CN205678645U - Waste heat of coke oven recovery system - Google Patents

Waste heat of coke oven recovery system Download PDF

Info

Publication number
CN205678645U
CN205678645U CN201620438819.0U CN201620438819U CN205678645U CN 205678645 U CN205678645 U CN 205678645U CN 201620438819 U CN201620438819 U CN 201620438819U CN 205678645 U CN205678645 U CN 205678645U
Authority
CN
China
Prior art keywords
heat
coke oven
cigarette channel
heat exchanger
row cigarette
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620438819.0U
Other languages
Chinese (zh)
Inventor
郭辉
王玲
于乔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA ENERGY SAVING REDUCTION Co Ltd
Shenhua Group Corp Ltd
University of Science and Technology Beijing USTB
Original Assignee
CHINA ENERGY SAVING REDUCTION Co Ltd
Shenhua Group Corp Ltd
University of Science and Technology Beijing USTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA ENERGY SAVING REDUCTION Co Ltd, Shenhua Group Corp Ltd, University of Science and Technology Beijing USTB filed Critical CHINA ENERGY SAVING REDUCTION Co Ltd
Priority to CN201620438819.0U priority Critical patent/CN205678645U/en
Application granted granted Critical
Publication of CN205678645U publication Critical patent/CN205678645U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/25Process efficiency
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P20/00Technologies relating to chemical industry
    • Y02P20/10Process efficiency
    • Y02P20/129Energy recovery, e.g. by cogeneration, H2recovery or pressure recovery turbines

Landscapes

  • Coke Industry (AREA)

Abstract

This utility model provides a kind of waste heat of coke oven recovery system, including: heat-exchanger rig, it is connected with the smoke extractor of coke oven;Water supply installation, is connected with heat-exchanger rig, and for supplying water to heat-exchanger rig, heat-exchanger rig, for the flue gas of the smoke extractor from coke oven is carried out heat exchange with the current from water supply installation, makes current form steam and is delivered to a point vapour device;Divide vapour device, be connected with gas utilization unit, for the steam that heat-exchanger rig is formed is delivered to gas utilization unit;The waste heat of coke oven recovery system of application the technical solution of the utility model, solves and enters the heat smoke of chimney through main chimney flue in coke oven of the prior art and cannot be carried out waste heat recovery thus cause the technical problem of energy waste.

Description

Waste heat of coke oven recovery system
Technical field
This utility model relates to coker field, is specifically related to a kind of waste heat of coke oven recovery system.
Background technology
Coke-oven plant for by raw coal conversion produce coke, raw coal in the carbonization chamber of coke oven through a coking cycles High-temperature retorting is made coke and produces raw coke oven gas.Existing coke-stove gas waste gas after burning is only by regenerator and checker brick The part Exposure degree of waste gas, but do not has corresponding waste heat recovery dress for entering the heat smoke of chimney through main chimney flue Put.Through the EGT about 250~300 DEG C that main chimney flue is drained, bigger waste heat recovery is still had to be worth.By direct for this portion Discharge causes the biggest energy waste.
Cannot be carried out waste heat recovery for coke oven of the prior art enters the heat smoke of chimney through main chimney flue thus make Become the technical problem of energy waste, the most not yet propose effective solution.
Utility model content
Main purpose of the present utility model is to provide a kind of waste heat of coke oven recovery system, to solve Jiao of the prior art Stove enters the heat smoke of chimney through main chimney flue cannot be carried out waste heat recovery thus cause the technical problem of energy waste.
To achieve these goals, according to an aspect of the present utility model, it is provided that a kind of waste heat of coke oven recovery system, Including: heat-exchanger rig, it is connected with the smoke extractor of coke oven;Water supply installation, is connected with heat-exchanger rig, for supplying to heat-exchanger rig Water, heat-exchanger rig, for the flue gas of the smoke extractor from coke oven is carried out heat exchange with the current from water supply installation, makes current Form steam and be delivered to a point vapour device;Divide vapour device, be connected with gas utilization unit, defeated for the steam that heat-exchanger rig is formed Deliver to gas utilization unit.
Further, heat-exchanger rig includes: First Heat Exchanger, and First Heat Exchanger is heat of transformation pipe evaporator.
Further, heat-exchanger rig also includes: the second heat exchanger, is connected with First Heat Exchanger, and the second heat exchanger is heat pipe Economizer.
Further, smoke extractor includes: first row cigarette channel, wherein, and the first heat exchanging part of First Heat Exchanger and second First heat exchanging part of heat exchanger sequentially connects with first row cigarette channel along the flow of flue gas direction of first row cigarette channel respectively.
Further, smoke extractor also includes: second row cigarette channel, arranges parallel with first row cigarette channel, wherein, and first The air inlet of discharge flue and the air inlet of second row cigarette channel are connected with the air vent of coke oven respectively;Chimney, the first smoke evacuation is logical The air vent in road and the air vent of second row cigarette channel are connected with chimney respectively.
Further, second row cigarette channel being provided with the first flue shutter, the first flue shutter is used for opening and closing Second row cigarette channel.
Further, heat-exchanger rig also includes: the 3rd heat exchanger, is arranged between First Heat Exchanger and the second heat exchanger, First heat exchanging part of the 3rd heat exchanger connects with first row cigarette channel.
Further, the 3rd heat exchanger is steam heater.
Further, first row cigarette channel includes: air-introduced machine, and the flow of flue gas direction along first row cigarette channel is arranged at The downstream of two heat exchangers.
Further, air-introduced machine includes: the first air-introduced machine and the second air-introduced machine, the first air-introduced machine and the second air-introduced machine are arranged side by side Arrange on first row cigarette channel.
Further, first row cigarette channel also includes: the second flue shutter, is arranged at the air inlet of the first air-introduced machine; 3rd flue shutter, is arranged on the exhaust ports of the first air-introduced machine.
Further, first row cigarette channel also includes: the 4th flue shutter, is arranged at the air inlet of the second air-introduced machine; 5th flue shutter, is arranged on the exhaust ports of the second air-introduced machine.
Further, first row cigarette channel also includes: the 6th flue shutter, is arranged on the air inlet of first row cigarette channel Place;7th flue shutter, is arranged on the exhaust ports of first row cigarette channel.
Further, water supply installation includes: water tank and water pump;Wherein, heat-exchanger rig includes: the second heat exchanger, and water pump divides It is not connected with the second heat exchanging part of water tank and the second heat exchanger, the water stored in water tank to be delivered to the second of the second heat exchanger Preheat in heat exchanging part.
Further, heat-exchanger rig also includes: First Heat Exchanger, the second heat exchanging part of First Heat Exchanger and the second heat exchanger Second heat exchanging part connection, with by through First Heat Exchanger preheat after current change into steam.
Further, heat-exchanger rig also includes: the 3rd heat exchanger, and the second heat exchanging part of the 3rd heat exchanger is changed with first respectively Second heat exchanging part of hot device and point vapour device connect, and are delivered to a point vapour after continuing heating with the steam formed by First Heat Exchanger Device.
Further, water supply installation also includes: softens water pump, connects with water pump with water tank respectively, and softening water pump is used for will Soften from the water in water tank.
Further, water supply installation also includes: oxygen-eliminating device, connects with water pump with water tank respectively, oxygen-eliminating device for from Water in water tank carries out deoxygenation.
The waste heat of coke oven recovery system of application the technical solution of the utility model, including: heat-exchanger rig, water supply installation and point Vapour device, heat-exchanger rig is connected with the smoke extractor of coke oven, and water supply installation is connected with heat-exchanger rig to heat-exchanger rig water supply, heat exchange The flue gas of the smoke extractor from coke oven is carried out heat exchange with the current from water supply installation by device, makes current form steam defeated Delivering to a point vapour device, point vapour device is connected with gas utilization unit and the steam of heat-exchanger rig formation is delivered to gas utilization unit thus supplies Gas utilization unit use, solve in coke oven of the prior art through main chimney flue enter chimney heat smoke cannot be carried out waste heat recovery Thus cause the technical problem of energy waste.
Accompanying drawing explanation
The Figure of description of the part constituting the application is used for providing being further appreciated by of the present utility model, this practicality Novel schematic description and description is used for explaining this utility model, is not intended that improper restriction of the present utility model. In the accompanying drawings:
Fig. 1 is the structural representation of the waste heat of coke oven recovery system according to this utility model embodiment.
Wherein, above-mentioned accompanying drawing includes the following drawings labelling:
10, heat-exchanger rig;11, First Heat Exchanger;12, the second heat exchanger;13, the 3rd heat exchanger;20, water supply installation;21、 Water tank;22, water pump;23, water pump is softened;24, oxygen-eliminating device;30, vapour device is divided;40, smoke extractor;41, first row cigarette channel; 411, air-introduced machine;412, the first air-introduced machine;413, the second air-introduced machine;414, the second flue shutter;415, the 3rd flue shutter; 416, the 4th flue shutter;417, the 5th flue shutter;418, the 6th flue shutter;419, the 7th flue shutter;42, second row Cigarette channel;421, the first flue shutter;43, chimney.
Detailed description of the invention
It should be noted that in the case of not conflicting, the embodiment in the application and the feature in embodiment can phases Combination mutually.Describe this utility model below with reference to the accompanying drawings and in conjunction with the embodiments in detail.
Waste heat of coke oven recovery system according to this utility model embodiment, as it is shown in figure 1, include: heat-exchanger rig 10, water supply Device 20 and point vapour device 30, heat-exchanger rig 10 is connected with the smoke extractor 40 of coke oven;Water supply installation 20 is with heat-exchanger rig 10 even Connecing for supplying water to heat-exchanger rig 10, heat-exchanger rig 10 is for filling the flue gas of the smoke extractor 40 from coke oven with carrying out self-water-supplying The current putting 20 carry out heat exchange, make current form steam and are delivered to a point vapour device 30;Vapour device 30 is divided to be connected with gas utilization unit, For the steam that heat-exchanger rig 10 is formed is delivered to gas utilization unit.
The waste heat of coke oven recovery system of application the technical solution of the utility model, including: heat-exchanger rig 10, water supply installation 20 With a point vapour device 30, heat-exchanger rig 10 is connected with the smoke extractor 40 of coke oven, and water supply installation 20 is connected to changing with heat-exchanger rig 10 Thermal 10 supplies water, and the flue gas of the smoke extractor 40 from coke oven is carried out by heat-exchanger rig 10 with the current from water supply installation 20 Heat exchange, makes current form steam and is delivered to a point vapour device 30, and a point vapour device 30 is connected heat-exchanger rig 10 shape with gas utilization unit The steam become is delivered to gas utilization unit thus for gas utilization unit, solves in coke oven of the prior art to enter through main chimney flue The heat smoke entering chimney cannot be carried out waste heat recovery thus causes the technical problem of energy waste.
When being embodied as, heat-exchanger rig 10 includes: First Heat Exchanger 11 and the second heat exchanger 12, and First Heat Exchanger 11 is phase Heating pipe evaporator, the second heat exchanger 12 is heat pipe economizer;First Heat Exchanger 11 and the second heat exchanger 12 include first respectively Heat exchanging part and the second heat exchanging part, the first heat exchanging part is fume side, and the second heat exchanging part is current side, by the high temperature of the first heat exchanging part The current of the second heat exchanging part are heated by flue gas.
Smoke extractor 40 includes: parallel arrangement of first row cigarette channel 41 and second row cigarette channel 42, first row cigarette channel The air inlet of 41 and the air inlet of second row cigarette channel 42 are connected with the air vent of coke oven respectively, the aerofluxus of first row cigarette channel 41 The air vent of mouth and second row cigarette channel 42 is connected with chimney 43 respectively, thus the flue gas that coke oven main chimney flue is discharged is divided into two-way Discharge.Wherein, the first heat exchanging part of First Heat Exchanger 11 and the first heat exchanging part of the second heat exchanger 12 are respectively along first row The flow of flue gas direction of cigarette channel 41 sequentially connects with first row cigarette channel 41, by first row cigarette channel 41 flowing flue gas with Steam is formed after carrying out heat exchange from the current of water supply installation 20.Heat-exchanger rig 10 also includes: the 3rd heat exchanger 13, is arranged on Connecting between First Heat Exchanger 11 and the second heat exchanger 12 and with first row cigarette channel 41, the 3rd heat exchanger 13 heats for steam Device, is delivered to a point vapour device 30 after the steam formed is continued heating after First Heat Exchanger 11 heat exchange.Owing to three are changed The needs of hot device function, in three heat exchangers, the flue-gas temperature at First Heat Exchanger 11 is the highest, and the 3rd heat exchanger 13 takes second place, At second heat exchanger 12, the temperature of flue gas is minimum.
Water supply installation 20 includes: water tank 21 and water pump 22, water pump 22 respectively with water tank 21 and the second of the second heat exchanger 12 Heat exchanging part connects, to preheat in the water stored in water tank 21 is delivered to the second heat exchanging part of the second heat exchanger 12, and first Second heat exchanging part of heat exchanger 11 connects with the second heat exchanging part of the second heat exchanger 12, the water after First Heat Exchanger 11 heat exchange Stream is fed directly in the second heat exchanging part of First Heat Exchanger 11 form steam under the effect of high-temperature flue gas and is delivered to the 3rd Heat exchanger 13;Second heat exchanging part of the 3rd heat exchanger 13 is respectively with the second heat exchanging part of First Heat Exchanger 11 and point vapour device 30 even Connecing, the steam formed in First Heat Exchanger 11 is delivered to be delivered to a point vapour device after the 3rd heat exchanger 13 continues heat temperature raising 30, a point vapour device 30 is connected with each gas utilization unit, for each gas utilization unit supplying high temperature high-pressure steam.
Water tank 21 connects with tap water, containing Ca+, Mg+ ion in tap water, and easy fouling during high temperature, impact heat transfer effect Really, even affect the safe operation of heat-exchanger rig 10, impact system worked in order to avoid tap water direct heat transfer, also set up Having the softening water pump 23 being respectively communicated with water tank 21 and water pump 22, the tap water in water tank 21 is through softening water pump 23 sofening treatment After be delivered to heat-exchanger rig 10 again.
In order to effectively reduce the oxygen heat exchanging device 10 and the corrosiveness of aqueduct dissolved in water, improve each and set In standby service life, it is additionally provided with oxygen-eliminating device 24 softening between water pump 23 and water pump 22, through softening water pump 23 sofening treatment After water after oxygen-eliminating device 24 carries out deoxygenation, be delivered to heat-exchanger rig 10 by water pump 22 again.
In order to heat-exchanger rig 10 because of fault or carry out maintenance need out of service time, it is possible to normally make from Jiao The flue gas of stove main chimney flue is discharged, it is achieved first row cigarette channel 41 and the switching of second row cigarette channel 42 work, logical in the second smoke evacuation It is provided with the first flue shutter 421 on road 42, at the air inlet of first row cigarette channel 41, is provided with the 6th flue shutter 418, Exhaust ports at first row cigarette channel 41 is provided with the 7th flue shutter 419;When heat-exchanger rig 10 normally works, by first Second row cigarette channel 42 is closed by flue shutter 421, and the 6th flue shutter 418 and the 7th flue shutter 419 are all opened, from Jiao The flue gas of stove main chimney flue all carries out heat exchange by first row cigarette channel 41 and heat-exchanger rig 10, it is achieved waste heat of coke-oven flue gas reclaims Efficiency maximizes;When heat-exchanger rig 10 because of fault or carry out maintenance need out of service time, the 6th flue shutter 418 He 7th flue shutter 419 is turned off, and the first flue shutter 421 is opened, and the flue gas from coke oven main chimney flue all passes through second row Cigarette channel 42 and chimney 43 are expelled directly out.
In order to improve the flowing velocity of flue gas in first row cigarette channel 41, the heat exchange efficiency of raising heat-exchanger rig 10, first Being additionally provided with air-introduced machine 411 on discharge flue 41, air-introduced machine 411 is arranged at along the flow of flue gas direction of first row cigarette channel 41 The downstream of two heat exchangers 12;Air-introduced machine 411 includes that the first air-introduced machine 412 and second being set up in parallel on first row cigarette channel 41 draws Blower fan 413, can run with a preparation and a use, it is simple to ensure the normal work of first row cigarette channel 41 when an air-introduced machine breaks down Make.
In order to can be to the first air-introduced machine 412 or the second when breaking down at the first air-introduced machine 412 or the second air-introduced machine 413 Air-introduced machine 413 keeps in repair, and needs to isolate the first air-introduced machine 412 or the second air-introduced machine 413 from first row cigarette channel 41 Come, therefore, at the air inlet of the first air-introduced machine 412, be provided with the second flue shutter 414, in the aerofluxus of the first air-introduced machine 412 The 3rd flue shutter 415 it is provided with at Kou;It is provided with the 4th flue shutter 416, at the air inlet of the second air-introduced machine 413 The exhaust ports of two air-introduced machines 413 is provided with the 5th flue shutter 417.Need repairing the first air-introduced machine 412 time, by the second flue Flashboard 414 and the 3rd flue shutter 415 are closed, need repairing the second air-introduced machine 413 time, by the 4th flue shutter 416 and the 5th Flue shutter 417 is closed.
The foregoing is only preferred embodiment of the present utility model, be not limited to this utility model, for this For the technical staff in field, this utility model can have various modifications and variations.All in spirit of the present utility model and principle Within, any modification, equivalent substitution and improvement etc. made, within should be included in protection domain of the present utility model.

Claims (18)

1. a waste heat of coke oven recovery system, it is characterised in that including:
Heat-exchanger rig (10), is connected with the smoke extractor (40) of coke oven;
Water supply installation (20), is connected with described heat-exchanger rig (10), and for supplying water to described heat-exchanger rig (10), described heat exchange fills Put (10) for being carried out with the current from described water supply installation (20) by the flue gas of the smoke extractor (40) from described coke oven Heat exchange, makes described current form steam and is delivered to a point vapour device (30);
Described point of vapour device (30), is connected with gas utilization unit, for being delivered to by the steam that described heat-exchanger rig (10) is formed Described gas utilization unit.
Waste heat of coke oven recovery system the most according to claim 1, it is characterised in that described heat-exchanger rig (10) including:
First Heat Exchanger (11), described First Heat Exchanger (11) is heat of transformation pipe evaporator.
Waste heat of coke oven recovery system the most according to claim 2, it is characterised in that described heat-exchanger rig (10) also includes:
Second heat exchanger (12), is connected with described First Heat Exchanger (11), and described second heat exchanger (12) is heat pipe economizer.
Waste heat of coke oven recovery system the most according to claim 3, it is characterised in that described smoke extractor (40) including:
First row cigarette channel (41), wherein, the first heat exchanging part of described First Heat Exchanger (11) and described second heat exchanger (12) The first heat exchanging part respectively along described first row cigarette channel (41) flow of flue gas direction sequentially with described first row cigarette channel (41) connection.
Waste heat of coke oven recovery system the most according to claim 4, it is characterised in that described smoke extractor (40) also includes:
Second row cigarette channel (42), is arranged parallel with described first row cigarette channel, wherein, and entering of described first row cigarette channel (41) The air inlet of QI KOU and described second row cigarette channel (42) air vent with described coke oven respectively is connected;
Chimney (43), the air vent of described first row cigarette channel (41) and the air vent of described second row cigarette channel (42) respectively with Chimney (43) connects.
Waste heat of coke oven recovery system the most according to claim 5, it is characterised in that set on described second row cigarette channel (42) Being equipped with the first flue shutter (421), described first flue shutter (421) is used for opening and closing described second row cigarette channel (42)。
Waste heat of coke oven recovery system the most according to claim 4, it is characterised in that described heat-exchanger rig (10) also includes:
3rd heat exchanger (13), is arranged between described First Heat Exchanger (11) and described second heat exchanger (12), the described 3rd First heat exchanging part of heat exchanger (13) connects with described first row cigarette channel (41).
Waste heat of coke oven recovery system the most according to claim 7, it is characterised in that described 3rd heat exchanger (13) is steam Heater.
Waste heat of coke oven recovery system the most according to claim 4, it is characterised in that described first row cigarette channel (41) is wrapped Including: air-introduced machine (411), the flow of flue gas direction along described first row cigarette channel (41) is arranged at described second heat exchanger (12) Downstream.
Waste heat of coke oven recovery system the most according to claim 9, it is characterised in that described air-introduced machine (411) including:
First air-introduced machine (412) and the second air-introduced machine (413), described first air-introduced machine (412) and described second air-introduced machine (413) It is set up in parallel on described first row cigarette channel (41).
11. waste heat of coke oven recovery systems according to claim 10, it is characterised in that described first row cigarette channel (41) is also Including:
Second flue shutter (414), is arranged at the air inlet of described first air-introduced machine (412);
3rd flue shutter (415), is arranged on the exhaust ports of described first air-introduced machine (412).
12. waste heat of coke oven recovery systems according to claim 10, it is characterised in that described first row cigarette channel (41) is also Including:
4th flue shutter (416), is arranged at the air inlet of described second air-introduced machine (413);
5th flue shutter (417), is arranged on the exhaust ports of described second air-introduced machine (413).
13. waste heat of coke oven recovery systems according to claim 4, it is characterised in that described first row cigarette channel (41) is also Including:
6th flue shutter (418), is arranged at the air inlet of described first row cigarette channel (41);
7th flue shutter (419), is arranged on the exhaust ports of described first row cigarette channel (41).
14. waste heat of coke oven recovery systems according to claim 1, it is characterised in that described water supply installation (20) including:
Water tank (21) and water pump (22);
Wherein, described heat-exchanger rig (10) including: the second heat exchanger (12), described water pump (22) respectively with described water tank (21) and Second heat exchanging part of described second heat exchanger (12) connects, and is delivered to described second with the water by middle for described water tank (21) storage and changes Preheat in second heat exchanging part of hot device (12).
15. waste heat of coke oven recovery systems according to claim 14, it is characterised in that described heat-exchanger rig also includes:
First Heat Exchanger (11), the second heat exchanging part of described First Heat Exchanger (11) and the second of described second heat exchanger (12) are changed Hot portion connects, so that the current after described First Heat Exchanger (11) preheats are changed into steam.
16. waste heat of coke oven recovery systems according to claim 14, it is characterised in that described heat-exchanger rig also includes: the Three heat exchangers (13), the second heat exchanging part of described 3rd heat exchanger (13) respectively with the second heat exchanging part of First Heat Exchanger (11) and Described point of vapour device (30) connects, and is delivered to described point after continuing heating with the steam formed by described First Heat Exchanger (11) Vapour device (30).
17. waste heat of coke oven recovery systems according to claim 14, it is characterised in that described water supply installation (20) also wraps Include:
Softening water pump (23), connect with water pump (22) with described water tank (21) respectively, described softening water pump (23) is used for will be from Water in described water tank (21) softens.
18. waste heat of coke oven recovery systems according to claim 14, it is characterised in that described water supply installation (20) also wraps Include:
Oxygen-eliminating device (24), connects with water pump (22) with described water tank (21) respectively, and described oxygen-eliminating device (24) is for from described Water in water tank (21) carries out deoxygenation.
CN201620438819.0U 2016-05-13 2016-05-13 Waste heat of coke oven recovery system Active CN205678645U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620438819.0U CN205678645U (en) 2016-05-13 2016-05-13 Waste heat of coke oven recovery system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620438819.0U CN205678645U (en) 2016-05-13 2016-05-13 Waste heat of coke oven recovery system

Publications (1)

Publication Number Publication Date
CN205678645U true CN205678645U (en) 2016-11-09

Family

ID=57437124

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620438819.0U Active CN205678645U (en) 2016-05-13 2016-05-13 Waste heat of coke oven recovery system

Country Status (1)

Country Link
CN (1) CN205678645U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107937183A (en) * 2017-07-10 2018-04-20 贵州南风日化有限公司 A kind of washing powder spray drying tower waste heat from tail gas recoverying and utilizing method and device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107937183A (en) * 2017-07-10 2018-04-20 贵州南风日化有限公司 A kind of washing powder spray drying tower waste heat from tail gas recoverying and utilizing method and device
CN107937183B (en) * 2017-07-10 2020-04-28 贵州南风日化有限公司 Washing powder spray drying tower tail gas waste heat recycling method and device

Similar Documents

Publication Publication Date Title
CN103047637B (en) Coke furnace flue gas waste heat and ascending pipe coal gas waste heat combined recycling system
CN103952162B (en) A kind of coke oven Exposure degree technique
CN106090880A (en) A kind of machine stove set heat circulation afterheat recycling system
CN106439855B (en) A kind of steam air pre-heating system of garbage burning boiler
CN105889897B (en) A kind of thermal power plant residual heat integrative recycling system and method
CN203810913U (en) Petrochemical-industry tubular heating furnace with regenerative burners
CN106322357A (en) Thermal power generation system based on boiler tail bypass flue
CN205332168U (en) Waste heat comprehensive recovery utilization system of thermal power factory
CN205065770U (en) Flue gas waste heat recovery device
CN107202318A (en) A kind of heat of smoke discharged from boiler of power station deep exploitation and water reclamation system
CN102589308A (en) Waste heat recycling system of industrial furnaces
CN205678645U (en) Waste heat of coke oven recovery system
CN201412821Y (en) Overheat steam injection boiler with non-desalted feed water
CN103528386B (en) Multi-variant phase change waste heat boiler system
CN205897879U (en) System is used multipurposely to heating furnace waste heat
CN104406144A (en) Double-medium waste heat boiler
CN104501198B (en) Heat conducting oil boiler afterheat generating system
CN206108961U (en) System for utilize coke oven smoke waste heat to prepare deaerated water
CN101666483A (en) Oil boiler heat energy recycling device
CN107120636A (en) A kind of coal fired power plant low temperature exhaust heat deep exploitation system
CN103759239B (en) Detachable steam generator
CN103468275A (en) Power generation system and method by waste heat of raw coke oven gases of coke oven
CN106352314A (en) Complementary energy utilization system for coke oven flue gas
CN207006112U (en) A kind of heat of smoke discharged from boiler of power station deep exploitation and water reclamation system
CN206093992U (en) Complementary energy utilization system for coke oven flue gas

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant