A kind of tower crane balance weight erecting device Download PDFInfo
- Publication number
- CN205772970U CN205772970U CN201620663413.2U CN201620663413U CN205772970U CN 205772970 U CN205772970 U CN 205772970U CN 201620663413 U CN201620663413 U CN 201620663413U CN 205772970 U CN205772970 U CN 205772970U
- Authority
- CN
- China
- Prior art keywords
- balance weight
- support plate
- pin
- oblique support
- tower crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
This utility model belongs to tower crane balance weight fixing device technical field, specifically a kind of tower crane balance weight erecting device, including crossbeam, main chord, pin and web member, one end of crossbeam is 90 ° with main chord and welds, the other end is by otic placode and installs bearing pin connection pin, described crossbeam is that two channel-section steels that are opposing and that be welded by batten plate are constituted, the slot for installing balance weight is left between two channel-section steels, on the channel-section steel of slot both sides symmetrical and be welded with multipair oblique support plate evenly and at intervals, the otic placode of every piece of balance weight is through slot and hang on load-bearing bearing pin, load-bearing bearing pin is held on a pair oblique support plate, and the both sides of load-bearing bearing pin are respectively provided with for being stuck in the groove on oblique support plate.This utility model simple in construction, be easily maintained, widely applicable.
Description
Technical field
This utility model belongs to tower crane balance weight fixing device technical field, and specifically a kind of tower crane balance weight installs dress
Put.
Background technology
The balance weight of large-scale tower crane generally uses bearing pin to be arranged on tower crane counterweight support, when balance weight is installed, and first will be flat
Weight hangs in the slot of counterweight rack beam from the bottom to top, and the lug plate holes on balance weight both sides respectively through a bearing pin, is shelved on
On crossbeam in corresponding channel bar, then by balance weight draw lever locking, multiple balance weights are connected into an entirety.This company
Connect mode structure complexity, operation inconvenience, it is often more important that balance weight has certain foozle in casting process so that balance
Leave certain gap when focusing on installation each other, cause tower crane balance weight when normal work to be rocked before and after bearing pin, phase
Mutual friction is collided and produces chip, the most fragile balance weight, also leaves hidden danger to safety in production.
Summary of the invention
The purpose of this utility model is to overcome above-mentioned deficiency, it is provided that a kind of tower crane balance weight erecting device, its structure letter
Single, be easily maintained, widely applicable.
For realizing above-mentioned technical purpose, the scheme that this utility model provides is: a kind of tower crane balance weight erecting device, including
Crossbeam, main chord, pin and web member, one end of crossbeam is 90 ° with main chord and welds, and the other end is by otic placode and installs bearing pin even
Connecing pin, described crossbeam is that two channel-section steels that are opposing and that be welded by batten plate are constituted, and leaves for pacifying between two channel-section steels
The slot of dress balance weight, symmetrical and be welded with multipair oblique support plate, every piece of balance weight evenly and at intervals on the channel-section steel of slot both sides
Otic placode through slot hanging on load-bearing bearing pin, load-bearing bearing pin is held on a pair oblique support plate, and load-bearing bearing pin
Both sides are respectively provided with for being stuck in the groove on oblique support plate.
And, the inclination angle of inclined plane of described oblique support plate is not more than 15 °.
And, near spacing between oblique support plate and pin described in a pair of pin no less than 100mm, and this
Tail end to oblique support plate is higher than other oblique support plate.
The beneficial effects of the utility model are: use oblique support plate to replace channel bar, due to balance weight self gravitation
Effect, polylith balance weight is mutually extruded from being integrated after installing, thus solves to rock when existing balance weight is installed to ask with collision
Topic, it also avoid the hidden danger leaving safety in production.It addition, carry out solid without increasing balance weight pull bar when this tower crane balance weight is installed
Fixed, also reduce production cost and the installation difficulty of weight-balancing device.
Accompanying drawing explanation
Fig. 1 is the main TV structure schematic diagram of tower crane balance weight erecting device.
Fig. 2 is the side-looking structural representation of tower crane balance weight erecting device.
Fig. 3 is the plan structure schematic diagram of tower crane balance weight erecting device.
Fig. 4 is the schematic diagram that tower crane balance weight installs bearing pin.
Wherein, 1, crossbeam, 2, main chord, 3, pin, 4, web member, 5, oblique support plate, 6, load-bearing bearing pin, 6.1, groove,
7, balance weight.
Detailed description of the invention
Below in conjunction with the accompanying drawings and embodiment the utility model is described in further detail.
The present embodiment provides a kind of tower crane balance weight erecting device, as shown in Fig. 1 ~ Fig. 3, including crossbeam 1, main chord 2, gear
Bar 3 and web member, one end of crossbeam 1 welds in 90 ° with main chord 2, and the other end is by otic placode and installs bearing pin and connects pin 3.Main
Many straight, diagonal web members 4 are welded between chord member 2.
Described crossbeam 1 is that two channel-section steels that are opposing and that be welded by batten plate are constituted, leave between two channel-section steels for
The slot of balance weight 7 is installed.
On the channel-section steel of slot both sides symmetrical and be welded with multipair oblique support plate 5 evenly and at intervals, oblique support plate 5 is right angle
Triangle, angle is unsuitable excessive, generally less than 15 °.Spacing between a pair oblique support plate 4 and the pin 3 of pin 3
No less than 100mm, its objective is that the production error for balance weight 7 leaves move place, prevent balance weight 7 because there being production by mistake
Difference and fill situation about unmatching.And the tail end of this pair oblique support plate 4 is higher than other oblique support plate 4, prevents balance weight 7
Slip.
The otic placode of every piece of balance weight 7 through slot hanging on load-bearing bearing pin 6, load-bearing bearing pin 6 be held on a pair oblique
On support plate 4, and the both sides of load-bearing bearing pin 6 are respectively provided with for being stuck in the groove 6.1 on oblique support plate 4, as shown in Figure 4, anti-
Only load-bearing bearing pin 6 axial float.
After this programme assembles, balance weight 7 is under the effect of self gravitation, the most crowded along the inclined-plane of oblique support plate 5
Tightly become an entirety, it is to avoid leaving gap between existing balance weight 7, work is rocked time around, mutual frictional impact also produces
Raw chip, the problem leaving hidden danger to safety in production.It addition, carry out without increasing balance weight pull bar when this tower crane balance weight is installed
Fixing, also reduce the production cost of balance weight erecting device.
The above is only preferred implementation of the present utility model, it is noted that for the common skill of the art
For art personnel, on the premise of without departing from this utility model principle, it is also possible to make some improvement or deformation, these improve or
Deformation also should be regarded as protection domain of the present utility model.
Claims (3)
1. a tower crane balance weight erecting device, including crossbeam, main chord, pin and web member, one end of crossbeam and main chord in
90 ° of welding, the other end is by otic placode and installs bearing pin and connects pin, it is characterised in that: described crossbeam be two opposing and pass through
The channel-section steel that batten plate is welded is constituted, and leaves the slot for installing balance weight, on the channel-section steel of slot both sides between two channel-section steels
Symmetrical and be welded with multipair oblique support plate evenly and at intervals, the otic placode of every piece of balance weight is through slot and hang on load-bearing bearing pin
On, load-bearing bearing pin is held on a pair oblique support plate, and the both sides of load-bearing bearing pin are respectively provided with for being stuck in oblique support plate
Groove.
A kind of tower crane balance weight erecting device the most according to claim 1, it is characterised in that: described oblique support plate oblique
Inclination angle, face is not more than 15 °.
A kind of tower crane balance weight erecting device the most according to claim 1, it is characterised in that: near a pair institute of pin
State the spacing between oblique support plate and pin and be no less than 100mm, and the tail end of this pair oblique support plate is oblique higher than other
Shape support plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620663413.2U CN205772970U (en) | 2016-06-29 | 2016-06-29 | A kind of tower crane balance weight erecting device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620663413.2U CN205772970U (en) | 2016-06-29 | 2016-06-29 | A kind of tower crane balance weight erecting device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205772970U true CN205772970U (en) | 2016-12-07 |
Family
ID=58128273
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620663413.2U Active CN205772970U (en) | 2016-06-29 | 2016-06-29 | A kind of tower crane balance weight erecting device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205772970U (en) |
-
2016
- 2016-06-29 CN CN201620663413.2U patent/CN205772970U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203474220U (en) | Spreader system for overturning and hoisting large diameter overweight sealing head | |
CN104088227A (en) | Rear pull rod | |
CN105220776A (en) | A kind of H profile steel beam bidirectional sliding support node with bidirectionally limited function | |
CN103663302B (en) | L-type portal installation frame | |
CN203173749U (en) | Assembled integral type vertical self-jacking device of hydraulic double-type crane tower | |
CN205772970U (en) | A kind of tower crane balance weight erecting device | |
CN204211323U (en) | A kind of counterweight with compensated chain guide piece | |
CN203715054U (en) | 3,000t combinable lifting balance beam | |
CN202658867U (en) | Overhanging construction platform | |
CN202031342U (en) | Edge protective railing | |
CN204435823U (en) | A kind of anti-drop device for scaffold | |
CN202899527U (en) | Quick decoration material dry-hanging and mounting base layer structure | |
CN205088798U (en) | Two -way sliding support node of H shaped steel roof beam with two -way limit function | |
CN202595964U (en) | Glass support block for frame-hidden curtain wall | |
CN203513048U (en) | Light assembling type counter-weight device | |
CN102230312A (en) | Cable-stayed cradle cambered head | |
CN202577688U (en) | Articulated cross beam-free metal plate curtain wall | |
CN204356973U (en) | Two Snap-type keel overhung construction | |
CN204940119U (en) | Bridge rhombus false work | |
CN105731239B (en) | The device that hanging device is shelved | |
CN203654536U (en) | Installation fixture connecting piece of full glass curtain wall large-size glass panel | |
CN204780637U (en) | Novel rhombus false work | |
CN208718102U (en) | A kind of anti-skidding crossbeam connector | |
CN204311354U (en) | Hanger box | |
CN204964114U (en) | Back lift -over device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |