporting and many diagonal brace compositions;Described horizontal plank is horizontal is inserted in the upright steel structure framework of bottom-sitting type formation exposed throughout type barricade; Described short steel plate is welded on bottom the upright steel structure framework of bottom-sitting type side by side;Described short steel pipes stake is positioned at the upright steel construction of bottom-sitting type Skeleton both sides and vertical supporting intersect at welding hole reserved on angle point;Described bottom-sitting type upright steel structure framework left and right cavity In equipped with air bag.
The interim breakwater structure of packaged type the most according to claim 1, it is characterised in that: the upright steel of described bottom-sitting type is tied The base of llex cornuta frame is made up of channel-section steel 14a, many vertical supportings are made up of Two bors d's oeuveres I-steel longitudinal pitch 2.5 meters and are fixed in base On, and reserve welding hole with the intersection of base, and the fixing steel plate that between vertical supporting, reserved horizontal plank barricade inserts, diagonal brace It is fixed between longitudinal bracing and base.
The interim breakwater structure of packaged type the most according to claim 1, it is characterised in that: the upright steel of described bottom-sitting type is tied It is fixed with under llex cornuta frame and does sill plate.
The interim breakwater structure of packaged type the most according to claim 1, it is characterised in that: the described elongated layout of short steel plate Three roads, and be welded on bottom the upright steel structure framework of bottom-sitting type.
The interim breakwater structure of packaged type the most according to claim 1, it is characterised in that: court in described short steel pipes stake The a diameter of 500mm of steel-pipe pile of wave direction, a length of 4.2m of stake, longitudinal pitch is 2.5m, a diameter of 299mm of steel-pipe pile of back of the body wave direction, The a length of 2.5m of stake, longitudinal pitch is 2.5m.
The interim breakwater structure of packaged type the most according to claim 1 and 2, it is characterised in that: described horizontal plank keeps off Wall is by the horizontal fixing steel plate being inserted in the upright steel structure framework of bottom-sitting type of root.
CN201620498615.6U 2016-05-27 2016-05-27 The interim breakwater structure of packaged type Expired - Fee Related CN205822125U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620498615.6U CN205822125U (en) 2016-05-27 2016-05-27 The interim breakwater structure of packaged type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620498615.6U CN205822125U (en) 2016-05-27 2016-05-27 The interim breakwater structure of packaged type

Publications (1)

Publication Number Publication Date
CN205822125U true CN205822125U (en) 2016-12-21

Family

ID=57558088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620498615.6U Expired - Fee Related CN205822125U (en) 2016-05-27 2016-05-27 The interim breakwater structure of packaged type

Country Status (1)

Country Link
CN (1) CN205822125U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106400734A (en) * 2016-05-27 2017-02-15 中交第航务工程局有限公司 Movable temporary breakwater structure
CN111877178A (en) * 2020-08-04 2020-11-03 广西路建工程集团有限公司 Overwater translation device for steel pipe pile in limited space and application method of device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106400734A (en) * 2016-05-27 2017-02-15 中交第航务工程局有限公司 Movable temporary breakwater structure
CN111877178A (en) * 2020-08-04 2020-11-03 广西路建工程集团有限公司 Overwater translation device for steel pipe pile in limited space and application method of device
CN111877178B (en) * 2020-08-04 2021-11-16 广西路建工程集团有限公司 Overwater translation device for steel pipe pile in limited space and application method of device

Similar Documents

Publication Publication Date Title
US11448193B2 (en) Self-aligning to wind facing floating platform supporting multi-wind turbines and solar for wind and solar power generation and the construction method thereon
ES2952964T3 (en) Maritime structure for the foundation of buildings and its installation method
EP2837554A1 (en) Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method
CN101886374B (en) Groove bottom-reinforced fully lined debris flow drainage groove and construction method thereof
CN111502725B (en) Artificial island type middle well structure of submarine tunneling tunnel
CN107700366B (en) Deep water high-block bridge degree the bridge construction naked rock river bed trestle of hard stone and construction method
CN102182203B (en) A kind of steel row's formula anemometer tower foundation and anemometer tower structure
CN102162256A (en) Maritime foundation base
CN103362113A (en) Local buoyancy ocean platform of offshore wind power, bridge and ocean structure, and construction method
CN205822125U (en) The interim breakwater structure of packaged type
CN105350526A (en) Method for setting up steel platform
CN102926350A (en) Floating transport and towing dock module and construction method thereof
CN106400734A (en) Movable temporary breakwater structure
JP2005180239A (en) Foundation of water surface wind power generation device
CN201305840Y (en) Flexible anti-collision device for underwater tower foundation
WO2016042173A1 (en) Gravity foundation for the installation of offshore wind turbines and meteorological towers
CN109423982A (en) From the interim breakwater structure of steady floating type
CN104746421A (en) Anti-collision facility for bridge pier
CN216515566U (en) Tension type single-point mooring combined anchorage structure based on spiral anchor
CN106677121B (en) Protect the movable permeable spur structure and construction method of Coastal erosion
JP2012127097A (en) Construction method of transmission type sea area control structure
CN105735196B (en) A kind of frame bucket dock structure and its manufacturing method
CN212358208U (en) High pile cap wharf revetment structure
CN209958290U (en) Take shore protection structure of pile foundation
CN204875664U (en) A retaining wall structure for interim pier in bay

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161221

CF01 Termination of patent right due to non-payment of annual fee