CN205636527U - Device is advanced on box culvert top - Google Patents

Device is advanced on box culvert top Download PDF

Info

Publication number
CN205636527U
CN205636527U CN201620279641.XU CN201620279641U CN205636527U CN 205636527 U CN205636527 U CN 205636527U CN 201620279641 U CN201620279641 U CN 201620279641U CN 205636527 U CN205636527 U CN 205636527U
Authority
CN
China
Prior art keywords
box culvert
steel
pipe
curtain
comb
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620279641.XU
Other languages
Chinese (zh)
Inventor
李勇
张树国
刘防震
武必秀
张前明
穆小龙
房昆
宁斌
苏世超
刁寒涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FORTH ENGINEERING OF ZHONGTIE BRIDGE BUREAU CO LTD
4th Engineering Co Ltd of MBEC
Original Assignee
FORTH ENGINEERING OF ZHONGTIE BRIDGE BUREAU CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FORTH ENGINEERING OF ZHONGTIE BRIDGE BUREAU CO LTD filed Critical FORTH ENGINEERING OF ZHONGTIE BRIDGE BUREAU CO LTD
Priority to CN201620279641.XU priority Critical patent/CN205636527U/en
Application granted granted Critical
Publication of CN205636527U publication Critical patent/CN205636527U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a device is advanced on box culvert top, including the box culvert, the compound steel grid, spray the concrete, the four rows of pipe -roof and I -steel, four rows of pipe -roof are hollow cubes and arrange, connect through the I -steel between two adjacent pipe -roof of one row of pipe -roof above being located, be located and connect through the I -steel between two adjacent pipe -roof of one row of left pipe -roof, be located and connect through the I -steel between two adjacent pipe -roof of one row of pipe -roof on right side, wherein one row of pipe -roof of the inside top of one deck steel grating and hollow cubes is connected, two -layer steel grating is connected with two rows of pipe -roof of hollow cubes inside two sides respectively in addition, all fill in every layer of steel grating and spray the concrete, the box culvert inserts among the hollow cubes. The utility model discloses a device is advanced on box culvert top can not only solve the difficulty that appears in the above -mentioned construction, can also effectively shorten construction period, creates higher benefit.

Description

A kind of box culvert advancing device
Technical field
This utility model relates to a kind of box culvert ancient cooking vessel and enters device.
Background technology
Currently known box culvert jacking construction technology is for eating soil jacking, and this construction method needs first in the place of jacking Arranging working pit, make slide plate at the end, hole, Prefabricated reinforced concrete box culvert on slide plate, box culvert front end is made prominent The basil gone out, then back is nearby being built from box culvert, then install very heavy between back and box culvert base plate Top, simultaneously to need through highway reinforce, box culvert is headed into by last jack by the counter-force of back Roadbed.During jacking, the box culvert front end basil is constantly cut the earth, with digging Sui Ding, till box culvert all heads into roadbed.
But eat soil jacking technology and be only applicable to weak soil basis, owing to this engineering geology is severely-weathered metasandstone, press Some problem following can be there is: 1, the basil is not yet when jacking force reaches to design jacking force according to eating soil jacking technology Insert roadbed.After continuing to strengthen top power, box culvert internode, correction tooth plate edge etc. occur in various degree burst apart 2, Whole box culvert twists new line phenomenon.3, during excavation, the soil body between pipe curtain and box culvert is different Down the dropping thus increase subgrade settlement of degree, surface subsidence is uneven, affects high speed traveling.
Utility model content
The utility model proposes a kind of box culvert advancing device, overcome during box culvert advancing due to jacking force mistake Cause greatly difficulty of burying, box culvert that damage and the defect cannot controling effectively subgrade settlement occur.
The technical solution of the utility model is achieved in that a kind of box culvert advancing device, including box culvert, three Layer steel grating, jetting cement, four comb curtain and I-steel, four comb curtains are the arrangement of hollow cubic body, are positioned at Connected by I-steel between adjacent two pipe curtains of one comb curtain of top, be positioned at a comb curtain in left side Connected by I-steel between adjacent two pipe curtains, between adjacent two pipe curtains of the comb curtain on right side Being connected by I-steel, wherein one layer of steel grating is connected, separately with a comb curtain of hollow cubic body inner upper Outer two-layer steel grating is connected with two comb curtains of two sides in portion in hollow cubic body respectively, every layer of steel grating In all fill jetting cement, box culvert inserts in described hollow cubic body.
Further, it is provided with cushion, grafting in described cushion between end face and the described pipe curtain of described box culvert Some concrete steel pipes.
Further, some concrete steel pipes are the most arranged in parallel.
Further, connected by two I-steel between adjacent two pipe curtains.
Further, two I-steel between adjacent two pipe curtains are located at the two ends of pipe curtain and company parallel with pipe curtain Connect.
Further, described box culvert includes that box culvert body and the basil, described box culvert body become with described basil one Type is arranged.
The beneficial effects of the utility model are: the box culvert advancing device basil of the present utility model easily inserts roadbed, Easily, box culvert is unlikely to deform box culvert excavation, reserved cushion, and box culvert will not occur the imagination that comes back, structure jail Gu, box culvert advancing device of the present utility model can not only solve the difficulty occurred in above-mentioned construction, moreover it is possible to effectively Shorten the construction period, create higher benefit.
Accompanying drawing explanation
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, below by right In embodiment or description of the prior art, the required accompanying drawing used is briefly described, it should be apparent that below, Accompanying drawing in description is only embodiments more of the present utility model, for those of ordinary skill in the art, On the premise of not paying creative work, it is also possible to obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 is the generalized section of this utility model a kind of box culvert advancing one embodiment of device;
Fig. 2 is the perspective view that box culvert advancing device shown in Fig. 1 is combined with culvert;
In accompanying drawing: 1-box culvert;3-steel grating;4-jetting cement;5-pipe curtain;6-concrete steel pipe;7-I-steel.
Detailed description of the invention
Below in conjunction with the accompanying drawing in this utility model embodiment, to the technical side in this utility model embodiment Case is clearly and completely described, it is clear that described embodiment is only that this utility model part is real Execute example rather than whole embodiments.Based on the embodiment in this utility model, ordinary skill people The every other embodiment that member is obtained under not making creative work premise, broadly falls into this utility model The scope of protection.
As shown in Figure 1, 2, a kind of box culvert advancing device, including box culvert 1, compound steel grid 3, jetting cement 4, Four comb curtains 5 and I-steel 7, four comb curtains 5 arrange in hollow cubic body, a comb curtain above Connected by I-steel 7 between adjacent two pipe curtains 5 of 5, be positioned at adjacent two of a comb curtain 5 in left side Connected, between adjacent two pipe curtains 5 of the comb curtain 5 on right side by I-steel 7 between pipe curtain 5 Being connected by I-steel 7, wherein a comb curtain 5 of one layer of steel grating 3 and hollow cubic body inner upper is even Connecing, additionally two-layer steel grating 3 is connected with two comb curtains 5 of two sides in portion in hollow cubic body respectively, All filling jetting cement 4 in every layer of steel grating 3, box culvert 1 inserts in described hollow cubic body.
Being provided with cushion between end face and the described pipe curtain 5 of described box culvert 1, in described cushion, grafting is some Concrete steel pipe 6.
Some concrete steel pipes 6 are the most arranged in parallel.
Connected by two I-steel 7 between adjacent two pipe curtains 5.
Two I-steel 7 between adjacent two pipe curtains 5 are located at the two ends of pipe curtain and connection parallel with pipe curtain.
Described box culvert 1 includes box culvert body and the basil, described box culvert body and the one-body molded setting of the described basil.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model, All within spirit of the present utility model and principle, any modification, equivalent substitution and improvement etc. made, all Within protection domain of the present utility model should be included in.

Claims (6)

1. a box culvert advancing device, it is characterised in that: include box culvert, compound steel grid, jetting cement, four Comb curtain and I-steel, four comb curtains are the arrangement of hollow cubic body, a comb curtain above adjacent Article two, connected by I-steel between pipe curtain, pass through between adjacent two pipe curtains of the comb curtain in left side I-steel connects, and is connected by I-steel, wherein between adjacent two pipe curtains of the comb curtain on right side One layer of steel grating is connected with a comb curtain of hollow cubic body inner upper, additionally two-layer steel grating respectively with sky Two comb curtains of two sides within body-centred cube connect, and all fill jetting cement, box culvert in every layer of steel grating Insert in described hollow cubic body.
2. box culvert advancing device as claimed in claim 1, it is characterised in that: the end face of described box culvert and institute State and between pipe curtain, be provided with cushion, grafting some concretes steel pipe in described cushion.
3. box culvert advancing device as claimed in claim 2, it is characterised in that: some concrete steel pipes are the most parallel Arrangement.
4. box culvert advancing device as claimed in claim 1, it is characterised in that: logical between adjacent two pipe curtains Cross two I-steel to connect.
5. box culvert advancing device as claimed in claim 4, it is characterised in that: between adjacent two pipe curtains Article two, I-steel is located at the two ends of pipe curtain and connection parallel with pipe curtain.
6. box culvert advancing device as claimed in claim 1, it is characterised in that: described box culvert includes that box culvert is originally Body and the basil, described box culvert body and the one-body molded setting of the described basil.
CN201620279641.XU 2016-04-06 2016-04-06 Device is advanced on box culvert top Expired - Fee Related CN205636527U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620279641.XU CN205636527U (en) 2016-04-06 2016-04-06 Device is advanced on box culvert top

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620279641.XU CN205636527U (en) 2016-04-06 2016-04-06 Device is advanced on box culvert top

Publications (1)

Publication Number Publication Date
CN205636527U true CN205636527U (en) 2016-10-12

Family

ID=57067340

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620279641.XU Expired - Fee Related CN205636527U (en) 2016-04-06 2016-04-06 Device is advanced on box culvert top

Country Status (1)

Country Link
CN (1) CN205636527U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105803957A (en) * 2016-04-06 2016-07-27 中铁大桥局集团第四工程有限公司 Box culvert jacking device and box culvert jacking method
CN113293665A (en) * 2021-06-02 2021-08-24 新疆铁道勘察设计院有限公司 Roadbed reinforcing method for long side of railway bridge and culvert connection

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105803957A (en) * 2016-04-06 2016-07-27 中铁大桥局集团第四工程有限公司 Box culvert jacking device and box culvert jacking method
CN105803957B (en) * 2016-04-06 2018-04-06 中铁大桥局集团第四工程有限公司 A kind of box culvert advancing device and box culvert advancing method
CN113293665A (en) * 2021-06-02 2021-08-24 新疆铁道勘察设计院有限公司 Roadbed reinforcing method for long side of railway bridge and culvert connection

Similar Documents

Publication Publication Date Title
CN203514328U (en) Combined anti-slide structure
KR100674366B1 (en) A Block for constructing reinforced earth wall
CN205636527U (en) Device is advanced on box culvert top
CN203960921U (en) A kind of existing cut slope stake board wall ruggedized construction
CN103603370A (en) Spatial crossed and embedded ecological building block retaining wall and construction method thereof
CN210712735U (en) Protective structure for preventing channel from being eroded
CN105803957B (en) A kind of box culvert advancing device and box culvert advancing method
CN102691277B (en) Special-shaped block as well as wall and earth-retaining slope-protecting structures built thereby
CN104612105A (en) Steel concrete structure type flood control wall
CN206359956U (en) Civil engineering bank protection step brick
CN201593261U (en) Wall body module
CN208105179U (en) A kind of combination unit with drainage steel bar concrete guard wall and reinforced gabion
CN203684271U (en) Space-crossed mutual-embedded ecological building block retaining wall
CN203716273U (en) Multifunctional ecological draining gutter
CN102277965A (en) Method for building underground garage through non-surface excavation on open space
CN205975675U (en) Utility tunnel system
CN203096686U (en) Novel composite structure combining long piled wharf and shore-connecting structure
CN210887112U (en) Ecological slope protection brick for highway side slope
CN205242357U (en) Cascaded bank protection goods of precast concrete
CN202969339U (en) Building block for dry piled retaining wall
CN106894390B (en) A kind of grout curtain method suitable for dam two sides
CN207537969U (en) One kind staggeredly embedded face layer building block
CN206052773U (en) A kind of retaining wall block
CN205934639U (en) Temporary road surface system
CN204690682U (en) A kind of combined biological slope protection block

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161012

Termination date: 20180406