CN205605796U - Wind -powered electricity generation gear box with sectional type threading pipe - Google Patents

Wind -powered electricity generation gear box with sectional type threading pipe Download PDF

Info

Publication number
CN205605796U
CN205605796U CN201620402419.4U CN201620402419U CN205605796U CN 205605796 U CN205605796 U CN 205605796U CN 201620402419 U CN201620402419 U CN 201620402419U CN 205605796 U CN205605796 U CN 205605796U
Authority
CN
China
Prior art keywords
penetration pipe
pipeline section
wind turbine
stagewise
turbine gearbox
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620402419.4U
Other languages
Chinese (zh)
Inventor
王初亮
赵晓宁
任超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sany Renewable Energy Co Ltd
Original Assignee
Sany Heavy Energy Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sany Heavy Energy Equipment Co Ltd filed Critical Sany Heavy Energy Equipment Co Ltd
Priority to CN201620402419.4U priority Critical patent/CN205605796U/en
Application granted granted Critical
Publication of CN205605796U publication Critical patent/CN205605796U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Wind Motors (AREA)

Abstract

The utility model discloses a wind -powered electricity generation gear box with sectional type threading pipe, including the planet carrier to and pass the threading pipe of planet carrier, be provided with the key on the planet carrier, the threading pipe is including first pipeline section and second pipeline section, be provided with on the outer wall of first pipeline section front end with key complex opening, keyway and ring channel, opening and keyway setting are in the ring channel front side and all communicate with the ring channel to the ring channel is gone into from the opening card to the key, moves to the keyway from the ring channel again, first pipeline section rear end can be dismantled with second pipeline section front end and is connected, first pipeline section rear end is sealed by the sealing member with the junction of second pipeline section front end. The utility model discloses do not cause the damage of sealing washer when making the assembly of threading pipe, and can realize dismantling in threading guan zaifeng field to change the sealing washer.

Description

A kind of wind turbine gearbox with stagewise penetration pipe
Technical field
This utility model belongs to technical field of wind power generation, is specifically related to a kind of wind turbine gearbox, particularly relates to A kind of wind turbine gearbox with stagewise penetration pipe.
Background technology
Gear-box in wind power generating set is an important mechanical part, and its main function is to be existed by wind wheel Under wind-force effect, produced power passes to electromotor and makes it obtain corresponding rotating speed.
The generally rotating speed of wind wheel is the lowest, does not far reach the rotating speed required by electrical power generators, it is necessary to pass through gear The accelerating function of case gear pair realizes, therefore also gear-box is referred to as gearbox.Overall cloth according to unit Put requirement, sometimes the power transmission shaft (being commonly called as big axle) being joined directly together with wind wheel hub be integrated with gear-box, Also have and big axle is respectively arranged with gear-box, utilize the structure that expansion sleeve device or shaft coupling connect therebetween.For Increasing the stopping power of unit, usually input or outfan at gear-box arrange brake gear, coordinate Blade tip braking (determining pitch wind wheel) or change pitch brake unit carry out Associated brake to set drive system jointly.
Wherein, during penetration pipe is wind power generation speed-increasing gearbox, Wind turbines becomes slurry mechanism controls and power cable The passage of process, is the important component part of step-up gear.Penetration pipe passes sun gear and planet carrier, its Front end and the synchronized rotation of line of input carrier, rear end is connected with gear-box by bearing.
But, the assembling of existing wind turbine gearbox mostly is penetration pipe and first assembles, and assembles after slow speed turbine stage bearing (ball) cover, And penetration pipe mostly is unitary design, this assembling structure is primarily present following two problem: 1, penetration pipe After assembling, the sagging destruction causing sealing ring in rear end;2, penetration pipe unitary design, its axial dimension is relatively big, And the restriction in fan engine room space, cause it in wind field dismounting difficulty, it is impossible to change sealing ring.
Therefore, this area urgently technical issues that need to address are: do not cause sealing ring during penetration pipe assembling Damaging, penetration pipe is capable of dismounting at wind field, changes sealing ring.
Utility model content
For the deficiencies in the prior art, the purpose of this utility model is to provide one to have stagewise penetration pipe Wind turbine gearbox so that do not cause the damage of sealing ring during penetration pipe assembling, and penetration pipe can at wind field Realize dismounting, in order to change sealing ring.
For solving the problems referred to above, this utility model provides a kind of wind turbine gearbox with stagewise penetration pipe, Including planet carrier, and the penetration pipe through planet carrier, described planet carrier is provided with key, described penetration pipe Including the first pipeline section and the second pipeline section, the outer wall of described first pipeline section front end is provided with and coordinates with described key Gap, keyway and cannelure, on front side of described gap is arranged on cannelure with keyway and all connect with cannelure, So that key snaps in cannelure from opening position, then moves to keyway from cannelure;Described first pipeline section rear end and second Pipeline section front end removably connects, and described first pipeline section rear end is close by sealing member with the junction of the second pipeline section front end Envelope.
As the improvement on the one hand of a kind of wind turbine gearbox with stagewise penetration pipe of this utility model, institute State push-to to cross screw and be fixedly installed on planet carrier.
As the improvement on the one hand of a kind of wind turbine gearbox with stagewise penetration pipe of this utility model, institute Stating the first pipeline section rear end and be provided with inside tapered thread, described second pipeline section front end is provided with joins with described inside tapered thread The outer cone thread closed, described sealing member is the first sealing ring being arranged on the first pipeline section rear end.
As the improvement on the one hand of a kind of wind turbine gearbox with stagewise penetration pipe of this utility model, institute Stating the first pipeline section front end and be provided with the second sealing ring, described second sealing ring is positioned on rear side of cannelure.
As the improvement on the one hand of a kind of wind turbine gearbox with stagewise penetration pipe of this utility model, institute State front casing and rear box that wind turbine gearbox includes being assembled together, by the most suitable on described rear box Sequence be disposed with slow speed turbine stage bearing (ball) cover and slow speed turbine stage bearing (ball) cover bolted penetration pipe end cap and The penetration pipe gland being connected with penetration pipe bolt of cover, described penetration pipe is sequentially passed through by order back to front and wears Spool gland, penetration pipe end cap, slow speed turbine stage bearing (ball) cover and planet carrier.
As the improvement on the one hand of a kind of wind turbine gearbox with stagewise penetration pipe of this utility model, institute State between penetration pipe end cap and penetration pipe by from front to back order be disposed with the first back-up ring, penetration pipe bearing, And oil sealing.
As the improvement on the one hand of a kind of wind turbine gearbox with stagewise penetration pipe of this utility model, institute Stating and be provided with lining between oil sealing and penetration pipe, described lining one end abuts with penetration pipe bearing, and the other end prolongs Extend below penetration pipe gland.
As the improvement on the one hand of a kind of wind turbine gearbox with stagewise penetration pipe of this utility model, institute Stating lining to arrange beyond penetration pipe gland rear end, the rear side of described lining is provided with the second back-up ring.
As the improvement on the one hand of a kind of wind turbine gearbox with stagewise penetration pipe of this utility model, institute State rear box to be made up of upper box and lower box.
The wind turbine gearbox with stagewise penetration pipe that this utility model provides, due to the front end of penetration pipe, Gap, keyway and the cannelure coordinated with the key on planet carrier it is provided with on the outer wall of the i.e. first pipeline section front end, Such that it is able to use slow speed turbine stage bearing (ball) cover first to assemble, the assembling mode of assembling after penetration pipe, and this kind of assembling Mode can play certralizing ability, and avoids the sagging damage in penetration pipe rear end sealing ring, and meanwhile, penetration pipe is adopted With sectional design, it is possible to achieve wind field is dismantled, in order to utilize limited space to change sealing ring, specifically fill Timing, first loads the first pipeline section rear end or the second pipeline section front end, then by the first pipeline section rear end by sealing member Removably connect with the second pipeline section front end, form penetration pipe, then by penetration pipe from wind power gear box back Slow speed turbine stage bearing (ball) cover inserts casing, rotates penetration pipe, in order to key snaps in cannelure from opening position, then rotates Penetration pipe, when the position of keyway with the position of key to moving axially penetration pipe time corresponding again, in order to key is from annular Groove falls in keyway.Therefore, the wind turbine gearbox that this utility model provides, it is possible to when penetration pipe is assembled Do not cause the damage of sealing ring, and penetration pipe is capable of dismounting at wind field, in order to change sealing ring.
Accompanying drawing explanation
The accompanying drawing constituting a part of the present utility model is further appreciated by of the present utility model for providing, this The schematic description and description of utility model is used for explaining this utility model, is not intended that this practicality new The improper restriction of type.In the accompanying drawings:
Fig. 1 is the structural representation that this utility model has the wind turbine gearbox specific embodiment of stagewise penetration pipe Figure;
Fig. 2 is the structural representation of Fig. 1 the first pipeline section front end;
Fig. 3 is the close-up schematic view of Fig. 1.
Description of reference numerals: 1, planet carrier;2, penetration pipe;3, key;4, the first pipeline section;5, the second pipe Section;6, gap;7, keyway;8, cannelure;9, screw;10, the first sealing ring;11, second is close Seal;12, front casing;13, rear box;14, slow speed turbine stage bearing (ball) cover;15, penetration pipe end cap;16、 Penetration pipe gland;17, the first back-up ring;18, penetration pipe bearing;19, oil sealing;20, lining;21, Two back-up rings;22, upper box;23, lower box.
Detailed description of the invention
It should be noted that in the case of not conflicting, in embodiment in this utility model and embodiment Feature can be mutually combined.Describe this utility model below with reference to the accompanying drawings and in conjunction with the embodiments in detail.
For the ease of describing, specifying at this, it is front that wind turbine gearbox is provided with the side of planet carrier, accordingly, It is provided with after the side of slow speed turbine stage bearing (ball) cover is.
As shown in Figure 1, Figure 2 and Figure 3, a kind of wind turbine gearbox with stagewise penetration pipe, including row Carrier 1, and through the penetration pipe 2 of planet carrier 1, described planet carrier 1 is provided with key 3, specifically, Described key 3 is fixedly installed on planet carrier 1 by screw 9, described penetration pipe 2 include the first pipeline section 4 with Second pipeline section 5, the outer wall of described first pipeline section 4 front end is provided with gap 6, the key coordinated with described key 3 Groove 7 and cannelure 8, described gap 6 and keyway 7 are arranged on front side of cannelure 8 and all with cannelure 8 and connect Logical, in order to key 3 snaps in cannelure 8 at gap 6, then moves to keyway 7 from cannelure 8, wherein it is desired to Illustrating, described gap 6 is corresponding with the quantity of key 3 with the quantity of keyway 7, and preferably 2, point It is not symmetricly set on the first pipeline section 4 both sides radially, certainly, it will be appreciated by persons skilled in the art that The gap 6 and the keyway 7 that use 3,4 or other quantity can also realize above-mentioned purpose, at this not Repeat again;And described first pipeline section 4 rear end removably connects with the second pipeline section 5 front end, described first pipeline section 4 rear ends are sealed by sealing member with the junction of the second pipeline section 5 front end.
The wind turbine gearbox that above-described embodiment is provided, due to the front end of penetration pipe 2, before the i.e. first pipeline section 4 It is provided with, on the outer wall of end, gap 6, keyway 7 and the cannelure 8 coordinated with the key 3 on planet carrier 1, thus First can assemble to use slow speed turbine stage bearing (ball) cover, the assembling mode of assembling after penetration pipe 2, and this kind of assembling side Formula can play certralizing ability, and avoids the sagging damage in penetration pipe 2 rear end sealing ring, meanwhile, penetration pipe 2 Use sectional design, it is possible to achieve wind field is dismantled, in order to utilize limited space to change sealing ring, specifically During assembling, first sealing member is loaded the first pipeline section 4 rear end or the second pipeline section 5 front end, then manages first Section 4 rear ends removably connect with the second pipeline section 5 front end, form penetration pipe 2, then by penetration pipe 2 from wind The slow speed turbine stage bearing (ball) cover of electrical gearbox rear end inserts casing, rotates penetration pipe 2, in order to key 3 is from gap 6 Place snaps in cannelure 8, then rotates penetration pipe 2, when the position of keyway 7 and the position of key 3 are to axle again time corresponding To mobile penetration pipe 2, in order to key 3 falls into keyway 7 from cannelure 8.Therefore, this utility model provides Wind turbine gearbox, it is possible to make penetration pipe 2 when assembling, not cause the damage of sealing ring, and penetration pipe 2 exist Wind field is capable of dismounting, in order to change sealing ring.
The detailed description of the invention removably connected with the second pipeline section 5 front end as the first pipeline section 4 rear end, described First pipeline section 4 rear end is provided with inside tapered thread, and described second pipeline section 5 front end is provided with and described inside tapered thread The outer cone thread coordinated, described sealing member is the first sealing ring 10 being arranged on the first pipeline section 4 rear end.Meanwhile, Described first pipeline section 4 front end is provided with the second sealing ring 11, and described second sealing ring 11 is positioned at cannelure 8 Rear side.
Specifically, described wind turbine gearbox includes front casing 12 and the rear box 13 being assembled together, described Rear box 13 is made up of upper box 22 and lower box 23, and described rear box 13 is depended on by order from front to back Secondary be provided with slow speed turbine stage bearing (ball) cover 14 and slow speed turbine stage bearing (ball) cover 14 bolted penetration pipe end cap 15, And penetration pipe gland 16 bolted with penetration pipe end cap 15, described penetration pipe 2 is by order back to front Sequentially pass through penetration pipe gland 16, penetration pipe end cap 15, slow speed turbine stage bearing (ball) cover 14 and planet carrier 1.And Between described penetration pipe end cap 15 and penetration pipe 2 by from front to back order be disposed with the first back-up ring 17, Penetration pipe bearing 18 and oil sealing 19.Lining 20 it is provided with between described oil sealing 19 and penetration pipe 2, described Lining 20 one end abuts with penetration pipe bearing 18, and the other end extends to below penetration pipe gland 16, and described Lining 20 is arranged beyond penetration pipe gland 16 rear end, and the rear side of described lining 20 is provided with the second back-up ring 21.
In this embodiment, when specifically assembling, first the first sealing ring 10 and the second sealing ring 11 are loaded first Pipeline section 4, then removably connects the first pipeline section 4 rear end and the second pipeline section 5 front end (as used taper thread Connect), form penetration pipe 2, then by penetration pipe 2 from the slow speed turbine stage bearing (ball) cover 14 of wind power gear box back Insert casing, rotate penetration pipe 2, in order to key 3 snaps in cannelure 8 at gap 6, then rotates penetration pipe 2, When the position of keyway 7 with the position of key 3 to moving axially penetration pipe 2 time corresponding again, in order to from cannelure 8 Fall in keyway 7, be then sequentially loaded into penetration pipe bearing 18 inner ring, lining the 20, second back-up ring 21 and Penetration pipe end cap 15 external member (including penetration pipe end cap 15, the first back-up ring 17, penetration pipe bearing 18 outer ring), Oil sealing 19, penetration pipe gland 16.
During dismounting, pull down penetration pipe gland 16, oil sealing 19, penetration pipe end cap 15 external member successively.Then axle To mobile penetration pipe 2 (together with penetration pipe bearing 18 inner ring, lining the 20, second back-up ring 21), make key 3 right The cannelure 8 of accurate first pipeline section 4, rotates penetration pipe 2 and makes key 3 align the gap 6 of the first pipeline section 4, from case Penetration pipe 2 is extracted out by body rear end, when the screwing position of penetration pipe 2 extracts casing out, by the first pipeline section 4 (together with the first sealing ring 10 and the second sealing rings 11) and the second pipeline section 5 are (together with in penetration pipe bearing 18 Circle, lining the 20, second back-up ring 21) separate, continue to move to the first pipeline section 4 until it being taken out from casing.
In sum, the wind turbine gearbox that this utility model provides, it is possible to penetration pipe 2 is not drawn when assembling Play the damage of sealing ring, and penetration pipe 2 is capable of dismounting at wind field, in order to change sealing ring.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model, All within spirit of the present utility model and principle, any modification, equivalent substitution and improvement etc. made, all Within protection domain of the present utility model should be included in.

Claims (9)

1. there is a wind turbine gearbox for stagewise penetration pipe, including planet carrier, and through planet carrier Penetration pipe, it is characterised in that:
Being provided with key on described planet carrier, described penetration pipe includes the first pipeline section and the second pipeline section, described first Gap, keyway and the cannelure coordinated with described key, described gap and key it is provided with on the outer wall of pipeline section front end Groove is arranged on front side of cannelure and all with cannelure and connects, in order to key snaps in cannelure from opening position, then from ring Shape groove moves to keyway;
Described first pipeline section rear end removably connects with the second pipeline section front end, described first pipeline section rear end and second The junction of pipeline section front end is sealed by sealing member.
The wind turbine gearbox with stagewise penetration pipe the most according to claim 1, it is characterised in that: Described push-to is crossed screw and is fixedly installed on planet carrier.
The wind turbine gearbox with stagewise penetration pipe the most according to claim 1, it is characterised in that: Described first pipeline section rear end is provided with inside tapered thread, and described second pipeline section front end is provided with and described inside tapered thread The outer cone thread coordinated, described sealing member is the first sealing ring being arranged on the first pipeline section rear end.
The wind turbine gearbox with stagewise penetration pipe the most according to claim 3, it is characterised in that: Described first pipeline section front end is provided with the second sealing ring, and described second sealing ring is positioned on rear side of cannelure.
The wind turbine gearbox with stagewise penetration pipe the most according to claim 1, it is characterised in that: Described wind turbine gearbox includes front casing and the rear box being assembled together, by from front to back on described rear box Order be disposed with slow speed turbine stage bearing (ball) cover and slow speed turbine stage bearing (ball) cover bolted penetration pipe end cap, And the penetration pipe gland being connected with penetration pipe bolt of cover, described penetration pipe is sequentially passed through by order back to front Penetration pipe gland, penetration pipe end cap, slow speed turbine stage bearing (ball) cover and planet carrier.
The wind turbine gearbox with stagewise penetration pipe the most according to claim 5, it is characterised in that: It is disposed with the first back-up ring, penetration pipe axle by order from front to back between described penetration pipe end cap and penetration pipe Hold and oil sealing.
The wind turbine gearbox with stagewise penetration pipe the most according to claim 6, it is characterised in that: Being provided with lining between described oil sealing and penetration pipe, described lining one end abuts with penetration pipe bearing, the other end Extend to below penetration pipe gland.
The wind turbine gearbox with stagewise penetration pipe the most according to claim 7, it is characterised in that: Described lining is arranged beyond penetration pipe gland rear end, and the rear side of described lining is provided with the second back-up ring.
9. according to the wind turbine gearbox with stagewise penetration pipe described in claim 5-8 any claim, It is characterized in that: described rear box is made up of upper box and lower box.
CN201620402419.4U 2016-05-06 2016-05-06 Wind -powered electricity generation gear box with sectional type threading pipe Active CN205605796U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620402419.4U CN205605796U (en) 2016-05-06 2016-05-06 Wind -powered electricity generation gear box with sectional type threading pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620402419.4U CN205605796U (en) 2016-05-06 2016-05-06 Wind -powered electricity generation gear box with sectional type threading pipe

Publications (1)

Publication Number Publication Date
CN205605796U true CN205605796U (en) 2016-09-28

Family

ID=56968228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620402419.4U Active CN205605796U (en) 2016-05-06 2016-05-06 Wind -powered electricity generation gear box with sectional type threading pipe

Country Status (1)

Country Link
CN (1) CN205605796U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019105697A1 (en) * 2017-11-29 2019-06-06 Zf Friedrichshafen Ag Fixing a pitch tube
CN110131392A (en) * 2019-04-05 2019-08-16 杭州前进齿轮箱集团股份有限公司 A kind of wind turbine gearbox slip ring tube seal structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019105697A1 (en) * 2017-11-29 2019-06-06 Zf Friedrichshafen Ag Fixing a pitch tube
CN111566343A (en) * 2017-11-29 2020-08-21 Zf 腓德烈斯哈芬股份公司 Fastening pitch tubes
US10920873B2 (en) 2017-11-29 2021-02-16 Zf Friedrichshafen Ag Fixing a pitch tube
CN111566343B (en) * 2017-11-29 2022-06-17 Zf 腓德烈斯哈芬股份公司 Fastening pitch tubes
CN110131392A (en) * 2019-04-05 2019-08-16 杭州前进齿轮箱集团股份有限公司 A kind of wind turbine gearbox slip ring tube seal structure

Similar Documents

Publication Publication Date Title
US9797504B2 (en) Gearbox lubrication system
US20120141270A1 (en) Drivetrain and method for lubricating bearing in wind turbine
CN102165218A (en) Wind-driven power generation system
CN202579057U (en) Step-up gear box of high-power wind driven generator
CN205639572U (en) Sealing structure for wind turbine gearbox
US10145363B2 (en) Method for performing up-tower maintenance on a gearbox bearing of a wind turbine
CN205605796U (en) Wind -powered electricity generation gear box with sectional type threading pipe
CN207004711U (en) It is a kind of that slurry tubular turbine is determined using non-axis transmission
US11085421B2 (en) Planet carrier of a wind turbine gearbox with improved lubricant path
CN106195136A (en) A kind of gear-driven fan (GTF) motor gear transmission device
CN108050021A (en) More than 6MW increasing gear box for half-direct-driven wind generation
CN208010523U (en) A kind of wind power generating set compact transmission chain structure
CN207111897U (en) A kind of wind turbine gearbox guides axle sealing structure
CN105221340B (en) A kind of structure-improved of compact wind power generating set
CN207879522U (en) 6MW or more increasing gear box for half-direct-driven wind generation
CN207989705U (en) It is association of activity and inertia in wind power speed-increasing gearbox the slip ring structure of portion's lubricant passage way
CN109578562A (en) The lubricant oil road structure of wind turbine gearbox
CN204357629U (en) A kind of integrated half directly driving type tidal power generating unit
CN206785987U (en) A kind of wind turbine gearbox carrier main-body sealing mechanism
CN203962946U (en) A kind of rotation axis seal structure of gear-box
CN209539406U (en) Magnetic suspension turbine power generation unit
CN206422653U (en) One kind exchange toothed gearing electric motor
WO2016145564A1 (en) Sealing system for a gearbox of a wind turbine
CN113357343A (en) Structure of generator shafting integrated in gear box
CN209129788U (en) The hollow Axile connection structure of cable and blower gearbox

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 102206 31 Industrial Park, North Qing Road, Beijing, Changping District

Patentee after: Sany Heavy Energy Co.,Ltd.

Address before: 102206 31 Industrial Park, North Qing Road, Beijing, Changping District

Patentee before: SANY HEAVY ENERGY Co.,Ltd.

Address after: 102206 31 Industrial Park, North Qing Road, Beijing, Changping District

Patentee after: SANY HEAVY ENERGY Co.,Ltd.

Address before: 102206 31 Industrial Park, North Qing Road, Beijing, Changping District

Patentee before: SANY HEAVY ENERGY EQUIPMENT Co.,Ltd.

CP01 Change in the name or title of a patent holder