CN205804275U - Slope, comb inland river passenger wharf - Google Patents

Slope, comb inland river passenger wharf Download PDF

Info

Publication number
CN205804275U
CN205804275U CN201620539068.1U CN201620539068U CN205804275U CN 205804275 U CN205804275 U CN 205804275U CN 201620539068 U CN201620539068 U CN 201620539068U CN 205804275 U CN205804275 U CN 205804275U
Authority
CN
China
Prior art keywords
ramp
platform
main
slope
comb
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620539068.1U
Other languages
Chinese (zh)
Inventor
刘小强
王晋
谢长文
刘赛龙
杨新才
罗健
邓伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Consultants Co Ltd
Original Assignee
CCCC Second Harbor Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Consultants Co Ltd filed Critical CCCC Second Harbor Consultants Co Ltd
Priority to CN201620539068.1U priority Critical patent/CN205804275U/en
Application granted granted Critical
Publication of CN205804275U publication Critical patent/CN205804275U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

This utility model relates to a kind of slope, comb inland river passenger wharf, including main ramp and secondary ramp, described main ramp side near water is provided with two or more secondary ramp, main ramp includes that main ramp platform and the spaced main ramp being arranged between main ramp platform are marked time, the bottom that main ramp is marked time is positioned at same elevation with the main ramp platform connected, described secondary ramp includes the secondary ramp bottom platform being positioned at bottom and the secondary ramp tip platform being positioned at top, it is provided with secondary ramp between secondary ramp bottom platform and secondary ramp tip platform to mark time, the elevation of the rear stage pair ramp bottom platform in described two adjacent secondary ramps is identical with the elevation of previous stage pair ramp tip platform.This utility model is owing to arranging secondary ramp in the passenger wharf of slope, comb inland river, in river, landform steep hills district, adaptability is higher, can reduce waters embankment or pile foundation engineering amount, reduce difficulty of construction, cost saving.

Description

Slope, comb inland river passenger wharf
Technical field
This utility model relates to slope passenger wharf, more particularly, it relates to a kind of slope, comb inland river passenger wharf.
Background technology
Slope, inland river passenger wharf, its alongside section ramp is generally divided into two kinds in " one " font, arrangement, Yi Zhongshi Ramp axis direction is substantially vertical with water (flow) direction, landing stage by springboard be overlapped on ramp domatic on, and along with design water Position change and move up and down along ramp axis;Another kind is that ramp axis direction is arranged along riverbank substantially, ramp On multi-stage platform is set, landing stage is overlapped on platform by Long Span Steel Bridge, along with SEA LEVEL VARIATION, need to be hung by hoisting facilities Play steel drawn bridge, be then overlapped on other platform.
The region, inland river narrower for waters, landform is precipitous and range of stage is bigger, when using, ramp axis is the most vertical During the slope passenger wharf that straight water (flow) direction is arranged, it is more that ramp extends vertically into river water area, causes water areas project amount relatively big, Add difficulty of construction and construction investment;It addition, when middle low water level alongside operation, boats and ships will take bigger water surface area, Adaptability is poor.When the slope passenger wharf using ramp axis direction substantially to arrange along riverbank, owing to classification arranges flat Platform, landing stage need to be overlapped with ramp platform by Long Span Steel Bridge, landing stage needs arrange bigger hoisting facilities, and this was both Add construction investment, be unfavorable for again the alongside operation of reality.
Utility model content
The technical problems to be solved in the utility model is, it is provided that one adapts to various different water level, reduces waters work Cheng Liang, can reduce again steel drawn bridge span and hoisting facilities scale, reduces slope, the comb inland river passenger wharf of construction investment.
This utility model solves its technical problem and be the technical scheme is that a kind of comb inland river slope passenger traffic of structure Harbour, including main ramp and secondary ramp, described main ramp side near water is provided with two or more secondary ramp, Main ramp includes that main ramp platform and the spaced main ramp being arranged between main ramp platform are marked time, main slope The bottom marked time in road is positioned at same elevation with the main ramp platform connected, and described secondary ramp includes the secondary slope being positioned at bottom Bottom, road platform and the secondary ramp tip platform being positioned at top, between secondary ramp bottom platform and secondary ramp tip platform Being provided with secondary ramp to mark time, the elevation of the rear stage pair ramp bottom platform in described two adjacent secondary ramps is with front The elevation of one-level pair ramp tip platform is identical, the secondary ramp tip platform of each rank and the main ramp platform connected It is positioned at same elevation.
By such scheme, described main ramp is cast-in-place concrete structure.
By such scheme, described secondary ramp is cast-in-place concrete structure.
Implement slope, comb inland river of the present utility model passenger wharf, have the advantages that
1, slope, the conventional inland river passenger wharf owing to being arranged in " one " font by Transverse to the flow direction changes to main slope Road and secondary ramp knockdown " comb " harbour, secondary ramp out reach is shorter, to river water when reducing ship berthing Taking of territory, it is to avoid impact on navigation safety during alongside operation;
2, owing to slope, the conventional inland river passenger wharf that axis is arranged in " one " font along bank substantially is changed to main slope Road and secondary ramp knockdown " comb " harbour, both adapted to various different SEA LEVEL VARIATION, reduced again steel drawn bridge span and wholesale Hoisting facilities scale on ship;
3, shorter, in river, landform steep hills district due to ramp out reach secondary in the passenger wharf of slope, comb inland river Middle adaptability is higher, can reduce waters embankment or pile foundation engineering amount, reduce difficulty of construction, cost saving;
4, it is provided with a plurality of extending type pair ramp due to passenger wharf main ramp side near water, slope, comb inland river, can expire The alongside operation of boats and ships during foot different water level, actually used in flexible, practical.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the utility model is described in further detail, in accompanying drawing:
Fig. 1 is the planar structure schematic diagram of slope, this utility model comb inland river passenger wharf;
Fig. 2 is slope, this utility model comb inland river passenger wharf cross section A-A schematic diagram;
Fig. 3 is slope, this utility model comb inland river passenger wharf section B-B schematic diagram.
Detailed description of the invention
In order to be more clearly understood from technical characteristic of the present utility model, purpose and effect, now comparison accompanying drawing is detailed Detailed description of the invention of the present utility model is described.
As shown in Figure 1-Figure 3, slope, comb inland river of the present utility model passenger wharf includes main ramp 1 and secondary ramp 2。
Main ramp 1 is cast-in-place concrete structure, and side is provided with two or more secondary ramp, this enforcement near water Example is provided with five secondary ramps.Main ramp 1 includes that main ramp platform 101 and main ramp mark time 102, main ramp Mark time being arranged between main ramp platform 101 of 102 intervals, main ramp mark time 102 bottom and the main ramp connected Platform 101 is positioned at same elevation.
Secondary ramp 2 is cast-in-place concrete structure.Secondary ramp 2 includes secondary ramp bottom platform 201 and secondary ramp Tip platform 203.Secondary ramp bottom platform 201 is positioned at bottom, and secondary ramp tip platform 203 is positioned at top, secondary ramp It is provided with secondary ramp between bottom platform 201 and secondary ramp tip platform 203 and marks time 202.Two adjacent secondary ramps In, the elevation of the secondary ramp bottom platform 201-1 of the second level and the elevation phase of the secondary ramp tip platform 203 of the first order With.
The secondary ramp tip platform 203 of each rank connects with the main ramp platform 101 of corresponding level, and is positioned at same One elevation.Main ramp 1 axis smoothes out layout substantially along water (flow) direction 11, and arrange in main ramp 1 side near water is a plurality of overhanging Formula pair ramp 2, forms " comb " shape, and when being available in different water level, springboard 8 is set up on landing stage 9, it is possible to be arranged to steel drawn bridge.
When low water level, boats and ships 10 alongside is on landing stage 9, and landing stage 9, by springboard 8, is overlapped on secondary ramp bottom platform On 201, passenger passes through landing stage 9 and springboard 8, marks time on 202 arrival main ramps 1 through secondary ramp, marks time 102 through main ramp Towards back-up land or vice versa.When water level rises, landing stage 9 and springboard 8 mark time 202 gradually toward main ramp 1 along secondary ramp Direction is moved, and springboard 8 can be overlapped on mark time on 202 according to water level feature, until main ramp platform 101 will be submerged, moves Dynamic landing stage 9 and the position of springboard 8, be overlapped on springboard 8 on the secondary ramp bottom platform 201-1 of the second level.
Platform on secondary ramps at different levels and the overlap joint of springboard 8 when supplying different water level of marking time, operating type is with above-mentioned Identical.Secondary ramp 2 out reach and platform height and springboard 8 length, the water-head adapted to are relevant, after specifically need to being computed Determine.Bar number, out reach and the shape of secondary ramp is only a kind of form of expression, and this utility model is not made any shape Restriction in formula.
Above in conjunction with accompanying drawing, embodiment of the present utility model is described, but on this utility model is not limited to The detailed description of the invention stated, above-mentioned detailed description of the invention is only schematic rather than restrictive, this area common Technical staff is under enlightenment of the present utility model, without departing from this utility model objective and scope of the claimed protection situation Under, it may also be made that a lot of form, within these belong to protection of the present utility model.

Claims (3)

1. slope, comb inland river passenger wharf, it is characterised in that include main ramp and secondary ramp, described main ramp Side is provided with two or more secondary ramp near water, and main ramp includes that main ramp platform is arranged on spaced Main ramp between main ramp platform is marked time, and the bottom that main ramp is marked time is positioned at same with the main ramp platform connected Elevation, described secondary ramp includes being positioned at the secondary ramp bottom platform of bottom and being positioned at the secondary ramp tip platform on top, It is provided with secondary ramp between secondary ramp bottom platform and secondary ramp tip platform to mark time, described two adjacent secondary slopes The elevation of the rear stage pair ramp bottom platform in road is identical with the elevation of previous stage pair ramp tip platform, each rank Secondary ramp tip platform be positioned at same elevation with the main ramp platform connected.
Slope, comb inland river the most according to claim 1 passenger wharf, it is characterised in that described main ramp is cast-in-place mixed Xtah Crude Clay structure.
Slope, comb inland river the most according to claim 1 passenger wharf, it is characterised in that described secondary ramp is cast-in-place mixed Xtah Crude Clay structure.
CN201620539068.1U 2016-06-03 2016-06-03 Slope, comb inland river passenger wharf Expired - Fee Related CN205804275U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620539068.1U CN205804275U (en) 2016-06-03 2016-06-03 Slope, comb inland river passenger wharf

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620539068.1U CN205804275U (en) 2016-06-03 2016-06-03 Slope, comb inland river passenger wharf

Publications (1)

Publication Number Publication Date
CN205804275U true CN205804275U (en) 2016-12-14

Family

ID=57501935

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620539068.1U Expired - Fee Related CN205804275U (en) 2016-06-03 2016-06-03 Slope, comb inland river passenger wharf

Country Status (1)

Country Link
CN (1) CN205804275U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108203963A (en) * 2017-11-28 2018-06-26 中交天津港航勘察设计研究院有限公司 A kind of novel inclined formula passenger wharf

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108203963A (en) * 2017-11-28 2018-06-26 中交天津港航勘察设计研究院有限公司 A kind of novel inclined formula passenger wharf

Similar Documents

Publication Publication Date Title
CN107524114B (en) A kind of staged pontoon bridge for heavy grade inclined wharf and floating wharf
CN104210627B (en) Build the device and method of lower water for jack-up unit level land
CN102433858A (en) Wave dissipation structure suitable for sloping sea dikes
CN105672197A (en) Method for heightening and reinforcing embankment and structure
CN204703119U (en) A kind ofly be provided with single high pile pier structure of going along with sb. to guard him sheet pile
CN205804275U (en) Slope, comb inland river passenger wharf
CN103806407A (en) Pile-bucket integrated wharf structure and construction method thereof
CN205501850U (en) Culvert structure with retaining wall combination
CN202899083U (en) Pile-bucket combined wharf structure
CN205822123U (en) 20 ton deep water sheet pile quay wall structure
CN109235221A (en) A kind of subterranean tunnel through bridge structure
CN204626330U (en) A kind of combined type frontier defense bank structure
CN110004873A (en) Water conservancy diversion breakwater based on piling strtucture
CN212358208U (en) High pile cap wharf revetment structure
CN205501926U (en) Add solid embankment structure of high pressure heater
CN106498977A (en) Outrigger formula retaining wall structure
CN108677980A (en) Upstream cofferdam heightening method and structure with traffic function
CN209082432U (en) A kind of efficient wave absorption structure applied in navigable tunnel
CN212580085U (en) Self-stabilizing deepwater navigation mark
CN204185819U (en) Honeycomb dykes and dams shore protection component
CN205421307U (en) Novel low stake bearing platform structure of empty formula type of falling pi is passed through in inland river
CN209891035U (en) Underground tunnel passes through bridge structures
CN203096686U (en) Novel composite structure combining long piled wharf and shore-connecting structure
CN204452814U (en) A kind of landing stage mooring unitized construction
CN206655180U (en) A kind of piled estabilishing revetment structure suitable for lock approach

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161214