CN205662796U - Highway medium -and -large -sized solution cavity punishment structure that underlies - Google Patents

Highway medium -and -large -sized solution cavity punishment structure that underlies Download PDF

Info

Publication number
CN205662796U
CN205662796U CN201620264297.7U CN201620264297U CN205662796U CN 205662796 U CN205662796 U CN 205662796U CN 201620264297 U CN201620264297 U CN 201620264297U CN 205662796 U CN205662796 U CN 205662796U
Authority
CN
China
Prior art keywords
solution cavity
arch
skewback
medium
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620264297.7U
Other languages
Chinese (zh)
Inventor
何忠明
邢逸航
吴贺鹏
刘清芳
刘森峙
范海山
杨卓栋
刘帅
李奕嫏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201620264297.7U priority Critical patent/CN205662796U/en
Application granted granted Critical
Publication of CN205662796U publication Critical patent/CN205662796U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a highway medium -and -large -sized solution cavity punishment structure that underlies, including geogrid (3), hunch (4), abut (5), stake (6). Laying hunchs (4) in solution cavity (7) top, encircleing the travel direction of putting the perpendicular road of direction of burying of (4), the vault should be apart from ground 1m~1.5m, and the span of hunch (4) should be greater than the span of solution cavity, in abut (5) that triangle -shaped was laid at the both ends of encircleing, abut (5) are greater than 3m with the probe distance of solution cavity (7) to pile (6) on the abut, lay above the vault geogrid (3), geogrid's the direction of laying for the horizontal direction, is laid the area and should be covered the projected area of solution cavity at the horizontal direction. The utility model aims to solve the technical problem that underlie medium -and -large -sized solution cavity to the potential safety hazard that highway exists to highway, provide a safe and reliable, economize on the use of funds, the punishment structure of comparatively environmental protection.

Description

A kind of Underlying Speedway medium-and-large-sized solution cavity treatment structures
Technical field
This utility model relates to a kind of Special Roadbed punishment field, at specifically a kind of medium-and-large-sized solution cavity of Underlying Speedway Control structure.
Background technology
Karst In China (karst) landforms are widely distributed, and Karst Problem is most important in the expressway construction of karst region One of engineering problem.Solution cavity is under the influence of by dynamic load, it is possible to makes its structure be destroyed, can cause molten time serious Hole top board ruptures suddenly thus causes the deformation of ground to cave in, and has a strong impact on the stability of road occupation.To Underlying Speedway Medium-and-large-sized solution cavity roadbed filling typically has two kinds of methods, 1. grouting reinforcement methods: it is closely knit that its principle mainly makes solution cavity fill, and reaches The stability of some strength, cuts off contacting of solution cavity and soil layer and subsoil water simultaneously, prevents the growth promoter of solution cavity, harm from building The safety of thing.Grouting reinforcement method is applicable to the process of the small-sized solution cavity of shallow embedding, if solution cavity is relatively big, relatively costly.Grouting reinforcement method pair Ecological environment also has bigger destruction.2. pile foundation facture: pile foundation is to process the method that karst foundation is the more commonly used, for Karsts developing area is more ripe, can use pile foundation.Pile Bearing Capacity is big, good stability, but high to construction process requirement, expense Expensive.
Summary of the invention
In order to solve above-mentioned technical problem, this utility model provides the punishment of a kind of new Underlying Speedway medium-and-large-sized solution cavity Structure.
The Underlying Speedway medium-and-large-sized solution cavity treatment structures that the utility model proposes include GSZ, arch, skewback, Stake.At solution cavity arch routed over, the burying of arch put direction should the travel direction of vertical road, vault away from ground 1m~1.5m, arch Span should be greater than the span of solution cavity;Lay skewback at the two ends of arch, skewback is more than 3m with the horizontal range of solution cavity;Above vault Lay GSZ.
Described GSZ uses steel plastic geogrid.GSZ is laid on dome portions, and laying direction is level side To, lay area and should cover solution cavity projected area in the horizontal direction.
Described arch uses steel reinforced concrete structure.The steel reinforced concrete that arch uses is to be welded with stirrup by arc I-steel Connect, pour C30 concrete and form.The two ends of arc I-steel should be welded mutually with the framework of steel reinforcement of skewback.
Described skewback uses the skewback of triangle.Skewback is to be skeleton by reinforcing bar and pours C40 concrete and form, and Drive piles on skewback.
Use above-mentioned treatment structures can reduce the solution cavity impact on foundation stability greatly.Compared with prior art Relatively, this utility model, by laying GSZ under ground, can to a certain degree reduce soil matrix differential settlement.Under GSZ Bury arch and skewback underground, the load force born is delivered to the soil body of surrounding, to reduce the load force that Upper Plate of Karst Cave is born.This reality With novel this solution cavity treatment structures is applied widely, safety is high, more environmental protection.
Accompanying drawing explanation
Fig. 1 is the elevational schematic view of Underlying Speedway medium-and-large-sized solution cavity roadbed filling new technique.
Fig. 2 is the structure section figure of arch.
Fig. 3 is the top view of Underlying Speedway medium-and-large-sized solution cavity roadbed filling new technique.
Detailed description of the invention
The utility model is described in further detail below in conjunction with the accompanying drawings.At a kind of medium-and-large-sized solution cavity of new Underlying Speedway Control structure, as it is shown in figure 1, Fig. 1 is plane graph of the present utility model, it can be seen that this process structure of the present utility model be Solution cavity arch routed over, the span of arch is more than the span of solution cavity, and vault is away from ground 1m~1.5m.Triangle arch is laid at the two ends of arch Seat, skewback piling ensures stablizing of skewback.Vault GSZ routed over, the laying direction of GSZ is level side To, lay area and should cover solution cavity projected area in the horizontal direction.
The karsts developing area of express highway roadbed bottom is detected first with geophysical probing technique or other Detection Techniques Situation, analyzes and understands the conditions such as the form of solution cavity, trend and size.Design situation according to this section of road combines the shape of solution cavity This structure bearing capacity under normal condition and limit state is divided by state, trend, size, position according to finite element method The parameters such as analysis calculates, and draws sagitta, span, thickness, arrangement of reinforcement, make design.
As in figure 2 it is shown, the sectional drawing that Fig. 2 is arch: arch uses steel reinforced concrete structure.Arch use steel reinforced concrete be by 24a# arc I-steel welds with stirrup, pours C30 concrete and forms.The two ends of arc I-steel should be with the framework of steel reinforcement of skewback Weld mutually.The span of arch and the ratio of arch span are between 4:1~3:1.The arc I-steel of every arch is distributed one every 0.5m, And stirrup is welded with I-steel.Burying direction underground and should being perpendicular to runway direction of arch, if solution cavity span is relatively big, then can examine Consider indirect type and bury the method for arch as it is shown on figure 3, the ratio of distance and arch span between two arches is about 1:1.
Skewback is placed on the two ends of arch, and skewback application reinforcing bar skeleton C40 concrete carries out pouring to be had enough with guarantee Comprcssive strength, skewback basis of should driving piles makes skewback sufficiently stable.Skewback and solution cavity horizontal range are at least 3m.If this area Soil property the loosest, need to carry out improveing or changing by the soil property around skewback filling out.
GSZ needs to meet that intensity is big, deform the features such as little, corrosion-resistant.GSZ uses steel plastic geogrid, Being laid on above vault, level is laid.GSZ and arch are carried out bind by the top steel wire rope at arch, the paving of GSZ If area should cover solution cavity projected area in the horizontal direction.

Claims (5)

1. a Underlying Speedway medium-and-large-sized solution cavity treatment structures, is characterized in that: include GSZ (3), arch (4), skewback (5), stake (6), at solution cavity (7) arch routed over (4), arch (4) buries the travel direction putting the vertical road in direction, vault should be away from ground Face 1m~1.5m, the span of arch (4) is more than the span of solution cavity;Skewback (5), skewback (5) and solution cavity (7) is laid at the two ends of arch Horizontal range is more than 3m, and skewback (5) is to be skeleton by reinforcing bar and casting concrete forms, and drives piles (6) on skewback;At vault GSZ (3) is laid in top.
Underlying Speedway the most according to claim 1 medium-and-large-sized solution cavity treatment structures, is characterized in that: described geotechnological lattice Grid (3) use steel plastic geogrid, and GSZ (3) is laid on dome portions, and laying direction is horizontal direction, and laying area should cover Lid solution cavity projected area in the horizontal direction;GSZ and arch are carried out bind by the top steel wire rope at arch.
The most according to claim 1, Underlying Speedway medium-and-large-sized solution cavity treatment structures, is characterized in that: described arch employing type Steel-concrete structure, the steel reinforced concrete that arch uses is to be welded with stirrup (9) by arc I-steel (8), pours C30 concrete (10) form;The two ends of arc I-steel (8) should be welded mutually with the framework of steel reinforcement of skewback.
Underlying Speedway the most according to claim 1 medium-and-large-sized solution cavity treatment structures, is characterized in that: described skewback (5) triangle skewback is used.
Underlying Speedway the most according to claim 1 medium-and-large-sized solution cavity treatment structures, is characterized in that: described solution cavity (7) span along runway direction is relatively big, uses indirect type to bury the method for arch as it is shown on figure 3, distance between two arches (4) It is about 1:1 with the ratio of arch span.
CN201620264297.7U 2016-04-01 2016-04-01 Highway medium -and -large -sized solution cavity punishment structure that underlies Expired - Fee Related CN205662796U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620264297.7U CN205662796U (en) 2016-04-01 2016-04-01 Highway medium -and -large -sized solution cavity punishment structure that underlies

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620264297.7U CN205662796U (en) 2016-04-01 2016-04-01 Highway medium -and -large -sized solution cavity punishment structure that underlies

Publications (1)

Publication Number Publication Date
CN205662796U true CN205662796U (en) 2016-10-26

Family

ID=57163354

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620264297.7U Expired - Fee Related CN205662796U (en) 2016-04-01 2016-04-01 Highway medium -and -large -sized solution cavity punishment structure that underlies

Country Status (1)

Country Link
CN (1) CN205662796U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964843A (en) * 2017-12-06 2018-04-27 中铁二院工程集团有限责任公司 A kind of high-speed railway Karst Subgrade construction and its restorative procedure for having warning function
CN109487640A (en) * 2018-10-15 2019-03-19 西南交通大学 A kind of closed conduit develops regional consolidation roadbed of high-speed structure and construction method
CN115305759A (en) * 2022-08-08 2022-11-08 中国十七冶集团有限公司 Road foundation protection system for deep soft foundation and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107964843A (en) * 2017-12-06 2018-04-27 中铁二院工程集团有限责任公司 A kind of high-speed railway Karst Subgrade construction and its restorative procedure for having warning function
CN109487640A (en) * 2018-10-15 2019-03-19 西南交通大学 A kind of closed conduit develops regional consolidation roadbed of high-speed structure and construction method
CN109487640B (en) * 2018-10-15 2020-11-17 西南交通大学 High-speed railway roadbed reinforcing structure in underdrain development area and construction method
CN115305759A (en) * 2022-08-08 2022-11-08 中国十七冶集团有限公司 Road foundation protection system for deep soft foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN106087629B (en) Without the prefabricated baffle foam concrete light road bank structure of conical slope and construction method
CN104746501B (en) Treatment method and structure of bridge-head foundation sliding settlement
CN110670433B (en) Construction structure for constructing road on soft soil foundation
CN104846840B (en) A kind of shallow embedding reinforcement of soft soil integrated pipe canal device and construction method
CN205662796U (en) Highway medium -and -large -sized solution cavity punishment structure that underlies
CN106400636B (en) A kind of control method of the soft soil roadbed differential settlement of Multi-layer road
CN103194962B (en) Structure and construction method for reducing abutment staggering based on flexible pile
CN203295966U (en) Structure for reducing bumping of bridge abutment based on flexible piles
CN204401384U (en) A kind of karst area antiseepage vibration damping roadbed
CN209836778U (en) Light bridge abutment
CN106320352B (en) Construction method of multifunctional steel sheet pile cofferdam
CN208869894U (en) The reinforced structure for preventing and treating old widening of subgrade position sedimentation and deformation
CN106168031A (en) A kind of functional steel sheet-pile cofferdam
CN213452051U (en) Along with bridge laying gas pipeline structure
CN209836779U (en) Light bridge abutment of reinforced concrete
KR101929161B1 (en) Method for Reparing Lateral Flow of Bridge Abutments
CN111172833A (en) Construction method of steep slope high embankment structure
JP4310502B1 (en) Reinforcement structure for embankment support ground
JP5421191B2 (en) Design method for embankment reinforcement structure
CN202247929U (en) Plug-shaped bearing platform structure
CN202989942U (en) Wall foundation structure for soft soil or high backfill soil area
CN207062955U (en) The foundation pit supporting construction that a kind of thick long stake is combined with thin stub
CN209836780U (en) Lightweight abutment with anchor plate
CN206858979U (en) A kind of high embankment ruggedized construction in shallow buried type karst area
CN211057808U (en) Span pipeline of foundation ditch and suspend protection architecture in midair

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161026

Termination date: 20170401

CF01 Termination of patent right due to non-payment of annual fee