CN203474220U - Spreader system for overturning and hoisting large diameter overweight sealing head - Google Patents

Spreader system for overturning and hoisting large diameter overweight sealing head Download PDF

Info

Publication number
CN203474220U
CN203474220U CN201320583810.5U CN201320583810U CN203474220U CN 203474220 U CN203474220 U CN 203474220U CN 201320583810 U CN201320583810 U CN 201320583810U CN 203474220 U CN203474220 U CN 203474220U
Authority
CN
China
Prior art keywords
end socket
main
lower edge
wire rope
slipping tail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201320583810.5U
Other languages
Chinese (zh)
Inventor
葛庆栋
贾桂军
郑浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Engineering Group Co Ltd
Sinopec Nanjing Engineering Co Ltd
Sinopec Heavy Lifting Transporting Engineering Co Ltd
Original Assignee
Sinopec Engineering Group Co Ltd
Sinopec Nanjing Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Engineering Group Co Ltd, Sinopec Nanjing Engineering Co Ltd filed Critical Sinopec Engineering Group Co Ltd
Priority to CN201320583810.5U priority Critical patent/CN203474220U/en
Application granted granted Critical
Publication of CN203474220U publication Critical patent/CN203474220U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Abstract

The utility model discloses a spreader system for overturning and hoisting a large diameter overweight sealing head. The spreader system comprises a main steel wire rope (4), an equalizing beam (5) and an auxiliary wire rope (6) and is characterized in that the main steel wire rope (4) is respectively connected with the upper parts of two ends of the equalizing beam (5), the lower parts of two ends of the equalizing beam (5) are respectively connected with two main lifting lugs (2) arranged on the outer wall of a sealing head (1) by virtue of the main steel wire rope (4), the lower end of the auxiliary wire rope (6) is connected with at least one tail dragging lifting lug (3) arranged on the sealing head (1) by virtue of a connecting shackle (7), and the midperpendicular of a circle enclosed by the lower edge of the sealing head (1) penetrates through a plane formed by the two main lifting lugs (2) and the tail dragging lifting lug (3). With the adoption of the spreader system, the sealing head can carry out self-balancing overturning with unequal moments under the action of self gravity, and the overturning process is smooth and safe. The spreader system has a simple structure, is convenient to use, is low in cost and is suitable for popularizing and using.

Description

A kind of sling system for the overweight end socket upset of major diameter lifting
Technical field
The utility model relates to hoisting technology field, relates in particular to the upset hoisting technology field of the overweight end socket of a kind of major diameter; The sling system for the overweight end socket upset of major diameter lifting that specifically a kind of self-balancing is overturn and process is steady, safe.
Background technology
In main equipment installation process, in order to meet group to construction process requirements such as, linings, the end socket of main equipment need to carry out repeatedly 180 ° of unsettled upset operations, and upset weight can reach more than 200 tons when maximum.At present, the upset operation of the overweight end socket of domestic major diameter mainly contains two kinds of methods.The one, at end socket outside face, be symmetrical arranged two groups of plate hole formula hangers, end socket inside is connected into a meter word bracing reinforcement with steel pipe welding, utilize two cranes to complete upset operation, its shortcoming is that hanger place local stress in switching process, whole amount of deflection are larger, and apparatus body and inner lining quality are affected greatly; The 2nd, above end socket center of gravity, be symmetrical arranged one group of tube shaft type lifting lug, vertical line direction arranges one group of board-like hanger, end socket inside is connected into a meter word bracing reinforcement with steel pipe welding, utilize two cranes to complete upset operation, shortcoming is that switching process very easily causes end socket centre-of gravity shift, there is sudden tumbling in the object that makes to overturn, produces impact load, and the overload of machine rigging is even caused the accident.
Summary of the invention
The purpose of this utility model is the problem existing for prior art, provides a kind of self-balancing upset and process steady, the safe sling system for the overweight end socket upset of major diameter lifting.
The purpose of this utility model solves by the following technical programs:
A kind of sling system for the overweight end socket upset of major diameter lifting, comprise main rope, main equalizing bar and auxiliary steel wire rope, it is characterized in that described main rope is connected with the top, two ends of main equalizing bar respectively, the bottom, two ends of main equalizing bar is connected with two main hoisting ears on end socket outer wall by main rope respectively, the lower end of auxiliary steel wire rope is connected with at least one the slipping tail hanger on end socket by joining shackle, the plane that the midperpendicalar of the circle that end socket lower edge forms forms through two main hoisting ears and slipping tail hanger, main hoisting ear on end socket outer wall and slipping tail hanger, main rope, main equalizing bar, auxiliary steel wire rope and joining shackle are configured for the sling system of the overweight end socket upset of major diameter lifting.
Vertical distance between the midperpendicalar of the circle that the connected axis of two main hoisting ears forms to end socket lower edge is 0.03-0.06:1 with the ratio of the circle diameter that end socket lower edge forms; Main hoisting Er center to the ratio of the circle diameter that the vertical distance of end socket lower edge and end socket lower edge form is 0.035-0.065:1.
The center of described slipping tail hanger to the ratio of the circle diameter that the vertical distance of end socket lower edge and end socket lower edge form is 0.065-0.105:1.
The length of described auxiliary steel wire rope is not less than slipping tail hanger to the maximum arc length of end socket lower edge.
When the quantity of described slipping tail hanger is two, the distance between two slipping tail hanger centers is 0.13-0.195:1 with the ratio of the circle diameter that end socket lower edge forms.
Described auxiliary steel wire rope is connected with the top, two ends of auxiliary balance beam respectively, and the bottom, two ends of auxiliary balance beam is connected with two slipping tail hangers by the joining shackle of auxiliary steel wire rope lower end respectively; And the length of the auxiliary steel wire rope that bottom, auxiliary balance beam two ends is connected with joining shackle is not less than slipping tail hanger to the maximum arc length of end socket lower edge.
Described main hoisting ear is tubular shaft type main hoisting ear and adopts solid drawn pipe or roll steel pipe and make, and the end of main hoisting ear is provided with stiffening plate.
Described slipping tail hanger is plate hole formula slipping tail hanger, and slipping tail hanger is along the direction setting of the axis that is connected perpendicular to main hoisting ear.
The utility model has the following advantages compared to existing technology:
The utility model by arranging main hoisting ear and slipping tail hanger on the outer wall of end socket, then make main hoisting ear be connected with corresponding crane respectively by steel rope, equalizing bar and joining shackle with slipping tail hanger, make end socket under self gravitation effect, carry out not waiting the upset of square self-balancing, switching process is steady, safety, the end socket after upset lifting and internals thereof, lining quality serviceability rate 100%; Whole sling system is simple in structure, easy to use and cost is low, suitable promoting the use of.
Accompanying drawing explanation
Accompanying drawing 1 is sling system structural representation of the present utility model.
Wherein: 1-end socket; 2-main hoisting ear; 3-slipping tail hanger; 4-main rope; 5-main equalizing bar; 6-auxiliary steel wire rope; 7-joining shackle; 8-auxiliary balance beam.
The specific embodiment
Below in conjunction with accompanying drawing and embodiment, the utility model is further described.
As shown in Figure 1: a kind of sling system for the overweight end socket upset of major diameter lifting, comprise main rope 4, main equalizing bar 5 and auxiliary steel wire rope 6, main rope 4 is connected with the top, two ends of main equalizing bar 5 respectively, the bottom, two ends of main equalizing bar 5 is connected with two main hoisting ears 2 on end socket 1 outer wall by main rope 4 respectively, the lower end of auxiliary steel wire rope 6 is connected with at least one the slipping tail hanger 3 on end socket 1 by joining shackle 7, the plane that the midperpendicalar of the circle that end socket 1 lower edge forms forms through two main hoisting ears 2 and slipping tail hanger 3, main hoisting ear 2 on end socket 1 outer wall and slipping tail hanger 3, main rope 4, main equalizing bar 5, auxiliary steel wire rope 6 and joining shackle 7 are configured for the sling system of the overweight end socket upset of major diameter lifting.Vertical distance between the midperpendicalar of the circle forming to end socket 1 lower edge at the connected axis of two main hoisting ears 2 is 0.03-0.06:1 with the ratio of the circle diameter that end socket 1 lower edge forms; The center of main hoisting ear 2 to the ratio of the circle diameter that the vertical distance of end socket 1 lower edge and end socket 1 lower edge form is 0.035-0.065:1; The center of slipping tail hanger 3 to the ratio of the circle diameter that the vertical distance of end socket 1 lower edge and end socket 1 lower edge form is 0.065-0.105:1.The quantity of slipping tail hanger 3 is determined as the case may be, and when the quantity of slipping tail hanger 3 is one, the length of this auxiliary steel wire rope 6 is not less than slipping tail hanger 3 to the maximum arc length of end socket 1 lower edge; When the quantity of slipping tail hanger 3 is two, the distance between two slipping tail hanger 3 centers is 0.13-0.195:1 with the ratio of the circle diameter that end socket 1 lower edge forms; And now auxiliary steel wire rope 6 is connected with the top, two ends of auxiliary balance beam 8 respectively, the bottom, two ends of auxiliary balance beam 8 is connected with two slipping tail hangers 3 by the joining shackle 7 of auxiliary steel wire rope 6 lower ends respectively, and the length of the auxiliary steel wire rope 6 that auxiliary balance beam 8 bottoms, two ends are connected with joining shackle 7 is not less than slipping tail hanger 3 to the maximum arc length of end socket 1 lower edge so that the crotch of auxiliary balance beam 8 does not interfere with the end opening edge of end socket 1 in switching process.This main hoisting ear 2 is for tubular shaft type main hoisting ear and adopt solid drawn pipe or roll steel pipe and make, and the end of main hoisting ear 2 is provided with the stiffening plate that wall thickness is end socket 1 0.8 times of left and right of wall thickness; Slipping tail hanger 3 is plate hole formula slipping tail hanger, and slipping tail hanger 3 is along the direction setting of the axis that is connected perpendicular to main hoisting ear 2.
Sling system of the present utility model in use, is connected the suspension hook of crane can use with corresponding main rope 4 and the upper end of auxiliary steel wire rope 6 respectively.The utility model is by arranging main hoisting ear 2 and slipping tail hanger 3 on the outer wall at end socket 1, then make main hoisting ear 2 be connected with corresponding crane respectively by steel rope, equalizing bar and joining shackle with slipping tail hanger 3, make end socket 1 under self gravitation effect, carry out not waiting the upset of square self-balancing, switching process is steady, safety, the end socket 1 after upset lifting and internals thereof, lining quality serviceability rate 100%; Whole sling system is simple in structure, easy to use and cost is low, suitable promoting the use of.
Above embodiment is only explanation technological thought of the present utility model, can not limit protection domain of the present utility model with this, every technological thought according to the utility model proposes, any change of doing on technical scheme basis, within all falling into the utility model protection domain; The technology that the utility model does not relate to all can be realized by prior art.

Claims (8)

1. the sling system for the overweight end socket of major diameter upset lifting, comprise main rope (4), main equalizing bar (5) and auxiliary steel wire rope (6), it is characterized in that described main rope (4) is connected with the top, two ends of main equalizing bar (5) respectively, the bottom, two ends of main equalizing bar (5) is connected with two the main hoisting ears (2) on end socket (1) outer wall by main rope (4) respectively, the lower end of auxiliary steel wire rope (6) is connected with at least one the slipping tail hanger (3) on end socket (1) by joining shackle (7), the plane that the midperpendicalar of the circle that end socket (1) lower edge forms forms through two main hoisting ears (2) and slipping tail hanger (3), main hoisting ear (2) on end socket (1) outer wall and slipping tail hanger (3), main rope (4), main equalizing bar (5), auxiliary steel wire rope (6) and joining shackle (7) are configured for the sling system of the overweight end socket upset of major diameter lifting.
2. the sling system for the overweight end socket upset of major diameter lifting according to claim 1, is characterized in that: the ratio of the circle diameter that the vertical distance between the midperpendicalar of the circle that the connected axis of two main hoisting ears (2) forms to end socket (1) lower edge and end socket (1) lower edge form is 0.03-0.06:1; The center of main hoisting ear (2) to the ratio of the circle diameter that the vertical distance of end socket (1) lower edge and end socket (1) lower edge form is 0.035-0.065:1.
3. the sling system for the overweight end socket of major diameter upset lifting according to claim 1, the center that it is characterized in that described slipping tail hanger (3) to the ratio of the circle diameter that the vertical distance of end socket (1) lower edge and end socket (1) lower edge form is 0.065-0.105:1.
4. the sling system for the overweight end socket upset of major diameter lifting according to claim 1, is characterized in that the length of described auxiliary steel wire rope (6) is not less than slipping tail hanger (3) to the maximum arc length of end socket (1) lower edge.
5. the sling system for the overweight end socket of major diameter upset lifting according to claim 1, when the quantity that it is characterized in that described slipping tail hanger (3) is two, the ratio of the circle diameter that the distance between two slipping tail hangers (3) center and end socket (1) lower edge form is 0.13-0.195:1.
6. the sling system for the overweight end socket of major diameter upset lifting according to claim 5, it is characterized in that described auxiliary steel wire rope (6) is connected with the top, two ends of auxiliary balance beam (8) respectively, the bottom, two ends of auxiliary balance beam (8) is connected with two slipping tail hangers (3) by the joining shackle (7) of auxiliary steel wire rope (6) lower end respectively; And the length of the auxiliary steel wire rope (6) that auxiliary balance beam (8) bottom, two ends is connected with joining shackle (7) is not less than slipping tail hanger (3) to the maximum arc length of end socket (1) lower edge.
7. the sling system for the overweight end socket upset of major diameter lifting according to claim 1, it is characterized in that described main hoisting ear (2) for tubular shaft type main hoisting ear and adopt solid drawn pipe or roll steel pipe making, and the end of main hoisting ear (2) is provided with stiffening plate.
8. the sling system for the overweight end socket upset of major diameter lifting according to claim 1, is characterized in that described slipping tail hanger (3) is plate hole formula slipping tail hanger, and slipping tail hanger (3) is along the direction setting of the axis that is connected perpendicular to main hoisting ear (2).
CN201320583810.5U 2013-09-22 2013-09-22 Spreader system for overturning and hoisting large diameter overweight sealing head Expired - Lifetime CN203474220U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320583810.5U CN203474220U (en) 2013-09-22 2013-09-22 Spreader system for overturning and hoisting large diameter overweight sealing head

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320583810.5U CN203474220U (en) 2013-09-22 2013-09-22 Spreader system for overturning and hoisting large diameter overweight sealing head

Publications (1)

Publication Number Publication Date
CN203474220U true CN203474220U (en) 2014-03-12

Family

ID=50222594

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320583810.5U Expired - Lifetime CN203474220U (en) 2013-09-22 2013-09-22 Spreader system for overturning and hoisting large diameter overweight sealing head

Country Status (1)

Country Link
CN (1) CN203474220U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104444762A (en) * 2014-11-03 2015-03-25 珠海南方广立风电设备有限公司 Wind power foundation ring overturning device and method for overturning foundation ring by using same
CN105384050A (en) * 2015-11-30 2016-03-09 西安航天动力机械厂 Overturning device for large metal shell
CN106081858A (en) * 2016-08-25 2016-11-09 优利康达(天津)科技有限公司 Wind-powered electricity generation kuppe capouch hanging apparatus
CN107758507A (en) * 2016-08-19 2018-03-06 中石化重型起重运输工程有限责任公司 The hanging method of annular-pipe reactor
CN108483223A (en) * 2018-05-18 2018-09-04 重庆海装风电工程技术有限公司 A kind of wind wheel slipping tail tooling
CN108862001A (en) * 2018-07-26 2018-11-23 西安长峰机电研究所 A kind of lifting turnover device
CN109969921A (en) * 2019-05-08 2019-07-05 张化机(苏州)重装有限公司 A kind of end socket hanging apparatus

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104444762A (en) * 2014-11-03 2015-03-25 珠海南方广立风电设备有限公司 Wind power foundation ring overturning device and method for overturning foundation ring by using same
CN105384050A (en) * 2015-11-30 2016-03-09 西安航天动力机械厂 Overturning device for large metal shell
CN105384050B (en) * 2015-11-30 2017-03-29 西安航天动力机械厂 It is a kind of to be used for band large-scale metal housing turning device
CN107758507A (en) * 2016-08-19 2018-03-06 中石化重型起重运输工程有限责任公司 The hanging method of annular-pipe reactor
CN107758507B (en) * 2016-08-19 2019-06-04 中石化重型起重运输工程有限责任公司 The hanging method of annular-pipe reactor
CN106081858A (en) * 2016-08-25 2016-11-09 优利康达(天津)科技有限公司 Wind-powered electricity generation kuppe capouch hanging apparatus
CN108483223A (en) * 2018-05-18 2018-09-04 重庆海装风电工程技术有限公司 A kind of wind wheel slipping tail tooling
CN108862001A (en) * 2018-07-26 2018-11-23 西安长峰机电研究所 A kind of lifting turnover device
CN109969921A (en) * 2019-05-08 2019-07-05 张化机(苏州)重装有限公司 A kind of end socket hanging apparatus

Similar Documents

Publication Publication Date Title
CN203474220U (en) Spreader system for overturning and hoisting large diameter overweight sealing head
CN103449301B (en) Overturning and lifting method for major-diameter superheavy end socket
CN202785258U (en) Hoisting device for air overturn of large-sized steel column
CN201961956U (en) Frame lifting appliance with adjustable lifting center of gravity
CN107758507A (en) The hanging method of annular-pipe reactor
CN103241645B (en) Self-locking composite conducting wire hoisting hook
CN205916895U (en) But chain hoist that multiple spot hung
CN204454235U (en) A kind of novel many suspension centres equalizing bar device
CN205527294U (en) Cross hanging beam
CN202214131U (en) Three-point lifting beam
CN203715054U (en) 3,000t combinable lifting balance beam
CN202265302U (en) Hoisting structure of reinforcement cage
CN204980821U (en) Pressure -bearing formula lifting device and pressure -bearing formula compensating beam
CN203781631U (en) Sling system for integral slinging of thin-wall equipment
CN202936087U (en) Adjustable steel tube equalizing beam for lifting
CN203639016U (en) Balance beam for hoisting reinforcing steel bars by tower crane
CN103738852A (en) Weight testing device of crane
CN205061339U (en) Dogging crane rope connection structure
CN204569238U (en) Omnipotent bracing or strutting arrangement bottom a kind of tower crane
CN204727438U (en) A kind of crane hanger
CN202116180U (en) Special support lifting beam for large-diameter barrel equipment
CN203048458U (en) Drawing-connection piece for adhering tower crane to concrete wall
CN203256726U (en) Steel wire rope interference-proof device of dynamic compactor, dynamic compactor arm and dynamic compactor
CN202003830U (en) Lifting appliance of rolled iron core device body
CN201695968U (en) Pipeline holding clamp

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160815

Address after: 100029 Beijing City, Chaoyang District Hui Street No. 6

Patentee after: SINOPEC HEAVY LIFTING & TRANSPORTATION Co.,Ltd.

Patentee after: SINOPEC NANJING ENGINEERING & CONSTRUCTION Inc.

Patentee after: Sinopec Engineering (Group) Co.,Ltd.

Address before: 211112 Nanjing Province, Jiangning District, Jiangsu Branch Road, No. 1189

Patentee before: Sinopec Nanjing Engineering & Construction Inc.

Patentee before: Sinopec Engineering (Group) Co.,Ltd.

CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20140312